Documente Academic
Documente Profesional
Documente Cultură
May 1, 2001
Hydrology is often defined as: "A science dealing Regardless of the size or cost of the drainage
with the properties, distribution, and circulation of feature the most important step prior to hydraulic
water on the surface of the land, in the soil and design is estimating the discharge (rate of runoff)
underlying rocks, and in the atmosphere." This is a or volume of runoff that the drainage facility will
very broad definition encompassing many be required to convey or control.
disciplines relating to water. The highway engineer While some hydrologic analysis is necessary in
is principally concerned with surface hydrology establishing the quantity of surface water that must
and controlling surface runoff. Controlling runoff be considered in the design of all highway drainage
includes the hydraulic design of drainage features facilities, the extent of such studies are to be
for both cross highway drainage (Chapter 820) and commensurate with the importance of the highway,
removal of runoff from the roadway (Chapter 830). the potential for damage to the highway, loss of
The runoff of water over land has long been studied property, and hazard to life associated with the
and some rather sophisticated theories and methods facilities.
have been proposed and developed for estimating The choice of analytical method must be a
flood flows. Most attempts to describe the process conscious decision made as each problem arises.
have been only partially successful at best. This is To make an informed decision, the highway
due to the complexity of the process and interactive engineer must determine:
factors. The random nature of rainfall, snowmelt,
and other sources of water further complicate the • What level of hydrologic analysis is
process. justified.
It should be understood that there are no exact • What data are available or must be
methods for hydrologic analysis. Different collected.
methods that are commonly used may produce • What methods of analysis are available
significantly different results for a specific site and including the relative strengths and
particular situation. weaknesses in terms of cost and accuracy.
Although hydrology is not an exact science, it is Cross drainage design, Chapter 820, normally
possible to obtain solutions which are functionally requires more extensive hydrologic analysis than is
acceptable to form the basis for design of highway necessary for roadway drainage design,
drainage facilities. Chapter 830. The well known and relatively
More complete information on the principles and simple "Rational Method" (see Index 819.2) is
engineering techniques pertaining to hydrology for generally adequate for estimating the rate or
transportation and highway engineers may be volume of runoff for the design of on-site roadway
found in FHWA Hydraulic Design Series (HDS) drainage facilities and removal of runoff from
No. 2, Hydrology. Key aspects of hydrologic highway pavements.
information and a general overview of hydrology
relevant to highway engineering are more fully 811.3 Peak Discharge
discussed in the AASHTO Highway Drainage Peak discharge is the maximum rate of flow of
water passing a given point during or after a
810-2 HIGHWAY DESIGN MANUAL
May 1, 2001
rainfall event. Peak discharge, often called peak categorized and briefly discussed in Topics 812
flow, occurs at the momentary "peak" of the through 814. It is important to recognize that the
stream's flood hydrograph. (See Index 816.5, factors discussed may exist concurrently within a
Flood Hydrograph.) watershed and their combined effects are very
difficult to quantify.
Design discharge, expressed as the quantity (Q) of
flow in cubic meters per second (m3/s), is the peak
discharge that a highway drainage structure is sized Topic 812 - Basin Characteristics
to handle. Peak discharge is different for every
storm and it is the highway engineer's 812.1 Size
responsibility to size drainage facilities and
structures for the magnitude of the design storm The size (area) of a drainage basin is the most
and flood severity. The magnitude of peak important watershed characteristic affecting runoff.
discharge varies with the severity of flood events Determining the size of the drainage area that
which is based on probability of exceedance (see contributes to flow at the site of the drainage
Index 811.4). The selection of design storm structure is a basic step in a hydrologic analysis
frequency and flood probability are more fully regardless of the method used to evaluate flood
discussed under Topic 818, Flood Probability and flows. The drainage area, expressed in hectares or
Frequency. square kilometers, is frequently determined from
field surveys, topographic maps, or aerial
811.4 Flood Severity photographs.
Snowpack and the rate at which snow melts will If channel storage is considered to be a significant
also be affected. A basin's orientation with respect factor, the assistance of an expert in combining the
to the direction of storm movement can affect a analysis of basin hydrology and stream hydraulics
flood peak. Storms moving upstream produce should be sought. The U.S. Army Corps of
lower peaks than storms tending to move in the Engineers has developed computer programs,
general direction of stream flow. HEC-1, HEC-HMS Flood Hydrograph Package
and HEC-RAS, Water Surface Profiles, for this
Topic 813 - Channel and type of analysis. For modeling complex water
surface profile problems, where one-dimensional
Floodplain Characteristics models fail, FHWA has developed the Finite
Element Surface Water Modeling System Two
813.1 General Dimensional Flow in a Horizontal Plane
Streams are formed by the gathering together of (FESWMS-2DH). See Topic 864.4(3).
