Documente Academic
Documente Profesional
Documente Cultură
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
TABLE OF CONTENT
0. Introduction..................................................................................................................................................... 7
1. Section 1: SafiSan and the sanitation chain..................................................................................................... 8
1.1 Sanitation chain and its various components......................................................................................... 8
1.2 SafiSan: user interfaces, the dry and wet toilets..................................................................................... 9
1.2.1 The dry toilets: how do they work?.................................................................................................... 9
1.2.2 Squatting pan & sitting pedestal......................................................................................................... 9
1.2.3 The double vault, above or underground?....................................................................................... 10
1.2.4 The superstructure........................................................................................................................... 11
1.3 SafiSan wet toilets................................................................................................................................. 11
1.3.1 The wet toilets.................................................................................................................................. 11
1.3.2 Cistern flush toilet............................................................................................................................ 11
1.3.3 Pour flush toilet................................................................................................................................ 12
1.4 SafiSan: storage systems....................................................................................................................... 12
1.4.1 Septic tank........................................................................................................................................ 12
1.4.2 Conservancy tank............................................................................................................................. 13
1.5 SafiSan: collection and transport systems............................................................................................ 13
1.5.1 Manual emptiers.............................................................................................................................. 13
1.5.2 Exhauster trucks............................................................................................................................... 14
1.5.3 DEWATS............................................................................................................................................ 14
1.5.4 Sludge drying bed............................................................................................................................. 15
1.6 SafiSan: disposal or reuse?................................................................................................................... 15
1.6.1 Use in agriculture/horticulture/agroforestry.................................................................................... 15
1.6.2 Landfill disposal................................................................................................................................ 15
2. Section 2: Technical drawings and Bills of Quantity of SafiSan sanitation facilities....................................... 16
2.1 Drawings and BoQs............................................................................................................................... 16
3. Section 3: Construction and working procedures.......................................................................................... 17
3.1 General instructions.............................................................................................................................. 17
3.1.1 Safety and hygiene........................................................................................................................... 17
3.1.2 Quality of provided services and work............................................................................................. 19
3.1.3 Proper use of tools........................................................................................................................... 20
3.2 Construction procedures for double vault urine diverting dry toilet (UDDT)....................................... 21
3.2.1 Required tools.................................................................................................................................. 21
3.2.2 Construction materials..................................................................................................................... 22
3.2.3 Construction steps............................................................................................................................ 22
3.2.3.1 General requirements...................................................................................................................... 22
3.2.3.2 Site selection and preparation.......................................................................................................... 22
3.2.3.3 Construction of foundation slab....................................................................................................... 23
3.2.3.4 Construction of vaults...................................................................................................................... 24
3.2.3.5 Construction of superstructure........................................................................................................ 24
Technical Handbook
2
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
TABLE OF CONTENT
3.3 Construction procedure for flush toilets (cistern- or pour flush).......................................................... 25
3.3.1 Construction materials..................................................................................................................... 25
3.3.2 Construction steps............................................................................................................................ 25
3.3.2.1 General requirements...................................................................................................................... 25
3.3.2.2 Site selection and preparation.......................................................................................................... 25
3.3.2.3 Construction of foundation slab....................................................................................................... 26
3.3.2.4 Construction of cistern and toilet pans............................................................................................ 26
3.3.2.5 Construction of super structure....................................................................................................... 27
3.4 Construction procedure for septic tanks............................................................................................... 27
3.4.1 Construction steps............................................................................................................................ 27
3.4.1.1 General requirements...................................................................................................................... 27
3.4.1.2 Site selection and preparation.......................................................................................................... 28
3.4.1.3 Construction of foundation slab....................................................................................................... 28
3.4.1.4 Construction of walls........................................................................................................................ 28
3.4.1.5 Construction of top slab................................................................................................................... 28
3.5 Construction procedures for soak away pits......................................................................................... 29
3.5.1 Construction steps............................................................................................................................ 29
3.5.1.1 General requirements...................................................................................................................... 29
3.5.1.2 Site selection and preparation.......................................................................................................... 29
3.5.1.3 Construction of circular soak away................................................................................................... 29
3.6 Construction procedures for conservancy tank................................................................................... 30
3.6.1 Construction step............................................................................................................................. 30
3.6.1.1 General requirements...................................................................................................................... 30
3.6.1.2 Site selection and preparation.......................................................................................................... 30
3.6.1.3 Construction..................................................................................................................................... 30
4. Section 4: Use and maintenance of SafiSan facilities.................................................................................... 31
4.1 Introduction.......................................................................................................................................... 31
4.1.1 How men should use the UDDT........................................................................................................ 32
4.1.2 How women should use the UDDT................................................................................................... 33
4.1.3 How children should use the UDDT.................................................................................................. 34
4.1.4 Accessibility of UDDTs to people with disabilities............................................................................ 35
4.1.5 Cleaning the UDDT(see also appendix0).......................................................................................... 36
4.2 Repairs.................................................................................................................................................. 38
4.3 Safely emptying of the vault................................................................................................................. 38
4.3.1 Transport.......................................................................................................................................... 39
4.3.2 Reuse................................................................................................................................................ 40
4.3.3 Disposal............................................................................................................................................ 41
Technical Handbook
3
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
TABLE OF CONTENT
4.3.4 Troubleshooting................................................................................................................................ 41
4.4 Safely emptying the septic tank....................................................................................................... 43
4.4.1 Inspection and emptying a septic tank............................................................................................. 43
4.4.2 Transport and disposal of sludge from septic tanks......................................................................... 44
4.4.3 Exhauster services............................................................................................................................ 44
5. Section 5: Pictures of SafiSan toilets.............................................................................................................. 46
5.1 UDDT..................................................................................................................................................... 46
5.2 Flush and pour flush............................................................................................................................. 47
5.3 Treatment facilities (bio -digesters, anaerobic baffled reactors and sludge drying beds...................... 47
6. Appendices.................................................................................................................................................... 48
6.1 Technical drawings and Bills of Quantity............................................................................................... 48
6.1.1 Single door urine diversion dry toilet............................................................................................... 49
6.1.2 Double door urine diversion dry toilet............................................................................................. 53
6.1.3 Cistern flush toilet............................................................................................................................ 58
6.1.4 Pour flush toilet................................................................................................................................ 60
6.1.5 PPR urine diversion dry toilet........................................................................................................... 62
6.1.6 Steel tube urine diversion dry toilet................................................................................................. 66
6.1.7 Double vault for urine diversion dry toilet....................................................................................... 70
6.1.8 Underground vault for urine diversion dry toilet............................................................................. 72
6.1.9 Soak pits........................................................................................................................................... 73
6.1.10 Septic tank........................................................................................................................................ 75
6.1.11 Conservancy tank............................................................................................................................. 76
6.1.12 Bio digester....................................................................................................................................... 77
6.1.13 Baffled reactor.................................................................................................................................. 78
6.1.14 Drying bed........................................................................................................................................ 80
6.1.15 Composting bed............................................................................................................................... 81
6.1.16 Bills of Quantity................................................................................................................................ 82
6.1.16.1 BoQ single door urine diversion dry toilet................................................................................... 82
6.1.16.2 BoQ double door urine diversion dry toilet................................................................................. 85
6.1.16.3 BoQ cistern flush toilet................................................................................................................. 88
6.1.16.4 BoQ pour flush toilet.................................................................................................................... 94
Technical Handbook
4
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
TABLE OF CONTENT
6.1.16.5 BoQ PPR frame urine diversion dry toilet.................................................................................. 100
6.1.16.6 BoQ steel tube urine diversion dry toilet................................................................................... 101
6.1.16.7 BoQ double vault for urine diversion dry toilet.......................................................................... 102
6.1.16.8 BoQ underground vault for urine diversion dry toilet................................................................ 108
6.1.16.9 BoQ soak away pits.................................................................................................................... 111
6.1.16.10 BoQ septic tanks......................................................................................................................... 112
6.1.16.11 BoQ conservancy tanks.............................................................................................................. 113
6.1.16.12 BoQ biodigester.......................................................................................................................... 113
6.1.16.13 BoQ baffled reactor.................................................................................................................... 115
6.1.16.14 BoQ drying bed.......................................................................................................................... 114
6.1.16.15 BoQ composting bed.................................................................................................................. 117
6.2 Construction manuals......................................................................................................................... 118
6.2.1 Concrete panel toilet...................................................................................................................... 118
6.2.2 Concrete panel vault....................................................................................................................... 130
6.3 Toilet instructions................................................................................................................................ 139
6.3.1 How to use your toilet.................................................................................................................... 139
6.3.2 How to clean your toilet................................................................................................................. 140
Technical Handbook
5
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
Technical Handbook
6
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
0. Introduction
This handbook is a tool to be used by various people who are involved in the construction, maintenance and/or
service delivery of the SafiSan products. These tools range from procedures with respect to safely emptying the
SafiSan toilets to detailed construction drawings of all the UBSUP facilities. Since the handbook covers information
on various topics for various users, it is divided into 5 sections:
Section 1 starts with a general overview of the sanitation chain. The various components and their interrelationship
will be depicted. The second part will depict which parts of the sanitation chain UBSUP is to intervene. An overview
of all the SafiSan products, double vault toilets, flush toilets, septic and conservancy tanks will be shown. In this
overview pictures and animated drawings of the products including their specifications can be found. It also gives
basic technical information on the operation of the double vault toilet and septic tanks. This information gives a
broader picture of the SafiSan products and explains why certain steps during construction and maintenance (see
section 3) are important.
Section 2 has technical drawings including Bill of Quantities of all the SafiSan products and prices (based on Nairobi
prices) are mentioned. In combination with section 3, this section is of particular interest for contractors and local
craftsmen constructing the facilities.
Section 3 has construction manuals and advises with respect to the construction of the various SafiSan products.
In combination with section 2, this section is of particular interest for contractors and local craftsmen constructing
the facilities.
Section 4 has instructions on the operation and maintenance of the SafiSan products. This section includes main
preventive maintenance and small preventive maintenance instructions, proper and safe use of tools and possible
spare parts required. This section is useful for owners of SafiSan products, local artisans involved in maintenance
but also emptiers of the Safisan products.
Section 5 contains a picture overview of various facilities built.
In the handbook, certain principles and features are depicted in animated drawings. These drawings should en-
hance the technical information provided.
Technical Handbook
7
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
TREATMENT
...GIVE ME A
SECOND, PLEASE!
I AM THE ONE
SELLING MAIZE
THERE
Note
Each link of the chain is related to the other. To ensure a sustainable sanitation chain, each
link should be addressed.
Technical Handbook
8
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
Important in the sanitation chain is that each link should work properly. If for instance solid waste such as diapers
is thrown into a toilet, empting the toilet and treatment of the waste becomes difficult and reuse might not be pos-
sible, if the treatment plant is not working properly, the environment and public is at risk.
1.2 SafiSan: user interfaces, the dry and wet toilets
1.2.1 The dry toilets: how do they work?
The dry toilet is a toilet which doesn’t use water to flush away waste. Well known dry toilets are the commonly used
pit latrines and the Ventilated Improved Latrines ( VIP). Not well known dry toilets are the so-called UDDTs; Urine
Diversion Dry Toilets (UDDT). The UBSUP has adopted the UDDT in its up-scaling concept as the dry toilet option.
The VIP and pit latrines are therefore not discussed here in detail. The basic idea behind a UDDT is the separation
of faeces and urine. Separation takes place in the toilet! . If this is done properly, the toilets won’t smell and will not
attract flies. In order to do so, the inside of the toilet is different than from most toilets. The squatting pan or toilet
seat of a UDDT consists of two parts. One section collects urine and the other part collects faeces and toilet paper.
Faeces
hole
Faeces
hole
Faeces
hole
Technical Handbook
9
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
Technical Handbook
10
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
Technical Handbook
11
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
The pour flush toilet super structure and slab is similar to that of the VIP la-
trine, except that it uses a pour-flush pan with a siphon connection to allow
flushing of faeces using water.
.
Figure 8 – Pour flush toilet
Because there are no mechanical parts, pour flush toilets are quite robust and rarely require repair. Despite the fact
that water is used continuously in the toilet, it should be cleaned regularly to prevent the build up of organics and
or/stains. To prevent clogging of the pour flush toilet, it is recommended that dry cleansing solid waste materials
(sanitary pads, diapers, etc) be collected separately and not flushed down the toilet.
1.4 SafiSan: storage systems
1.4.1 Septic tank
A septic tank is a simple, low tech underground wastewater treatment system. Because septic tanks store and treat
wastewater partially onsite, they are often more economical than centralized sewer systems.
Technical Handbook
12
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
Because the wastewater stays for quite some time in the septic tank, the solids and liquids separate. The wastewater
forms three layers inside the tank. Solids lighter than water (such as greases and oils) float to the top forming a layer
of scum. Solids heavier than water settle at the bottom of the tank forming a layer of sludge. This leaves a middle
layer of partially clarified wastewater. This water is disposed of by soaking it away in the soak away pit.
1.4.2 Conservancy tank
Technical Handbook
13
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
Low income urban areas in Kenya predominantly use on-site sanitation facilities most of which are traditional pit
latrines with poor dilapidated superstructures. The toilet emptying is mostly done manually using buckets and drums
as shown in Picture 8. The faecal sludge is transported on wheelbarrows or makeshift handcarts and disposed off
in rivers and water channels.1 This is a major source of water resource pollution in many rivers flowing through the
informal settlements of Kenya which are chocking in faecal and solid waste.
1.5.2 Exhauster trucks
Exhauster trucks are very often used for emptying sepctic or conservancy tanks. Their main advantage is that they
are able to collect a lot of waste in 1 go (6000 – 10,000l). Exhausters truck suck out the liquid part of tanks and pits,
leaving the more solid parts behind. Sometimes manual emptiers are contracted to remove the remaining waste
from pits or tanks. Their main dis-advantage is the high cost of the services and also the accessibility of trucks into
areas. SafiSan: treatment systems
1.5.3 DEWATS
Decentralised wastewater treatment systems or DEWATS are very low tech, low maintenance treatment facilities.
DEWATS consist of different modules.
Sludge from DEWATS bio-digesters and anaerobic baffled reactors can be removed regularly (basically every 2 – 3
years) and put to dry in drying beds.
