GENERAL CONSTRUCTION / CIVIL WORKS

MAIN WORK AND ACTIVITY DESCRIPTION

SITE WORK (DEMOLITION) UNIT PARAMETER REMARKS INCLUDED EXCLUDED

DEMOLITION Clearing & Stockpiling of Removed All repair works as maybe required on
Building Demolition MH/M³ 1.480 Measured Overall Materials to within 50 M haul distance. removed materials.
FENCE DEMOLITION
Cyclone, Chainlink or Mesh Wire MH/LM 0.500 Height of fence should not Demolition of steel structure into Truckloading, hauling & stockpiling
Sheet Metal Cladding MH/LM 0.820 exceed 2.5M. For every convenient sections appropriate for to more than 50M haul distance
Wrought Iron Grill MH/LM 0.820 .3M increase in height, clearing.
Wooden MH/LM 0.500 multiply value by 1.05 Clearing & stockpiling of removed All repair works as may be required on
Barbed Wire MH/LM 0.300 materials to within 50 M haul distance removed materials.
only. Excavating & breaking-out of concrete
SELECTIVE DEMOLITION - ROOFING AND HOOD SHEETING Completely dismantling of sheeting
GI Corrugated Metal Sheets MH/M² 0.140 Without insulation matl's works, weather flashing, gutters and Truckloading, hauling & stockpiling
RIB Type, Long Span Metal Sheets MH/M² 0.140 Multiply value by 1.5 if downspouts. to more than 50M haul distance
Corrugated Asbestos Sheets MH/M² 0.250 there is insulation Demolition of steel structure into
Plain G.I. Sheets (Ridge Vents & Hoods) MH/M² 0.140 convenient sections appropriate for All repair works as may be required on
clearing. removed materials.
REMOVE WALL AND SIDE SHEETING
GI Corrugated Metal Sheets MH/M² 0.150 Without insulation matl's Clearing & stockpiling of removed Truckloading, hauling & stockpiling
RIB Type, Long Span Metal Sheets MH/M² 0.150 Multiply value by 1.5 if materials to within 50 M haul distance to more than 50M haul distance
Corrugated Asbestos Sheets MH/M² 0.250 there is insulation only.
Plain Asbestos Sheets MH/M² 0.250 All repair works as may be required on
Plain G.I. Sheets (Ridge Vents & Hoods) MH/M² 0.150 up to 12M high Setting-up & clearing of scaffolds removed materials.
SELECTIVE STRUCTURAL DEMOLITION
Heavy Sections (25 lbs/ft & up) MH/MT 12.000 up to 12M high Demolition of steel structure into All repair works as may be required on
Medium / Light Sections (24 lbs/ft & below) MH/MT 15.000 convenient sections appropriate for removed materials.
Structural Steel Accessories MH/MT 19.000 clearing. Sorting, truckloading, hauling and
Setting-up & clearing of scaffolds stockpiling of demolished matl's
CONCRETE REMOVAL
REINFORCED CONCRETE REMOVAL Breaking by machines Breaking-out of concrete structures into Truckloading, hauling & stockpiling
Curves and Gutters MH/M³ 2.500 convenient blocks appropriate for to more than 50M haul distance
Chambers, Manholes, Basins & Culverts MH/M³ 5.750 clearing.
Trenches MH/M³ 3.350 Grading & leveling of disposal area
Footings, Foundations & Pile Caps MH/M³ 5.230 Clearing & disposing of removed if required
Grade Beams MH/M³ 5.230 materials to within 50M haul distance
Columns, Elevated Beams & Girders MH/M³ 4.310 only. All repair works as may be required on
Hollow Concrete Block Walls MH/M³ 1.980 removed materials.
Solid Concrete Walls MH/M³ 3.920 Setting-up & clearing of scaffolds when All repair works damaged by demolition

437475391.xls Page 1
Ground Slabs & Pavements MH/M³ 3.100 applicable. to retained or unremoved adjacent
materials or structure.
GENERAL CONSTRUCTION / CIVIL WORKS

MAIN WORK AND ACTIVITY DESCRIPTION

SITE WORK (DEMOLITION) UNIT PARAMETER REMARKS INCLUDED EXCLUDED

Elevated Slabs, Decks, Platforms & Canopie MH/M² 5.62 Clearing & Stockpiling of Removed All repair works as maybe required on
Stairs And Railings MH/M² 5.620 Measured Overall Materials to within 50 M haul distance. removed materials.
REMOVE CONCRETE WALL FINISH
Masonry Finish MH/M² 0.110 Setting-up & clearing of scaffolds & Grading & Leveling of disposal Area if
Tile Works - Cemented MH/M² 0.330 pertinent falseworks. required.
Tile Works - Mortar Grouted MH/M² 0.350
REMOVE FLOOR TOPPING & FINISH
Cement Mortar Topping MH/M² 0.330 Breaking-out of concrete structures into Truckloading, hauling & stockpiling
Asphalt Topping MH/M² 0.330 convenient blocks appropriate for to more than 50M haul distance
Metallic Hardener Topping MH/M² 0.500 clearing.
Tile Works - Cemented MH/M² 0.400 All repair works as may be required on
Tile Works - Mortar Grouted MH/M² 0.250 removed materials.
Vinyl Tiles MH/M² 0.250

WOODEN & MISC. METAL FRAME STRUCTURES DEMOLITION


Roof Frames (Trusses, Rafters, Purlins, etc.) MH/M² 0.450 Dismantling of wooden structures into Truckloading, hauling & stockpiling
Siding and Partition Frames & Furring MH/M² 0.220 convenient sections appropriate for to more than 50M haul distance
Ceilings Frames & Furring MH/M² 0.330 clearing.
Floor Deck & Canopy Frames MH/M² 0.400 All repair works as may be required on
Structural Frames ( Columns, Beams, Girder ) MH/M² 0.220 Clearing & Stockpiling of Removed removed materials.
Wood Sidings with doors & windows MH/M² 0.220 Materials to within 50 M haul distance.
Wood Flooring with stairs and railings MH/M² 0.220 Cut-out & restoration of electrical,
Partition Boards with doors & windows MH/M² 0.220 Setting-up & clearing of scaffolds when mechanical, piping lines & other
Ceiling Boards with metal Runners MH/M² 0.220 applicable. utility lines.
PIPING CLADDING & LAGGING WORKS DEMOLITION
REMOVE MECHANICAL CLADDING & LAGGING WORKS Above ground Dismantling of cladding & lagging works Truckloading, hauling & stockpiling
On Apparatus MH/M² 1.410 Manhours do not include into convenient sections appropriate for to more than 50M haul distance
On Machineries MH/M² 1.680 loading and hauling of clearing.
On Ductworks & Stack MH/M² 1.410 removed materials. All repair works as may be required on
Clearing & Stockpiling of Removed removed materials.
REMOVE PIPE CLADDING & LAGGING WORKS Materials to within 50 M haul distance.
1" ø & below (33.4 mm) MH/LM 0.850 Above ground Loading and Hauling of removed
1 1/4" ø (42.2 mm) MH/LM 0.850 Setting-up & clearing of scaffolds matl's.