surface waters into channels that are usually well
813.4 Hydraulic Roughness
defined. The natural or altered condition of the
channels can materially affect the volume and rate Hydraulic roughness represents the resistance to
of runoff and is a significant consideration in the flows in natural channels and floodplains. It affects
hydrological analysis for cross drainage design. both the time response of a drainage channel and
channel storage characteristics. The lower the
A useful reference relative to problems associated
roughness, the higher the peak discharge and the
with transverse and longitudinal highway
shorter the time of the resulting hydrograph. The
encroachments upon river channels and floodplains
total volume of runoff however is virtually
is the FHWA Training and Design Manual,
independent of hydraulic roughness.
"Highways in the River Environment - Hydraulic
and Environmental Design Considerations" Streamflow is frequently indirectly computed by
using Manning's equation, see Index 864.3.
813.2 Length and Slope Procedures for selecting an appropriate coefficient
of hydraulic roughness, Manning's "n", may be
The longer the channel the more time it takes for
found in the FHWA report, "Guide for Selecting
water to flow from the beginning of the channel to
Manning's Roughness Coefficient for Natural
the site under consideration. Channel length and
Channels and Flood Plains".
effective channel slope are important parameters in
determining the response time of a watershed to
813.5 Natural and Man-made Constrictions
precipitation events of given frequency.
Natural constrictions, such as gravel bars, rock
In the case of a wide floodplain with a meandering
outcrops and debris jams as well as artificial
main channel the effective channel length will be
constrictions such as diversion and storage dams,
reduced during flood stages when the banks are
grade-control structures, and other water-use
overtopped and flow tends more toward a straight
facilities may control or regulate flow. Their effect
line.
on the flood peak may be an important
consideration in the hydrologic analysis.
813.3 Cross Section
Flood peaks may be estimated by using data from 813.6 Channel Modifications
stream gaging stations and natural channel cross
Channel improvements such as channel-
section information.
straightening, flood control levees, dredging, bank
Although channel storage is usually ignored in the clearing and removal of obstructions tend to reduce
hydrologic analysis for the design of highway natural attenuation and increase downstream flood
drainage structures, channel cross section may peaks.
significantly affect discharge, particularly in wide
floodplains with heavy vegetation.
HIGHWAY DESIGN MANUAL 810-5
May 1, 2001
Much of the precipitation that falls in the Or from the following web-site:
mountainous areas of the state falls as frozen water http://co-ops.nos.noaa.gov/bench.html.
in the form of snow, hail, and sleet. Since frozen One of the most devastating forces affecting the
precipitation cannot become part of the runoff until coastline occurs when an astronomical high tide
melting occurs it is stored as snowpack until and a storm of hurricane proportion arrive on the
thawed by warmer weather. land at the same time. This is also true of the effect
Rain upon an accumulation of snow can cause a of a tsunami. A tsunami is a wave caused by an
much higher peak discharge than would occur from earthquake at sea. If shore protection were
rainfall alone. The parameters of snow which may designed to withstand the forces of a tsunami, it
need to be considered in quantifying peak flood would be extremely costly to construct. Since it
runoff are: would be so costly and the probability of
occurrence is so slight, such a design may not be
• Mean annual snowfall justified.
• Water content of snowpack Wind-waves directly affect coastal structures and
• Snowmelt rate cause dynamic changes in coastal morphology.
