Material consumption norms for various civil works

P.C.C. With Graded Stone Chips :


For 10 cu.m. Of Plane Cement Concrete Work with Graded Stone Chips

For M10 Grade :-(10 CU M)


Cement @ 1.54 cu.m or 45 Bags
Sand @ 4.62 cu.m or 133 Bags
Stone Chips @ 9.24 cu.m. or 266 Bags.

For M15 Grade :- (10 CUM )


Cement @ 2.2 cu.m or 65 Bags
Sand @ 4.4 cu.m or 127 Bags
Stone Chips @ 8.8 cu.m. or 254 Bags.

For M20 Grade :- (10 CUM)

Cement @ 2.8 cu.m or 81 Bags


Sand @ 4.2 cu.m or 121 Bags
Stone Chips @ 8.4 cu.m. or 242 Bags.

For M25 Grade :- 10 CUM)


Cement @ 3.85 cu.m or 111 Bags
Sand @ 3.85 cu.m or 111 Bags
Stone Chips @ 7.7 cu.m. or 222 Bags.

P.C.C. With Brick Ballast or Brick Chips :


For 10 cu.m. Of Plane Cement Concrete Work with Brick Ballast

For M5 Grade :- 10 CUM


Cement @ 1.00 cu.m or 29 Bags
Sand @ 5.00 cu.m or 144 Bags
Brick Ballast @ 10.00 cu.m. or 288 Bags.

For M7.5 Grade :- 10 CUM)


Cement @ 1.18 cu.m or 34 Bags
Sand @ 4.74 cu.m or 137 Bags
Brick Ballast @ 9.48 cu.m. or 273 Bags.

For M10 Grade :- 10 CUM


Cement @ 1.23 cu.m or 36 Bags
Sand @ 4.92 cu.m or 142 Bags
Brick Ballast @ 9.85 cu.m. or 284 Bags.

For M15 Grade :- 10 CUM


Cement @ 2.29 cu.m or 66 Bags
Sand @ 4.57 cu.m or 132 Bags
Brick Ballast @ 9.14 cu.m. or 264 Bags.

R.C.C. With Graded Stone Chips : 10 CUM


For 10 cu.m. Of Reinforced Cement Concrete Work with Graded Stone Chips, The Amount Of Cement,
Sand, Stone Chips Required are same as that of the P.C.C.

Quantity Of Steel Required :- per cum of concrete


For Normal Slab, Chajja, Lintel = 785kg or 0.785 Ton
For Roof Slab = 1180kg or 1.18 Ton
For Stair = 1570kg or 1.57 Ton
For Column and Beams = 1960kg or 1.96 Ton

Quantity Of Binding ( Black Annealed Wire) Wire Required


For Normal Slab, Chajja, Lintel = 0.785kg
For Roof Slab = 1.18kg
For Stair = 1.57kg
For Column and Beams = 1.96kg\

Brickwork in Cement Mortar (1:6)


For 10 cu.m. Of Brickwork in Cement Mortar (1:6) The Consumption Of Materials are

With Modular Bricks


Bricks @ 5000 Nos.
Cement @ 0.504 cu.m. or 15 Bags
Sand @ 3.02cu.m. or 87 Bags

With Traditional Bricks


Bricks @ 4079 Nos.
Cement @ 0.313 cu.m. or 9 Bags
Sand @ 1.88cu.m. or 54 Bags

Brickwork in Cement Mortar (1:4)

With Modular Bricks


For 100 Sq.m.100mm thick Brickwork in Cement Mortar (1:4) The Consumption Of Materials are
Bricks @ 5000 Nos.
Cemnent @ 0.63 cu.m. or 19 Bags.
Sand @ 2.52 cu.m. or 73 Bags

With Traditional Bricks


For 100 Sq.m.127mm thick Brickwork in Cement Mortar (1:4) The Consumption Of Materials are
Bricks @ 5181 Nos.
Cement @ 0.80 cu.m. or 23 Bags.
Sand @ 3.20 cu.m. or 92 Bags

Materials Required For ASF, Plastering & Neat Cement


Here is how to become a Concrete Calculator by yourself for different types of concrete operation like
concrete floor , plaster wall , ceiling plaster, cement finishing etc. works.

Artificial Stone Flooring


The Quantity of materials required for 100 Sq.m. 25mm Thick Artificial Stone Flooring 3mm Topping is
Cement @ 0.859 or 25 Bags
Sand @ 0.97 cu.m or 28 Bags
Stone Chips (6mm and Down) @ 1.94 cu.m or 56 Bags
Cement and Sand Plastering
For 100 Sq.m Of Plastering the required Quantity Of Materials are :

With Cement Mortar (1:6)


12 mm thick
Cement = 0.274 cu.m or 8 Bags
Sand = 1.64 cu.m. or 48 Bags

15 mm thick
Cement = 0.342 cu.m. or 10 Bags
Sand = 2.05 cu.m. or 59 Bags

20 mm thick
Cement = 0.456 cu.m. or 13 Bags
Sand = 2.74 cu.m. or 79 Bags

With Cement Mortar (1:4)


10 mm thick
Cement = 0.319 cu.m. or 9 Bags
Sand = 1.29 cu.m. or 37 Bags

6 mm thick
Cement = 0.192 cu.m. or 6 Bags
Sand = 0.77 cu.m. 22 Bags

Neat Cement Punning


Quantity Of Materials Required for 100 Sq.m. Of Neat Cement Punning is as follows:-

1.5mm Thick
Cement = 0.186 cu.m. or 5.5 Bags

3mm Thick
Cement = 0.375 cu.m. or 11 Bags

6mm Thick
Cement = 0.750 cu.m. or 22 Bags