Documente Academic
Documente Profesional
Documente Cultură
TROPICAL
NET ZERO
Building and Construction Authority
BY STEPHEN WITTKOPF
Before the retrofit, the building was Integrated Approach (NUS) and the Solar Energy Research
used as a training center for craft The planning began in 2007 as a Institute of Singapore (SERIS) to
workers for the rapidly growing public-private partnership project retrofit an existing building into a net
construction industry in Singapore. with the building owner (BCA), local zero energy building. The building
It was part of a larger campus that designers/consultants and builders footprint is about 250 ft (76 m) long
was restructured to become the partnering with researchers from the and 65 ft (20 m) deep, with an exter-
BCA Academy. National University of Singapore nal corridor on the longer east side
This article was published in High Performing Buildings, Spring 2015. Copyright 2015 ASHRAE. Posted at www.hpbmagazine.org. This article may not be copied
and/or distributed electronically or in paper form without permission of ASHRAE. For more information about High Performing Buildings, visit www.hpbmagazine.org.
Z E R O E N E R G Y B U I L D I N G @ B C A A C A D E M Y
providing access to the deep building energy efficiency and renewable temperature and relative humid-
spaces on all three stories. energy. International case studies ity in tropical Singapore during
The east façade is oriented north- were analyzed and various concepts the day is around 88°F (31°C) and
south and faces an internal rectilinear developed and reviewed, often 80%, respectively, with relatively
courtyard. Three identical buildings aided by computational simulation
are opposite, and another abuts the and visualization.
north side and the entrance building Various iterations helped to identify B U I L D I N G AT A G L A N C E
on the south side. All six buildings best practices and the need for sup-
Name
are connected by internal walkways porting research projects. The main Zero Energy Building @ BCA Academy
or intermediate staircase cores, form- goals for the passive design included Renovation Scope
ing the BCA Academy. The nearest reducing heat transmittance, Net Zero Energy Building
building to the campus entrance enhancing daylight and increasing Location 200 Braddell Road, Singapore
was chosen for the net zero energy natural ventilation, followed by effi- Owner Building and Construction
retrofit. The building was partially cient electrical lighting and air con- Authority (BCA) of Singapore
funded by the BCA, the Ministry of ditioning and mechanical ventilation Completion October 2009
National Development (MND) and using building management systems. Principal Use
the Economic Development Board Integrating photovoltaics into the Office, visitor center, library and
multipurpose room (67% of the gross
(EDB). The project used a design- building envelope was critical for
floor area) (air conditioned)
build-operate process. Reducing achieving net zero energy goals. Classrooms and school hall (33%)
operational costs and emissions were (naturally ventilated)
the driver for the design, rather than Natural Ventilation With Occupancy
80 permanent staff
reducing upfront capital costs. Solar Chimneys 100% occupied
In design charrettes the stake- The other campus buildings were Average 90 visitors per week
holders discussed passive design, previously converted into partly Gross Square Footage (GSF)
air-conditioned offices. This project 48,440
Opposite Vertical green wall, photovoltaics building, which includes classrooms 23,476 air-conditioned space
and lightshelves create the shading skin for
the west façade and southern entrance. and a school hall (one-third of the Distinctions/Awards
Certified, Green Mark Platinum Award,
Below Solar chimneys are characteristic gross floor area), was cooled by Building and Construction Authority (2009)
features of the building. They provide natu- natural ventilation. The average air Winner, Minister’s Team Award, Ministry of
ral ventilation for classroms via ducts along
National Development, Singapore (2010)
the roof and façade.