The U.S. Corps of Engineers collects and publishes
814.4 Evapo-transpiration data which may be used to predict size of Pacific
Coast wind-waves. Information pertaining to the
Evaporation and transpiration are two natural California coastline from the Mexican border north
processes by which water reaching the earth's to Cape San Martin can be obtained from:
surface is returned to the atmosphere as vapor. The
losses due to both phenomena are important to long U.S. Army Corps of Engineers
term hydrology and water balance in the watershed Los Angeles District
and are usually ignored in the hydrologic analysis P.O. Box 2711
for the design of highway drainage facilities. Los Angeles, CA 90053
(213) 688-5400
814.5 Tides and Waves For information from Cape San Martin to the
The combined effect of upland runoff and tidal Oregon border from:
action is a primary consideration in the design of U.S. Army Corps of Engineers
highway drainage structures and shore protection San Francisco District
facilities along the coastlines, on estuaries, and in 211 Main Street
river delta systems. San Francisco, CA 94105
The time and height of high and low water caused (415) 556-3582
by the gravitational attraction of the sun and moon Wind-waves are also generated on large inland
upon the earth's oceans are precisely predictable. bodies of water and their effect should be
Information on gravitational tides and tidal bench considered in the design of shoreline highway
marks for the California Coastline is available facilities.
from:
HIGHWAY DESIGN MANUAL 810-7
June 26, 2006
• Volume I. Short-Duration Precipitation Stream flow data are usually available as mean
Frequency Data daily flow or peak daily flow. Daily flow is a
measurement of the rate of flow in cubic meters per
• Volume II. Long-Duration Precipitation second (m3/s) for the 24-hour period from midnight
Data to midnight.
HIGHWAY DESIGN MANUAL 810-9
June 26, 2006
"Paleoflood" (ancient flood) data has been found • Filling surface depressions (puddles,
useful in extending stream gaging station records. swamps and ponds). As rain continues to
(See Topic 817 for further discussion on measuring fall, surface waters flow down slope
stream flow) toward an established channel or stream.
Rainfall data are collected by recording and non- Overland flow is surface waters which travel over
recording rain gages. Rainfall collected by vertical the ground as sheet flow, in rivulets and in small
cylindrical rain gages of about 200 mm in diameter channels to a watercourse.
is designated as "point rainfall".
816.3 Subsurface Flow
Regardless of the care and precision used, rainfall
measurements from rain gages have inherent and Waters which move laterally through the upper soil
unavoidable shortcomings. Snow and wind surface to streams are called "interflow" or
problems frequently interrupt rainfall records. "subsurface flow". For the purpose of highway
Extreme rainfall data from recording rain gage drainage hydrology, where peak design discharge
charts are generally underestimated. (flood peaks) are the primary interest, subsurface
flows are considered to be insignificant.
Rain gage measurements are seldom used directly Subsurface flows travel slower than overland flow.
by highway engineers. The statistical analysis
which must be done with precipitation While groundwater and subsurface water may be
measurements is nearly always performed by ignored for runoff estimates, their detrimental
qualified hydrologists and meteorologists such as effect upon highway structural section stability
those employed by the Department of Water cannot be overstated. See Chapter 840, Subsurface
Resources (DWR). The intensity-duration- Drainage.
frequency (IDF) tables and curves are the products 816.4 Detention and Retention
of rainfall measurement analyses which have direct
application to highway drainage design. Water which accumulates and ponds in low points
or depressions in the soil surface with no
815.6 Adequacy of Data possibility for escape as runoff is in retention
All hydrologic data that has been collected must be storage. Where water is moving over the land it is
evaluated and compiled into a usable format. in detention storage. Detained water, as opposed to
Experience, knowledge and judgment are an retained water, contributes to runoff.
important part of data evaluation. It must be
ascertained whether the data contains 816.5 Flood Hydrograph and Flood Volume
inconsistencies or other unexplained anomalies In response to a rainstorm the quantity of water
which might lead to erroneous calculations and flowing in a stream increases. The water level rises
conclusions that could result in the over design or and may continue to do so after rainfall ceases.
under design of drainage structures. The response of an affected stream, during and
after a storm event, can be pictured by plotting
Topic 816 - Runoff discharge against time to produce a flood
hydrograph. The principal elements of a typical
flood hydrograph are shown in Figure 816.5
816.1 General
Flood volume is the area under the flood
The process of surface runoff begins when hydrograph. Although flood volume is not
precipitation exceeds the requirements of: normally a consideration in the design of highway
• Vegetal interception.
• Infiltration into the soil.
810-10 HIGHWAY DESIGN MANUAL
June 26, 2006
drainage facilities, it is occasionally used in the For all-paved watersheds (e.g., parking lots,
hydrologic analysis for other design parameters. roadway travel lanes and shoulders, etc.) it is not
necessary to calculate a separate shallow
Information on flood hydrographs and methods to
concentrated flow travel time segment. Such flows
estimate the hydrograph may be found in Chapters
will typically transition directly from sheet flow to
6, 7 and 8 of HDS No. 2, Hydrology.
channel flow or be intercepted at inlets with either
no, or inconsequential lengths of, shallow
concentrated flow.
