Sunteți pe pagina 1din 5

PT WARRIOR INDO ASIA PASIFIK

The H Tower.Jl.H.R Rasuna Said Kav.20 Suite 19D-Kuningan Jakarta 12940


Phone +62-21-29533200

DAILY OPERATION SUMMARY


DATE : 14-Nov-2013 TOP DRIVE UNIT : WTD-094. DAYS ON LOC : 14
OPERATOR : Star Energy WELL NO : WWA-06 DAY OPERATION : 4
LOCATION : Wayang Windhu PROV : West Java SUPERVISOR : Jhonson / Faisal / Hargalianto / Tris
CONTRACTOR : PT Drill Co Jaya RIG : RIG-02 DJA
Abadi
WELL DATA KOP DEPTH : HOLE ANGLE : deg LAST CSG SET : HOLE SIZE :

TIME STATUS
From To Hrs O S-W/C RU RD DT OPERATION SUMARRY
00-00 06:00 6 6 W/O Daylight

06:00 07:00 1 1 Tail gate meeting at WWA, Highlight Activities ( Today )

07:00 12:00 5 5 Continue prepared to spud in on location WW#6 Install


and welded water line.
Function test double rams, Pipe rams open / close, Blind
Rams open / close , HCR valve ok. Set console at rig floor
12:00 18:00 6 6 Stop Activity crew program from Star Energy
18:00 24:00 6 6 Prepare blind flange for pressure test BOP ( welded 4” IF
connection for pipe )
M/U 13.5/8” rams BOP and blind flange & Tight en all
bolts, fabricated 3” release line on RDN pump 3&4

Total 24 24

Supervisor Company Representative

Jhonson.Hutapea Lamijan Junaidi

Status note:
O = Operation
S(w/c) = Stand by with crew
RU = Rig Up
RD = Rig Down
DT = Down Time
PT WARRIOR INDO ASIA PASIFIK
The H Tower.Jl.H.R Rasuna Said Kav.20 Suite 19D-Kuningan Jakarta 12940
Phone +62-21-29533200

DAILY OPERATION SUMMARY


DATE : 15-Nov-2013 TOP DRIVE UNIT : WTD-094. DAYS ON LOC : 15
OPERATOR : Star Energy WELL NO : WWA-06 DAY OPERATION : 5
LOCATION : Wayang Windhu PROV : West Java SUPERVISOR : Jhonson / Faisal / Hargalianto / Tris
CONTRACTOR : PT Drill Co Jaya RIG : RIG-02 DJA
Abadi
WELL DATA KOP DEPTH : HOLE ANGLE : deg LAST CSG SET : HOLE SIZE :

TIME STATUS
From To Hrs O S-W/C RU RD DT OPERATION SUMARRY
00-00 06:00 6 6 Pressure Test Blind Rams W/400 PSI for 10 Mnt ( Ok )
06:00 07:00 1 1 Tail Gate Meeting at WWA
07:00 18:00 11 11 Continue prepared to spud in, test running water pump
pressure test pipe rams ( leak on tool joint with flange )
Re Welding tool joint to flange, function test discharge
line and test running flow meter ( Ok )
18:00 24:00 6 6 Repair on BOP Hydraulic line, Build up plug for 5” DP
Contd pressure test line rig pump to 2500 psi for 10 Mnt
Hold at 2300 PSI.

Total 24 24

Supervisor Company Representative

Jhonson.Hutapea Lamijan Junaidi

Status note:
O = Operation
S(w/c) = Stand by with crew
RU = Rig Up
RD = Rig Down
DT = Down Time
PT WARRIOR INDO ASIA PASIFIK
The H Tower.Jl.H.R Rasuna Said Kav.20 Suite 19D-Kuningan Jakarta 12940
Phone +62-21-29533200

DAILY OPERATION SUMMARY


DATE : 16-Nov-2013 TOP DRIVE UNIT : WTD-094. DAYS ON LOC : 16
OPERATOR : Star Energy WELL NO : WWA-06 DAY OPERATION : 6
LOCATION : Wayang Windhu PROV : West Java SUPERVISOR : Jhonson / Faisal / Hargalianto / Tris
CONTRACTOR : PT Drill Co Jaya RIG : RIG-02 DJA
Abadi
WELL DATA KOP DEPTH : HOLE ANGLE : deg LAST CSG SET : HOLE SIZE :

TIME STATUS
From To Hrs O S-W/C RU RD DT OPERATION SUMARRY
00-00 02:30 2.5 2.5 Pressure test pipe rams,blind rams,400 psi low / 1000
psi high hold 10 mnt each testing
02:30 03:00 0.5 0.5 Pre job meeting : Killing well program , JSA
03:00 06:00 3 3 Wait On decision from STAR ENERGY as engineer
prediction problem on well head after kill well
06:00 07:00 1 11 Tail gate meeting at WWA
07:00 12:00 5 5 W/O program from STAR ENERGY problem on well head
after kill,
12:00 12:30 0.5 0.5 Cut plat on substructur
12:30 14:00 1.5 1.5 H2S drill all crew and service company
14:00 15:30 1.5 1.5 Open valve on well head leak from welding union
hammer ( Line from stand pipe to well head ) re welding
Hammer union
15:30 17:30 2 Start Spud In Operation, Kill well while monitoring
downward movement of well head as the following step
17:30 21:00 3.5 Stopped pumping due to predicated movement will be
more than 13 cm mean while pressure drop only 10 psi
Final movement 5.5 cm, Discussed with facility and
subsurface teams and other 3 options to project manager
21:00 24:00 3 Wait On decision from management
Total 24 8.5 15.5

