Sunteți pe pagina 1din 3

WORK SAFETY & HEALTH ANALYSIS WORK SHEET

TASK NAME: WORKING AT HEIGHT WITH CONTAINER. Date:


06/09/2015
TEAM: J. Pepple, L. Jumbo, G. Pepple, I. Kalio, F. Pullen.
Step Description of Hazard - potential Who / What Recommended Safe Condition/Activity
# Job Step incident Affected
1 Prepare container 1. Fall while accessing a height. Load / Personnel carrying 1.1. Ladder to be used for access to the top of containers and
for lifting out task. must be footed.
2. Incorrect lifting equipment. 1.2. Inertia reel to be attached to crane hook by 2 Ton SWL nylon
1.3. Retrieving line attached to inertia reel hook must be
effective.
1.3. The personnel working at height shall wear a safety harness
which shall be attached before he climbs the access ladder and
removed when the person ascends.
1.4. The retrieving line will let the reel retract and release when
required.
2.1. Rigging Equipment must be selected by a competent person
based on the SWL.
2.2. Use certified and correctly colour coded equipment.
2.3. Pre-use inspection by user.
2.4. Only competent personnel to carry out lifting task.
2.5. Competent crane operator to carry out crane operation.
2.6. Use proper PPE/hand glove/safety eye glass/safety boot.

Print Date 17/09/19 15:42 – Hardcopy only valid on Print Date Page 1 of 3
2 Lifting the 1.Overloaded container Load and personnel 1. Supervisor to confirm weight to Lifting team.
container carrying out the task
2. Corroded container Load and personnel 2. Supervisor confirms the integrity of the container before
carrying out the task loading and Lifting.

3. Moving loads from truck to Load/Personnel carrying 3.1 Tag line to be used at all times to control the load.
ground and vice versa. out task 3.2 Strap and Secure container prior to transportation.
3.3 Driver to follow approve route.
3.4 Use a helper when required to revers.

4. Dropped load Personnel carrying out the 4.1 Strap and Secure container prior to transportation.
task plus personnel 4.2 Do not work under suspended load.
around the area 4.3 Do not drop any item from container top use rope if required.
4.4 Barriers must be in place with warning signs.
4.5 Do not exceed the SWL of rigging equipment/accessories.
4.6 Competent persons to carry out the rigging activity and Crane
operation.
1.7 Secure tools and equipment to avoid the risk of objects being
dropped.
3 Landing the 1. Personnel Crushed Personnel carrying out the 1.1. Do not touch or go near the container before it has landed.
container between or under task.
containers 1.2. Ensure that container landing area is clear and safe to land
2. Poor condition of container.
container 1.3. Care must be taken when working off the trailer.
3. Open roof container 1.4. Use tag-line for easy control of container.
4. Damaged to content 1.5. Do not work under suspended load.
1.6. Do not exceed the SWL of rigging equipment/accessories.
1.7. Use proper PPE/hand glove/safety eye glass/safety boot.
2.1 Do not lift any container in poor condition
2.2 Inspect container prior to lifting
2.3 confirm PEQ/5 inspection tag prior to lift
3.1 Prior to lifting of open roof container team must be careful
3.2 secure ladder when accessing open roof container.
4.1 Ensure container door are closed and secured by
team/requestor prior to lift.

Print Date 17/09/19 15:42 – Hardcopy only valid on Print Date Page 2 of 3
4. Remove lifting 1.Trip hazards if left lying Personnel carrying out the 1.1Do not remove any piece of rigging gears attach to crane or
accessories around task. container without instruction of team lead.
1.2. Use proper PPE/hand glove/safety eye glass/safety boot.
2.1. Do not climb without the use of inertia reel.
2.2. fall arrestor must be attached to crane hook by 2 Ton SWL
2. Accessing container top nylon
2.3. Retrieving line attached to inertia reel hook must be effective
2.4. Vehicle to be available to receive remove rigging gears to
Workshops store.
2.5. Pre-check after use inspection.
3.1The Permit Holder shall check the PTW site graphics prior to
3 Conflicting Work Activities use
3.2 Ensure awareness of simultaneous operations going on in
safe work area

5 Transport 1. Transport Vehicles. (Motion) People 1.1Keys are to remain in the ignition with engine stopped when
(People) the vehicle is left unattended.
1.2On hearing Plant Alarm switch engine off and leave keys in
ignition.
1.3 Vehicle engine Shall not be left running when vehicle is
unattended.
1.4 Vehicle shall be packed so as not to block Fire Hydrants.

Print Date 17/09/19 15:42 – Hardcopy only valid on Print Date Page 3 of 3