Figure 816.5 In many cases a minimum time of concentration
will have to be assumed as extremely short travel
Typical Flood Hydrograph times will lead to calculated rainfall intensities that
are overly conservative for design purposes. For
all-paved areas it is recommended that a minimum
time of concentration of 5 minutes be used. For
rural or undeveloped areas, it is recommended that
a minimum TC of 10 minutes be used for most
situations. However, for slopes steeper than
1V:10H, or where there is limited opportunity for
surface storage, a TC of 5 minutes should be
assumed.
Designers should be aware that maximum runoff
estimates are not always obtained using rainfall
intensities determined by the time of concentration
for the total area. Peak runoff estimates may be
obtained by applying higher rainfall intensities
from storms of short duration over a portion of the
816.6 Time of Concentration (Tc) and watershed.
Travel Time (Tt) (1) Sheet flow travel time. Sheet flow is flow of
Time of concentration is defined as the time uniform depth over plane surfaces and usually
required for storm runoff to travel from the occurs for some distance after rain falls on the
hydraulically most remote point of the drainage ground. The maximum flow depth is usually
basin to the point of interest. less than 20 - 30 mm. For unpaved areas, sheet
flow normally exists for a distance less than
An assumption made in some of the hydrologic 25 – 30 m. An upper limit of 91 m is
methods for estimating peak discharge, such as the recommended for paved areas.
Rational and NRCS Methods (Index 819.2), is that
maximum flow results when rainfall of uniform A common method to estimate the travel time
intensity falls over the entire watershed area and of sheet flow is based on kinematic wave
the duration of that rainfall is equal to the time of theory and uses the Kinematic Wave Equation:
concentration. Time of concentration (TC) is 3/5 3/5
typically the cumulative sum of three travel times, 6.92 L n
including: Tt = 2/5 3/10
i S
• Sheet flow
where
• Shallow concentrated flow
Tt = travel time in minutes.
• Channel flow
L = Length of flow path in meters.
S = Slope of flow in m/m.
HIGHWAY DESIGN MANUAL 810-11
July 1, 2008
Average velocities for the Upland Method can Selecting Manning's Roughness Coefficient for
be taken directly from Figure 816.6 or may be Natural Channels and Flood Plains".
calculated from the following equation: Generally, the channel roughness factor will be
much lower than the values for overland flow
V = kS1/2
with similar surface appearance.
Where S is the slope in percent and k (m/s) is
Culvert or Storm Drain Flow. Flow velocities
an intercept coefficient depending on land
in a short culvert are generally higher than they
cover as shown in Table 816.6B.
would be in the same length of natural channel
and comparable to those in a lined channel. In
Table 816.6B most cases, including short runs of culvert in
Intercept Coefficients for Shallow the channel, flow time calculation will not
materially affect the overall time of
Concentrated Flow concentration (Tc). When it is appropriate to
Land cover/Flow regime K separate flow time calculations, such as for
(m/s) urban storm drains, Manning's equation may be
Forest with heavy ground litter; hay 0.076 used to obtain flow velocities within pipes.
meadow The TR-55 library of equations for sheet flow,
Trash fallow or minimum tillage 0.152 shallow concentrated flow and open channel
cultivation; contour or strip cropped; flow is incorporated into the Watershed
woodland Modeling System (WMS) for Time of
Short grass pasture 0.213 Concentration Calculations using Triangulated
Cultivated straight row 0.274 Irregular Networks (TINs) and Digital
Nearly bare and untilled alluvial fans 0.305 Elevation Maps (DEMs).