Technical Handbook
14
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
Note
Remember: proper treated faeces are a resource, not a waste!
Technical Handbook
15
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
bricks/blocks walling
2,100
to manufacturer spec's
2,100
2,100
2,100
bricks/blocks walling
Xmm thick brick/blocks
partition wall
100
100mm thick mass 100mm thick mass
concrete class X slab concrete class X slab
Y
100
100
100
SECTION Y - Y
75 x 50mm timber
wall plate 04. 04.
800+2X
03. 02.
X 800 X
ventilation gap
304
X
450
1,100
2,100
1,500
2,100
2,300
door wedge
plastic bowl urinal
1,650
800
915
inspection bend
X 800 X line of the roof above
339
100
X 800 X
Y
03. 02.
2100 mm H x 800mm W
.
Z.
GENERAL CONSTRUCTION
Project Title: Drawing Title: Designed & Drawn by: Notes: 'GL' denotes unfinished ground level. All slabs at ground level to be poured over 1000 gauge polythene Date: 07/02/2013
All dimensions are shown in mm unless otherwise specified. sheeting on 50mm thick murram blinding on hard-core
Pour Flush Toilet Edward Kung'u Measurement 'Y' depends on the ground soil condition
Up-scaling Basic Sanitation Drawings are not to be scaled. Only figured dimensions to be used. All soil under slabs and around external foundations to be poisoned
Sitting Type Approved by: Measurement 'X' depends on the width of the bricks Scale: 1 : 25
for Urban Poor ie: Dressed quarry stones = 100 / 150mm The Contractor must check and verify all dimensions on site before for termite control.
(UBSUP) commencement of any work. All soils on cut embankments to be stabilized. The slope not to exceed
Clay bricks = 100mm
Version 1.0 Concrete Brick = 150 / 175mm
the natural angle of repose. page:
For all R.C. work, refer to Structural Engineer's details.
Technical Handbook
16
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
Technical Handbook
17
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
IMPORTANT
• Never eat or drink while emptying a pit or septic tank. Because of the unhealthy environ-
ment you will easily contract a disease.
• Never smoke while emptying a pit or septic tank. Gases in the pit can explode easily, hurt-
ing or even killing you.
• Never work alone in a pit or septic tank. Gases can suddenly Keep your protective clothes
on at all times when at work.
• be released and some of these can be very dangerous.
It is very difficult not to spil waste when emptying a pit or septic tank. Since you are providing a service to people
you should make sure to leave the environment clean. Therefore follow the following steps in case of spilling waste:
• Remove the waste using a scoop or plastic bag;
• In case waste has polluted concrete, wash the surface with water and soap. The disinfect with a little bleach
or Jik;
• Use soil to cover the spilled waste on a non paved surface.
Technical Handbook
18
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
The tools that are used for emptying a pit should be cleaned after each emptying. Cleaning involves rinsing of the
tools and disinfecting them with Jik or bleach. After cleaning, the tools need to be dried properly before storing
them in an area outside the house. These tools should never be used for other purposes.
3.1.2 Quality of provided services and work
Quality is everyone’s responsibility. Quality should be part and parcel of one’s work. Quality is about meeting the
needs and expectations of customers.
When constructing a toilet, quality starts with the purchase of the right materials and basically ends with the com-
missioning of the final construction. If somewhere along this chain the quality of work is poor, it affects the quality of
the final construction. Poor mixing of cement results in poor binding material which affects the structural strength of
the toilet. Bad site preparation might result in a sagging of the construction.
When emptying a pit or septic tank, quality starts with proper preparation. Making sure that all the tools are col-
lected, that the job is done on time etc. And, last but not least, important is also that the place is left behind clean
.
Technical Handbook
19
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
If you do a good job, customers will come back to you. They appreciate the quality of work and will remember you
when additional work is required. Your business will cease when you run out of quality.
Technical Handbook
20
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
3.2 Construction procedures for double vault urine diverting dry toilet (UDDT)
3.2.1 Required tools
For the construction of the SafiSan UDDT toilets, various tools are required. Find below a table of tools which could
be used for construction of the facilities.
Technical Handbook
21
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
IMPORTANT
• The interior walls of the vaults MUST be plastered to minimize infiltration of moisture.
• The vault doors must close well to keep the faecal matter safely contained and prevent
water from entering the vault.
• The vaults must have good air circulation via vertical ventilation pipes that remove moisture
and odour above the level of the roof.
• Build prefabricated toilets on flat ground (high water table, rocky soils, loose soils) or partially underground
(low water table).
• Clear and level the ground where the toilet is to be located and remove the top soil and debris. The depth de-
pends on the type of soil and will be given by the site engineer.
• Make sure all of the materials and tools are at the site before each construction step is started.
• There should be a space of 1.5m between the vault door and the nearest wall to allow emptying.
Figure 20 – When constructing, leave enough space to enter the toilet freely.
Technical Handbook
22
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
Figure 21 – Use the right amount of sand and cement and never compromise with materials.
• Build foundation using quarry stones/concrete blocks using 1:3 mortar to the dimensions in the specific draw-
ing.
• Backfill the slab formation with marrum.
• Hand compact the foundation area.
• Place the dump proof membrane (DPM).
• Place concrete mix of 1:2:4 and 8mm reinforcement steel bar or BRC A98 mesh where necessary (e.g. black
cotton soil).
• Backfill the area around foundation with excavated soil.
2
Ratios given in cement: sand: aggregates
Technical Handbook
23
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
Note
The foundation slab should dry and cure for at least 2 days.
Build the vault using bricks/concrete blocks/stones/concrete panel. For other prefabricated options see the specific
manufacturer’s user instructions.
• Build the vault walls using mortar of mix 1:3 (cement: sand).
• Use the design drawing to set the height, length and width of the vault.
• Plaster the inside of the vault with a thin coat (2-3mm) mortar of mix 1:1.
• Cast the top slab and fix the squatting pan and anal cleansing pan where necessary.
Note
The top slab should dry and cure for at least 3 days.
Note
• Always clean the construction site after completion of the job.
• Allow use after 7 days for the in-situ toilets. For prefabricated, allow immediate use if there
are no parts fixed on-site using concrete.
3.3 Construction procedure for flush toilets (cistern- or pour flush)
3.3.1 Construction materials
For material list and BoQs see paragraph 6.1
3.3.2 Construction steps
3.3.2.1 General requirements
The basic design rules for Cistern Flush
• Ensure that there is a sewer network or septic tank and soak pit.
• Ensure that there is proper gradient to allow waste water flow by gravity to a sewer or septic tank via manholes.
• The manhole chambers must be built to the technical standards to avoid stagnation and blockage.
• Use a qualified plumber to install appropriate piping for waste water.
• All replaceable valves and fittings should be fitted in a way that allow for easy repairs and maintenance. NEVER
cover them with wall tiles or plaster.
3.3.2.2 Site selection and preparation
• The location of the cistern flush toilet should allow for easy piping and plumbing works
• The floor should have a drain in case of water overflow.
Figure 23 – A flush toilet should have a drain to drain away possible spillage
• Connect the overflow pipe of the cistern to the outside of the toilet cubicle.
Technical Handbook
25
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
Note
The foundation slab should dry and cure for at least 3 days to be strong enough for the instal-
lation of either sitting or squatting pan.
Fix the low level squatting pan before plastering the floor and sitting pan after plastering.
• Use mortar of mix 1:3 (cement: sand).
• Fix the sitting pan after plastering the floor according to the type and specification of the supplier. This has to
be done by a qualified plumber. Fix the pan tightly with screws on the floor.
• Plaster the walls with a thin coat (2-3mm) mortar of mix 1:1 before fixing the cisterns/relevant pipes.
Note
Ensure that the plaster works do not hinder the plumbing/fitting works
Technical Handbook
26
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
Figure 24 – The vent pipe should stick at least 50cm above the roof
• Fix the necessary sewage pipes/fittings leading to manhole chambers
3.4 Construction procedure for septic tanks
3.4.1 Construction steps
3.4.1.1 General requirements
The basic design rules for Septic tanks
• A septic tank must have at least two compartments, with T-shaped inlet baffle (100mm) and outlet baffle
(100mm). Each compartment must have an access manhole which is air tight
• All septic tanks shall discharge to a soak away
• There must be adequate and reliable water supply at all times
• Should be water tight
• A septic tank should have a minimum size (about 1,700 litres) to be capable of receiving one day’s max. Sewer-
age flow from a dwelling
• A septic tank shall have a means of access for the purpose of emptying and cleaning
• The depth in such a tank should be below the outlet invert level, not less than 1m and there is an air space of
not less than 200mm between the surface of the liquid contained therein and the underside of the top cover
• Inspection chambers must be installed at all bends and junctions of the drains
Technical Handbook
27
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
Technical Handbook
28
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
Technical Handbook
29
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
Technical Handbook
30
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
IMPORTANT
WATER is the main enemy of the UDDT. If water enters the vault, drying of the faeces slows down
and the toilet will start smelling and attracting flies.
The use of a UDDT may not be immediately obvious to some users. They may be hesitant to use it because they are
not sure how to separate the urine and the faeces. Education and public awareness creation are essential in achiev-
ing acceptance with users. The most common mistakes that have been documented are as follows:
1. Careless pouring of ash or wood shavings and dumping solid waste in the urine hole thus blocking the urine
pipe;
2. Dumping of solid waste such as sanitary towels and diapers (non-biodegradable items) into the faeces cham-
ber;
3. Defecating in the urine hole thus blocking the urine pipe (a mistake mostly made by children);
4. Urinating in the faeces chamber.
1
2
The mistakes above can be tackled if appropri-
ate training of the users is in the forefront.
1
The UDDT squatting pan has 3 holes. Two holes
(1) which are connected to the faeces chamber.
The last hole (2) is connected to the soak away
1 pit.
Technical Handbook
31
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
Note
Always wash your hands with soap and water after using the toilet.
5. After use, dispose the used tissue or paper in the big hole;
6. If you practice anal cleansing, please cleanse yourself on top of the urine section, if there is an anal cleansing
pan, please ensure that you cleanse yourself on top of the anal cleansing pan. That way, there is no cross-
contamination;
7. Put a scoop or a cupful of ash or wood shavings (drying agents) into the big hole ONLY. No ash should spill on
the urine hole/section to avoid blockage;
8. Replace the lid once you have finished to avoid bad odour;
Note
Please ensure that you aim at the urine hole whilst urinating.
NEVER urinate in the big hole because that will make the toilet smell badly.
9. If there is a urinal, ensure that there is no spillage of urine into the floor or dumping of any solid waste in the
urinal;
10. The urinals installed are waterless therefore use them appropriately to ensure that they do not smell. Aim at
the urinal to avoid spillage on the floor;
11. If there is no urinal in the toilet, please use the urine section (labelled 2);
12. Wash hands with soap and water after using the toilet.
Technical Handbook
32
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
Figure 30: Put ash in the big hole after a long call
7. If you practice anal cleansing, please cleanse yourself on top of the urine section, if there is an anal cleansing
pan; please ensure that you cleanse yourself on top of the anal cleansing pan. That way, there is no cross-
contamination;
8. Put a scoop or a cupful of ash or wood shavings (drying agents) into the big hole ONLY. No ash or wood shavings
should spill on the urine hole/section to avoid blockage;
9. Replace the lid once you have finished;
10. For urination, squat and ensure that you aim for the urine hole whilst urinating. Please do not urinate while
standing to avoid spillage. Squat on top of the big hole, facing the urine section, to aim for the urine hole;
11. If you practice anal cleansing, please cleanse yourself on top of the urine section, if there is an anal cleansing
pan; please ensure that you cleanse yourself on top of the anal cleansing pan. That way, there is no cross-
contamination;
12. Never throw sanitary towels and any other solid waste in the toilet. Use the dustbin instead;
13. Wash hands with soap and water after using the toilet.
Technical Handbook
33
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
Note
Parents: Your children will find it difficult to use the toilet initially. Please take some time to
teach them with the information and posters that have been provided. Monitor them initially
in the first few occasions to ensure that they are using the toilet correctly. Correct them when
they are not using it correctly so that common mistakes such as blockages do not occur.
Technical Handbook
34
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
Figure 32: Urine diversion seats for people with disabilities at Kentainers, Nairobi
Technical Handbook
35
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
IMPORTANT
• Never pour water in the toilet as it will enter the dehydration vault.
• Never use boiling water to clean the urine pipe.
Technical Handbook
36
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
Figure 34: Remember to always wash your hands after visiting a toilet!
Technical Handbook
37
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
4.2 Repairs
The common repairs involve the following components
• Urine pipe: Sometimes ash or faeces accumulates in the urine pipe causing blockages. Appropriate O&M is
required to ensure that the urine pipe does not completely block and will then need to be replaced;
• If the vault doors are lined with wood, they can easily be eaten by termites. It is important that wood is not used
to ensure sustainability of the doors. Steel should be used instead;
• Minor repairs are related to wear and tear such as replacement of door hinges and locks, resealing the door
panels and maintaining the ventilation pipes and rain covers.
Figure 35: Vault doors attacked by termites Figure 36: Blocked urine pipe and damaged UDDT pan
4.3 Safely emptying of the vault
1. Once the vault that you are currently using becomes full, please cover it with the lid that has been provided to
you. This ensures that nobody uses the vault during the treatment period
2. The lid with the handle is currently in use and the lid without the handle is not. No one should use the full
vault during the treatment period
3. Once the vault is full, ensure that it has enough ash for drying and leave it to dry for a minimum period of 6
months. The longer it stays, the better the quality will be for reuse.
4. Ensure that you have closed the vault door so that it is not accessible to children
5. You may open the vault from time to time to monitor the process. If you see that some sections require a little
bit more ash, please do add some. You can tell if some sections require a bit more ash if the faeces is bare and
has not been mixed with a drying agent. In addition, it is good to mix the content from time to time to ensure
that each of the sections has enough of the drying agent
6. You may therefore add more ash (or the drying agent used) and mix it with a spade so that it may dry uni-
formly.
7. Wash your hands with soap and water after you have handled the contents of the vaults
Note
Don’t worry! After the 6 months, the faeces are dry and odourless and looks like soil.