437475391.xls Page 2
1 1/2" ø (48.3 mm) MH/LM 0.850
2" ø (60.3 mm) MH/LM 0.850 Shoring and bracing as required for Add'l protective measures that may
2 1/2" ø (73. mm) MH/LM 0.850 changes being made. be needed due to weather, mobility
and partially dismantled structures
GENERAL CONSTRUCTION / CIVIL WORKS
MAIN WORK AND ACTIVITY DESCRIPTION

SITE WORK (DEMOLITION) UNIT PARAMETER REMARKS INCLUDED EXCLUDED

3" ø & below (88.9 mm) MH/LM 1.500


3 1/2" ø (101.6 mm) MH/LM 1.500
4" ø (114.3 mm) MH/LM 1.500
5" ø (141.3 mm) MH/LM 1.500
6" ø (168.3 mm) MH/LM 1.500
8" ø (219.1 mm) MH/LM 3.280
10" ø (273.1 mm) MH/LM 3.280
12" ø (323.9 mm) MH/LM 3.280
14" ø (355.6 mm) MH/LM 5.670
16" ø (406.4 mm) MH/LM 5.670
18" ø (457.2 mm) MH/LM 8.200
20" ø (508.0 mm) MH/LM 8.200
22" ø (558.8 mm) MH/LM 8.200
24" ø (609.6 mm) MH/LM 9.840
26" ø (660.4 mm) MH/LM 9.840
28" ø (711.2 mm) MH/LM 9.840
30" ø (762.2 mm) MH/LM 9.840
32" ø (812.8 mm) MH/LM 9.840
34" ø (863.6 mm) MH/LM 9.840
36" ø (914.4 mm) MH/LM 9.840
42" ø (1066.8 mm) MH/LM 11.480
48" ø (1219.2 mm) MH/LM 11.480
REMOVE ASBESTOS PIPES
2" ø (60.3 mm) MH/LM - U/G Piping Dismantling of pipes into convenient Excavation, backfilling and surface
2 1/2" ø (73. mm) MH/LM - sections appropriate for clearing. restoration works.
3" ø & below (88.9 mm) MH/LM -
3 1/2" ø (101.6 mm) MH/LM - Disconnecting all valves & Hauling to more than 50M haul distance
4" ø (114.3 mm) MH/LM 1.800 appurtenances. to storage or disposal area.
5" ø (141.3 mm) MH/LM 2.060
6" ø (168.3 mm) MH/LM 2.060 Clearing & placing of Removed Cleaning, de-gassing, wrapping,
8" ø (219.1 mm) MH/LM 2.330 Materials to within 50 M haul distance. surface coating & crating works.
10" ø (273.1 mm) MH/LM 2.700 All repairs & rehabilitation works as
12" ø (323.9 mm) MH/LM 3.000 Setting-up & clearing of scaffolds maybe required on removed matl's

437475391.xls Page 3
REMOVE VITRIFIED CLAY PIPES Dismantling of pipes into convenient Excavating & breaking out of
2" ø (60.3 mm) MH/LM - U/G Piping sections appropriate for clearing. concrete pipe sleepers.
2 1/2" ø (73. mm) MH/LM - Dismantling of structural steel pipe
3" ø & below (88.9 mm) MH/LM - Disconnecting all valves & supports
appurtenances. Dewaterign works.
GENERAL CONSTRUCTION / CIVIL WORKS

MAIN WORK AND ACTIVITY DESCRIPTION

SITE WORK (DEMOLITION) UNIT PARAMETER REMARKS INCLUDED EXCLUDED

3 1/2" ø (101.6 mm) MH/LM -


4" ø (114.3 mm) MH/LM 1.730
5" ø (141.3 mm) MH/LM 1.990
6" ø (168.3 mm) MH/LM 1.990
8" ø (219.1 mm) MH/LM 2.210
10" ø (273.1 mm) MH/LM 2.480
12" ø (323.9 mm) MH/LM 2.700
REMOVE PVC PIPES
1" ø & below (33.4 mm) MH/LM 0.860 U/G Piping
1 1/4" ø (42.2 mm) MH/LM 0.900
1 1/2" ø (48.3 mm) MH/LM 1.160
2" ø (60.3 mm) MH/LM 1.310
2 1/2" ø (73. mm) MH/LM 1.500
3" ø & below (88.9 mm) MH/LM 1.650
3 1/2" ø (101.6 mm) MH/LM 1.800
4" ø (114.3 mm) MH/LM 1.800
5" ø (141.3 mm) MH/LM 1.990
6" ø (168.3 mm) MH/LM 1.990
8" ø (219.1 mm) MH/LM 2.480

REMOVE PLASTIC PIPES


1" ø & below (33.4 mm) MH/LM 0.410
1 1/4" ø (42.2 mm) MH/LM 0.490
1 1/2" ø (48.3 mm) MH/LM 0.530
2" ø (60.3 mm) MH/LM 0.640
2 1/2" ø (73. mm) MH/LM 0.680
3" ø & below (88.9 mm) MH/LM 0.830
3 1/2" ø (101.6 mm) MH/LM 1.050
4" ø (114.3 mm) MH/LM 1.050
5" ø (141.3 mm) MH/LM 1.310

437475391.xls Page 4
6" ø (168.3 mm) MH/LM 1.390
REMOVE CONCRETE PIPES
4" ø (114.3 mm) MH/LM 0.960
5" ø (141.3 mm) MH/LM 1.200
6" ø (168.3 mm) MH/LM 1.200
8" ø (219.1 mm) MH/LM 1.440
10" ø (273.1 mm) MH/LM 1.680

GENERAL CONSTRUCTION / CIVIL WORKS

MAIN WORK AND ACTIVITY DESCRIPTION

SITE WORK (DEMOLITION) UNIT PARAMETER REMARKS INCLUDED EXCLUDED

12" ø (323.9 mm) MH/LM 1.920


14" ø (355.6 mm) MH/LM 3.180
16" ø (406.4 mm) MH/LM 3.420
18" ø (457.2 mm) MH/LM 3.600
20" ø (508.0 mm) MH/LM 3.900
22" ø (558.8 mm) MH/LM 4.200
24" ø (609.6 mm) MH/LM 4.500
26" ø (660.4 mm) MH/LM 4.800
28" ø (711.2 mm) MH/LM 5.220
30" ø (762.2 mm) MH/LM 5.640
32" ø (812.8 mm) MH/LM 6.000
34" ø (863.6 mm) MH/LM 6.360
36" ø (914.4 mm) MH/LM 6.780
42" ø (1066.8 mm) MH/LM 7.800
48" ø (1219.2 mm) MH/LM 8.940

437475391.xls Page 5
GENERAL CONSTRUCTION / CIVIL WORKS

MAIN WORK AND ACTIVITY DESCRIPTION

SITE WORK (SITE PREPARATION) UNIT PARAMETER REMARKS INCLUDED EXCLUDED


SITE CLEARING
CLEARING AND GRUBBING Site surface stripping-off of top soil,
1,000 sm & below MH/SM 0.020 D7 DOZER grass & shrubs at 50mm ave. below
1,000 to 2,500 sm area MH/SM 0.020 existing natural grade.
3,000 to 4,000 sm area MH/SM 0.020
1,000 sm & above MH/SM 0.020