Grassed waterway 0.457
Figure 816.6
(4) Maximum Historical Flood. "The maximum appropriate design flood frequency. Due
flood that has been recorded or experienced at consideration should be given to all the other factors
any particular highway location". This listed under Index 801.5. If the analysis is correct,
information is very desirable and where the highway drainage system will occasionally be
available is an indication that the flood of this overtaxed. The alternative of accommodating the
magnitude may be repeated at the project site. worst possible event that could happen is usually so
Hydrologic analysis may suggest that the costly that it may not be justified.
probability for recurrence of the "maximum
Highway engineers should understand that the
historical flood" is very small, less than 1%.
option to select a predetermined design flood
Nevertheless consideration should be given to
frequency is generally only applicable to new
sizing drainage structures to convey the
highway locations. Because of existing constraints,
"maximum historical flood".
the freedom to select a prescribed design flood
(5) Probable Maximum Flood. "The flood frequency may not exist for projects involving
discharge that may be expected from the most replacement of existing facilities. Caltrans policy
severe combination of critical meteorological relative to up-grading of existing drainage facilities
and hydrological conditions that are reasonably may be found in Index 803.3.
possible in the region". The "probable
Although the procedures and methodology
maximum flood" is generally not applicable to
presented in HEC 17, Design of Encroachments on
highway projects. The possibility of a flood of
Flood Plains Using Risk Analysis, are not fully
such rare magnitude, as used by the Corps of
endorsed by Caltrans, the circular is an available
Engineers, is applicable to projects such as
source of information on the theory of "least total
major dams, when consideration is to be given
expected cost (LTEC) design". Highway engineers
to virtually complete security from potential
are cautioned about applying LTEC methodology
floods.
and procedures to ordinary drainage design
problems. The Headquarters Hydraulics Engineer
818.2 Establishing Design Flood Frequency in the Division of Design should be consulted
There are two recognized alternatives to establishing before committing to design by the LTEC method
an appropriate highway drainage design frequency. since its use can only be justified and recommended
That is, by policy or by economic analysis. Both under extra-ordinary circumstances.
alternatives have merit and may be applied
exclusively or jointly depending upon general Topic 819 - Estimating Design
conditions or specific constraints.
Discharge
Application of traditional predetermined design
flood frequencies implies that an acceptable level of
819.1 Introduction
risk was considered in establishing the design
standard. Modern design concepts, on the other Before highway drainage facilities can be
hand, recommend that a range of peak flows be hydraulically designed, the quantity of run-off
considered and that the design flood be established (design Q) that they may reasonably be expected to
which best satisfies the specific site conditions and convey must be established. The estimation of peak
associated risks. A preliminary evaluation of the discharge for various recurrence intervals is
inherent flood-related risks to upstream and therefore the most important, and often the most
downstream properties, the highway facility, and to difficult, task facing the highway engineer. Refer to
the traveling public should be made. This Table 819.5A for a summary of methods for
evaluation will indicate whether a predetermined estimating design discharge.
design flood frequency is applicable or additional
study is warranted. 819.2 Empirical Methods
Highway classification is one of the most important Because the movement of water is so complex,
factors, but not the sole factor, in establishing an numerous empirical methods have been used in
810-16 HIGHWAY DESIGN MANUAL
June 26, 2006
Figure 819.2A
Runoff Coefficients for Undeveloped Areas
Watershed Types
Figure 819.2C
Regional Flood-Frequency Equations (1)
HIGHWAY DESIGN MANUAL 810-21
July 1, 2008
Figure 819.2D
Regional Flood Frequency Equations for California Regions within USGS
Southwestern United States Study*
*USGS Open File Report 93-419 (1994)
810-22 HIGHWAY DESIGN MANUAL
June 26, 2006
(3) National Resources Conservation Service programs are available which may be used to
(NRCS) Methods. The Soil Conservation systematically arrange data and perform the
Service's SCS (former title) National statistical computations.
Engineering Handbook, 1972, and their 1975,
Some common types of data groupings are as
"Urban Hydrology for Small Watersheds",
follows:
Technical Release 55 (TR-55), present a
graphical method for estimating peak • Magnitude
discharge. Most NRCS equations and curves • Time of Occurrence
provide results in terms of inches of runoff for
unit hydrograph development and are not • Geographic Location
applicable to the estimation of a peak design Several standard frequency distributions have been
discharge unless the design hydrograph is first studied extensively in the statistical analysis of
developed in accordance with prescribed hydrologic data. Those which have been found to
NRCS procedures. NRCS methods and be most useful are:
procedures are applicable to drainage areas less (1) Log-Pearson Type III Distribution. The
than 8 km2 (800 ha) and result in a design popularity of the Log-Pearson III distribution is
hydrograph and design discharge that are simply based on the fact that it very often fits
functionally acceptable to form the basis for the the available data quite well, and it is flexible
design of highway drainage facilities. enough to be used with a wide variety of
distributions. Because of this flexibility, the
819.3 Statistical Methods U.S. Water Resources Council recommends its
Statistical methods of predicting stream discharge use by all U.S. Government agencies as the
utilize numerical data to describe the process. standard distribution for flood frequency
Statistical methods, in general, do not require as studies.
