CRONOGRAMA DE DESEMBOLSO ECONOMICO

OBRA: INSTALACIÓN DEL PUENTE MODULAR “SANTA ROSA” , DISTRITO DE SANTA ROSA, PROVINCIA DE PALLASCA
REGIÓN

PRESUPUESTO
Item Descripción Und. Metrado Precio (S/.) Parcial (S/.) TOTAL
MES 1 MES 2
01 OBRAS CIVILES PARA INSTALACION DE PUENTE MODULAR 215,103.61
01.01 OBRAS PROVISIONALES 10,132.94
01.01.01 CARTEL DE OBRA und 1.00 1,752.14 1,752.14 S/. 1,752.14 S/. 1,752.14
01.01.02 CAMPAMENTO m2 108.00 77.60 8,380.80 S/. 8,380.80 S/. 8,380.80
01.02 TRABAJOS PRELIMINARES 69,463.59
01.02.01 MOVILIZACION Y DESMOVILIZACION DE und 1.00 18,500.00 18,500.00 S/. 9,250.00 S/. 9,250.00 S/. 18,500.00
01.02.02 FLETE TERRESTRE glb 1.00 3,500.00 3,500.00 S/. 3,500.00 S/. 3,500.00
01.02.03 DEMOLICION DE ESTRIBOS DE CONCRET m3 50.00 293.87 14,693.50 S/. 14,693.50 S/. 14,693.50
01.02.04 DEMOLICION DE LA SUPERESTRUCTURA m3 50.00 293.87 14,693.50 S/. 14,693.50 S/. 14,693.50
01.02.05 CONTROL TOPOGRAFICO DE PROCESO C día 30.00 334.29 10,028.70 S/. 10,028.70 S/. 10,028.70
01.02.06 INSTALACION DE PASE PEATONAL PROVIC und 1.00 3,500.00 3,500.00 S/. 3,500.00 S/. 3,500.00
01.02.07 HABILITACION DE ACCESO PROVICIONAL m3 121.18 37.53 4,547.89 S/. 4,547.89 S/. 4,547.89
01.03 HABILITACION DE ACCESOS 2,513.18
01.03.01 RELLENO COMPACTADO PARA HABILITAC m3 16.00 50.10 801.60 S/. 801.60 S/. 801.60
01.03.02 AFIRMADO m3 22.50 76.07 1,711.58 S/. 1,711.58 S/. 1,711.58
01.04 MOVIMIENTO DE TIERRAS 7,278.38
01.04.01 EXCAVACION CON MAQUINARIA PARA DA m3 94.40 19.15 1,807.76 S/. 1,807.76 S/. 1,807.76
01.04.02 RELLENO COMPACTADO CON MATERIAL P m3 95.20 50.10 4,769.52 S/. 4,769.52 S/. 4,769.52
01.04.03 ELIMINACION DE MATERIAL EXCEDENTE D m3 61.50 11.40 701.10 S/. 701.10 S/. 701.10
01.05 CONCRETO SIMPLE 34,015.20
01.05.01 SOLADO DE CONCRETO e=2" 1:12 C.H m2 32.00 35.12 1,123.84 S/. 1,123.84 S/. 1,123.84
01.05.02 CONCRETO EN DADO DE ANCLAJE FC=240 m3 64.00 438.24 28,047.36 S/. 28,047.36 S/. 28,047.36
01.05.03 ENCOFRADO Y DESENCOFRADO EN DADO m2 80.00 60.55 4,844.00 S/. 4,844.00 S/. 4,844.00
01.06 CONCRETO ARMADO 23,720.27
01.06.01 PARAPETOS 6,351.35
01.06.01.01 CONCRETO EN PARAPETO FC=210 KG/ m3 3.84 487.07 1,870.35 S/. 1,870.35 S/. 1,870.35
01.06.01.02 ENCOFRADO Y DESENCOFRADO DE ES m2 25.60 76.56 1,959.94 S/. 1,959.94 S/. 1,959.94
01.06.01.03 ACERO DE REFUERZO fy=4,200 kg/cm2 kg 580.89 4.34 2,521.06 S/. 2,521.06 S/. 2,521.06