Winner, BCI Green Leadership Awards,
Building and Construction Authority
A solar chimney system was cho- light, they heat up, create internal Roof
sen for natural ventilation of the hot air, which expands, becoming Type Ventilated PV modules over metal
roof with 150 mm thick Rockwool
classrooms and school hall. Four lighter and rises (buoyancy effect)
insulation
chimneys on the roof, which are the and, in turn, “sucks” warm indoor Overall R-value 27 ft2 ·°F·hr/Btu
end of a series of partially hidden air through various inlets draw- Walls
ducts along the building envelope, ing ambient air through the façade Type 150 mm dry wall (light grey)
Overall R-value 18.65 ft2 ·°F·hr/Btu
Glazing percentage 43%
E A R LY V I S U A L I Z AT I O N O F G R E E N B U I L D I N G T E C H N O L O G I E S Basement/Foundation
Type concrete slab
R-value 5 ft2 ·°F·hr/Btu
Windows (West)
Type 24 mm thick tempered double
glazing unit
R-value (West) 1.66 ft2 ·°F·hr/Btu
Solar Heat Gain Coefficient (SHGC)
Solar Energy Research Institute of Singapore (SERIS)
Location
Latitude and Longitude 1.34482° N
103.85824° (1° 20’ 41.3514”, 103°
51’ 29.6634”)
The lightshelves as multifunctional shading exposed concrete walls and metal Heating degree days 0
elements results in the typical deep roofs that have little shading, heated Operational hours 2,780 (2013),
western façade. annual air-conditioning operating hours
up during the day and re-radiated
the heat into the interior due to the
mean vote (PMV) and predicted absence of insulation. Because of
percentage dissatisfied (PPD) and the strong solar radiation (more than cooling skin to the building enve-
reconfirmed through an occupant 507 kBtu/ft2 [1,600 kWh/m2] per lope. Sun shades and vertical green
survey of 15 to 20 high school year), peak temperatures of external walls were added on the western
students during a time when the surfaces could exceed 120°F (50°C). side, and the roof received a layer of
solar chimney system shifted the The overall strategy was to add a photovoltaic (PV) modules. The PV
roof was elevated about 1 ft (300 mm)
off the metal roof and had horizontal
SOLAR CHIMNEY gaps between the modules to ensure
ventilation and cool the PV modules
and metal roof below.
The cooling skins served additional
purposes beyond shading. Some sun
shades on the façade had PV on the
upper parts, generating additional
electricity. Others had reflective
films, doubling as lightshelves,
redirecting daylight deeper into the
building. The green walls and roof
Building and Construction Authority
kBIM Template and Library for Autodesk Revit is a package of standardized Revit
tools designed to provide large-firm capabilities to smaller firms and improve drawing
development efficiency.
kBIM Template and Library includes a Revit template, customized Revit library, and
supporting help documentation, all designed to enhance the building information
modeling (BIM) process for mechanical, electrical, plumbing, fire protection, and
technology disciplines.
Provides large-firm capabilities to smaller firms
HPB.hotims.com/54438-31 Autodesk and Revit are registered trademarks of Autodesk, Inc., in the USA and other countries.
building areas. However, this is at up to 8 m (26 ft) from the roof to
the expense of color rendition, as the ceiling-mounted diffusers in the
the light appeared slightly yellow- office spaces below.
ish at the exit opening. The vertical The longer curved light pipe sup-
light pipe systems were commer- plied enough light for a meeting
cially available products, with light- room without any windows, while
collecting domes on the roof and the shorter straight light pipe with
Stephen Wittkopf
vertical and curved pipes running a diameter of 3 ft (1 m) would
Feb 2014
Mar 2014
Apr 2014
May 2014
Jun 2014
Jul 2014
Aug 2014
Sep 2014
Oct 2014
Nov 2014
Dec 2014
tive films. The film with more than Cumulative energy consumption in kWh Cumulative energy generation in kWh
Linear (energy consumption in kWh) Linear (energy generation in kWh)
98% reflectance provided daylight
factors of above 5% in the deep
Many lessons were learned regarding the Traditionally, windows only have thermal value appears low, but actually compares
generation of accurate energy models, and optical properties and not electrical, well to the range of 30% to 40% reported
enabling of monitoring and verification, and PV modules have only electrical prop- for some advanced net zero and plus energy
designing for maintenance and responding to erties, and even if they are integrated in buildings in Europe. Design for load matching
increasing energy use. The integrated design the building envelope, they remain mono- is an emerging design criterion that building
process with all stakeholders at the early functional energy generators. Therefore, BIM performance label systems are preparing
stage of the project was beneficial in setting was used for integration and communication to incorporate.