GRASS AND SHRUB REMOVAL


1.2m high shrub, approx. density of 6m MH/SM -
50 mm depth of grass MH/SM -

LARGE TRUNK TREES CLEARING


4" ø trunk MH/EA 0.470 Trimming-off tree branches cutting Hauling to more than 50m. haul
6" ø trunk MH/EA 0.710 down & cutting trunks into covenient distance to stockpile area.
8" ø trunk MH/EA 1.000 lengths for hauling to w/in 50m haul
10" ø trunk MH/EA 1.250 distance to stockpile area. Piling and removal of stumps.
12" ø trunk MH/EA 1.500
14" ø trunk MH/EA 1.930 Cutting down of trees. Digging, excavation, cutting of roots.
16" ø trunk MH/EA 2.200 USING CHAINSAW
18" ø trunk MH/EA 2.480
20" ø trunk MH/EA 3.150
24" ø trunk (323.9 mm) MH/EA 3.780
30" ø trunk (355.6 mm) MH/EA 5.030
36" ø trunk (406.4 mm) MH/EA 6.030

SELECTIVE CLEARING
TREE AND SHRUB REMOVAL
4 ~ 6" ø trunk MH/EA 3.000 D7 OR D8 DOZER Cutting down of trees. Excavating & removing of roots.
8 ~ 12" ø trunk MH/EA 6.000
14 ~ 18" ø trunk MH/EA 7.500 Clearing and hauling of stumps to w/in Hauling to more than 50m. haul
20 ~ 24" ø trunk MH/EA 9.000 50m haul distance to stockpile. distance to stockpile area.
26 ~ 36" ø trunk MH/EA 11.200

437475391.xls Page 6
GENERAL CONSTRUCTION / CIVIL WORKS

MAIN WORK AND ACTIVITY DESCRIPTION

SITE WORK (EARTHWORK) UNIT PARAMETER REMARKS INCLUDED EXCLUDED


GRADING
ROUGH GRADING (Cutting & Compacting to Grade)
130m haul distance & below MH/M³ 0.150 D7 OR D8 DOZER Establishing & Staking-out of control Rock Excavation, breaking &
250m haul distance MH/M³ 0.170 datum points. blasting.
300m haul distance MH/M³ 0.180
450m haul distance MH/M³ 0.190 Checking of finished grade line. Site clearing of trees and stumps.
750m haul distance MH/M³ 0.270
900m haul distance MH/M³ 0.280 Checking of fill compaction. Hauling-off & disposal of spoils.
1,000m haul distance MH/M³ 0.300
1,200m haul distance MH/M³ 0.310
FINISH GRADING (Cutting, Filling & Compacting to Grade)
130m haul distance & below MH/M³ 0.150 Cut and fill then compacting same as above same as above
250m haul distance MH/M³ 0.170 to grade
300m haul distance MH/M³ 0.180
450m haul distance MH/M³ 0.190
750m haul distance MH/M³ 0.270
900m haul distance MH/M³ 0.280
1,000m haul distance MH/M³ 0.300
1,200m haul distance MH/M³ 0.310
FINISH GRADING (Filling & Compacting to Grade)
130m haul distance & below MH/M³ 0.200 Filling ( fill material from same as above same as above
250m haul distance MH/M³ 0.200 outside) then compacting
300m haul distance MH/M³ 0.200
450m haul distance MH/M³ 0.200
750m haul distance MH/M³ 0.200
900m haul distance MH/M³ 0.200
1,000m haul distance MH/M³ 0.200
1,200m haul distance MH/M³ 0.200
EXCAVATING
MANUAL EXCAVATION The unit manhour is for Staking-out datum lines & control Well heads driving & sub-surface
Trench - 3 ft deep & below MH/M³ 6.000 medium type of soil. points. and surface dewatering works.
Trench - 4 ft deep & average MH/M³ 6.500
Footing / Foundation - 2 ft. deep & below MH/M³ 6.000 For Soft soil apply factor Trimming, Grade Checking Basefilling, backfilling & disposing
Footing / Foundation - 3 ft. deep MH/M³ 6.500 of 0.85 of spoils.
Footing / Foundation - 4 ft. deep MH/M³ 6.500 Shoring, Bracing, Barricades &
Footing / Foundation - 5 ft. deep MH/M³ 8.000 For Hard soil apply factor Cross-over placing & clearing

437475391.xls Page 7
of 1.35

GENERAL CONSTRUCTION / CIVIL WORKS

MAIN WORK AND ACTIVITY DESCRIPTION

SITE WORK (EARTHWORK) UNIT PARAMETER REMARKS INCLUDED EXCLUDED


Soft Soil: sand, silty sand
Open - 8 ft wide & up - 2 ft deep & below MH/M³ 6.000 Medium soil: gravelly sand,
Open - 8 ft wide & up - 3 ft MH/M³ 6.000 clay, silty clay
Open - 8 ft wide & up - 4 ft MH/M³ 6.500 Hard soil: loose weathered
Open - 8 ft wide & up - 5 ft MH/M³ 8.000 rocks, hardened clay

MACHINE EXCAVATION
Trench - 3 ft deep & below MH/M³ 0.160 The unit manhour is for Staking-out datum lines & control Well heads driving & sub-surface
Trench - 5 ft deep & average MH/M³ 0.160 medium type of soil. points. and surface dewatering works.
Trench - 7 ft deep & average MH/M³ 0.180
Trench - 9 ft deep & average MH/M³ 0.220 For Soft soil apply factor Trimming, Grade Checking Basefilling, backfilling & disposing
of 0.85 of spoils.
Footing / Foundation - 3 ft. deep & below MH/M³ 0.160 Shoring, Bracing, Barricades &
Footing / Foundation - 5 ft. deep MH/M³ 0.160 For Hard soil apply factor Cross-over placing & clearing
Footing / Foundation - 7 ft. deep MH/M³ 0.180 of 1.35
Footing / Foundation - 9 ft. deep MH/M³ 0.220
Footing / Foundation - 12 ft. deep MH/M³ 0.280 3/4 CY Backhoe up to 1.5m

Open - 8 ft wide & up - 3 ft deep & below MH/M³ 0.160


Open - 8 ft wide & up - 5 ft MH/M³ 0.160
Open - 8 ft wide & up - 7 ft MH/M³ 0.180
Open - 8 ft wide & up - 9 ft MH/M³ 0.220
Open - 8 ft wide & up - 12 ft MH/M³ 0.280
Open - 8 ft wide & up - 15 ft MH/M³ 0.320
Open - 8 ft wide & up - 18 ft MH/M³ 0.370

ROCK EXCAVATION
ROCK BREAKING
By Rock Breaker MH/M³ 3.000 Operator and Spotter Hours Rock Extraction
By Jackhammer MH/M³ 32.000

ROCK BLASTING
Rock Drilling MH/LM 1.000 Operator and Spotter Hours Rock Extraction
Rock Demolition MH/M³ 0.450

ROCK EXTRACTION

437475391.xls Page 8
Rock Extraction MH/M³ - Use 1.25 times value in Operator and Spotter Hours
machine excavation

437475391.xls Page 9
GENERAL CONSTRUCTION / CIVIL WORKS

MAIN WORK AND ACTIVITY DESCRIPTION

SITE WORK (EARTHWORK) UNIT PARAMETER REMARKS INCLUDED EXCLUDED


BASE COURSES / SOIL FILLING / BACKFILLING TAMPING MACHINE
MANUAL BASE FILLING/BACKFILLING & COMPACTING Up to 95% maximum
For Trenches MH/M³ 1.890 density of layer not
exceeding 300 mm thk
For Footing & Foundation MH/M³ 1.890 Apply 1.2 factor for layer
not exceeding 150mm
For Open - 8 ft wide & up Excavation MH/M³ 1.890 thk

MACHINE BASE FILLING/BACKFILLING & COMPACTING VIBRO ROLLER


For Trenches MH/M³ 0.460 Up to 95% maximum Hauling & disposing of spoils to w/n Grading & levelling of disposal area
density of layer not 50M haul distance only. if required
For Footing & Foundation MH/M³ 0.460 exceeding 300 mm thk
Apply 1.2 factor for layer
For Open - 8 ft wide & up Excavation MH/M³ 0.140 not exceeding 150mm
thk
DISPOSAL
Disposal MH/M³ 0.060 Hauling & disposing of spoils to w/n
50M haul distance only.

