Documente Academic
Documente Profesional
Documente Cultură
Chapter 14
ON SITE SANITATION
On site sanitation
This is the treatment and disposal of wastewater at the point of production without
conveyance of the wastewater through a sewer reticulation system. However,
some on site systems have facilities to remove the wastewater (off-site disposal)
like the bucket latrines, vaults and sea disposal). The technology is suitable to
small communities and especially in the rural areas where the population density is
low and hence construction of a water-borne sewerage becomes uneconomic.
However the technology should create opportunities for the spread of diseases and
should be culturally acceptable to the community. Other advantages include:
Disadvantages
• Septic tanks
• aqua privy
• Pit latrines
• Eco-san
• Vacuum systems
• Container systems (bucket and Vaults)
• Sea disposal
• open defection or ground surface disposal
Open defecation
Excreta are deposited on the ground and is not recommended because of the high
health risks. A small improvement is achieve by digging a very shallow pit before
defecation and then covering the excreta with soil, but although the fly and smell
nuisance may be reduced, there is still risk of transmission of hookworm.
Septic tanks
Rectangular chambers, below ground level which receive waterborne wastewater
(toilet waste and household sullage). The septic tank is separated from the
household and receives water-borne sewage. The wastewater is retained for 1-3
days and during this retention period solids settle to the bottom of the tank and are
digested anaerobically (consolidation and stabilization of sludge). A thick scum is
formed at the surface and this help to maintain anaerobic conditions i.e. growth of
microorganisms in the tank. The treatment in a septic tank is partial and therefore
the effluent stills a health hazard and still needs further treatment before disposal.
The disposal is sometimes discharged to soakaways but no longer recommended
practice. Desludging is necessary approximately in 1-5 years. In general septic
tanks are suitable for individual households.
The schematic illustration of the layout of a septic tank system is shown in Fig. 1.0
and the cross-section of the septic tank is illustrated in Fig. 2.
Application
• Septic tanks are slightly expensive compared to pit-latrines
• Suitable to medium or low-density housing areas with large plot sizes
because more space is needed for disposal of effluent.
completely empty the tank. This will disrupt the microorganisms system and
maturation time of the microorganisms will be required.
• The septic tank should be located away from wells, streams, embankments,
water table to avoid water pollution.
Some of the guidelines for location of septic tanks are summarised in Table 1.
Tank volume = V = Q × n × t
n =population
t =retention time, t ≅ 3 days
V = pq
w = Pnfs
The total volume of the tank is equal to the scum, sludge and liquid volumes:
Table 3: s values
Material used Flush toilet wastes only Domestic sullage and wastes
Water, soft paper 25 40
Leaves, hard paper 40 55
Sand, stone, earth 55 70
Desludging frequency
The tank is empted when it is approximately 1/3 full of sludge:
1
V
t= 3
sludge accumulation × n
Disposal of effluent
The effluent is still a health hazard and still needs further treatment before disposal.
Also, the effluent should not be discharged into sewers because it is anaerobic.
The hydrogen sulphide will be converted to sulphuric acid which will attack the
sewers. The effluent is sometimes discharged to soakaways but it is no longer a
recommended practice. Other options of disposal are:
• soakaways
• small bore sewers
• evapotranspiration beds
• upflow filters
• wastewater stabilisation ponds for large population
• flood irrigation
• Nearest conventional sewer reticulation or wastewater treatment plant (but
note that it is septic and may affect the sewer pipes), small bore sewers.
Soakaways
These are subsurface drainage trenches filled with rocks of 20 to 50mm or even
more. The soil must be course and permeable and the infiltration rate should be
above 10l/day/m2. There should be provision for future replacement of drainfield
due to clogging.
7
Effluent
Septic 0.5m
tank Filter
(a)
(b)
Fig. 4: Septic tanks with upflow filters
Evapotranspiration bed
It consists of a top layer of sand and gravel, and a bottom layer of top soil with a fast
growing grass. The effluent is lost due to evapotranspiration from the grass. The
organic fraction is converted to grass and is periodically cut.