Technical Handbook
38
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
Technical Handbook
39
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
• If it is removed before a minimum of 6 months, manual emptiers should be employed to empty the faeces
chambers and transport it to the designated disposal or decentralised treatment points (sludge drying beds)
4.3.2 Reuse
• The risks involve how the faeces and or urine is applied on the crop, crop restriction and withholding period.
• The compost should be worked into the soil rather than distributed into the surface.
It is safest when applied to fruit trees, agro-forestry, or crops that are processed further such as coffee and
cotton rather than vegetables such as sukumawiki.
• The danger comes from the transmission of helminth eggs (worm infestation) if the faeces is used before the
6 month period.
• If the dehydrated faeces are used as soil conditioner on crops like tree crops, flowers, agro-forestry and the
users follow hygienic conditions then there are no risks as the helminth eggs will die gradually and will not
pose any dangers.
• The risks exist if the dehydrated faeces is used in plants prematurely before the six months or before further
treatment.
Figure 39 Faeces have been used as a soil conditioner for the maize plants
• Fresh unsorted urine should not be used as fertiliser immediately in case of typhoid within the household
members.
Note
Faeces are a resource! Treated faeces have a high content of organic matter which acts
as a good conditioner. It also contains considerable amounts of the nutrients nitrogen,
potassium, and phosphorous as well as other micronutrients. If ash has been used, it
provides an additional source of potassium!
Technical Handbook
40
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
4.3.3 Disposal
• There are no risks to human beings and the environment as long as the faeces from the UDDT has dehydrated
and decomposed for more than 6 months in the vault or has undergone further treatment in the decentralised
treatment points (DEWATs-sludge drying beds)
• Risks are there if it is removed and disposed off before the six month period. The emptiers who will therefore
be employed to empty the faeces chamber before the six months should have to wear protective equipment
such as gloves and boots to empty the vaults. See also paragraph 3.1.1.
• They should then wash their hands with soap and water after emptying the toilet.
4.3.4 Troubleshooting1
Pedestal or squatting pan is not tightly Fill any void space with an appropriate seal-
fixed to the slab. ant.
Bad smells from the Urine has become stagnant. This may re- Use a pipe cleaning snake of bottle cleaner
urine drainage or col- sult from leakages that cause urine pool- can be used to unblock the urine pipe.
lection system ing on surfaces, accumulation of urine in
Regular rinsing of the urine pipe with warm
the piping system or from a waterlogged
water (and caustic soda) can prevent block-
or clogged soak pit.
ages
Ensure that that all urine and anal cleansing
water pipes have adequate slope
In case of urine storage, makes sure that he
urine containers are not overflowing. Install
an overflow pipe on the urine container if
appropriate in order to avoid accidental
overflow
The vault is infested Faecal matter is wet or cover material has Add more cover material and make sure all
with flies or insects been insufficiently applied. the faeces are covered
One or more users are suffering from diar- Make sure that all possible users have been
rhea. trained on basic UDDT operation.
There has been a spike in the number of Ensure that an insect screen has been in-
untrained users e.g. visitors stalled on the vent pipe
There are fresh faeces Users or caretaker have removed the lid Make sure the drop-hole cover on the inac-
in the inactive vault and defecated in the resting/inactive tive vault is tightly fixed and clearly demar-
vault. cated to prevent accidental misuse
Technical Handbook
42
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
Advantages Disadvantages
An easy way of managing household waste Requires a reliable water supply
water where there is no sewer network
Soak away/seepage pits can be a source of
Easy to design and construct ground water pollution
Requires very little space Treats waste water only to about 40% BOD
and COD elimination
Has a long life span
No flies and odour
Low investment costs
4.4.1 Inspection and emptying a septic tank
• One needs to know where the septic tank is located. The tank has to be operated and maintained well.
• Make sure that the septic tank will not pollute the environment by discharging or leaking waste anywhere it is
not supposed to, that is, into the ground or any water source
• Ensure that roof water or surface water run-off cannot enter a domestic waste water treatment system.
• De-sludge the system at intervals appropriate to the tank capacity and the number of people resident in the
premises connected to it. De-sludging should be carried out by an authorized contractor or emptiers who are
conversant with the emptying of pit latrines.
• When a septic tank is not emptied, sewage can back up into the household toilet or waste may seep into ground.
• Check the toilets and ensure that they flow normally when flushed. Toilets that consistently flush slowly may be
a sign that your septic tank is getting full.
• Check every location where drainage pipes exit your house. This includes drain pipes and sinks. Look for any
leaks, pooling water, or signs of waste escaping from the drains or pipes.
• Carry out a smell check. If you smell waste or strong odors in your house, your septic tank may be backing up.
Technical Handbook
43
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
Figure 40: Strong smell in the house might indicate a filled up septic tank
4.4.2 Transport and disposal of sludge from septic tanks
Once the septic tank has been emptied the sludge should be transported by an exhauster or a manual emptier to a
treatment facility.
4.4.3 Exhauster services
Exhauster trucks offer faster and more efficient emptying and transport services of sludge from septic tanks. The ser-
vices are offered in most cities and towns either by licensed water utilities or private operators. The highest number of
private operators is currently found in Nairobi. Most exhausters cannot access pit latrines in low income urban areas
due to the dense housing patterns which hinder accessibility therefore when installing a septic tank, one must ensure
that the septic tank is accessible for exhauster services.
Advantages and disadvantages of Exhauster operators
Advantages Disadvantages
Fast and efficient High investment cost
Creates job opportunities High operation and maintenance cost
Provides an essential service in on site sanita- Cannot pump thick solid sludge
tion
Suction pipes are prone to blockage
Less health risks than human powered systems
Difficulty in accessing densely populated ar-
eas with poor accessibility.
Technical Handbook
44
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
Picture 41: Private exhaustion of a pit latrine at Dagoretti Corner Nairobi at a cost of KSh 10,000
In low income areas, many households and landlords are not able to afford the services of a private exhauster and
thus have to contact the licensed water utility whose price is subsided and is pro poor. Unfortunately most of water
utilities in Kenya have a maximum of 2 exhausters and they prioritise their services to the needs of public schools and
institutional facilities. Most residents therefore resort to manual pit emptying. Therefore only those who can afford
the emptying services should have septic tanks installed in their households.
Technical Handbook
45
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
5.1 UDDTs
Picture 42: Concrete panel vault with MgO-board su- Picture 43: Concrete panel vault with mabati super-
perstructure structure
Picture 44: Full MgO-board toilet Picture 45: Full MgO-board toilet; double unit
Picture 46: Full concrete panel toilet Picture 47: Underground vault with PPR framed super-
structure
Technical Handbook
46
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
5.3 Treatment facilities (bio -digesters, anaerobic baffled reactors and sludge drying beds
These type of facilities have not been constructed at the time of completing this document. Therefore pictures are
not yet available. As soon as they are constructed, pictures can be found on the UBSUP-Flickr account: http://www.
flickr.com/photos/ubsup/sets/.
Technical Handbook
47
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
APPENDICES
6.1 Technical drawings and bills of quantity;
6.2 Construction manuals.
6.3 Toilet instructions
Technical Handbook
48
6. Appendices
6.1 Technical drawings and Bills of Quantity
6.1.1 Single door urine diversion dry toilet
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
80
80
painted black
200 200 200 200
80
Steel plate shutter
600
600
painted black
680
150 150 150 150
GL GL GL
80
80
X 775 X 775 X
300 X 1,000 X 800
80
80
80
suspended concrete slab
150 150
bricks/blocks walling
600
X 775 X 775 X
680
80mm thick reinforced
suspended concrete slab
80
150 150
GL GL to Eng's specification
80
Y
mass concrete class X laid to ELEVATION 01
fall 1% slope to the back 450 450
mass concrete class X
Y
X
03 SECTION X - X
foundation footing
300
X
X
04
ECO plate (Squatting pan)
370
325
365 970 365
240
260
1,000
bricks/blocks walling
436
370
X
02 X 1,700 X
01
Y
X
GENERAL CONSTRUCTION
Project Title: Drawing Title: Designed & Drawn by: Notes: 'GL' denotes unfinished ground level. All slabs at ground level to be poured over 1000 gauge polythene Date: 07/02/2013
Single Door Urine Diversion 'PL' denotes permanent ventilation. sheeting on 50mm thick murram blinding on hard-core
Edward Kung'u Measurement 'Y' depends on the ground soil condition
Up-scaling Basic Sanitation All dimensions are shown in mm unless otherwise specified. All soil under slabs and around external foundations to be poisoned
Dry Toilet (UDDT). Measurement 'X' depends on the width of the bricks Scale: 1 : 25
for Urban Poor Approved by: Drawings are not to be scaled. Only figured dimensions to be used. for termite control.
Vaults, ie: Dressed quarry stones = 100 / 150mm
(UBSUP) The Contractor must check and verify all dimensions on site before All soils on cut embankments to be stabilized. The slope not to exceed
Clay bricks = 100mm
Version 1.0 commencement of any work. the natural angle of repose. page: 1/5
Concrete Brick = 150 / 175mm
For all R.C. work, refer to Structural Engineer's details.
Technical Handbook
49
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
10 X
10 mm thick plaster
on the inside of keys on the outside
bricks/blocks
450
325
175
175
ventilation gap
GIS roof at 10 degrees above the door. WALL SECTION
slope to approval
1,900
1,900
1,800
1,800
200mm gap left bricks/blocks walling
to allow ventilation
700
ECO plate (Squatting pan) concrete steps. (raiser 150mm) anal cleansing pan
(going 200mm)
150
80
80
80
150
(going 200mm) painted black
vault vault
600
680
450 100
530
1" urine hose
X 1,000 950
80
Y X
160
mass concrete class X 450 700 450 mass concrete class X
laid to fall 1% slope foundation footing
650 450 700 450 186
SECTION Y - Y SECTION X - X
GENERAL CONSTRUCTION
Project Title: Drawing Title: Designed & Drawn by: Notes: 'GL' denotes unfinished ground level. All slabs at ground level to be poured over 1000 gauge polythene Date: 07/02/2013
Single Door Urine Diversion Edward Kung'u 'PL' denotes permanent ventilation. sheeting on 50mm thick murram blinding on hard-core
Measurement 'Y' depends on the ground soil condition
Up-scaling Basic Sanitation All dimensions are shown in mm unless otherwise specified. All soil under slabs and around external foundations to be poisoned
Dry Toilet (UDDT). Measurement 'X' depends on the width of the bricks Scale: 1 : 25
for Urban Poor Approved by: Drawings are not to be scaled. Only figured dimensions to be used. for termite control.
Sections, ie: Dressed quarry stones = 100 / 150mm
(UBSUP) The Contractor must check and verify all dimensions on site before All soils on cut embankments to be stabilized. The slope not to exceed
Clay bricks = 100mm
Version 1.0 commencement of any work. the natural angle of repose. page: 3/5
Concrete Brick = 150 / 175mm
For all R.C. work, refer to Structural Engineer's details.
Technical Handbook
50
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
450
175
175
ventilation gap
above the door
ventilation holes
480
800
1,800
1,900
1,900
1900mm H x 800mm W bricks/blocks walling
steel door
160
50mm dia pvc
80
80
80
outlet pipe
steps. (raiser 150mm) Steel plate shutter
600
680
680
(going 200mm) painted black
150
700 600 700
2,000
ELEVATION 01 ELEVATION 03
GENERAL CONSTRUCTION
Project Title: Drawing Title: Designed & Drawn by: Notes: 'GL' denotes unfinished ground level. All slabs at ground level to be poured over 1000 gauge polythene Date: 07/02/2013
Single Door Urine Diversion 'PL' denotes permanent ventilation. sheeting on 50mm thick murram blinding on hard-core
Edward Kung'u Measurement 'Y' depends on the ground soil condition
Up-scaling Basic Sanitation All dimensions are shown in mm unless otherwise specified. All soil under slabs and around external foundations to be poisoned
Dry Toilet (UDDT). Measurement 'X' depends on the width of the bricks Scale: 1 : 25
for Urban Poor Approved by: Drawings are not to be scaled. Only figured dimensions to be used. for termite control.
Elevations, ie: Dressed quarry stones = 100 / 150mm
(UBSUP) The Contractor must check and verify all dimensions on site before All soils on cut embankments to be stabilized. The slope not to exceed
Version Clay bricks = 100mm
commencement of any work. the natural angle of repose. page: 4/5
Concrete Brick = 150 / 175mm
For all R.C. work, refer to Structural Engineer's details.
Technical Handbook
51
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
450
450
pipe 450mm above the roof
2,000 325
175
75 x 50mm timber
wall plate 1900mm H x 800mm W
steel door
1,900
1,900
1,800
bricks/blocks walling
80
80
80
80
600
partition wall X 775 X 775 X
600
bricks/blocks walling
680
680
80
Y
ELEVATION 02 SECTION Z - Z
GENERAL CONSTRUCTION
Project Title: Drawing Title: Designed & Drawn by: Notes: 'GL' denotes unfinished ground level. All slabs at ground level to be poured over 1000 gauge polythene Date: 07/02/2013
Single Door Urine Diversion 'PL' denotes permanent ventilation. sheeting on 50mm thick murram blinding on hard-core
Edward Kung'u Measurement 'Y' depends on the ground soil condition
Up-scaling Basic Sanitation All dimensions are shown in mm unless otherwise specified. All soil under slabs and around external foundations to be poisoned
Dry Toilet (UDDT). Measurement 'X' depends on the width of the bricks Scale: 1 : 25
for Urban Poor Approved by: Drawings are not to be scaled. Only figured dimensions to be used. for termite control.
Elevations, ie: Dressed quarry stones = 100 / 150mm
(UBSUP) The Contractor must check and verify all dimensions on site before All soils on cut embankments to be stabilized. The slope not to exceed
Version 1.0 Clay bricks = 100mm
commencement of any work. the natural angle of repose. page: 5/5
Concrete Brick = 150 / 175mm
For all R.C. work, refer to Structural Engineer's details.