SITE WORK (SLOPE PROTECTION & EROSION CONTROL) UNIT PARAMETER REMARKS INCLUDED EXCLUDED
RIPRAP
RIP-RAPPING W/OUT GROUT Material hauling from laydown area. Slope preparing & leveling to furnished
6" ~ 12" ø boulders MH/M² gradeline.
16" ~ 24" ø boulders MH/M² Setting up gabion baskets.
30" ~ 36" ø boulders MH/M²
Placing & setting of boulders.
RIP-RAPPING W/OUT GROUT Mixing of grout & gunite matl's
6" ~ 12" ø boulders MH/M³ 3.500
16" ~ 24" ø boulders MH/M³ 5.000 Setting up & clearing of guniting
30" ~ 36" ø boulders MH/M³ 6.000 equipment

GABION BASKET ENCASED BOULDERS MH/M³ 4.300 Placing of 25 mm top soil for
sodding.
ROCK EMBANKMENT W/OUT GROUT MH/M³ 3.000

SLOPE SODDING MH/M² 0.320

SLOPE PAVING (Guniting) MH/M² 1.790

437475391.xls Page 10
437475391.xls Page 11
GENERAL CONSTRUCTION / CIVIL WORKS

MAIN WORK AND ACTIVITY DESCRIPTION

SITE WORK (PILES AND CAISSONS) UNIT PARAMETER REMARKS INCLUDED EXCLUDED
DRIVEN PILES
PRE-CAST CONCRETE PILES Pile hooking-on, pulling into leads & Soil excavtion works & pouring of
10" Square Piles MH/LM 0.040 cutting-off above dowels. concrete pile caps.
12" Square Piles MH/LM 0.050 1. Testing
14" Square Piles MH/LM 0.060 Setting-up & clearing of pile driving 2. Splicing
16" Square Piles MH/LM 0.070 equipment 3. Cutting
18" Square Piles MH/LM 0.070 4. Batter piling
WOOD PILES 50T Crane pile driving eqpt. feeder 5. Off-shore piling
10" Square Piles MH/LM - crane
12" Square Piles MH/LM - assume level at site Preparation of platform if
14" Square Piles MH/LM - no underground obstruction necessary
16" Square Piles MH/LM -
18" Square Piles MH/LM -
STEEL "H", "I" & "SHELL" PILES
8" HP, I, or SHELL Piles MH/LM 0.040
10" HP, I, or SHELL Piles MH/LM 0.040
12" HP, I, or SHELL Piles MH/LM 0.040
14" HP, I, or SHELL Piles MH/LM 0.040

SITE WORK (PAVING AND SURFACING) UNIT PARAMETER REMARKS INCLUDED EXCLUDED
PORTLAND CEMENT CONCRETE PAVING
CURBS & GUTTERS, RC SIDEWALK
Formwork (Curb/Gutter) MH/M² 2.700 Ground preparation works (e.g.
Formwork (Side Walk) MH/M² 2.100 levelling, trimming, etc.)
Rebarwork (Manual) MH/MT 80.000
Rebarwork (Mechanical) MH/MT 60.000
Concreting (Curb/Gutter) MH/M³ 14.000
Concreting (Side Walk) MH/M³ 3.900

SITE WORK (UTILITY PIPING MATERIALS) UNIT PARAMETER REMARKS INCLUDED EXCLUDED
UTILITY STRUCTURES
CHAMBERS, MANHOLES & BASINS
Formwork (Wood) MH/M² 3.200 Earthworks and dewatering
Formwork (Steel) MH/M² 2.750
Rebarwork (Manual) MH/MT 80.000
Rebarwork (Mechanical) MH/MT 60.000

437475391.xls Page 12
Concreting (Bagger-MIxed) MH/M³ 12.000
Concreting (Ready-MIxed) MH/M³ 5.400
GENERAL CONSTRUCTION / CIVIL WORKS

MAIN WORK AND ACTIVITY DESCRIPTION

SITE WORK (SEWERAGE AND DRAINAGE) UNIT PARAMETER REMARKS INCLUDED EXCLUDED
STORM DRAINAGE
TRENCHES AND CULVERTS
Formwork (Wood) MH/M² 2.700 Earthworks and dewatering
Formwork (Steel) MH/M² 2.100
Rebarwork (Manual) MH/MT 80.000
Rebarwork (Mechanical) MH/MT 60.000
Concreting (Bagger-MIxed) MH/M³ 12.000
Concreting (Ready-MIxed) MH/M³ 5.400

SITE WORK (PONDS AND RESERVOIRS)


CONCRETE TANKS
Formwork (Wall) MH/M² 3.100 Earthworks and dewatering
Formwork (Slab) MH/M² 2.700
Rebarwork (Manual) MH/MT 80.000
Rebarwork (Mechanical) MH/MT 60.000
Concreting (Bagger-MIxed) MH/M³ 16.000
Concreting (Ready-MIxed) Wall MH/M³ 5.300
Concreting (Ready-MIxed) Slab MH/M³ 4.100

437475391.xls Page 13
GENERAL CONSTRUCTION / CIVIL WORKS

MAIN WORK AND ACTIVITY DESCRIPTION

CONCRETE(FORMWORK FOR CONCRETE) UNIT PARAMETER REMARKS INCLUDED EXCLUDED


STRUCTURAL CAST-IN-PLACE CONCRETE FORMS
STEEL FORMS/PANEL (PRE-FABRICATED) Material sorting and hauling from Placing of reinforcing bars & pouring
Footings & Foundations MH/M² 2.700 Manhours do not include stockpile. of concrete.
Pile Caps MH/M² 2.100 extra time required when Blanking, sleeving, form oil coating Shop fabrication of steel forms
Grade Beams MH/M² 1.200 structures have recesses, & stripping.
Ground Slabs & Pavements MH/M² 1.500 trenches, pads, sumps, Setting-up & clearing of pertinent Setting-up & clearing of scaffoldings.
Columns MH/M² 3.300 grooves, chamfers, falseworks.
Elevated Beams & Girders MH/M² 2.800 openings, depressed areas
Walls MH/M² 2.700 and complicating features. Note : "SM" area of formworks shall only be the concrete surface area that needs
Elevated Slabs and Roof Decks MH/M² 2.700 to be fully covered and firmly secured during concrete pouring. Total area of
Stairs & Railings MH/M² 3.500 formworks shall include whatever stiffeners, bracing, supports and holding
Concrete Stack/Pit MH/M² 3.000 stakes required to firmly secure it in-place.
Elevator Shaft/ Core Walls MH/M² 2.700 Tower Crane System
Phenolic plywood w/ steel frame.
WOODEN FORMS
Formwork (Wall) MH/M² 3.100 Same as above except that wooden Placing of reinforcing bars & pouring
Formwork (Slab) MH/M² 2.700 of concrete.
Rebarwork (Manual) MH/M² 80.000
Rebarwork (Mechanical) MH/M² 60.000 Setting-up & clearing of scaffoldings.
Concreting (Bagger-MIxed) MH/M² 16.000
Concreting (Ready-MIxed) Wall MH/M² 5.300
Concreting (Ready-MIxed) Slab MH/M² 4.100

