Testing and Commissionin

Commissioning activity with CSD


 380 KV GIS
 Sync Check completed
 FCT primary injection in progress

 115 KV GIS
 Interlock checking in progress. 95% completed.
 Preparation for 115kV GT Stability in progress.

 SAS
 SAS Open Loop for 13.8kV in Progress
 13.8kV Measurement completed.

 Fault recorder
 Completed.

CSD Punch list status


# Description Status A Status B Total
1 Cleared Items 208 58 266
2 Pending Items 116 263 379
3 Total 324 321 645