much subjective judgment to apply as the The three parameters necessary to describe the
previously described deterministic methods. They Log-Pearson III distribution are:
are usually well documented mathematical
procedures which are applied to measured or • Mean flow
observed data. The accuracy of statistical methods • Standard deviation
can also be measured quantitatively. However, to • Coefficient of skew
assure that statistical method results are valid, the
method and procedures used should be verified by Log-Pearson III distributions are usually
an experienced engineer with a thorough plotted on log-normal probability graph paper
knowledge of engineering statistics. for convenience even though the plotted
frequency distribution may not be a straight
Analysis of gaged data permits an estimate of the line.
peak discharge in terms of its probability or
frequency of recurrence at a given site. This is (2) Log-normal Distribution. The characteristics
done by statistical methods provided sufficient data of the log-normal distribution are the same as
are available at the site to permit a meaningful those of the classical normal or Gaussian
statistical analysis to be made. Water Resources mathematical distribution except that the flood
Council Bulletin 17B, 1981, suggests at least 10 flow at a specified frequency is replaced with
years of record are necessary to arrant astatistical its logarithm and has a positive skew. Positive
analysis. The techniques of inferential statistics, the skew means that the distribution is skewed
branch of statistics dealing with the inference of toward the high flows or extreme values
population characteristics, are described in HDS (3) Gumbel Extreme Value Distribution. The
No. 2. characteristics of the Gumbel extreme value
Before data on the specific characteristics to be distribution (also known as the double
examined can be properly analyzed, it must be exponential distribution of extreme values) are
arranged in a systematic manner. Several computer that the mean flood occurs at the return period
HIGHWAY DESIGN MANUAL 810-23
June 26, 2006
Table 819.5A
Summary of Methods for Estimating Design Discharge
METHOD ASSUMPTIONS DATA NEEDS
Rational • Small catchment (< 1.3 km 2)
• Concentration time < 1 hour Time of Concentration
• Storm duration >or = concentration time Drainage area
• Rainfall uniformly distributed in time Runoff coefficient
and space Rainfall intensity
• Runoff is primarily overland flow
• Negligible channel storage
USGS Regional Regression • Catchment area limit varies by region
Equations: • Basin not located on floor of Sacramento or San Drainage area
Joaquin Valleys Mean annual precipitation
USGS Water-Resources • Peak discharge value for flow under natural Altitude index
Investigation 77-21* conditions unaffected by urban development and
little or no regulation by lakes or reservoirs
USGS Open-File Report • Ungaged channel
93-419**
NRCS (TR55) • Small or midsize catchment (< 8 km 2)
• Concentration time range from 0.1-10 hour (tabular 24-hour rainfall
hydrograph method limit < 2 hour) Rainfall distribution
• Runoff is overland and channel flow Runoff curve number
• Simplified channel routing Concentration time
• Negligible channel storage Drainage area
Unit Hydrograph (Gaged data) • Midsize or large catchment (0.4 –2500 km 2)
• Uniformity of rainfall intensity and duration Rainfall hyetograph and
NRCS unit Hydrograph • Rainfall-runoff relationship is linear direct runoff hydrograph for
• Duration of direct runoff constant for all uniform- one or more storm events
Synthetic Unit Hydrograph intensity storms of same duration, regardless of
differences in the total volume of the direct runoff. Drainage area and
• Time distribution of direct runoff from a given lengths along main channel
storm duration is independent of concurrent runoff to point on watershed divide
from preceding storms and opposite watershed
• Channel-routing techniques used to connect centroid (Synthetic Unit
streamflows Hydrograph)
Statistical (gage data) • Midsized and large catchments with stream gage 10 or more years of gaged
Log-Pearson Type III data flood records
• Appropriate station and/or generalized skew
Bulletin #17B – U.S. coefficient relationship applied
Department of the Interior • Channel storage
Basin Transfer of Gage Data • Similar hydrologic characteristics Discharge and area for
• Channel storage gaged watershed