CONCRETE(CONCRETE REINFORCEMENT FAB'N & INST'LN) UNIT PARAMETER REMARKS INCLUDED EXCLUDED
REINFORCING STEEL BAR, MANUAL CUT & BEND
Footings & Foundations MH/MT 70.000 Material sorting and hauling from Placing of formworks & pouring
Pile Caps MH/MT 70.000 stockpile. of concrete.
Grade Beams MH/MT 80.000
Ground Slabs MH/MT 80.000 Fabrication & installation of steel
Columns MH/MT 80.000 spacers or steel chairs.
Elevated Beams & Girders MH/MT 80.000
Walls MH/MT 80.000
Elevated Slabs and Roof Decks MH/MT 80.000
Topping on Pre-cast T-joist MH/MT 80.000
Stairs & Railings MH/MT 80.000
Concrete Stack MH/MT 80.000

437475391.xls Page 14
437475391.xls Page 15
GENERAL CONSTRUCTION / CIVIL WORKS

MAIN WORK AND ACTIVITY DESCRIPTION

CONCRETE(CONCRETE REINFORCEMENT FAB'N & INST'LN) UNIT PARAMETER REMARKS INCLUDED EXCLUDED
REINFORCING STEEL BAR, MANUAL CUT & BEND
Footings & Foundations MH/MT 50.000 Mechanical Rebar Bender Same as above Same as above
Pile Caps MH/MT 50.000 & Rebar Cutter
Grade Beams MH/MT 50.000
Ground Slabs MH/MT 50.000
Columns MH/MT 60.000
Elevated Beams & Girders MH/MT 60.000
Walls MH/MT 60.000
Elevated Slabs and Roof Decks MH/MT 50.000
Topping on Pre-cast T-joist MH/MT 50.000
Stairs & Railings MH/MT 75.000
Concrete Stack/Pit MH/MT 60.000
Core Walls MH/MT 70.000
WELDED WIRE FABRIC (WWF)
Size 4/4 x 4" x 4" MH/M² 0.050 Material Sorting and hauling from Placing of formworks & pouring of
Size 6/6 x 4" x 4" MH/M² 0.050 Stockpile. concrete.
Size 4/4 x 6" x 6" MH/M² 0.050
Size 6/6 x 6" x 6" MH/M² 0.050 Fabrication & installation of spacers.
Size 4/4 x 8" x 8" MH/M² 0.050

CONCRETE(CONCRETE ACCESSORIES) UNIT PARAMETER REMARKS INCLUDED EXCLUDED


INSERTS (EMBEDDED STEEL)
ANCHOR BOLT
Size 1/2" ø (12.7 mm) MH/EA 0.280 Preparing templates, setting-on Pouring of concrete.
Size 5/8" ø (15.9 mm) MH/EA 0.330 sleeves & securing embeds in-place.
Size 3/4" ø (19.0 mm) MH/EA 0.380
Size 7/8" ø (22.2 mm) MH/EA 0.530 Measuring & checking specified setting
Size 1" ø (25.4 mm) MH/EA 0.580 clearances & tolerances on critical
Size 1-1/8" ø (28.5 mm) MH/EA 0.600 steel embeds.
Size 1-3/16" ø (30.2 mm) MH/EA 0.620
Size 1-1/4" ø (31.8 mm) MH/EA 0.650 Setting & clearing of false works.
Size 1-5/16" ø (33.3 mm) MH/EA 0.680
Size 1-3/8" ø (35.0 mm) MH/EA 0.680 Providing protections for bolt threads
Size 1-7/16" ø (36.5 mm) MH/EA 0.700 before concrete pouring.
Size 1-1/12" ø (38.1 mm) MH/EA 0.700
Size 1-9/16" ø (40.0 mm) MH/EA 0.720
Size 1-5/8" ø (41.3 mm) MH/EA 0.750

437475391.xls Page 16
Size 1-11/16" ø (42.9 mm) MH/EA 0.780

GENERAL CONSTRUCTION / CIVIL WORKS

MAIN WORK AND ACTIVITY DESCRIPTION

CONCRETE(CONCRETE ACCESSORIES) UNIT PARAMETER REMARKS INCLUDED EXCLUDED

Size 1-3/4" ø (44.5 mm) MH/EA 0.800


Size 1-13/16" ø (46.0 mm) MH/EA 0.800
Size 1-7/8" ø (47.6 mm) MH/EA 0.800
Size 1-15/16" ø (49.2 mm) MH/EA 0.800
Size 2" ø (50.8 mm) MH/EA 0.800

EXPANSION AND CONSTRUCTION JOINTS MH/LM -

WATERSTOPS MH/LM 0.140

CONCRETE(CAST IN PLACE CONCRETE) UNIT PARAMETER REMARKS INCLUDED EXCLUDED


STRUCTURAL CONCRETE
BAGGER MIXED CONCRETE Manhours do not include Material hauling from stockpile Placing Re-bars and formworks.
Footings & Foundations MH/M³ 12.000 extra time to form plinths, 50 M away.
Pile Caps MH/M³ 12.000 set reinforcing steel dowels
Grade Beams MH/M³ 12.000 support, place templates Levelling to flatness and plumbness Setting of joint filler, construction
Ground Slabs w/ integral topping MH/M³ 12.000 for anchor bolts. mixing, handling, curing and dressing. joint, expansion joint.
Ground Slabs w/ separate topping MH/M³ 12.000
Columns MH/M³ 14.000 Concrete surface shall be Setting-up and clearing of shoring and Cement mortar plastering, finishing,
Elevated Beams & Girders MH/M³ 14.000 straight to finish. falseworks. grouting and fireproofing works.
Walls MH/M³ 14.000
Elevated Slabs w/ integral topping MH/M³ 14.000 2 ~ 3 Bagger Mixer
Elevated Slabs w/ separate topping MH/M³ 14.000 Concrete Vibrator.
Topping on Pre-cast T-joist MH/M³ 12.000
Stairs & Railings MH/M³ 12.000
Concrete Stack/Pit MH/M³ 16.000
BATCH PLANT & TRANSIT MIXED CONCRETE
Footings & Foundations MH/M³ 4.100 Manhours do not include Levelling to flatness and plumbness Placing Re-bars and formworks.
Pile Caps MH/M³ 4.000 extra time to form plinths,
Grade Beams MH/M³ 3.600 set reinforcing steel dowels Setting-up and clearing of shoring and
Ground Slabs w/ integral topping MH/M³ 4.000 support, place templates falseworks. Setting of joint filler, construction
Ground Slabs w/ separate topping MH/M³ 3.600 for anchor bolts. joint, expansion joint.
Columns MH/M³ 5.400
Elevated Beams & Girders MH/M³ 5.000 Concrete surface shall be Concrete Vibrator Cement mortar plastering, finishing,

437475391.xls Page 17
Walls MH/M³ 4.600 straight to finish. grouting and fireproofing works.
Elevated Slabs w/ integral topping MH/M³ 4.800
Elevated Slabs w/ separate topping MH/M³ 4.100
GENERAL CONSTRUCTION / CIVIL WORKS