Supervisor Company Representative

Jhonson.Hutapea
Lamijan Junaidi

Status note:
O = Operation
S(w/c) = Stand by with crew
RU = Rig Up
RD = Rig Down
DT = Down Time
PT WARRIOR INDO ASIA PASIFIK
The H Tower.Jl.H.R Rasuna Said Kav.20 Suite 19D-Kuningan Jakarta 12940
Phone +62-21-29533200

DAILY OPERATION SUMMARY


DATE : 17-Nov-2013 TOP DRIVE UNIT : WTD-094. DAYS ON LOC : 16
OPERATOR : Star Energy WELL NO : WWA-06 DAY OPERATION : 7
LOCATION : Wayang Windhu PROV : West Java SUPERVISOR : Jhonson / Faisal / Hargalianto / Tris
CONTRACTOR : PT Drill Co Jaya RIG : RIG-02 DJA
Abadi
WELL DATA KOP DEPTH : HOLE ANGLE : deg LAST CSG SET : HOLE SIZE :

TIME STATUS
From To Hrs O S-W/C RU RD DT OPERATION SUMARRY
00-00 06:00 6 6 Continue W/O decision from management Cont W/O
decision from management
06:00 07:00 1 1 Tail gate meeting
2 at WWA
07:00 09:00 2 2 Continue W/O decision re arrange band well of fuel tank
09:00 09:30 0.5 0.5 Got decision to rig down ,move to lower spot area of rig
09:30 10:30 1 1 Conducted prejob meeting
10:30 11:00 0.5 0.5 R/D Top Drive 10% discharge line of mud pump
11:00 19:00 8 8 Post poned R/D due to consider to re kill well
Got decision to continue rig down top drive 50%
reposition some equipment while team project
Management and drilling conducted meeting, stop
operation due to team come up with offered decision to
Management for approval
19:00 24:00 5 5 Got decision to rig up top drive back and re set up
accumulator unit, M/U BOP Hydraulic line, Re Install 5”
Water line ,Re move double ram BOP close to well

Total 24 10.5 13.5

Supervisor Company Representative

Jhonson.Hutapea
Lamijan Junaidi

Status note:
O = Operation
S(w/c) = Stand by with crew
RU = Rig Up
RD = Rig Down
DT = Down Time
PT WARRIOR INDO ASIA PASIFIK
The H Tower.Jl.H.R Rasuna Said Kav.20 Suite 19D-Kuningan Jakarta 12940
Phone +62-21-29533200

DAILY OPERATION SUMMARY


DATE : 18-Nov-2013 TOP DRIVE UNIT : WTD-094. DAYS ON LOC : 18
OPERATOR : Star Energy WELL NO : WWA-06 DAY OPERATION : 8
LOCATION : Wayang Windhu PROV : West Java SUPERVISOR : Jhonson / Faisal / Hargalianto / Tris
CONTRACTOR : PT Drill Co Jaya RIG : RIG-02 DJA
Abadi
WELL DATA KOP DEPTH : HOLE ANGLE : deg LAST CSG SET : HOLE SIZE :

TIME STATUS
From To Hrs O S-W/C RU RD DT OPERATION SUMARRY
00-00 06:00 6 6 Continue to re –install mud pump, discharge line & 6”
water line, Function test & pressure test MP#1,2,3,4
06:00 07:00 1 1 Tail gate meeting
2 at WWA
07:00 10:00 3 3 Continue pressure test combination of discharge line
mud pump#1,2,3,4 to 2500 psi and hold @2300 psi for
10 mnt,OK. Re install Top Drive
10:00 12:00 2 2 Disconnected crown valve and installed additional
master valve above old master valve
12:00 13:00 1 1 Fill up upper MV and opened lower MV. Found upper MV
leaks, install crwon valve, @ 13:00 R/U Top Drive
completed.
13:00 14:30 1.5 1.5 Cut off yoke and steam of old MV and welded steam to
packing gland
14:30 15:00 0.5 0.5 Prepared to kill well ( install shut in pressure 457
psi,installed height from top of old MV to substructure
beam was 59 cm )
15:00 24:00 9 9 5 Killed Well as follow program from SE

Total 24 9 15

Supervisor Company Representative

Jhonson.Hutapea
Lamijan Junaidi

Status note:
O = Operation
S(w/c) = Stand by with crew
RU = Rig Up
RD = Rig Down
DT = Down Time

S-ar putea să vă placă și