ID Task Name Duration Start  May Mon 06 May Tue 07 May Wed 08 May Thu 09 May Fri 10 May

6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6
1 0 days Fri 03/05/13
Change of bearings at Lamali rocker arms
2 PREREQUISITES. 0 days Mon 06/05/13 06/05
3 Check all start up systems of main drive, fans, HGG, ...etc, are deenergised and locked. 4 hrs Mon 06/05/13
4 Dampers connecting to Hot gas circuits are closed and locked. 4 hrs Mon 06/05/13
5 All hydraulic systems deenergised, locked and depresurised. Rollers on the table 4 hrs Mon 06/05/13
6 Temperature at table. 1 hr Mon 06/05/13
7 Clean table. 2 hrs Mon 06/05/13
8
9 Remove roller speed and rocker arm monitoring.  1 hr Mon 06/05/13
10 Disconect sealing air and HSLM hoses. Plugs for the three holes at the roller. 1 hr Mon 06/05/13
11 Install auxilar block to swing out roller (2h) 2 people. Crane 30/40t. 2 hrs Mon 06/05/13
12 remove sealing air pipe (2h) 4 people 2 hrs Mon 06/05/13
13 Remove Lever sealing . (2h) 4 people. 2 hrs Mon 06/05/13
14 Remove Mill door (3h) 4 people.  Crane 30/40t. (Scaffolding needed?) 4 hrs Mon 06/05/13
15 Remove Plattform.  (2h) 2 people. Crane 30/40t 2 hrs Mon 06/05/13
16 Install Swing cylinder and HSAV unit. (2h) 2 people. Crane 30/40t. 2 hrs Tue 07/05/13
17 Connect Swing cylinder to rocker arm. 1 hr Tue 07/05/13
18 Remove clamping nuts at both cylinders, (3h) 4 people  (Required some scaffolding?) 4 hrs Mon 06/05/13
19 Release taper sleeves at rocker arm 1 hr Fri 03/05/13
20 Remove pins at rocker arm. (2h) 2 people. 2 hrs Tue 07/05/13
21 Swing out roller. 0,5 hrs Tue 07/05/13
22 Remove Roller clamp bolts. Install "donut" and hydro jack to release roller. (4h) 4 people. (Required some scaffolding?) Crane 30/40t.
4 hrs Tue 07/05/13
23 Remove roller. Crane 150t. (Have special support to leave it in vertical position?). 0,5 hrs Tue 07/05/13
24 Swing in Rocker arm, reinsert pins. (2h). 4 people. 1 hr Tue 07/05/13
25 Install rocker arms lifting auxiliaries.  1 hr Tue 07/05/13
26 Disconnect of swing cylinder, 0,5 hrs Wed 08/05/13
27 remove swing block.  (2h) 2 people. Crane 30/40t 1 hr Wed 08/05/13
28 Remove pedestal bearing housing top. (1h) 2 people..Crane 30/40t 2 hrs Wed 08/05/13
29 Prepare new bearings (clean, preheat around 100ºC, lifting device to install. (2h) 2 people.Crane 30/40t 3 hrs Tue 07/05/13
30 Lift Rocker arm out of the pedestal. (1h) 2 people. Crane 150t. (wooden bed ready to lay it down?) 1 hr Wed 08/05/13
31 Clean and check bearing housing at pedestal. 1 hr Wed 08/05/13
32 Remove damaged bearings, cleaning and check  surfaces, install new ones and fix bearing. (2h) 6 people. Crane 30/40t 2 hrs Wed 08/05/13
33 Pack them with grease. cover with clean plastic film.   1 hr Wed 08/05/13
34 Lift rocker arm to pedestal. (2h) 2people Crane 150t. 1 hr Wed 08/05/13
35 Close bearing caps. (2h) 6 people.  1 hr Wed 08/05/13
36 Reassembly clamping nuts. (3h) 4 people. 1 hr Wed 08/05/13
37 Assembly swing block. Connect to swing cylinder. (2h) 4 people. 30/40 t crane. 1 hr Wed 08/05/13
38 Remove lifting devices at rocker arm 1 hr Wed 08/05/13
39 Remove pins, swing out rocker arm. 2 hrs Wed 08/05/13
40 Assembly Roller. (4h) 5 people. 150t crane. 4 hrs Wed 08/05/13
41 Swing in roller.  1 hr Thu 09/05/13
42 Assembly pins at rocker arms. (2h)  4 people. 2 hrs Thu 09/05/13
43 Disconnect and remove Swing cylinder 2 hrs Thu 09/05/13
44 Assembly plattform. (2h) 2 people. Crane 30/40t. 2 hrs Thu 09/05/13
45 Assembly mill body cover. (4h) 4 people. Crane 30/40 t. 4 hrs Thu 09/05/13
46 Assembly lever sealing. (3h) 4 people. 3 hrs Thu 09/05/13
47 Remove connection block. (1h) crane 30/40t. 1 hr Fri 10/05/13
48 Install roller speed and rocker arm monitoring.  1 hr Fri 10/05/13
49 Connect sealing air and HSLM hoses. 1 hr Fri 10/05/13

Project: 20130503_Change rocker arm Task Progress Summary External Tasks Deadline


Date: Sat 04/05/13 Split Milestone Project Summary External Milestone