MAIN WORK AND ACTIVITY DESCRIPTION

CONCRETE(CAST IN PLACE CONCRETE) UNIT PARAMETER REMARKS INCLUDED EXCLUDED

Topping on Pre-cast T-joist MH/M³ 4.200


Stairs & Railings MH/M³ 5.200
Concrete Stack/Pit including stair walls MH/M³ 4.500
Elevator Shaft / Core Wall MH/M³ 5.500

SPECIALLY PLACED CONCRETE


FIREPROOFING WORKS ON COLUMN
Round Sections MH/M³ 63.000 Material hauling from stockpile Placing, stripping of formworks.
Square Sections MH/M³ 50.400 50 M away.
"H" Shape Sections MH/M³ 48.200
Placing of wiremesh & wire laths. Welding of anchor studs
ON CROSS BRACING
Sections MH/M³ - Setting-up and clearing of falseworks.
"H" Shape Sections MH/M³ -
"L" Shape Sections MH/M³ -

ON BEAMS AND GIRDERS


Round Sections MH/M³ -
Square Sections MH/M³ -
"H" Shape Sections MH/M³ -
"L" Shape Sections MH/M³ -

CONCRETE(CEMENTITIOUS DECKS AND TOPPINGS) UNIT PARAMETER REMARKS INCLUDED EXCLUDED


CONCRETE & ROAD TOPPING WORKS
FLOOR, GROUND SLAB & PAVEMENT TOPPING Material hauling from stockpile Concreting & preparing of road sub
Portland Cement Mortar Topping (Smooth Finish) MH/M² 1.400 50 M away. base and basefill.
Metallaic Hardener Topping MH/M² 1.200
Bituminous Asphalt Topping MH/M² 0.850 Mixing and steel trowel finishing

PLATFORM, DECK AND ELEVATED SLAB TOPPING


Portland Cement Mortar Topping (Smooth Finish) MH/M² 1.200
Metallaic Hardener Topping MH/M² 1.200

437475391.xls Page 18
Pea Gravel / Pebble Toping MH/M² 3.490

437475391.xls Page 19
GENERAL CONSTRUCTION / CIVIL WORKS

MAIN WORK AND ACTIVITY DESCRIPTION

CONCRETE(FOUNDATION GROUTING WORKS) UNIT PARAMETER REMARKS INCLUDED EXCLUDED

MANUAL MIXED & PLACED


Non-shrink Grout MH/M² 6.190 1" thk Material hauling from stockpile Concreting and anchor bolt setting.
Plain Cement Mortar Grout MH/M² 5.380 1" thk 50 M away.

MACHINE MIXED & PLACED Placing of bushing & Shims Grout Sample Testing.
Non-shrink Grout MH/M² -
Plain Cement Mortar Grout MH/M²

MASS CONCRETE (LEVELLING, LEAN, BUILDING)


MASS CONCRETE (LEVELLING, LEAN, BUILDING) MH/M³ 5.500

MASONRY UNIT PARAMETER REMARKS INCLUDED EXCLUDED


UNIT MASORY
REINFORCED UNIT MASONRY Up to 4M high from Material hauling from stockpile @ max. Surface plastering & architectural
4" x 8" x 16" CHB MH/M² 2.600 floor/and or grade level horizontal distance of 30 meters. finishing.
6" x 8" x 16" CHB MH/M² 2.800
8" x 8" x 16" CHB MH/M² 3.000 For medium & high rise Cement Grout & Fill Mixing. Surface preparing and painting works.
10" x 8" x 16" CHB MH/M² - building project apply a Lintel beams / columns.
factor of 1.20 Leveling & aligning.
NON-REINFORCED MASONRY Material hauling from whse or source to
4" x 8" x 16" CHB MH/M² 2.280 stockpile area & from ground level to
6" x 8" x 16" CHB MH/M² 2.300 upper floor level for high rise bldg.
8" x 8" x 16" CHB MH/M² 2.500
10" x 8" x 16" CHB MH/M² - Setting-up & clearing of scaffolds.

METALS UNIT PARAMETER REMARKS INCLUDED EXCLUDED


METAL FASTENING
Bolting
Brazing (Welding) MH/M²
Chemical Bonding Riveting MH/M²
Soldering MH/M²
Special Fasteners Welding MH/M²

437475391.xls Page 20
GENERAL CONSTRUCTION / CIVIL WORKS

MAIN WORK AND ACTIVITY DESCRIPTION

METALS UNIT PARAMETER REMARKS INCLUDED EXCLUDED

STRUCTURAL (METAL) STEEL Material shaking-out, sorting & hauling Concreting, anchor bolt setting,
Heavy Shape Sections (25 lbs./ft and up) MH/MT 45.000 Manhours do not include from laydown area. grouting & fireproofing works.
Medium & Light Shapes Sections ( 24 lbs./ft. & below) MH/MT 55.000 RT, UT & MPT, finish
Structural Steel Accessories MH/MT 60.000 painting and grouting Setting-up and clearing of falseworks Surface preparing and painting.
works. and temporary supports.
WELDED CONSTRUCTION Site drilling / punching of hole.
Heavy Shape Sections (25 lbs./ft and up) MH/MT 50.000 Full field welding of structural joints
Medium & Light Shapes Sections ( 24 lbs./ft. & below) MH/MT 60.000 & connections. Shop Fabricating works.
Structural Steel Accessories MH/MT 70.000
Grinding of weld joints.
WOODS AND PLASTICS (ROUGH CARPENTRY) UNIT PARAMETER REMARKS INCLUDED EXCLUDED

WOOD FRAMING Material sorting & hauling from stockpile Surface preparing and painting.
ASSEMBLED WOOD COMPONENT 50 M away.
Catwalk floor, 2" x 4" lumber MH/BF 0.020
Catwalk floor, 2" x 4" lumber MH/BF 0.020 Nailing-on ceiling corner mouldings & Setting-up & clearing of scaffolds.
partition baseboards, include ceiling
WOODEN FLOORS AND TILE CEMENTING WORKS corner mouldings and partition
Nailer Joist and Frames MH/BF 0.030 baseboards wherever applicable. Miscellaneous hardwares.
T & G Floor Lumbers 4" MH/M² 0.170
T & G Floor Lumbers 5" MH/M² 0.200
T & G Floor Lumbers 6" MH/M² 0.220

WOODS AND PLASTICS (ARCHITECTURAL WOODWORK) UNIT PARAMETER REMARKS INCLUDED EXCLUDED
CUSTOM CASEWORK
LUMBER COMPONENTS KILN DRIED S-4S MH/BF 0.040 Material sorting & hauling from stockpile Surface preparing and painting.
1/4" Plywood Componets MH/EA 0.420 50 M away.
1/2" Plywood Componets MH/EA 0.420 Nailing-on ceiling corner mouldings & Setting-up & clearing of scaffolds.
3/4" Plywood Componets MH/EA 0.420 partition baseboards, include ceiling
1" Plywood Componets MH/EA 0.420 corner mouldings and partition Placing doors and windows with
baseboards wherever applicable. miscellaneous hardwares.
PANEL FORMS
WOODEN WALLS & PARTITIONS
Nailer Frames & Furring MH/BF 0.030
Decorative Panel Frames MH/BF 0.030
Door Heads and Jambs MH/BF 0.040