Technical Handbook
52
6.1.2 Double door urine diversion dry toilet
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
80
80
80
Steel plate shutter (going 200mm)
painted black
600
600
600
painted black
80
80
X 775 X 775 X 775 X 775 X
300 X 1,000
ELEVATION 03
bricks/blocks walling
ELEVATION 02
160
80
80
80
bricks/blocks walling
600
bricks/blocks walling
600
80mm thick reinforced
680
suspended concrete slab
80
to Eng's specification
80
Y
mass concrete class X laid to 450
fall 1% slope to the back
ELEVATION 01 mass concrete class X
foundation footing
SECTION X - X
06
05
X 775 X 775 X 775 X 775 X
X
ECO plate (Squatting pan)
X1 X1
ECO plate (Squatting pan)
1,000
1,300
bricks/blocks walling
80mm thick reinforced
suspended concrete slab
to Eng's specification
X
07
concrete steps. (raiser 150mm) FLOOR PLAN SUSPENDED SLAB
(going 200mm)
08
GENERAL CONSTRUCTION
Project Title: Drawing Title: Designed & Drawn by: Notes: 'GL' denotes unfinished ground level. All slabs at ground level to be poured over 1000 gauge polythene Date: 07/02/2013
Measurement 'Y' depends on the ground soil condition 'PV' denotes permanent Ventiration sheeting on 50mm thick murram blinding on hard-core
Up-scaling Basic Sanitation Double Door Urine Diversion Edward Kung'u All soil under slabs and around external foundations to be poisoned
Measurement 'X' depends on the width of the bricks All dimensions are shown in mm unless otherwise specified. Scale: 1 : 25
for Urban Poor Dry Toilet (UDDT). Approved by: ie: Dressed quarry stones = 100 / 150mm Drawings are not to be scaled. Only figured dimensions to be used. for termite control.
(UBSUP) Vaults, Clay bricks = 100mm The Contractor must check and verify all dimensions on site before All soils on cut embankments to be stabilized. The slope not to exceed
Version 1.0 Concrete Brick = 150 / 175mm commencement of any work. the natural angle of repose. page: 1/5
For all R.C. work, refer to Structural Engineer's details.
Technical Handbook
53
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
z
03, 02, 02,
02 02
01,
50mm dia pvc
03 01. outlet pipe X 1,000 X
ECO plate to
manufacturer spec's
X
X
315 260 425 1" urine hose pipe 1900mm H x 800mm W
365
700
450
to soak pit steel door
775
line of the roof
X
800
970
600
600
1,700
1,700
pv
pv
100mm Ø PVC plastic bowl urinal
ventilation pipe
775
to manufacturer spec's
300 1,150
X
700
365
X
X
1,050
100mm Ø PVC
plastic bowl urinal ventilation pipe
365
X, X,
700
775
urine hole
200mm gap left
to allow ventilation
Y, Y, Y Y
X
concrete steps.
800
970
600
600
1,700
1,700
pv
pv
(raiser 150mm)
(going 200mm)
Xmm thick brick/blocks
partition wall Xmm thick brick/blocks
775
336 240 425 X 200 200 200 200 370 260 370 200 200 200 200 partition wall
450
700
365
X
X
line of the roof above
X 1,000 X
300 1,000 01.
X
X
03 ventilation holes
03, 01,
z
GENERAL CONSTRUCTION
Project Title: Drawing Title: Designed & Drawn by: Notes: 'GL' denotes unfinished ground level. All slabs at ground level to be poured over 1000 gauge polythene Date: 07/02/2013
Measurement 'Y' depends on the ground soil condition 'PV' denotes permanent Ventiration sheeting on 50mm thick murram blinding on hard-core
Up-scaling Basic Sanitation Double Door Urine Diversion Edward Kung'u All soil under slabs and around external foundations to be poisoned
Measurement 'X' depends on the width of the bricks All dimensions are shown in mm unless otherwise specified. Scale: 1 : 25
for Urban Poor Dry Toilet (UDDT). Approved by: ie: Dressed quarry stones = 100 / 150mm Drawings are not to be scaled. Only figured dimensions to be used. for termite control.
(UBSUP) Plans Layout, Clay bricks = 100mm The Contractor must check and verify all dimensions on site before All soils on cut embankments to be stabilized. The slope not to exceed
Version 1.0 Concrete Brick = 150 / 175mm commencement of any work. the natural angle of repose. page: 2/5
For all R.C. work, refer to Structural Engineer's details.
Technical Handbook
54
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
450
325
ventilation gap
275
275
GIS roof at 10 degrees above the door .
slope to approval
75 x 50mm timber
wall plate
Ventilation holes left on
the wall to approval
1,800
1,800
1,800
bricks/blocks walling
200mm gap left
to allow ventilation plastic bowl urinal
to manufacturer spec's
800
X 1,000 X
ECO plate (Squatting pan)
bricks/blocks walling
150
80
200
concrete steps. (raiser 150mm) .
80
80
painted black (going 200mm) Steel plate shutter
vault vault painted black
600
600
480
500 100
80
80
Y
80
Y
160
mass concrete class X 1,150 X 800 650 450 700 450 150 mass concrete class X
foundation footing
SECTION Y - Y
SECTION X - X
GENERAL CONSTRUCTION
Project Title: Drawing Title: Designed & Drawn by: Notes: 'GL' denotes unfinished ground level. All slabs at ground level to be poured over 1000 gauge polythene Date: 07/02/2013
Measurement 'Y' depends on the ground soil condition 'PV' denotes permanent Ventiration sheeting on 50mm thick murram blinding on hard-core
Up-scaling Basic Sanitation Double Door Urine Diversion Edward Kung'u All soil under slabs and around external foundations to be poisoned
Measurement 'X' depends on the width of the bricks All dimensions are shown in mm unless otherwise specified. Scale: 1 : 25
for Urban Poor Dry Toilet (UDDT). Approved by: ie: Dressed quarry stones = 100 / 150mm Drawings are not to be scaled. Only figured dimensions to be used. for termite control.
(UBSUP) Sections, Clay bricks = 100mm The Contractor must check and verify all dimensions on site before All soils on cut embankments to be stabilized. The slope not to exceed
Version 1.0 Concrete Brick = 150 / 175mm commencement of any work. the natural angle of repose. page: 3/5
For all R.C. work, refer to Structural Engineer's details.
Technical Handbook
55
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
175
ventilation gap
above the door
480
ventilation holes
1,800
1,900
bricks/blocks walling
160
Steel plate shutter
80
80
painted black
680
outlet pipe
150
700 600 1,250 600 700 (going 200mm)
ELEVATION 01 ELEVATION 03
GENERAL CONSTRUCTION
Project Title: Drawing Title: Designed & Drawn by: Notes: 'GL' denotes unfinished ground level. All slabs at ground level to be poured over 1000 gauge polythene Date: 07/02/2013
Double Door Urine Diversion Measurement 'Y' depends on the ground soil condition 'PV' denotes permanent Ventiration sheeting on 50mm thick murram blinding on hard-core
Up-scaling Basic Sanitation Edward Kung'u All soil under slabs and around external foundations to be poisoned
Dry Toilet (UDDT). Measurement 'X' depends on the width of the bricks All dimensions are shown in mm unless otherwise specified. Scale: 1 : 25
for Urban Poor Approved by: ie: Dressed quarry stones = 100 / 150mm Drawings are not to be scaled. Only figured dimensions to be used. for termite control.
Elevations, Clay bricks = 100mm The Contractor must check and verify all dimensions on site before All soils on cut embankments to be stabilized. The slope not to exceed
(UBSUP)
Version 1.0 Concrete Brick = 150 / 175mm commencement of any work. the natural angle of repose. page: 5/5
For all R.C. work, refer to Structural Engineer's details.
Technical Handbook
56
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
450
pipe 450mm above the roof
450
450
GIS roof at 10 degrees
325 slope to approval
75 x 50mm timber
wall plate 1900mm H x 800mm W
steel door
1,900
1,900
1,800
bricks/blocks walling bricks/blocks walling
80
80
80
600
600
680
X 775 X 775 775 X 775 X
80
50mm dia pvc
Y
outlet pipe
1,300 300
ELEVATION 02 SECTION Z - Z
GENERAL CONSTRUCTION
Project Title: Drawing Title: Designed & Drawn by: Notes: 'GL' denotes unfinished ground level. All slabs at ground level to be poured over 1000 gauge polythene Date: 07/02/2013
Double Door Urine Diversion Measurement 'Y' depends on the ground soil condition 'PV' denotes permanent Ventiration sheeting on 50mm thick murram blinding on hard-core
Up-scaling Basic Sanitation Edward Kung'u All soil under slabs and around external foundations to be poisoned
Dry Toilet (UDDT). Measurement 'X' depends on the width of the bricks All dimensions are shown in mm unless otherwise specified. Scale: 1 : 25
for Urban Poor Approved by: ie: Dressed quarry stones = 100 / 150mm Drawings are not to be scaled. Only figured dimensions to be used. for termite control.
Elevations, All soils on cut embankments to be stabilized. The slope not to exceed
(UBSUP) Clay bricks = 100mm The Contractor must check and verify all dimensions on site before
Version 1.0 Concrete Brick = 150 / 175mm commencement of any work. the natural angle of repose. page: 4/5
For all R.C. work, refer to Structural Engineer's details.
Technical Handbook
57
6.1.3 Cistern flush toilet
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
354
ventilation gap Ventilation holes left on
.
450
above the door the wall to approval
bricks/blocks walling
2,100
to manufacturer spec's
2,100
2,100
2,100
bricks/blocks walling
1,650
Xmm thick brick/blocks
partition wall
100
100
100
100
GIS roof at 10 degrees
ELEVATION 02 ELEVATION 04 mass concrete class X
slope to approval
foundation footing
Z
SECTION Y - Y
75 x 50mm timber
wall plate 04 04
800+2X
03
X 800 X 02
354
ventilation gap
200
above the door pv
450
GIS roof at 10 degrees
slope to approval
1,500
2,100
1,500+2X
2,300
2,100
1,650
400 plastic bowl urinal
plastic bowl urinal
to manufacturer spec's
to manufacturer spec's Y Y
800
400
915
steel door hinges
Asian squatting pan)
300
100
100mm thick mass
concrete class X slab
100
X 03 02 X 800 X
2100 mm H x 800mm W
Z
GENERAL CONSTRUCTION
Project Title: Drawing Title: Designed & Drawn by: Notes: 'GL' denotes unfinished ground level. All slabs at ground level to be poured over 1000 gauge polythene Date: 07/02/2013
All dimensions are shown in mm unless otherwise specified. sheeting on 50mm thick murram blinding on hard-core
Cirstern Flush Toilet Edward Kung'u Measurement 'Y' depends on the ground soil condition
Up-scaling Basic Sanitation Drawings are not to be scaled. Only figured dimensions to be used. All soil under slabs and around external foundations to be poisoned
Squatting Type Measurement 'X' depends on the width of the bricks Scale: 1 : 25
for Urban Poor Approved by: The Contractor must check and verify all dimensions on site before for termite control.
ie: Dressed quarry stones = 100 / 150mm
(UBSUP) commencement of any work. All soils on cut embankments to be stabilized. The slope not to exceed
Clay bricks = 100mm
Version 1.0 the natural angle of repose. page: 1/1
Concrete Brick = 150 / 175mm
For all R.C. work, refer to Structural Engineer's details.
Technical Handbook
58
6.1.4 Pour flush toilet
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
354
ventilation gap Ventilation holes left on
.
above the door the wall to approval
bricks/blocks walling
2,100
to manufacturer spec's
2,100
2,100
2,100
bricks/blocks walling
Xmm thick brick/blocks
partition wall
100
100mm thick mass 100mm thick mass
concrete class X slab concrete class X slab
Y
100
100
100
GIS roof at 10 degrees
ELEVATION 02 ELEVATION 04 mass concrete class X
slope to approval
foundation footing
Z.
SECTION Y - Y
75 x 50mm timber
wall plate 04. 04.
800+2X
03. 02.
X 800 X
304
ventilation gap
above the door pv
161
450
GIS roof at 10 degrees ceramic pedestal toilet
slope to approval
1,100
partition wall
bricks/blocks walling
2,400
1,500
2,100
door wedge
2,300
1,500+2X
plastic bowl urinal
1,650
to manufacturer spec's plastic bowl urinal
Y. Y. to manufacturer spec's
1,000
800
915
steel door hinges
X
ceramic sitting toilet
inspection bend
X 800 X line of the roof above
339
100
100mm thick mass
concrete class X slab
100
Y X 800 X
03. 02.
2100 mm H x 800mm W
.
Z.
GENERAL CONSTRUCTION
Project Title: Drawing Title: Designed & Drawn by: Notes: 'GL' denotes unfinished ground level. All slabs at ground level to be poured over 1000 gauge polythene Date: 07/02/2013
All dimensions are shown in mm unless otherwise specified. sheeting on 50mm thick murram blinding on hard-core
Pour Flush Toilet Edward Kung'u Measurement 'Y' depends on the ground soil condition
Up-scaling Basic Sanitation Drawings are not to be scaled. Only figured dimensions to be used. All soil under slabs and around external foundations to be poisoned
Sitting Type Measurement 'X' depends on the width of the bricks Scale: 1 : 25
for Urban Poor Approved by: The Contractor must check and verify all dimensions on site before for termite control.
ie: Dressed quarry stones = 100 / 150mm
(UBSUP) commencement of any work. All soils on cut embankments to be stabilized. The slope not to exceed
Clay bricks = 100mm
Version 1.0 the natural angle of repose. page:
Concrete Brick = 150 / 175mm
For all R.C. work, refer to Structural Engineer's details.
Technical Handbook
59
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
354
ventilation gap Ventilation holes left on
.
450
above the door the wall to approval
bricks/blocks walling
2,100
2,100
2,100
2,100
bricks/blocks walling
1,650
Xmm thick brick/blocks
partition wall
100
100
100
100
100
Z
SECTION Y - Y
75 x 50mm timber
wall plate 04 04
800+2X
03
X 800 X 02
ventilation gap
100mm Ø PVC
200
above the door pv
ventilation pipe
X
GIS roof at 10 degrees
slope to approval
Asian type squatting toilet
2100 mm H x 800mm W Xmm thick brick/blocks
timber door partition wall
2,400
1,500
2,100
1,500+2X
2,300
915
steel door hinges
Asian squatting pan)
X
X 800 X line of the roof above
100mm thick mass 300
concrete class X slab
100
03 02 X 800 X
2100 mm H x 800mm W
Z
GENERAL CONSTRUCTION
Project Title: Drawing Title: Designed & Drawn by: Notes: 'GL' denotes unfinished ground level. All slabs at ground level to be poured over 1000 gauge polythene Date: 07/02/2013
All dimensions are shown in mm unless otherwise specified. sheeting on 50mm thick murram blinding on hard-core
Pour Flush Toilet Edward Kung'u Measurement 'Y' depends on the ground soil condition
Up-scaling Basic Sanitation Drawings are not to be scaled. Only figured dimensions to be used. All soil under slabs and around external foundations to be poisoned
Squatting Type Measurement 'X' depends on the width of the bricks Scale: 1 : 25
for Urban Poor Approved by: The Contractor must check and verify all dimensions on site before for termite control.
ie: Dressed quarry stones = 100 / 150mm
(UBSUP) commencement of any work. All soils on cut embankments to be stabilized. The slope not to exceed
Clay bricks = 100mm
Version 1.0 the natural angle of repose. page: 5/5
Concrete Brick = 150 / 175mm
For all R.C. work, refer to Structural Engineer's details.