10
Coarse sand
and gravel
0.2-0.5m
Grass
Aquaprivy
An aqua privy is similar to a septic tank but the difference is that it is located
directly below the house (Fig, ), and only water is needed to maintain the water level
in the tank this will control flies and smells. The water level is controlled by
downward projection of a pipe from the bowl to below the water level in the tank.
The amount of wastewater treated is less than in a septic tank.
11
Design aspects
The tank is designed similar to the septic tank. The average inflow is about 5-
18l/ca. day.
Vacuum systems
The excreta is transported by suction and air pressure but are expensive and are
rarely used.
disposal. Can also be served by pour flush systems or a squatting hole can be
directly located above the tank.
Sea disposal
The pit latrine discharges directly over the sea or into a river (over hung latrine).
The system can be considered as off-site. This type of disposal has health hazards
since if the water is to be used by the communities.
PIT LATRINES
A pit is dug and excreta is disposed in the pit. Common types are:
• simple
• pits with sealed lids
• ventilated improved (VIP)
• pour flush
Simple pits
The hole is directly above the squatting hole, which receives the wastes and
decomposition takes place in the pit. They could be single pit, alternate double pit
and multiple pits. There is super structure above the hole. It takes all anal
cleansing material and minimum water requirements. Its disadvantage are:
• odours and flies
• shortage of space for relocation if pit is full
13
A fly screen is fitted on the top of the vent pipe to prevent flies entering the pit (Fig.
), hence minimal risk to health compared to the simple pit. The ideal mesh wire is of
stainless steel because of the corrosive nature of the gases through the vent and of
size 1.5mm x 1.5mm. Plastic meshes deteriorate due to sunlight but nylon coated
glass fibre is also acceptable. Internal diameter of the vent should be 150mm for
smooth pipe; 225 for a reed and cement mortar; or 225mm square brick. It must
project at least 300mm above the highest point of the roof. Wind blowing across the
top of the vent sucks air out of the pit.
Ideally a smooth concrete slab for ease of cleaning sloping towards the squatting
hole. The squatting should not be larger that 350mm x 180mm with a key hole
shape. Children might fall in if its is big hole and if it is too small it is easily fouled.
Seats can be designed for comfort ability. The slab should raise for about 150mm
to prevent debris entering the pit. The pit should lined for its full length unless the
foundation is stable. In all the soils the top 500mm must be lined to prevent rodents
entering the pit. The bottom part of the pit should be permeable and hence no lining
to allow the waste to infiltrate into the ground. Circular shapes of pits are more
stable than rectangular.
14
Fig. : Combined pan and water seal for direct pour-flush latrine
15
16
17
1. Dig one trail pit about 500mm deep, and clean out the base.
2. In the base of the pit, carefully dig a hole about 300 mm in diameter and
about 300mm. deep.
4. Measure and record the actual size of this hole (Diameter and Depth).
6. Pour water into the hole, without washing the sides of the hole, until the
water level is just below the base of the trail pit.
7. Over a period of four hours keep topping up the water level to replace the
water that drains away.
8. Check and record the actual diameter of the hole once again. The diameter
may have changed from that measured earlier.
9. Allow the water level to drop until it is about 150mm below the top of the
hole.
11. Measure the depth from the underside of the straight edge to the water
surface at intervals of 15 minutes over a period of at least one hour and for a
total measured change of level of 30 mm. Record the depths and the times
of measurement.
12. Deepen the trail pit tot a total depth of about 1500mm.
14. When the percolation tests have been completed, and the description and
levels of the various soil levels in the trail pit have been recorded, fill in the
trial pit.
Notes.
1. Try not to leave a trail pit open overnight. If this cannot be avoided, provide
safety barriers around the trail pit.
2. Percolation through the base of the hole is ignored; only the perimeter of the
hole is assumed to allow percolation.
18
Example
Design a septic tank for a family of 12 which has a water consumption of
100l/household per day. The effluent disposal is to be subsurface irrigation in a
drain field. Return flow is 80% of water consumption and allowing 3 day detention
start0up.
Solution
Tank volume:
19
References
20