437475391.xls Page 21
Window Heads, Sills and Jambs MH/BF 0.040

GENERAL CONSTRUCTION / CIVIL WORKS

MAIN WORK AND ACTIVITY DESCRIPTION

WOODS AND PLASTICS (ARCHITECTURAL WOODWORK) UNIT PARAMETER REMARKS INCLUDED EXCLUDED

Plywood Boards, nailed on 4' x 8' MH/M² 0.140


Plywood Boards, nailed on 2' x 8' MH/M² 0.140
Plywood Boards, nailed on 1' x 8' MH/M² 0.140
T & G Wall Lumber 4" MH/M² 0.170
T & G Wall Lumber 5" MH/M² 0.200
T & G Wall Lumber 6" MH/M² 0.220
CEILING WORKS
Nailer Frames & Furring MH/BF 0.040
Decorative Panel Frames MH/BF 0.040
Plywood Boards, nailed on 4' x 8' MH/M² 0.160
Plywood Boards, nailed on 2' x 8' MH/M² 0.160
Plywood Boards, nailed on 1' x 8' MH/M² 0.160
Board tiles, nailed-on 24" x 24" MH/M² 0.220
Board tiles, nailed-on 18" x 18" MH/M² 0.220
Board tiles, nailed-on 12" x 12" MH/M² 0.220
Board tiles, on tee runners 24" x 24" MH/M² 0.220
Board tiles, on tee runners 18" x 18" MH/M² 0.220
Board tiles, cemented-on 24" x 24" MH/M² 0.250
Board tiles, cemented-on 18" x 18" MH/M² 0.250
Board tiles, cemented-on 12" x 12" MH/M² 0.250
WOODEN STAIRS AND RAILINGS Material sorting & hauling from stockpile Surface preparing and painting.
Landing Frames & Flooring MH/BF 0.040 50 M away.
Stringers, Threads and Risers MH/BF 0.030 Nailing-on ceiling corner mouldings & Setting-up & clearing of scaffolds.
Banisters and Handrails MH/BF 0.040 partition baseboards, include ceiling
corner mouldings and partition Placing doors and windows with
baseboards wherever applicable. miscellaneous hardwares.
THERMAL & MOISTURE PROTECTION UNIT PARAMETER REMARKS INCLUDED EXCLUDED
WATER PROOFING
SHEET MEMBRANE WATERPROOFING
Bituminous Membrane MH/M² 0.720 2 ply - 3 mopping witdth: 100mm,
FLUID APPLIED WATERPROOFING - 125mm & 150mm
SHEET METAL WATERPROOFING -
DAMPROOFING
Vapor Barrier (Vinyl Sheet) MH/M² 0.030

437475391.xls Page 22
Vapor Barrier (Plastic Sheet) MH/M² 0.030
RETARDER MH/M² 0.030 Polyethylene - 0.04 to 0.10 mm thk

GENERAL CONSTRUCTION / CIVIL WORKS

MAIN WORK AND ACTIVITY DESCRIPTION

THERMAL & MOISTURE PROTC'N ( MFTRD ROOFING & SIDING) UNIT PARAMETER REMARKS INCLUDED EXCLUDED
MANUFACTURED ROOFING & SIDING
ROOF DECK & HOOD SHEETING WORKS
G.I. CORRUGATED SHEETS Material hauling from stockpile Erecting of Steel or Wooden structural
Gage 18 MH/M² 1.700 50 M away. Frameworks.
Gage 20 MH/M² 1.700 Sealing Overlaps
Gage 22 MH/M² 1.700 Pre-fabricated & installing roof
Gage 24 MH/M² 1.500 drainage & weather flashing.
Gage 26 MH/M² 1.500
Gage 28 MH/M² 1.500 Surface preparing and painting.
Gage 29 MH/M² 1.290
Gage 30 MH/M² 1.290 Insulation
req'd. (e.g.works & itswiremesh,
screens, supports ifetc.)
ALUMINUM CORRUGATED SHEETS
Gage 18 MH/M² 1.700 Setting-up & clearing of scaffolds.
Gage 20 MH/M² 1.700
Gage 22 MH/M² 1.700
Gage 24 MH/M² 1.500
Gage 26 MH/M² 1.500
Gage 28 MH/M² 1.500
Gage 29 MH/M² 1.290
Gage 30 MH/M² 1.290
RIB TYPE, LONG SPAN METAL SHEETS
Gage 18 MH/M² 1.700
Gage 20 MH/M² 1.700
Gage 22 MH/M² 1.700
Gage 24 MH/M² 1.500
Gage 26 MH/M² 1.500
Gage 28 MH/M² 1.500
Gage 29 MH/M² 1.290
Gage 30 MH/M² 1.290
PLAIN G.I. SHEETS (for ridge vent. Hoods)
Gage 18 MH/M² 1.800
Gage 20 MH/M² 1.800
Gage 22 MH/M² 1.800

437475391.xls Page 23
Gage 24 MH/M² 1.600
Gage 26 MH/M² 1.600
Gage 28 MH/M² 1.600
Gage 29 MH/M² 1.350
Gage 30 MH/M² 1.350

437475391.xls Page 24
GENERAL CONSTRUCTION / CIVIL WORKS

MAIN WORK AND ACTIVITY DESCRIPTION

THERMAL & MOISTURE PROTC'N ( MFTRD ROOFING & SIDING) UNIT PARAMETER REMARKS INCLUDED EXCLUDED

ASBESTOS CORRUGATED SHEETS


3/16" Thick MH/M² 1.290
1/4" Thick MH/M² 1.290

WALL AND HOOD SIDE SHEETING WORKS


ALUMINUM CORRUGATED SHEETS Material hauling from stockpile Setting-up & clearing of scaffolds.
Gage 18 MH/M² 1.610 50 M away. Frameworks.
Gage 20 MH/M² 1.610 Sealing Overlaps
Gage 22 MH/M² 1.610 Pre-fabricating & installing roof
Gage 24 MH/M² 1.610 drainage & weather flashing.
Gage 26 MH/M² 1.610
Gage 28 MH/M² 1.610 Surface preparing and painting.
Gage 29 MH/M² 1.610
Gage 30 MH/M² 1.610 Setting-up & clearing of scaffolds.

ASBESTOS CORRUGATED SHEETS


3/16" Thick MH/M² -
1/4" Thick MH/M² -

PLASTIC ASBESTOS CORRUGATED SHEETS


3/16" Thick MH/M² -
1/4" Thick MH/M² -
3/8" Thick MH/M² -

G.I. CORRUGATED SHEETS


Gage 18 MH/M² 1.610
Gage 20 MH/M² 1.610
Gage 22 MH/M² 1.610
Gage 24 MH/M² 1.610
Gage 26 MH/M² 1.610
Gage 28 MH/M² 1.610
Gage 29 MH/M² 1.610
Gage 30 MH/M² 1.610

437475391.xls Page 25
GENERAL CONSTRUCTION / CIVIL WORKS

MAIN WORK AND ACTIVITY DESCRIPTION

THERMAL & MOISTURE PROTC'N ( MFTRD ROOFING & SIDING) UNIT PARAMETER REMARKS INCLUDED EXCLUDED
RIB TYPE, LONG SPAN METAL SHEETS
Gage 18 MH/M² 1.610
Gage 20 MH/M² 1.610
Gage 22 MH/M² 1.610
Gage 24 MH/M² 1.610
Gage 26 MH/M² 1.610
Gage 28 MH/M² 1.610
Gage 29 MH/M² 1.610
Gage 30 MH/M² 1.610
PLAIN G.I. SHEETS (for ridge vent. Hoods)
Gage 18 MH/M² -
Gage 20 MH/M² -
Gage 22 MH/M² -
Gage 24 MH/M² -
Gage 26 MH/M² -
Gage 28 MH/M² -
Gage 29 MH/M² -
Gage 30 MH/M² -