Technical Handbook
60
6.1.5 PPR urine diversion dry toilet
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
80
80
painted black
200 200 200 200
80
150
Steel plate shutter
600
600
painted black
680
150 150 150
GL GL GL
80
80
X 775 X 775 X
300 X 1,000 X 800
80
80
80
suspended concrete slab
150
hose pipe to soak pit bricks/blocks walling
600
bricks/blocks walling
600
X 775 X 775 X
680
80mm thick reinforced
suspended concrete slab
80
80
Y
mass concrete class X laid to ELEVATION 01
fall 1% slope to the back 450 450
Y.
SECTION X - X mass concrete class X
03 foundation footing
2,000
300
X
X
04
ECO plate (Squatting pan) 370
325
365 970 365
240
260
1,000
X X
bricks/blocks walling
436
370
X
02 X 1,700 X
01
GENERAL CONSTRUCTION
Project Title: Drawing Title: Designed & Drawn by: Notes: 'GL' denotes unfinished ground level. All slabs at ground level to be poured over 1000 gauge polythene Date: 07/02/2013
Measurement 'Y' depends on the ground soil condition 'PV' denotes permanent Ventiration sheeting on 50mm thick murram blinding on hard-core
Up-scaling Basic Sanitation Edward Kung'u All soil under slabs and around external foundations to be poisoned
Measurement 'X' depends on the width of the bricks All dimensions are shown in mm unless otherwise specified. Scale: 1 : 25
for Urban Poor Approved by: ie: Dressed quarry stones = 100 / 150mm Drawings are not to be scaled. Only figured dimensions to be used. for termite control.
(UBSUP) Clay bricks = 100mm The Contractor must check and verify all dimensions on site before All soils on cut embankments to be stabilized. The slope not to exceed
Concrete Brick = 150 / 175mm commencement of any work. the natural angle of repose. page:
For all R.C. work, refer to Structural Engineer's details.
Technical Handbook
61
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
1,850
1,850
to allow ventilation
150
Steel plate shutter
80
painted black
Xmm thick brick/blocks
vault partition wall X 775 X 775 X
600
505 175
1" urine hose
1,000 950
80
160
mass concrete class X 450 700 450
laid to fall 1% slope
GENERAL CONSTRUCTION
Project Title: Drawing Title: Designed & Drawn by: Notes: 'GL' denotes unfinished ground level. All slabs at ground level to be poured over 1000 gauge polythene Date: 07/02/2013
Measurement 'Y' depends on the ground soil condition 'PV' denotes permanent Ventiration sheeting on 50mm thick murram blinding on hard-core
Up-scaling Basic Sanitation Edward Kung'u All soil under slabs and around external foundations to be poisoned
Measurement 'X' depends on the width of the bricks All dimensions are shown in mm unless otherwise specified. Scale: 1 : 25
for Urban Poor Approved by: ie: Dressed quarry stones = 100 / 150mm Drawings are not to be scaled. Only figured dimensions to be used. for termite control.
(UBSUP) Clay bricks = 100mm The Contractor must check and verify all dimensions on site before All soils on cut embankments to be stabilized. The slope not to exceed
Concrete Brick = 150 / 175mm commencement of any work. the natural angle of repose. page:
For all R.C. work, refer to Structural Engineer's details.
Technical Handbook
62
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
338
1'' PPR pipe Tee
1,850
steel door
550
quarry stones/ bricks wall
ELEVATION 02 ELEVATION 01
GENERAL CONSTRUCTION
Project Title: Drawing Title: Designed & Drawn by: Notes: 'GL' denotes unfinished ground level. All slabs at ground level to be poured over 1000 gauge polythene Date: 07/02/2013
Measurement 'Y' depends on the ground soil condition 'PV' denotes permanent Ventiration sheeting on 50mm thick murram blinding on hard-core
Up-scaling Basic Sanitation Edward Kung'u All soil under slabs and around external foundations to be poisoned
Measurement 'X' depends on the width of the bricks All dimensions are shown in mm unless otherwise specified. Scale: 1 : 25
for Urban Poor Approved by: ie: Dressed quarry stones = 100 / 150mm Drawings are not to be scaled. Only figured dimensions to be used. for termite control.
(UBSUP) Clay bricks = 100mm The Contractor must check and verify all dimensions on site before All soils on cut embankments to be stabilized. The slope not to exceed
Concrete Brick = 150 / 175mm commencement of any work. the natural angle of repose. page:
For all R.C. work, refer to Structural Engineer's details.
Technical Handbook
63
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
ELEVATION 04 ELEVATION 03
GENERAL CONSTRUCTION
Project Title: Drawing Title: Designed & Drawn by: Notes: 'GL' denotes unfinished ground level. All slabs at ground level to be poured over 1000 gauge polythene Date: 07/02/2013
Measurement 'Y' depends on the ground soil condition 'PV' denotes permanent Ventiration sheeting on 50mm thick murram blinding on hard-core
Up-scaling Basic Sanitation Edward Kung'u All soil under slabs and around external foundations to be poisoned
Measurement 'X' depends on the width of the bricks All dimensions are shown in mm unless otherwise specified. Scale: 1 : 25
for Urban Poor Approved by: ie: Dressed quarry stones = 100 / 150mm Drawings are not to be scaled. Only figured dimensions to be used. for termite control.
(UBSUP) Clay bricks = 100mm The Contractor must check and verify all dimensions on site before All soils on cut embankments to be stabilized. The slope not to exceed
Concrete Brick = 150 / 175mm commencement of any work. the natural angle of repose. page:
For all R.C. work, refer to Structural Engineer's details.
Technical Handbook
64
6.1.6 Steel tube urine diversion dry toilet
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
80
80
painted black
200 200 200 200
80
150
Steel plate shutter
600
600
painted black
680
150 150 150
GL GL GL
80
80
X 775 X 775 X
300 X 1,000 X 800
80
80
80
suspended concrete slab
150
hose pipe to soak pit bricks/blocks walling
600
bricks/blocks walling
600
X 775 X 775 X
680
80mm thick reinforced
suspended concrete slab
80
80
Y
mass concrete class X laid to ELEVATION 01
fall 1% slope to the back 450 450
Y.
SECTION X - X mass concrete class X
03 foundation footing
2,000
300
X
X
04
ECO plate (Squatting pan) 370
325
365 970 365
240
260
1,000
X X
bricks/blocks walling
436
370
X
02 X 1,700 X
01
GENERAL CONSTRUCTION
Project Title: Drawing Title: Designed & Drawn by: Notes: 'GL' denotes unfinished ground level. All slabs at ground level to be poured over 1000 gauge polythene Date: 07/02/2013
Single Door Urine Diversion Measurement 'Y' depends on the ground soil condition 'PV' denotes permanent Ventiration sheeting on 50mm thick murram blinding on hard-core
Up-scaling Basic Sanitation Edward Kung'u All soil under slabs and around external foundations to be poisoned
Dry Toilet (UDDT). Measurement 'X' depends on the width of the bricks All dimensions are shown in mm unless otherwise specified. Scale: 1 : 25
for Urban Poor Approved by: ie: Dressed quarry stones = 100 / 150mm Drawings are not to be scaled. Only figured dimensions to be used. for termite control.
Vaults, All soils on cut embankments to be stabilized. The slope not to exceed
(UBSUP) Clay bricks = 100mm The Contractor must check and verify all dimensions on site before
Version 1.0 Concrete Brick = 150 / 175mm commencement of any work. the natural angle of repose. page: 1/4
For all R.C. work, refer to Structural Engineer's details.
Technical Handbook
65
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
1900mm H x 800mm W
ironsteel door
950
950
1/4'' steel square tube
1/4'' steel square tube
950
950
ECO plate (Squatting pan)
393 267 483
concrete steps. (raiser 150mm)
(going 200mm)
150
Steel plate shutter
80
painted black
Xmm thick brick/blocks
vault partition wall X 775 X 775 X
600
505
1" urine hose
150 150
1,000 950
pipe to soak pit
80
160
450 700 450 450 1,400 450
mass concrete class X
laid to fall 1% slope
GENERAL CONSTRUCTION
Project Title: Drawing Title: Designed & Drawn by: Notes: 'GL' denotes unfinished ground level. All slabs at ground level to be poured over 1000 gauge polythene Date: 07/02/2013
Single Door Urine Diversion Measurement 'Y' depends on the ground soil condition 'PV' denotes permanent Ventiration sheeting on 50mm thick murram blinding on hard-core
Up-scaling Basic Sanitation Edward Kung'u All soil under slabs and around external foundations to be poisoned
Dry Toilet (UDDT). Measurement 'X' depends on the width of the bricks All dimensions are shown in mm unless otherwise specified. Scale: 1 : 25
for Urban Poor Approved by: ie: Dressed quarry stones = 100 / 150mm Drawings are not to be scaled. Only figured dimensions to be used. for termite control.
Sections, All soils on cut embankments to be stabilized. The slope not to exceed
(UBSUP) Clay bricks = 100mm The Contractor must check and verify all dimensions on site before
Version 1.0 Concrete Brick = 150 / 175mm commencement of any work. the natural angle of repose. page: 2/4
For all R.C. work, refer to Structural Engineer's details.
Technical Handbook
66
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
338
1'' PPR pipe Tee
1,850
iron steel door
550
quarry stones/ bricks wall
ELEVATION 02 ELEVATION 01
GENERAL CONSTRUCTION
Project Title: Drawing Title: Designed & Drawn by: Notes: 'GL' denotes unfinished ground level. All slabs at ground level to be poured over 1000 gauge polythene Date: 07/02/2013
Single Door Urine Diversion Measurement 'Y' depends on the ground soil condition 'PV' denotes permanent Ventiration sheeting on 50mm thick murram blinding on hard-core
Up-scaling Basic Sanitation Edward Kung'u All soil under slabs and around external foundations to be poisoned
Dry Toilet (UDDT). Measurement 'X' depends on the width of the bricks All dimensions are shown in mm unless otherwise specified. Scale: 1 : 25
for Urban Poor Approved by: ie: Dressed quarry stones = 100 / 150mm Drawings are not to be scaled. Only figured dimensions to be used. for termite control.
Elevations, All soils on cut embankments to be stabilized. The slope not to exceed
(UBSUP) Clay bricks = 100mm The Contractor must check and verify all dimensions on site before
Version Concrete Brick = 150 / 175mm commencement of any work. the natural angle of repose. page: 3/4
For all R.C. work, refer to Structural Engineer's details.
Technical Handbook
67
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
ELEVATION 04 ELEVATION 03
GENERAL CONSTRUCTION
Project Title: Drawing Title: Designed & Drawn by: Notes: 'GL' denotes unfinished ground level. All slabs at ground level to be poured over 1000 gauge polythene Date: 07/02/2013
Single Door Urine Diversion Measurement 'Y' depends on the ground soil condition 'PV' denotes permanent Ventiration sheeting on 50mm thick murram blinding on hard-core
Up-scaling Basic Sanitation Edward Kung'u All soil under slabs and around external foundations to be poisoned
Dry Toilet (UDDT). Measurement 'X' depends on the width of the bricks All dimensions are shown in mm unless otherwise specified. Scale: 1 : 25
for Urban Poor Approved by: ie: Dressed quarry stones = 100 / 150mm Drawings are not to be scaled. Only figured dimensions to be used. for termite control.
Elevations, All soils on cut embankments to be stabilized. The slope not to exceed
(UBSUP) Clay bricks = 100mm The Contractor must check and verify all dimensions on site before
Version Concrete Brick = 150 / 175mm commencement of any work. the natural angle of repose. page: 4/4
For all R.C. work, refer to Structural Engineer's details.
Technical Handbook
68
6.1.7 Double vault for urine diversion dry toilet
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
80
GL GL
ECO plate (Squatting pan) bricks/blocks walling
Vault A Vault B
700
50mm thick reinforced
Toilet
hose pipe to soak pit concrete slab
bricks/blocks walling
to Eng's specification
150 1,000 150
ELEVATION X-X mass concrete class X
ECO plate (Squatting pan)
Steel plate shutter foundation footing
Toilet
GL painted black
GL
GL GL
700
Vault A
650
bricks/blocks walling
GL bricks/blocks walling
480 150
GL Vault A Vault B
bricks/blocks walling
1,550
550
150
X
530
bricks/blocks walling
for super structure
100
240
bricks/blocks walling
1,000
1,550 380
concrete slab
to Eng's specification ECO plate (Squatting pan)
150
Y
04
ELEVATION 01 LAYOUT PLAN
GENERAL CONSTRUCTION
Project Title: Drawing Title: Designed & Drawn by: Notes: 'GL' denotes unfinished ground level. All slabs at ground level to be poured over 1000 gauge polythene Date: 07/02/2013
Single Door Urine Diversion 'PV' denotes permanent ventilation. sheeting on 50mm thick murram blinding on hard-core
Edward Kung'u Measurement 'Y' depends on the ground soil condition
Up-scaling Basic Sanitation All dimensions are shown in mm unless otherwise specified. All soil under slabs and around external foundations to be poisoned
Dry Toilet (UDDT). Measurement 'X' depends on the width of the bricks Scale: 1 : 25
for Urban Poor Approved by: Drawings are not to be scaled. Only figured dimensions to be used. for termite control.