01.06.02 LOSA DE APROXIMACION 14,883.18
CRONOGRAMA DE DESEMBOLSO ECONOMICO
OBRA: INSTALACIÓN DEL PUENTE MODULAR “SANTA ROSA” , DISTRITO DE SANTA ROSA, PROVINCIA DE PALLASCA
REGIÓN

PRESUPUESTO
Item Descripción Und. Metrado Precio (S/.) Parcial (S/.) TOTAL
MES 1 MES 2
01.06.02.01 SOLADO DE CONCRETO e=2" 1:12 C.H m2 32.00 35.12 1,123.84 S/. 1,123.84 S/. 1,123.84
01.06.02.02 CONCRETO EN LOSA DE APROXIMACION m3 12.96 455.03 5,897.19 S/. 5,897.19 S/. 5,897.19
01.06.02.03 ENCOFRADO Y DESENCOFRADO EN LO m2 16.40 76.56 1,255.58 S/. 1,255.58 S/. 1,255.58
01.06.02.04 ACERO DE REFUERZO fy=4,200 kg/cm2 kg 1,522.25 4.34 6,606.57 S/. 6,606.57 S/. 6,606.57
01.06.03 MUROS CONTRAIMPACTO 2,485.74
01.06.03.01 CONCRETO EN MURO CONTRAIMPACTO m3 1.44 455.03 655.24 S/. 655.24 S/. 655.24
01.06.03.02 ENCOFRADO Y DESENCOFRADO EN M m2 12.48 76.56 955.47 S/. 955.47 S/. 955.47
01.06.03.03 ACERO DE REFUERZO fy=4,200 kg/cm2 kg 110.06 4.34 477.66 S/. 477.66 S/. 477.66
01.06.03.04 PINTURA EN MURO CONTRAIMPACTO m2 13.08 30.38 397.37 S/. 397.37 S/. 397.37
01.07 OBRAS DE PROTECCION (MURO ENROCADO) 60,693.15
01.07.01 ENCAUSAMIENTO DEL RIO YAUYOS PARA REALIZAR TRABAJOS 1,644.00
01.07.01.01 ENCAUSAMIENTO DE LA QUEBRADA IN m3 240.00 6.85 1,644.00 S/. 822.00 S/. 822.00 S/. 1,644.00
01.07.02 MOVIMIENTO DE TIERRAS 4,320.39
01.07.02.01 CORTE Y EXCAVACION A NIVEL DE CI m3 192.00 13.62 2,615.04 S/. 1,307.52 S/. 1,307.52 S/. 2,615.04
01.07.02.02 RELLENO CON MATERIAL PROPIO m3 90.00 6.00 540.00 S/. 270.00 S/. 270.00 S/. 540.00
01.07.02.03 ELIMINACION DE MATERIAL EXCEDENTE m3 127.50 9.14 1,165.35 S/. 582.68 S/. 582.68 S/. 1,165.35
01.07.03 OBRAS DE CONCRETO 54,728.76
01.07.03.01 CONCRETO 1:10 + 30% P.G. PARA CIMIE m3 89.60 264.59 23,707.26 S/. 11,853.63 S/. 11,853.63 S/. 23,707.26
01.07.03.02 CONCRETO 1:6 + 75% P.G. PARA MUROS m3 60.00 366.96 22,017.60 S/. 11,008.80 S/. 11,008.80 S/. 22,017.60
01.07.03.03 ENCOFRADO Y DESENCOFRADO DE MU m2 224.00 31.98 7,163.52 S/. 3,581.76 S/. 3,581.76 S/. 7,163.52
01.07.03.04 SOLADO EN FONDO DE ESTRUCTURA F m3 6.40 287.56 1,840.38 S/. 920.19 S/. 920.19 S/. 1,840.38
01.08 SEÑALIZACION 7,286.90
01.08.01 SEÑAL IMFORMATIVA (1.6 x 1.0) und 2.00 2,907.34 5,814.68 S/. 5,814.68 S/. 5,814.68
01.08.02 SEÑAL PREVENTIVA (0.6M x 0.6M) und 2.00 736.11 1,472.22 S/. 1,472.22 S/. 1,472.22
02 INSTALACIONES PROVICIONALES (PUENTE) 56,792.01
