Sunteți pe pagina 1din 8

Quantity Calculation of Brick Masonry Work of Mohanlalganj Site

S.No Description Unit Nos Length Width Depth Quantity Remarks


A : BRICK MASONRY WORK
1 Front Wall CFt 1 104 0.75 10 780 9 Inches = 0.75 Ft
2 Deduction of Window CFt -4 3 0.75 4 -36
3 Deduction of Door Type 2 CFt -1 3.5 0.75 7 -18.375
4 Deduction of Door Type 3 CFt -1 3 0.75 7 -15.75

5 Back Side Wall CFt 1 99 0.75 10 742.5


6 Deduction of Window CFt -4 3 0.75 4 -36

7 Right side Wall CFt 1 23.5 0.75 10 176.25 Slightly in Rach

8 Left Side Wall CFt 1 23 0.75 10 172.5


9 Deduction of Window CFt -1 3 0.75 4 -9
10 Deduction of Door Type 1 CFt -1 6 0.75 7 -31.5

11 Median Wall CFt 1 23 0.75 10 172.5


12 Deduction of Opening CFt -1 5 0.75 7 -26.25

13 Supporting Coulmns CFt 3 1.167 0.75 10 26.2575 14 Inches = 1.167 FT

14 Stairs Supporting Wall CFt 1 8 0.75 4 24

14 Stairs Supporting Wall 2 CFt 1 8 0.75 4 24

15 Stairs CFt 19 4 0.833 0.583 36.91 10" = 0.833 Ft, 7" = 0.583 Ft
Total Brick Work (Cft) 1982.04 1 cum= 35.29 Cft
Total Brick Work (Cum) 56.164
Quantity Calculation of Plaster Work of Mohanlalganj Site
S.No Description Unit Nos Length Width Quantity Remarks
C : PLASTER WORK
1 Front Wall Inner Side Sqft 1 102.5 10 1025
2 Front Wall Outer Side Sqft 1 104 10 1040
3 Deduction of Window Inner Side Sqft -4 4 3 -48
4 Deduction of Window Outer Side Sqft -4 4 3 -48
5 Window Frames Sqft 4 14 0.75 42
6 Deduction of Door Type 2 Inner Side Sqft -1 3.5 7 -24.5
7 Deduction of Door Type 2 Outer Side Sqft -1 3.5 7 -24.5
8 Door 2 Frame Sqft 1 21 0.75 15.75
9 Deduction of Door Type 3 Inner Side Sqft -1 3 7 -21
10 Deduction of Door Type 3 Outer Side Sqft -1 3 7 -21
11 Door 3 Frame Sqft 1 20 0.75 15

12 Back Side Wall Inner Side Sqft 1 97.5 10 975


13 Back Side Wall Outer Side Sqft 1 99 10 990
14 Deduction of Window Inner Side Sqft -4 4 3 -48
15 Deduction of Window Outer Side Sqft -4 4 3 -48
16 Window Frames Sqft 4 14 0.75 42

17 Right side Wall Inner Side Sqft 1 23.5 10 235 Slightly in Rach
18 Right side Wall Outer Side Sqft 1 23.5 10 235 Slightly in Rach

19 Left Side Wall Inner Side Sqft 1 23 10 230


20 Left Side Wall Outer Side Sqft 1 23 10 230
21 Deduction of Window Inner Side Sqft -1 4 3 -12
22 Deduction of Window Inner Side Sqft -1 4 3 -12
23 Window Frames Sqft 1 14 0.75 10.5
24 Deduction of Door Type 1 Inner Side Sqft -1 6 7 -42
25 Deduction of Door Type 1 Outer Side Sqft -1 6 7 -42
Quantity Calculation of Plaster Work of Mohanlalganj Site
S.No Description Unit Nos Length Width Quantity Remarks
C : PLASTER WORK
26 Door 1 Frame Sqft 1 26 0.75 19.5

27 Median Wall Inner side Sqft 1 23 10 230


28 Median Wall Outer side Sqft 1 23 10 230
29 Deduction of Opening Inner Side Sqft -1 5 7 -35
30 Deduction of Opening Outer Side Sqft -1 5 7 -35
26 Opening Frame Sqft 1 24 0.75 18