Excavated Vaults, ie: Dressed quarry stones = 100 / 150mm
(UBSUP) The Contractor must check and verify all dimensions on site before All soils on cut embankments to be stabilized. The slope not to exceed
Clay bricks = 100mm
Version 1.0 commencement of any work. the natural angle of repose. page: 1/1
Concrete Brick = 150 / 175mm
For all R.C. work, refer to Structural Engineer's details.
Technical Handbook
69
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
80
80
80
Steel plate shutter (going 200mm)
painted black
150
Steel plate shutter
600
600
600
150
painted black
150
150
GL GL
80
80
X 775 X 775 X 775 X 775 X
300 X 1,000
ELEVATION 03
bricks/blocks walling
ELEVATION 02
160
80
80
80
bricks/blocks walling
600
bricks/blocks walling
600
80mm thick reinforced
680
suspended concrete slab
80
to Eng's specification
80
Y
mass concrete class X laid to 450
fall 1% slope to the back
ELEVATION 01 mass concrete class X
foundation footing
SECTION X - X
06
05
X 775 X 775 X 775 X 775 X
X
ECO plate (Squatting pan)
X1 X1
ECO plate (Squatting pan)
1,000
1,300
bricks/blocks walling
80mm thick reinforced
suspended concrete slab
to Eng's specification
X
07
concrete steps. (raiser 150mm) FLOOR PLAN SUSPENDED SLAB
(going 200mm)
08
GENERAL CONSTRUCTION
Project Title: Drawing Title: Designed & Drawn by: Notes: 'GL' denotes unfinished ground level. All slabs at ground level to be poured over 1000 gauge polythene Date: 07/02/2013
Measurement 'Y' depends on the ground soil condition 'PV' denotes permanent Ventiration sheeting on 50mm thick murram blinding on hard-core
Up-scaling Basic Sanitation Double Door Urine Diversion Edward Kung'u All soil under slabs and around external foundations to be poisoned
Measurement 'X' depends on the width of the bricks All dimensions are shown in mm unless otherwise specified. Scale: 1 : 25
for Urban Poor Dry Toilet (UDDT). Approved by: ie: Dressed quarry stones = 100 / 150mm Drawings are not to be scaled. Only figured dimensions to be used. for termite control.
(UBSUP) Vaults, Clay bricks = 100mm The Contractor must check and verify all dimensions on site before All soils on cut embankments to be stabilized. The slope not to exceed
Version 1.0 Concrete Brick = 150 / 175mm commencement of any work. the natural angle of repose. page: 1/1
For all R.C. work, refer to Structural Engineer's details.
Technical Handbook
70
6.1.8 Underground vault for urine diversion dry toilet
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
80
GL GL
ECO plate (Squatting pan) bricks/blocks walling
Vault A Vault B
700
50mm thick reinforced
Toilet
hose pipe to soak pit concrete slab
bricks/blocks walling
to Eng's specification
150 1,000 150
ELEVATION X-X mass concrete class X
ECO plate (Squatting pan)
Steel plate shutter foundation footing
Toilet
GL painted black
GL
GL GL
700
Vault A
650
bricks/blocks walling
GL bricks/blocks walling
480 150
GL Vault A Vault B
bricks/blocks walling
1,550
550
150
X
530
bricks/blocks walling
for super structure
100
240
bricks/blocks walling
1,000
1,550 380
concrete slab
to Eng's specification ECO plate (Squatting pan)
150
Y
04
ELEVATION 01 LAYOUT PLAN
GENERAL CONSTRUCTION
Project Title: Drawing Title: Designed & Drawn by: Notes: 'GL' denotes unfinished ground level. All slabs at ground level to be poured over 1000 gauge polythene Date: 07/02/2013
Single Door Urine Diversion 'PV' denotes permanent ventilation. sheeting on 50mm thick murram blinding on hard-core
Edward Kung'u Measurement 'Y' depends on the ground soil condition
Up-scaling Basic Sanitation All dimensions are shown in mm unless otherwise specified. All soil under slabs and around external foundations to be poisoned
Dry Toilet (UDDT). Measurement 'X' depends on the width of the bricks Scale: 1 : 25
for Urban Poor Approved by: Drawings are not to be scaled. Only figured dimensions to be used. for termite control.
Excavated Vaults, ie: Dressed quarry stones = 100 / 150mm
(UBSUP) The Contractor must check and verify all dimensions on site before All soils on cut embankments to be stabilized. The slope not to exceed
Clay bricks = 100mm
Version 1.0 commencement of any work. the natural angle of repose. page: 1/1
Concrete Brick = 150 / 175mm
For all R.C. work, refer to Structural Engineer's details.
Technical Handbook
71
6.1.9 Soak pits
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
straw fill
reinforced concrete
50 to 100mm hard-core
15mm thick plaster
FGL FGL
150
150mm dia. pvc drainage pipe
from the septic tank
200mm thick concrete brick
wall with full joints
1/3 H
200
pvc bend
A A
100mm thick concrete brick 200mm thick concrete brick
chamber with dry joints wall with full joints
2/3 H
H
PLAN A
50 to 100mm hard-core
200 D 200
200 D 200
1 25 5 3.25 59.35
200mm thick concrete
200
2 50 7 3.6 89.3 brick wall with dry joints
3 100 10 5 193.25
150mm dia. pvc drainage pipe
from the septic tank
A. D
A.
Square Soak pit
Type No of Users Depth (H) in m Perimeter (P) in m Area of absorption
100mm thick concrete brick
1 25 5 9 54 chamber with dry joints
2 50 7 16 128
3 100 8 25 225
200
PLAN B
Technical Handbook
72
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
100
. inlet pipe laid at gradient 200mm thick layer
200
not less than 1/200 of granular fill
1,200
C 150 Ø
G G
1,000
200mm thick honeycomb
block work
200
200 1,000 200
200mm thick honeycomb
200 1,000 200
block work
200
G. C 150 Ø G.
1,000
200
Technical Handbook
73
6.1.10 Septic tank
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
300
150 450
150mm baffle wall 100 150mm dia pvc pipe
Y
Inlet M.H Outlet M.H
750
300
100mm mass concrete To sub soil irrigation
class x slab or soak away pit
F2
carrying 150mm thick masonry wall 10mm plastering on both sides
F2
plastered on both sides 100mm concrete partition wall with E
10mm plastering on both sides
H
200mm Masonry Wall With
10mm plastering on both sides
Outlet M.H
600x450 M.H
Cover & Frame
200
Litres Persons Intervals (Yrs) A B C D E F1 F2
G G
600
1,000
A B C 3,000 10 3 800 1,000 1,000 3,000 1,400 1,500 1,400
200
6,000 20 3 800 1,400 1,200 3,600 1,400 1,500 1,400
H
Plan
Technical Handbook
74
6.1.11 Conservancy tan
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
450 x 600mm
450 x 600mm
manhole cover
manhole cover
Y
200mm thick 100mm dia. vent pipe
975 450 975 975 450 930 645
masonry wall plaster
in both sides 1nlet manhole
GL GL GL
200 2,000 200 500 200 2,000 200 600
350
250
pvc pipe
200
200
Secondary tank Primary tank 200mm thick
2,000
masonry wall plaster
in both sides
1,650
1,750
1,500
mass concrete
Secondary tank Primary tank slab class 20/20
400
200
100
100
600
4,000
4,400
SECTION X - X
inlet manhole
200
450 x 600mm
1,500
manhole cover
1,900 600 1,900
GL GL 200mm thick
masonry wall plaster
in both sides
200
200
200 2,000 200 500 200 2,000 200
100mm thick pvc pipe 100mm diameter
connecting the tanks inlet PVC pipe
2,000
Y
Primary tank
GROUND LAYOUT PLAN mass concrete
slab class 20/20
400
SECTION Y - Y
Technical Handbook
75
6.1.12 Bio digester
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
800
78
250
600 600 600
Tap
125
1,000
700
267
1,500
IC 150
Y Y 375 150
1,500
NECK DETAIL. (Scale 1: 15)
R8-250-C/C
350
350
Inlet pipe
1,200 900mm Dia. precast concrete culvert
12Y
gas out let ( used as a formwork for concrete 600 x 600mm concrete cover 300mm Ø RC column
150
700
650
700
Y12
860
Y8 Y8 Y12 R8-250-C/C
Compressed 750 200 200
Backfilling
129
Compressed Expansion Chamber
1,450
Backfilling
DETAIL B
850
1,533
150mm Sanitation Pipe PVC DETAIL C
2,300
2,547
Y12 Y12
C C
850
BRC A-142
3,150
4,289
1,479
Bio-Digester
850
600
300
5 R8-250-C/C
17
4,001
4,000
4,
2,660
4,301
300
350
B B
intermediate
350
ring beam
1,298
842
Y12 Y12
997
5,299
3,200 3,200
5,299
300
200
5,499
592
Ø at 45° A
5,934
957
DETAIL A
936
936
6,256
6,256
165
2 Y8
2,700 1,000 2,700
R6-250 C/C
Diameter Excavation 7,200
2 Y8
SECTION ALONG
Cross Section Y-Y THE BEAMS
GENERAL CONSTRUCTION
Project Title: Drawing Title: Designed & Drawn by: Notes: 'GL' denotes unfinished ground level. All slabs at ground level to be poured over 1000 gauge polythene Date: 07/02/2013
'PV' denotes permanent Veneration sheeting on 50mm thick murram blinding on hard-core
124m3 Bio-digester Edward Kung'u Measurement 'Y' depends on the ground soil condition
Up-scaling Basic Sanitation All dimensions are shown in mm unless otherwise specified. All soil under slabs and around external foundations to be poisoned
Measurement 'X' depends on the width of the bricks Scale: 1 : 25
for Urban Poor Approved by: Drawings are not to be scaled. Only figured dimensions to be used. for termite control.
ie: Dressed quarry stones = 100 / 150mm
(UBSUP) Version 1.0 The Contractor must check and verify all dimensions on site before All soils on cut embankments to be stabilized. The slope not to exceed
Clay bricks = 100mm
commencement of any work. the natural angle of repose. page:
Concrete Brick = 150 / 175mm
For all R.C. work, refer to Structural Engineer's details.
Technical Handbook
76
6.1.13 Baffled reactor
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
X
25mm dia. GI vent 25mm dia. GI vent
pipe with gate valve pipe with gate valve .
for gas release for gas release
200 400 200 1,000 200 1,000 200 1,000 200 1,000 200 1,000 200 1,000 200
200 7,800
200 x 100mm
8,000 8,000
gas vent hole 200 x 100mm
200
200
200
200
200
gas vent hole
250
250
200
200
100mm PVC
50
50
150mm PVC
200
200
in let pipe in let pipe
800
800
500
500
900
900
200 800
inlet trench
1,400
1,400
200mm PVC.
1,400
1,400
200
200
out pipe
500
500
Y Y Y. Y.
IC
500
500
IC IC manhole cover IC
1,100
1,100
3,400
200mm PVC to detail
200
200
200
200
1,000
200 1,000
200 1,000
in let pipe
500
500
1,400
1,400
150mm PVC
900
900
1,400
1,400
500
500
150mm PVC in let pipe
800
800
800 200
in let pipe
inlet trench
50
50
250
250
200mm thick
200
200
partition wall
250
200
200
200
200
200
200
200
200 1,200 200 1,000 200 1,000 200 1,000 200 1,000 200 1,000 200 957 350 200 1,600 200 1,000 200 1,000 200 1,000 200 1,000 200 1,000 200
100mm PVC
in let pipe
X
INTERNAL PLAN TOP VIEW
100mm PVC 100mm PVC pipe 200 x 100mm gas vent hole manholes lid to detail A
in let pipe 200 950 1,100 950 200
100 450 100 100 450 100 100 450 100 100 450 100
175
30
175
GL GL
100mm dia pvc tee pipe
400 25 400 25 400
300
150 75
150
100
inlet
500
IC
200
840
trench 150mm PVC out let pipe
150mm PVC
215
40
40
in let pipe
100
200mm thick masonry wall
110
300
plastered on both sides
800 140
450
150mm PVC 800 200 300 300 1,000 200 1,000 200 1,000 200 1,000 200 1,000 200 1,000 1,000
2,425
170
2,425
100mm PVC pipe.
in let pipe
2,200
2,425
140
2,000
1,825
200mm thick 100 100 100 100
200 400 400 310
masonry wall 150mm thick concrete slab.
150
400
200 750
150 150
150
150
BAFFLED REACTOR SECTION Y-Y BAFFLED REACTOR SECTION X-X MANHOLE COVER
Technical Handbook
77
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
X.
X,
for gas release
pipe with gate valve
for gas release 200 7,800
200 400 200 1,000 200 1,000 200 1,000 200 1,000 200 1,000 200 1,000 200
200
200
200
750
200
200
200
200
200
200
750
1,050
1,050
500
500
200 x 100mm
200 x 100mm
2,300
gas vent hole
2,300
2,300
gas vent hole
500
500
900
900
2,900
2,900
2,900
2,900
inlet trench
150mm PVC
100mm PVC in let pipe
500
500
in let pipe
200
200mm PVC
.
out pipe
500
500
Y, Y, Y' IC Y'
500
500
IC IC IC
2,100
2,100
6,400
1,000 200
1,000 200
200
200
200
1,000
200
200mm PVC
500
500
in let pipe
200
200
200
150mm PVC
500
500
150mm PVC in let pipe
in let pipe
inlet trench
200
1,200
500
500
200mm thick
900
900
partition wall
2,900
2,900
2,900
2,900
500
500
2,300
2,300
2,300
100mm PVC
750
500
in let pipe 1,050
1,050
250
200
200
200
200
200
200
200
200
200
200 1,600 200 1,000 200 1,000 200 1,000 200 1,000 200 1,000 200
900 140
450
X.