02.01 POLIZAS DE SEGURO 1,458.58
02.01.01 SEGUROS DE TRANSPORTE NACIONAL glb 1.00 1,458.58 1,458.58 S/. 1,458.58 S/. 1,458.58
02.02 TRANSPORTE 17,396.58 S/. 0.00
02.02.01 TRANSPORTE DE ESTRUCTURA METALICA ton 21.08 469.67 9,900.64 S/. 9,900.64 S/. 9,900.64
CRONOGRAMA DE DESEMBOLSO ECONOMICO
OBRA: INSTALACIÓN DEL PUENTE MODULAR “SANTA ROSA” , DISTRITO DE SANTA ROSA, PROVINCIA DE PALLASCA
REGIÓN

PRESUPUESTO
Item Descripción Und. Metrado Precio (S/.) Parcial (S/.) TOTAL
MES 1 MES 2
02.02.02 TRANSPORTE DE NARIZ DE LANZAMIENTO ton 7.98 469.67 3,747.97 S/. 3,747.97 S/. 3,747.97
02.02.03 TRANSPORTE DE NARIZ DE LANZAMIENT ton 7.98 469.67 3,747.97 S/. 3,747.97 S/. 3,747.97
02.03 SUPERESTRUCTURA (MONTAJE Y LANZAMIENTO) 37,936.85
02.03.01 MONTAJE DE ESTRUCTURA DE METALICASton 29.07 772.61 22,459.77 S/. 22,459.77 S/. 22,459.77
02.03.02 LANZAMIENTO DE ESTRUCTURA DE METALton 29.07 471.26 13,699.53 S/. 13,699.53 S/. 13,699.53
02.03.03 SUMINISTRO Y COLOCACION DE ANGULO und 1.00 1,777.55 1,777.55 S/. 1,777.55 S/. 1,777.55
03 SEGURIDAD Y SALUD 15,330.00
03.01 IMPLEMENTACION DE PLAN DE SEGURIDAD glb 1.00 2,500.00 2,500.00 S/. 1,250.00 S/. 1,250.00 S/. 2,500.00
03.02 EQUIPOS DE PROTECCION INDIVIDUAL und 16.00 410.00 6,560.00 S/. 3,280.00 S/. 3,280.00 S/. 6,560.00
03.03 EQUIPOS DE PROTECCION COLECTIVA und 1.00 1,200.00 1,200.00 S/. 600.00 S/. 600.00 S/. 1,200.00
03.04 SEÑAL TEMPORAL DE SEGURIDAD glb 1.00 1,000.00 1,000.00 S/. 500.00 S/. 500.00 S/. 1,000.00
03.05 CAPACITACION EN SEGURIDAD Y SALUD glb 1.00 2,400.00 2,400.00 S/. 1,200.00 S/. 1,200.00 S/. 2,400.00
03.06 RECURSOS PARA RESPUESTA DE EMERGEN glb 1.00 1,670.00 1,670.00 S/. 835.00 S/. 835.00 S/. 1,670.00
04 MITIGACION DE IMPACTO AMBIENTAL 23,334.65
04.01 RIEGO CONTINUO EN LA ZONA DE MOVIMIE día 30.00 326.59 9,797.70 S/. 4,898.85 S/. 4,898.85 S/. 9,797.70
04.02 ELIMINACION DE DESECHOS DE LA OBRA m3 10.00 23.06 230.60 S/. 115.30 S/. 115.30 S/. 230.60
04.03 RESTAURACION DE ZONA DE CAMPAMENTO ha 0.30 246.37 73.91 S/. 36.96 S/. 36.96 S/. 73.91
04.04 REVEGETACION DE ZONAS AFECTADAS ha 0.80 1,428.05 1,142.44 S/. 571.22 S/. 571.22 S/. 1,142.44
04.05 LIMPIEZA FINAL EN OBRA m2 3,000.00 4.03 12,090.00 S/. 6,045.00 S/. 6,045.00 S/. 12,090.00
COSTO DIRECTO S/. 310,560.27 S/. 206,407.62 S/. 104,152.65 S/. 310,560.27
% EQUIVALENTE 66.46% 33.54% 100.00%