THERMAL & MOISTURE PROTC'N ( FLASHING & SHEET METAL) UNIT PARAMETER REMARKS INCLUDED EXCLUDED
FLASHING AND ROOFING DRAINAGE (TINSMITH) WORKS
Sheet Metal, Edge Gutters MH/LM 0.300 Material hauling from stockpile Erecting of Steel or wooden
Sheet Metal, Center Gutters & Ridge Rolls MH/LM 0.300 50 M away. structural frameworks.
Sheet Metal, Roof & Wall Flashing MH/LM 0.300
Sheet Metal, Downspouts MH/LM 0.500 On site pre-fabricating (in sections) of Roof & wall sheeting works.
Asbestos pre-formed Gutters MH/LM 0.300 pertinent sheet metal items.
Asbestos pre-formed Flashing MH/LM 0.300 Surface preparing & painting works.
Asbestos pre-formed Ridge Rolls MH/LM 0.300 Setting-up and clearing of metal
Asbestos or PVC Downspouts MH/LM 0.500 forming machines. Setting-up & clearing of scaffolds.

DOORS & WINDOWS UNIT PARAMETER REMARKS INCLUDED EXCLUDED


METAL DOORS & FRAMES
STEEL DOORS AND FRAMES Material uncrating, sorting and hauling Preparing, setting and placing of
Metal - Hollow Core, Hinges Type MH/M² 10.600 from stockpile 50m away. head jamb and sill.
Metal - Hollow Core, Slide Type MH/M² 10.600 Surface preparing & painting works.
Setting of glass and glazing works. Setting-up & clearing of scaffolds.
All repairs and modification work as

437475391.xls Page 26
Chipping, patching maybe req'd on damaged item or for
Sealant non-conformance to technical specs.

437475391.xls Page 27
GENERAL CONSTRUCTION / CIVIL WORKS

MAIN WORK AND ACTIVITY DESCRIPTION

DOORS & WINDOWS UNIT PARAMETER REMARKS INCLUDED EXCLUDED


WOOD DOORS
WOODEN DOORS AND FRAMES
Wood - Hollow Core, Hinged Type MH/M² 9.500
Wood Framed Louvers Hinged Type MH/M² 9.500
Wood Solid Paneled, Hinged Type MH/M² 9.500

SPECIAL DOORS
Glass Aluminum Casement Hinged Type MH/M² 10.600
Screen Aluminum Casement Hinged Type MH/M² 10.600
Glass Aluminum Casement Slide Type MH/M² 10.600
Metal-Rolled up Type MH/M² 10.600

METAL WINDOWS WITH HARDWARES


STEEL WINDOWS
Glass, Steel Casement Hinged Type MH/M² 3.200
Metal Jalousie, Fixed Metal Frame MH/M² 3.200

ALUMINUM WINDOWS
Glass, Aluminum Casement Hinged Type MH/M² 2.700
Glass Jalousie, Aluminum Frame MH/M² 2.700

FINISHES UNIT PARAMETER REMARKS INCLUDED EXCLUDED


LATH AND PLASTER
PORTLAND CEMENT PLASTER
VERTICAL SURFACE PLASTERING
Flat Surface MH/M² 2.200 Material Hauling from stockpile Surface preparing & painting works.
Curved (Long Radius) Surface MH/M² 2.300
Curved (Short Radius) Surface MH/M² 2.400 Mixing and steel trowel finishing Setting-up & clearing of scaffolds.
Outside Straight Corners MH/LM 1.200
Outside Curved Corners MH/LM 1.300 Placing of wire lath & mesh wire for Concreting & concrete hollow block
wood surface mortar plastering. laying.
HORIZONTAL, TOP SURFACE PLASTERING
Flat Surface MH/M² 2.100 Roughing-off or chipping cured conc.
Curved (Long Radius) Surface MH/M² 2.200 surface prior to plastering.
Curved (Short Radius) Surface MH/M² 2.300
Outside Straight Corners MH/LM 1.100

437475391.xls Page 28
Outside Curved Corners MH/LM 1.200

437475391.xls Page 29
GENERAL CONSTRUCTION / CIVIL WORKS

MAIN WORK AND ACTIVITY DESCRIPTION

FINISHES UNIT PARAMETER REMARKS INCLUDED EXCLUDED

HORIZONTAL, OVERHEAD SURFACE PLASTERING


Flat Surface MH/M² 3.000
Curved (Long Radius) Surface MH/M² 3.200
Curved (Short Radius) Surface MH/M² 3.500
Outside Straight Corners MH/LM 2.000
Outside Curved Corners MH/LM 2.200
CERAMIC TILES
ON FLOOR SURFACES Material uncrating, sorting and hauling Concrete laying & hollow concrete
Size 3" x 3" Ceramic Mosaic Tiles MH/M² 2.900 from stockpile 50m away. block laying.
Size 4" x 4" Ceramic Mosaic Tiles MH/M² 2.900
Size 8" x 8" Ceramic Mosaic "Sheet" Tiles MH/M² 2.900 Grout mixing, plastering & levelling Setting-up & clearing of scaffolds.
Size 12" x 12" Ceramic Mosaic "Sheet" Tiles MH/M² 2.900
Size 12" x 12" Cement or Mineral Tiles MH/M² 2.900 Cove, nosing, stretcher, corner, cap &
trim tiles included
ON WALL SURFACES
Size 3" x 3" Ceramic Mosaic Tiles MH/M² 3.200
Size 2" x 4" Ceramic Mosaic Tiles MH/M² 3.200
Size 4" x 4" Ceramic Mosaic Tiles MH/M² 3.200
Size 12" x 12" Ceramic Mosaic "Sheet" Tiles MH/M² 3.200
SPECIAL WALL SURFACES
WALL MASONRY FINISH
Granolithic Finish MH/M² 3.500
Marble Crazy Cut Finish MH/M² 4.500
Pebble Washout Finish MH/M² 4.000
Glasse Washout Finish MH/LM 4.000
Sandblast Finish MH/LM 2.000
Synthetic Adobe Finish MH/LM 4.500
Anay Finish MH/LM 2.500
SPECIAL CEILING SURFACES
CEILING MASONRY FINISH
Sandblast Finish MH/M² -
Anay Finish MH/M² -
WOOD FLOORING
Parquet Tiles, Cemented-on MH/M² 2.500
Vinyl Bonded Tiles, Cemented-on MH/M² 2.500

437475391.xls Page 30
437475391.xls Page 31
GENERAL CONSTRUCTION / CIVIL WORKS

MAIN WORK AND ACTIVITY DESCRIPTION

FINISHES UNIT PARAMETER REMARKS INCLUDED EXCLUDED

STONE FLOORING
Pebble Washout Finish MH/M² 4.000 Material uncrating, sorting and hauling Concrete laying & hollow concrete
Marble Crazy Cut Finish MH/M² 4.500 from stockpile 50m away. block laying.
Granolithic Finish MH/M² 3.500
Grout mixing, plastering & levelling Setting-up & clearing of scaffolds.

GENERAL NOTES:
1. When execution of the project falls within the rainy season, multiply unit manhour by certain factor.
2. When work at site is within an area where there are existing structures and utilities, apply appropriate factor.
3. For other special conditions, consider some factors to offset difficulties of work.