X,
170
INTERNAL PLAN TOP VIEW 140
MANHOLE COVER
119 210 119 120 210 120 119 210 119 200mm PVC out let pipe
30
GL GL GL GL
400 25 400 25 400
250
300
150 75
150
inlet
500
IC
200
840
trench
150mm PVC
215
40
40
in let pipe
100
manholes lid to detail A
110
300
2,425
150mm PVC in let pipe 200mm thick masonry wall
2,025
2,425
2,200
2,200
plastered on both sides
2,000
200mm thick
1,825
masonry wall 800 200 300 300 1,000 200 1,000 200 1,000 200 1,000 200 1,000 200 1,000 1,000 100mm PVC pipe 100 100 100 100 100 100
700 400 400 400 400
150
150
150
150
150
150
Technical Handbook
78
6.1.14 Drying bed
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
X
25mm dia. GI vent 25mm dia. GI vent
pipe with gate valve pipe with gate valve .
for gas release for gas release
200 400 200 1,000 200 1,000 200 1,000 200 1,000 200 1,000 200 1,000 200
200 7,800
200 x 100mm
8,000 8,000
gas vent hole 200 x 100mm
200
200
200
200
200
gas vent hole
250
250
200
200
100mm PVC
50
50
150mm PVC
200
200
in let pipe in let pipe
800
800
500
500
900
900
200 800
inlet trench
1,400
1,400
200mm PVC.
1,400
1,400
200
200
out pipe
500
500
Y Y Y. Y.
IC
500
500
IC IC manhole cover IC
1,100
1,100
3,400
200mm PVC to detail
200
200
200
200
1,000
200 1,000
200 1,000
in let pipe
500
500
1,400
1,400
150mm PVC
900
900
1,400
1,400
500
500
150mm PVC in let pipe
800
800
800 200
in let pipe
inlet trench
50
50
250
250
200mm thick
200
200
partition wall
250
200
200
200
200
200
200
200
200 1,200 200 1,000 200 1,000 200 1,000 200 1,000 200 1,000 200 957 350 200 1,600 200 1,000 200 1,000 200 1,000 200 1,000 200 1,000 200
100mm PVC
in let pipe
X
INTERNAL PLAN TOP VIEW
100mm PVC 100mm PVC pipe 200 x 100mm gas vent hole manholes lid to detail A
in let pipe 200 950 1,100 950 200
100 450 100 100 450 100 100 450 100 100 450 100
175
30
175
GL GL
100mm dia pvc tee pipe
400 25 400 25 400
300
150 75
150
100
inlet
500
IC
200
840
trench 150mm PVC out let pipe
150mm PVC
215
40
40
in let pipe
100
200mm thick masonry wall
110
300
plastered on both sides
800 140
450
150mm PVC 800 200 300 300 1,000 200 1,000 200 1,000 200 1,000 200 1,000 200 1,000 1,000
2,425
170
2,425
100mm PVC pipe.
in let pipe
2,200
2,425
140
2,000
1,825
200mm thick 100 100 100 100
200 400 400 310
masonry wall 150mm thick concrete slab.
150
400
200 750
150 150
150
150
BAFFLED REACTOR SECTION Y-Y BAFFLED REACTOR SECTION X-X MANHOLE COVER
Technical Handbook
79
6.1.15 Composting bed
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
6,600
steel sheet ridge cap.
100 3,150 100 3,150 100
100 x 100 x 4mm thick steel
3,200 3,200 column painted to approval
steel trusses to struct's
engineer's specification .
4,034
100 x 50 x 2mm thick "Z" purlins
fix on the steel truss.
948
1,865
1,148
100
1,150
455
02
100 x 100 x 4mm thick steel
column painted to approval
1,990
concrete coping
roof fall 15% roof fall 15%
4,200
200mm thick, 500mm high
4,150
masonry wall
plastered on the insides
550
150mm thick concrete
class Q floor slab with
B.R.C. mesh type A145
150
ELEVATION 01
8,600
100
translucent roofing
pvc roofing sheet .
4,200
4,150
roof fall 15% roof fall 15% 100 x 100 x 4mm thick steel
column painted to approval
100
150mm thick concrete
class Q floor slab with
01 01 B.R.C. mesh type A145
Technical Handbook
80
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
6,000 4,000
4,600
4,600
drying bed demonstration point
above the ground
12,200
Expansion
Parking Bay Bio-digester
chamber
Technical Handbook
81
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
Item Description Size Unit Quantity Unit cost Total Contribution Subsidy
in Ksh Landlord/Lady UBSUP
CONCRETE WORKS
1 Portland cement 50kg bags 6
2 Building sand tonnes 2
3 Ballast 1/4" tonnes 1
4 Hardcore tonnes 1
5 Burnt Bricks 9"X6"X4" pcs 500
6 BRC mesh (commercial) Medium gauge ms 2
7 Shuttering Timber 6"x1" ft 60
8 Poles for shuttering 3ft x dia 3" pcs 2
9 Poles for scaffolding 8ft x dia 3" pcs 2
10 Y8 Reinforcement bars 12m pcs 1
SANITATION WARE
1 Plastic squatting pan pcs 1
2 Plastic nipple 3/4'' external dia pcs 1
3 Transparent hose pipe for squatting pan 1'' internal dia ft 6
4 Prefabricated plastic urinal pcs 1
5 Transparent hose pipe for urinal 1'' internal dia ft 6
VENTILATION
1 PVC Vent pipe Class B 4"x10ft pcs 0,5
2 PVC Vent pipe cover pcs 1
DOORS
1 Door with frame and wall pass 2000m x 0.8m pcs 1
2 Door hinges 4" pcs 2
3 Tower bolt 4" pcs 1
4 Tower bolt 2" pcs 1
5 Screws 1 3/4'' pcs 20
6 Back door steel panels and steel frame painted 75cm X 80cm pcs 2
ROOFING
1 Corrugated iron sheets 2m x 32gauge pcs 3
2 Roofing timber 4"X2" ft 35
3 Roofing nails Standard kg 0,5
HAND WASHING FACILITY
1 Complete hand washing facility 20 ltr 1
GENERAL
1 Wire nails 4" kg 0,5
2 Wire nails 2" kg 0,5
3 Wire nails 1 1/2'' kg 0,5
4 Wall-pass kg 3
5 Urine soak pit Lump sum 1
6 Thread seal Tape pcs 1
7 Transport Lump sum 1
Sub Total (material)
A Skilled labour Man days 5
B Unskilled labour Man days 5
Sub Total (labour)
Grant total
Technical Handbook
82
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
Item Description Size Unit Quantity Unit cost Total Contribution Subsidy
in Ksh Landlord/Lady UBSUP
CONCRETE WORKS
1 Portland Cement 50kg bags 5
2 Building sand tonnes 2
3 Ballast 1/4" tonnes 1
4 Hardcore tonnes 1
5 Quarry stones 14"X6"X6" MS 10
6 BRC mesh (commercial) Medium gauge MS 2
7 Shuttering Timber 6"x1" ft 60
8 Poles for shuttering 3ft x dia 3" pcs 2
9 Poles for scaffolding 8ft x dia 3" pcs 2
10 Y8 Reinforcement bars 12m pcs 1
SANITATION WARE
1 Plastic squatting pan pcs 1
2 Plastic nipple 3/4'' external dia pcs 1
3 Transparent hose pipe for squatting pan
1'' internal dia ft 6
4 Prefabricated plastic urinal pcs 1
5 Transparent hose pipe for urinal 1'' internal dia ft 6
VENTILATION
1 PVC Vent pipe Class B 4"x10ft pcs 0,5
2 PVC Vent pipe cover pcs 1
DOORS
1 Door with frame and wall pass 2000m x 0.8m pcs 1
2 Door hinges 4" pcs 2
3 Tower bolt 4" pcs 1
4 Tower bolt 2" pcs 1
5 Screws 1 3/4'' pcs 20
6 Back door steel panels and steel frame75cm
painted
X 80cm pcs 2
ROOFING
1 Corrugated iron sheets 2m x 32gauge pcs 3
2 Roofing timber 4"X2" ft 35
3 Roofing nails Standard kg 0,5
HAND WASHING FACILITY
1 Complete hand washing facility 20 ltr 1
GENERAL
1 Wire nails 4" kg 0,5
2 Wire nails 2" kg 0,5
3 Wire nails 1 1/2'' kg 0,5
4 Wall-pass kg 3
5 Urine soak pit Lump sum 1
6 Thread seal Tape pcs 1
7 Transport Lump sum 1
Sub Total (material)
A Skilled labour Man days 5
B Unskilled labour Man days 5
Sub Total (labour)
Grant total
Landlords/Lady signature and date % %
WSP Tech. Manager signature and date
Technical Handbook
83
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
Item Description Size Unit Quantity Unit cost Total Contribution Subsidy
in Ksh Landlord/Lady UBSUP
CONCRETE WORKS
1 Portland cement 50kg bags 5
2 Building sand tonnes 2
3 Ballast 3/4'' and 1/2'' tonnes 1
4 Hardcore tonnes 1
5 Concrete bricks 14"X6"X6" MS 10
6 BRC mesh (commercial) Medium gauge MS 2
7 Shuttering Timber 6"x1" ft 60
8 Poles for shuttering 3ft x dia 3" pcs 2
9 Poles for scaffolding 8ft x dia 3" pcs 2
10 Y8 Reinforcement bars 12m pcs 1
SANITATION WARE
1 Plastic squatting pan pcs 1
2 Plastic nipple 3/4'' external dia pcs 1
3 Transparent hose pipe for squatting pan 1'' internal dia ft 6
4 Prefabricated plastic urinal pcs 1
5 Transparent hose pipe for urinal 1'' internal dia ft 6
VENTILATION
1 PVC Vent pipe Class B 4"x10ft pcs 0,5
2 PVC Vent pipe cover pcs 1
DOORS
1 Door with frame and wall pass 2000m x 0.8m pcs 1
2 Door hinges 4" pcs 2
3 Tower bolt 4" pcs 1
4 Tower bolt 2" pcs 1
5 Screws 1 3/4'' pcs 20
6 Back door steel panels and steel frame painted 75cm X 80cm pcs 2
ROOFING
1 Corrugated iron sheets 2m x 32gauge pcs 3
2 Roofing timber 4"X2" ft 35
3 Roofing nails Standard kg 0,5
HAND WASHING FACILITY
1 Complete hand washing facility 20 ltr 1
GENERAL
1 Wire nails 4" kg 0,5
2 Wire nails 2" kg 0,5
3 Wire nails 1 1/2'' kg 0,5
4 Wall-pass kg 3
5 Urine soak pit Lump sum 1
6 Thread seal Tape pcs 1
7 Transport Lump sum 1
Sub Total (material)
A Skilled labour Man days 5
B Unskilled labour Man days 5
Sub Total (labour)
Grant total
Landlords/Lady signature and date % %
WSP Tech. Manager signature and date
Technical Handbook
84
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
Item Description Size Unit Quantity Unit cost Total Contribution Subsidy
in Ksh Landlord/Lady UBSUB
CONCRETE WORKS
1 Portland cement 50kg bags 11
2 Building sand tonnes 3,5
3 Ballast 1/4" tonnes 1,5
4 Hardcore tonnes 2
5 Burnt Bricks 9"X6"X4" pcs 900
6 BRC mesh (commercial) Medium gauge ms 4
7 Shuttering Timber 6"x1" ft 120
8 Poles for shuttering 3ft x dia 3" pcs 4
9 Poles for scaffolding 8ft x dia 3" pcs 4
10 Y8 Reinforcement bars 12m pcs 2
SANITATION WARE
1 Plastic squatting pan pcs 2
2 Plastic nipple 3/4'' external dia pcs 2
3 Transparent hose pipe for squatting pan 1'' internal dia ft 12
4 Prefabricated plastic urinal pcs 2
5 Transparent hose pipe for urinal 1'' internal dia ft 10
VENTILATION
1 PVC Vent pipe Class B 4"x10ft pcs 1
2 PVC Vent pipe cover pcs 2
DOORS
1 Door with frame and wall pass 2000m x 0.8m pcs 2
2 Door hinges 4" pcs 4
3 Tower bolt 4" pcs 2
4 Tower bolt 2" pcs 2
5 Screws 1 3/4'' pcs 40
6 Back door steel panels and steel frame painted 75cm X 80cm pcs 4
ROOFING
1 Corrugated iron sheets 2m x 32gauge pcs 6
2 Roofing timber 4"X2" ft 70
3 Roofing nails Standard kg 1
HAND WASHING FACILITY
1 Complete hand washing facility 20 ltr 1
GENERAL
1 Wire nails 4" kg 1
2 Wire nails 2" kg 1
3 Wire nails 1 1/2'' kg 1
4 Wall-pass kg 6
5 Urine soak pit Lump sum 1
6 Thread seal Tape pcs 2
7 Transport Lump sum 1
Sub Total (material)
A Skilled Labour Man days 9
B Unskilled Labour Man days 9
Sub Total (labour)
Grant total
Technical Handbook
85
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
Technical Handbook
86
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
Technical Handbook
87
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
Item Description Size Unit Quantity Unit cost Total Contribution Subsidy
in Ksh Landlord/Lady UBSUB
CONCRETE WORKS
1 Portland Cement 50kg bags 6
2 Building sand tonnes 3
3 Ballast 1/4" tonnes 0.5
4 Hardcore tonnes 0.5
5 Burnt Bricks 9"X6"X4" pcs 450
SANITATION WARE
1 Cistern flush sitting toilet pcs 1
2 Plastic nipple 3/4'' external dia pcs 1
3 Transparent hose pipe for urinal 1'' internal dia ft. 3
4 Prefabricated Plastic urinal pcs 1
VENTILATION
1 Black PVC Vent pipe Class B 4"x10ft pcs 0.5
2 PVC Vent pipe cover pcs 1
DOORS
1 Steel door with frame 2000m x 0.8m pcs 1
2 Door hinges 4" pcs 2
3 Tower bolt 4" pcs 1
4 Tower bolt 2" pcs 1
5 Screws 1 3/4'' pcs 30
ROOFING
1 Corrugated Iron Sheets 2m x 32gauge pcs 2