the stage and identifying best practices. purposes, but not as a front end for energy
A further challenge is that space use may
performance simulation. Energy simulations
The design-build-operate approach was also change over time. Here, some of the class-
were performed independently from BIM with
beneficial as it considered the operational room spaces planned for natural ventilation
the locally prevailing tools for PV system siz-
costs, too, which is usually ignored in the were converted to air-conditioned spaces with
ing, building energy performance and HVAC
standard design-build-sell approach. different use. Responding to an increased
and daylighting systems.
energy use is another key takeaway point.
Simulations on energy savings and yield The development of the building monitoring This requires constant monitoring to identify
were instrumental in sizing different energy system turned out to be very complex. The areas for further energy savings. For example,
systems. However, building accurate and building systems with their sensors, calibra- the initial lighting was using T5 lamps, but
integrated energy models with occupancy tion routines and communication protocols after replacing them with LED lamps, the
schedules and dynamically responsive were very diverse. Recording, synchronizing energy consumption was reduced by about
systems was challenging. Occupancy sched- and analyzing massive amounts of data was 40%, partially absorbing the increased energy
ules are very difficult to predict, but their very complex and took much longer than consumption for the enlarged air-conditioned
resulting energy loads have a strong impact expected. PV monitoring systems, on the space. There were some difficulties mainly
on the predicted energy consumption of a other hand, are quite common and monitor- due to the lack of experience and craftsman-
building. Actual and predicted occupancy ing procedures set in international standards. ship in installing green building technologies
schedules usually differ, especially if the Unfortunately, both monitoring systems run properly on site. This was especially true
prediction is outdated. separately. But data from both systems were if it was the first of its kind in Singapore,
The planning of the project included some eventually compared to determine the load such as the solar chimney system and PV
reserves, e.g., for extension of air-condi- matching, e.g., the percentage of time where façades. Most of the extra work could for-
tioned spaces. In fact, the EUI of the building
the PV electricity meets the consumption. tunately be supported by the accompanying
has increased 15% over the first two years A net zero energy building has a 100% load research projects, which also brought in
and keeps increasing due to converting more matching over the course of one year. But on foreign experts and their experiences. What
of the naturally ventilated spaces into air-con-
an hourly scale that looks much different. For also turned out to be essential was the call
ditioned zones. But with additional energy- this project, the hourly profile over a day for for a performance-based arrangement for
efficiency measures, it has remained a net energy consumption and occupancy is very the building integrated PV system unlike the
zero energy building over the first five years.
asynchronous and different for a typical day usual capacity-based arrangement. For per-
Building information modeling (BIM) was during office hours and weekends. For 37% formance based, the supplier had to ensure
used to create and communicate design of cases, the hourly averaged generation that the specified annual electricity generation
aspects. However, not all of the green build- matches (or even exceeds) the corresponding is achieved. Again, the consideration of the
ing systems were a part of the standard consumption, which means that the building operation phase of the building (not just the
building products library and had to be cre- runs autonomously and theoretically could be construction phase) paved the way to sustain-
ated and added first. Multifunctional objects disconnected from the grid (although this is ing the net zero energy target for more than
such as electricity-producing semitransparent technically not the case, also due to the high five years of operation since October 2009.