13 Supporting Coulmns Sqft 3 3.834 10 115.02

14 Stairs Supporting Wall Sqft 1 8 10 80

14 Stairs Supporting Wall 2 Sqft 1 8 4 32

15 Stairs Sqft 19 4 1.416 107.62 10" = 0.833 Ft, 7" = 0.583 Ft


Total Qty Plastering (Sqft) 5456.39 1 Sqm= 10.76 Sqft
Total Qty Plastering (Sqm) 507.099
Quantity Calculation of Concrete Work of Mohanlalganj Site
S.No Description Unit Nos Length Width Depth Quantity Remarks
B : Concrete Work
1 RCC Slab CFt 1 101.5 27 0.333 912.587 4 Inches = 0.333 Ft
2 Beam at Middle Wall CFt 1 23 0.75 0.75 12.938
3 Stairs Inclined Slab CFt 1 19 4 0.333 25.308 Inclined Length
4 Stairs Bottom Landing Slab CFt 1 2.5 4 0.333 3.330
5 Stairs Top Landing Slab CFt 1 8 4 0.333 10.656
6 Stairs Top Landing Slab B CFt 1 4 4 0.333 5.328
7 Lintel for D1 CFt 1 7 0.75 0.333 1.748
8 Lintel for D2 CFt 1 3.5 0.75 0.333 0.874
9 Lintel for D3 CFt 1 3 0.75 0.333 0.749
10 Lintel For Opening CFt 1 6 0.75 0.333 1.499
11 Lintel for Window CFt 9 3 0.75 0.333 6.743
Total Concrete (Cft) 981.76
Total Concrete Work (Cum) 27.82
Qty Qty
S.No Description (CFt/Sqft) (Cum/Sqm)
1 Brick Masonry Work 1982.04 56.164
2 Concrete Work 981.76 27.82
3 Plaster work 5456.39 507.099

Coarse Fine
Cement Aggregate
Grade of Concrete/ Mortar Sand Sand
1 Brick Masonry Work 1:5 1 5
2 Concrete Work 1 : 1.5 : 3 1 1.5 3
3 Plaster work 1:5 1 5

1 Brcik Masonry Work 56.164 cum

A Calculation of brick
Brick Size 230 x 115 x 75
1 Brick Voulme (Cum) 0.00198
Nos of Bricks in 1 Cum 504
Total Nos of Brick Required 28307

B Mortar Calculation

Considering 25 % mortar used in Brick Work

Dry Volume of Mortar = 0.25 x 1.35


Dry Volume of Mortar = 0.3375 (35% Increment due to volume
shrink in water)

Cement = (0.3375 x 1)/(1+ 5)


Cement = 0.05625 cum
Cement in Kg /Cum 81
Cement in Bag/Cum 1.62
Total Cement Required 91 Bags

Sand = (0.3375 x 5)/ (1+5)


Sand = 0.281 Cum
Sand in MT /Cum 0.45 MT
Total Sand Required 25.27 MT
Total Sand Required 558 Cft
2 Concrete Work 27.82 cum
Grade of Concrete 1 : 1.5 : 3

Cement
Cement Required for 1 cum = (1.54 x 1)/ 5.5
Cement Required for 1 cum = 0.28
Total Cement Required for Concrete 7.7896 Cum
Total Cement Required for Concrete 11217 Kg
Total Cement Required for Concrete 224 Bag

Coarse Sand
Coarse Sand Required for 1 cum = (1.54 x 1.5)/ 5.5
Coarse Sand Required for 1 cum = 0.42
Total Sand Required for Concrete 11.684 Cum
Total Sand Required for Concrete 18.7 MT
Total Sand Required for Concrete 412 Cft

Aggregate
Aggregate Required for 1 cum = (1.54 x 3)/ 5.5
Aggregate Required for 1 cum = 0.84
Total Aggregate Required for Concrete 23.369 Cum
Total Aggregate Required for Concrete 37.39 MT
Total Aggregate Required for Concrete 825 Cft

3 Plastering Work Sqm 507.1


Thickness of Plaster mm 12
Plaster work Cum 6.085
Add 20% Extra Quantity for Filling joints & Wastage 7.302
Grade of Mortar 1:5

Dry volume of Plaster = Wet Voulme x 1.35


Dry volume of Plaster = 7.302 x 1.35
Dry volume of Plaster = 9.86 Cum

Cement
Quantity of Cement= (9.86 x 1) / (1+5)
Quantity of Cement= 1.64 Cum
Total Cement Required for Plaster 2362 Kg
Total Cement Required for Plaster 47 Bag

Fine Sand
Quantity of Fine Sand= (9.86 x 5) / (1+5)
Quantity of Fine Sand= 8.22 Cum
Total Sand Required for Concrete 13.15 MT
Total Sand Required for Concrete 290 Cft
MATERIAL QUANTITY SUMMARY REQUIRED FOR MOHANLALGANJ SITE

S.No Items Unit Brick Work Concrete Plaster Total Qty


1 Bricks Nos 28307 28307
2 Cement Bags 91 224 47 362
3 Coarse Sand MT 25.27 18.7 43.97
4 Aggregate MT 37.39 37.39
5 Fine Sand MT 13.15 13.15

S.No Items Unit Brick Work Concrete Plaster Total Qty


1 Bricks Nos 28307 28307
2 Cement Bags 91 224 47 362
3 Coarse Sand Cft 558 413 971
4 Aggregate Cft 825 825
5 Fine Sand Cft 290 290

S-ar putea să vă placă și