PV windows are difficult to represent in BIM. variability of the irradiance in Singapore). The
oversupply light with daylight fac- neutrality. However, this solution As there is no heating required, all
tors sometimes exceeding 50% required more space and planning energy was electric for air-condi-
during noontime with sun positions compared to electric lighting and tioning, ventilation, lighting and
near the zenith. slightly increased the mean radiant plug loads, which was estimated
In conclusion, the concept of col- temperature by 1°F (0.5°C). to be about 706,300 kBtu (207
lecting bright zenithal light on roofs MWh) or 14.6 kBtu/ft2 (55.3 kWh/
and façades and directing them into Photovoltaic Integration m2) per year. To produce an equiva-
deep building zones was found to be The energy target for the building lent amount of electricity with PV,
an effective and innovative alterna- was to be net zero, i.e., to produce as it became clear that the building
tive or supplement to electric light- much electricity as the building con- roof would need to be completely
ing and provided excellent color sumes over the course of one year. reserved for PV.
strate the variety of PV technologies air-conditioning system for better indoor quality
and their multifunctionality, such in the tropics.” Urban Sustainability Congress.
as serving as sunshades, railings, Garde, F., et al. 2014. “A review of 30 Net
ZEBs case studies worldwide.” A report from
Six external scoops on the eastern facade opaque and semitransparent walls
IEA Joint SHC Task 40/ECBCS Annex 52:
collect zenithal daylight and redirect it into and windows. Towards Net Zero Energy Solar Buildings,
horizontal light ducts for daylighting of
multipurpose rooms.
Those smaller systems were off- Subtask C.
grid, meaning their dc electricity Grobe, L.O., et al. 2010. “Singapore’s Zero
Energy Building’s daylight monitoring system.”
After a few iterations to define was consumed on the spot by a cell International Conference on Applied Energy.
the benefits of electricity genera- phone charger. Both grid-connected Kishnani, N. 2012. “Greening Asia: Emerging
tion with PV versus energy sav- and off-grid systems are owned Principles for Sustainable Architecture.”
BCA Asia.
ings through solar chimneys, roof and operated by the BCA, follow-
Lee Siew Eang. 2014. “The design, develop-
greening or reflective coatings, a ing the requirements for electrical
ment and performance of a retrofitted net zero
PV system of 190 kWp capacity power systems set by Singapore energy building in Singapore.” High Energy
covering some 16,577 ft2 (1540 Energy Market Authority (EMA) Performance Buildings.
m2) was chosen. A large grid-con- and the design guidelines on con- Lynn, N., et al. 2012. “Color rendering proper-
ties of semi-transparent thin-film PV modules.”
nected system designed to produce servation and development con- Building and Environment 54.
trol by the Urban Redevelopment Tan Yong Kwang, A., et al. 2012. “Natural ven-
BUILDING TEAM Authority (URA). tilation performance of classroom with solar
chimney system.” Energy and Buildings 53.
Building Owner Building and Wittkopf, S., et al. 2010. “Ray tracing study
Conclusion
Construction Authority of Singapore for non-imaging daylight collectors.” Solar
The BCA retrofit project was Energy 84(6).
Architect DP Architects Pte Ltd
intended to demonstrate efficient Wittkopf, S., et al. 2012. “Analytical per-
Principal Investigators for Green
use of energy in a retrofit building. formance monitoring of a 142.5 kWp grid-
Building Technologies, Environmental connected rooftop BIPV System in Singapore.”
Design and Energy Modeling Shading devices, lightshelves, verti- Renewable Energy 47.
National University of Singapore cal green walls, high-performance Wong Nyuk Hien, et al. 2011. “Performance
Main Contractor glazing, and lightweight wall systems of greenery systems in Zero Energy Building
ACP Construction Pte Ltd of Singapore.” International Conference on
are integrated in the west façade.
Project Manager, Mechanical & Electrical Light pipes and ducts are installed
Sustainable Design and Construction. •
Engineer, Civil & Structural Engineer
Beca Carter Hollings & Ferner (S. E. on the roof and east façade. The roofs
Asia) Pte Ltd are covered with large PV systems
ABOUT THE AUTHOR
Quantity Surveyor to generate enough electricity for the
Langdon & Seah Singapore Pte Ltd building to become net zero. Parts Stephen Wittkopf is professor of archi-
Photovoltaic Contractor of the roof have solar chimneys for tecture at the Lucerne University of
Grenzone Pte Ltd Applied Sciences and Arts, Switzerland.
improving the air movement within
the naturally ventilated spaces.