2 Roofing Timber 4"X2" ft. 45
3 Roofing Nails Standard kg 0.5
HAND WASHING FACILITY
1 Complete Hand washing facility 20 ltr 1
GENERAL
1 Wire nails 4" kg 0.5
2 Wire nails 2" kg 0.5
3 Wire nails 1 1/2'' kg 0.5
4 Wall-pass kg 3
5 Urine Soak pit pcs 1
6 Thread seal Tape Lump sum 1
7 Transport Lump sum 1
Sub Total (material)
A Skilled labour Man days 5
B Unskilled labour Man days 5
Sub Total (labour)
Grant total
Technical Handbook
88
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
Item Description Size Unit Quantity Unit cost Total Contribution Subsidy
in Ksh Landlord/Lady UBSUP
CONCRETE WORKS
1 Portland Cement 50kg bags 5
2 Building sand tonnes 3
3 Ballast 1/4" tonnes 0.5
4 Hardcore tonnes 0.5
5 Quarry stone 15"X6"X8" ms 8
SANITATION WARE
1 Cistern flush sitting toilet pcs 1
2 Plastic nipple 3/4'' external dia pcs 1
3 Transparent hose pipe for urinal 1'' internal dia ft. 3
4 Prefabricated Plastic urinal pcs 1
VENTILATION
1 Black PVC Vent pipe Class B 4"x10ft pcs 0.5
2 PVC Vent pipe cover pcs 1
DOORS
1 Steel door with frame 2000m x 0.8m pcs 1
2 Door hinges 4" pcs 2
3 Tower bolt 4" pcs 1
4 Tower bolt 2" pcs 1
5 Screws 1 3/4'' pcs 30
ROOFING
1 Corrugated Iron Sheets 2m x 32gauge pcs 2
2 Roofing Timber 4"X2" ft. 45
3 Roofing Nails Standard kg 0.5
HAND WASHING FACILITY
1 Complete Hand washing facility 20 ltr 1
GENERAL
1 Wire nails 4" kg 0.5
2 Wire nails 2" kg 0.5
3 Wire nails 1 1/2'' kg 0.5
4 Wall-pass kg 3
5 Urine Soak pit Lump sum 1
6 Thread seal Tape pcs 1
7 Transport Lump sum 1
Sub Total (material)
A Skilled labour Man days 5
B Unskilled labour Man days 5
Sub Total (labour)
Grant total
Landlords/Lady signature and date % %
WSP Tech. Manager signature and date
Technical Handbook
89
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
Item Description Size Unit Quantity Unit cost Total Contribution Subsidy
in Ksh Landlord/Lady UBSUP
CONCRETE WORKS
1 Portland Cement 50kg bags 5
2 Building sand tonnes 3
3 Ballast 1/4" tonnes 0.5
4 Hardcore tonnes 0.5
5 Concrete Bricks 15"X6"X8" ms 8
SANITATION WARE
1 Cistern flush sitting toilet pcs 1
2 Plastic nipple 3/4'' external dia pcs 1
3 Transparent hose pipe for urinal 1'' internal dia ft. 3
4 Prefabricated Plastic urinal pcs 1
VENTILATION
1 Black PVC Vent pipe Class B 4"x10ft pcs 0.5
2 PVC Vent pipe cover pcs 1
DOORS
1 Steel door with frame 2000m x 0.8m pcs 1
2 Door hinges 4" pcs 2
3 Tower bolt 4" pcs 1
4 Tower bolt 2" pcs 1
5 Screws 1 3/4'' pcs 30
ROOFING
1 Corrugated Iron Sheets 2m x 32gauge pcs 2
2 Roofing Timber 4"X2" ft. 45
3 Roofing Nails Standard kg 0.5
HAND WASHING FACILITY
1 Complete Hand washing facility 20 ltr 1
GENERAL
1 Wire nails 4" kg 0.5
2 Wire nails 2" kg 0.5
3 Wire nails 1 1/2'' kg 0.5
4 Wall-pass kg 3
5 Urine Soak pit Lump sum 1
6 Thread seal Tape pcs 1
7 Transport Lump sum 1
Sub Total (material)
A Skilled labour Man days 5
B Unskilled labour Man days 5
Sub Total (labour)
Grant total
Landlords/Lady signature and date % %
WSP Tech. Manager signature and date
Technical Handbook
90
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
Item Description Size Unit Quantity Unit cost Total Contribution Subsidy
in Ksh Landlord/Lady UBSUP
CONCRETE WORKS
1 Portland Cement 50kg bags 6
2 Building sand tonnes 3
3 Ballast 1/4" tonnes 0.5
4 Hardcore tonnes 0.5
5 Burnt Bricks 9"X6"X4" pcs 450
SANITATION WARE
1 Squatting toilet with a cistern pcs 1
2 Plastic nipple 3/4'' external dia pcs 1
3 Transparent hose pipe for urinal 1'' internal dia ft. 3
4 Prefabricated Plastic urinal pcs 1
VENTILATION
1 Black PVC Vent pipe Class B 4"x10ft pcs 0.5
2 PVC Vent pipe cover pcs 1
DOORS
1 Steel door with frame 2000m x 0.8m pcs 1
2 Door hinges 4" pcs 2
3 Tower bolt 4" pcs 1
4 Tower bolt 2" pcs 1
5 Screws 1 3/4'' pcs 30
ROOFING
1 Corrugated Iron Sheets 2m x 32gauge pcs 2
2 Roofing Timber 4"X2" ft. 45
3 Roofing Nails Standard kg 0.5
HAND WASHING FACILITY
1 Complete Hand washing facility 20 ltr 1
GENERAL
1 Wire nails 4" kg 0.5
2 Wire nails 2" kg 0.5
3 Wire nails 1 1/2'' kg 0.5
4 Wall-pass kg 3
5 Urine Soak pit sum 1
6 Thread seal Tape Lump pcs 1
7 Transport Lump sum 1
Sub Total (material)
A Skilled labour Man days 5
B Unskilled labour Man days 5
Sub Total (labour)
Grant total
Technical Handbook
91
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
Item Description Size Unit Quantity Unit cost Total Contribution Subsidy
in Ksh Landlord/Lady UBSUP
CONCRETE WORKS
1 Portland Cement 50kg bags 5
2 Building sand tonnes 3
3 Ballast 1/4" tonnes 0.5
4 Hardcore tonnes 0.5
5 Quarry stone 15"X6"X8" ms 8
SANITATION WARE
1 Squatting toilet with a cistern pcs 1
2 Plastic nipple 3/4'' external dia pcs 1
3 Transparent hose pipe for urinal 1'' internal dia ft. 3
4 Prefabricated Plastic urinal pcs 1
VENTILATION
1 Black PVC Vent pipe Class B 4"x10ft pcs 0.5
2 PVC Vent pipe cover pcs 1
DOORS
1 Steel door with frame 2000m x 0.8m pcs 1
2 Door hinges 4" pcs 2
3 Tower bolt 4" pcs 1
4 Tower bolt 2" pcs 1
5 Screws 1 3/4'' pcs 30
ROOFING
1 Corrugated Iron Sheets 2m x 32gauge pcs 2
2 Roofing Timber 4"X2" ft. 45
3 Roofing Nails Standard kg 0.5
HAND WASHING FACILITY
1 Complete Hand washing facility 20 ltr 1
GENERAL
1 Wire nails 4" kg 0.5
2 Wire nails 2" kg 0.5
3 Wire nails 1 1/2'' kg 0.5
4 Wall-pass kg 3
5 Urine Soak pit Lump sum 1
6 Thread seal Tape pcs 1
7 Transport Lump sum 1
Sub Total (material)
A Skilled Labour Man days 5
B Unskilled Labour Man days 5
Sub Total (labour)
Total Grant
Technical Handbook
92
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
Item Description Size Unit Quantity Unit cost Total Contribution Subsidy
in Ksh Landlord/Lady UBSUP
CONCRETE WORKS
1 Portland Cement 50kg bags 5
2 Building sand tonnes 3
3 Ballast 1/4" tonnes 0.5
4 Hardcore tonnes 0.5
5 Concrete Bricks 15"X6"X8" ms 8
SANITATION WARE
1 Squatting toilet with a cistern pcs 1
2 Plastic nipple 3/4'' external dia pcs 1
3 Transparent hose pipe for urinal 1'' internal dia ft. 3
4 Prefabricated Plastic urinal pcs 1
VENTILATION
1 Black PVC Vent pipe Class B 4"x10ft pcs 0.5
2 PVC Vent pipe cover pcs 1
DOORS
1 Steel door with frame 2000m x 0.8m pcs 1
2 Door hinges 4" pcs 2
3 Tower bolt 4" pcs 1
4 Tower bolt 2" pcs 1
5 Screws 1 3/4'' pcs 30
ROOFING
1 Corrugated Iron Sheets 2m x 32gauge pcs 2
2 Roofing Timber 4"X2" ft. 45
3 Roofing Nails Standard kg 0.5
HAND WASHING FACILITY
38 Complete Hand washing facility 20 ltr 1
GENERAL
1 Wire nails 4" kg 0.5
2 Wire nails 2" kg 0.5
3 Wire nails 1 1/2'' kg 0.5
4 Wall-pass kg 3
5 Urine Soak pit Lump sum 1
6 Thread seal Tape pcs 1
7 Transport Lump sum 1
Sub Total (material)
A Skilled labour Man days 5
B Unskilled labour Man days 5
Sub Total (labour)
Grant total
Landlords/Lady signature and date % %
WSP Tech. Manager signature and date
Technical Handbook
93
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
Item Description Size Unit Quantity Unit cost Total Contribution Subsidy
in Ksh Landlord/Lady UBSUP
CONCRETE WORKS
1 Portland Cement 50kg bags 6
2 Building sand tonnes 3
3 Ballast 1/4" tonnes 0.5
4 Hardcore tonnes 0.5
5 Burnt Bricks 9"X6"X4" pcs 450
SANITATION WARE
1 Pour flush sitting toilet pcs 1
2 Plastic nipple 3/4'' external dia pcs 1
3 Transparent hose pipe for urinal 1'' internal dia ft. 3
4 Prefabricated Plastic urinal pcs 1
VENTILATION
1 Black PVC Vent pipe Class B 4"x10ft pcs 0.5
2 PVC Vent pipe cover pcs 1
DOORS
1 Steel door with frame 2000m x 0.8m pcs 1
2 Door hinges 4" pcs 2
3 Tower bolt 4" pcs 1
4 Tower bolt 2" pcs 1
5 Screws 1 3/4'' pcs 30
ROOFING
1 Corrugated Iron Sheets 2m x 32gauge pcs 2
2 Roofing Timber 4"X2" ft. 45
3 Roofing Nails Standard kg 0.5
HAND WASHING FACILITY
1 Complete Hand washing facility 20 ltr 1
GENERAL
1 Wire nails 4" kg 0.5
2 Wire nails 2" kg 0.5
3 Wire nails 1 1/2'' kg 0.5
4 Wall-pass kg 3
5 Urine Soak pit sum 1
6 Thread seal Tape Lump pcs 1
7 Transport Lump sum 1
Sub Total (material)
A Skilled labour Man days 5
B Unskilled labour Man days 5
Sub Total (labour)
Grant total
Technical Handbook
94
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
Item Description Size Unit Quantity Unit cost Total Contribution Subsidy
in Ksh Landlord/Lady UBSUP
CONCRETE WORKS
1 Portland Cement 50kg bags 5
2 Building sand tonnes 3
3 Ballast 1/4" tonnes 0.5
4 Hardcore tonnes 0.5
5 Quarry stone 15"X6"X8" ms 8
SANITATION WARE
1 Pour flush sitting toilet pcs 1
2 Plastic nipple 3/4'' external dia pcs 1
3 Transparent hose pipe for urinal 1'' internal dia ft. 3
4 Prefabricated Plastic urinal pcs 1
VENTILATION
1 Black PVC Vent pipe Class B 4"x10ft pcs 0.5
2 PVC Vent pipe cover pcs 1
DOORS
1 Steel door with frame 2000m x 0.8m pcs 1
2 Door hinges 4" pcs 2
3 Tower bolt 4" pcs 1
4 Tower bolt 2" pcs 1
5 Screws 1 3/4'' pcs 30
ROOFING
1 Corrugated Iron Sheets 2m x 32gauge pcs 2
2 Roofing Timber 4"X2" ft. 45
3 Roofing Nails Standard kg 0.5
HAND WASHING FACILITY
1 Complete Hand washing facility 20 ltr 1
GENERAL
1 Wire nails 4" kg 0.5
2 Wire nails 2" kg 0.5
3 Wire nails 1 1/2'' kg 0.5
4 Wall-pass kg 3
5 Urine Soak pit Lump sum 1
6 Thread seal Tape pcs 1
7 Transport Lump sum 1
Sub Total (material)
A Skilled Labour Man days 5
B Unskilled Labour Man days 5
Sub Total (labour)
Total Grant
Landlords/Lady signature and date % %
WSP Tech. Manager signature and date
Technical Handbook
95
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
Item Description Size Unit Quantity Unit cost Total Contribution Subsidy
in Ksh Landlord/Lady UBSUP
CONCRETE WORKS
1 Portland Cement 50kg bags 5
2 Building sand tonnes 3
3 Ballast 1/4" tonnes 0.5
4 Hardcore tonnes 0.5
5 Concrete Bricks 15"X6"X8" ms 8
SANITATION WARE
1 Pour flush sitting toilet pcs 1
2 Plastic nipple 3/4'' external dia pcs 1
3 Transparent hose pipe for urinal 1'' internal dia ft. 3
4 Prefabricated Plastic urinal pcs 1
VENTILATION
1 Black PVC Vent pipe Class B 4"x10ft pcs 0.5
2 PVC Vent pipe cover pcs 1
DOORS
1 Steel door with frame 2000m x 0.8m pcs 1
2 Door hinges 4" pcs 2
3 Tower bolt 4" pcs 1
4 Tower bolt 2" pcs 1
5 Screws 1 3/4'' pcs 30
ROOFING
1 Corrugated Iron Sheets 2m x 32gauge pcs 2
2 Roofing Timber 4"X2" ft. 45
3 Roofing Nails Standard kg 0.5
HAND WASHING FACILITY
1 Complete Hand washing facility 20 ltr 1
GENERAL
1 Wire nails 4" kg 0.5
2 Wire nails 2" kg 0.5
3 Wire nails 1 1/2'' kg 0.5
4 Wall-pass kg 3
5 Urine Soak pit Lump sum 1
6 Thread seal Tape pcs 1
7 Transport Lump sum 1
Sub Total (material)
A Skilled Labour Man days 5
B Unskilled Labour Man days 5
Sub Total (labour)
Total Grant
Landlords/Lady signature and date % %
WSP Tech. Manager signature and date
Technical Handbook
96
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
Item Description Size Unit Quantity Unit cost Total Contribution Subsidy
in Ksh Landlord/Lady UBSUP
CONCRETE WORKS
1 Portland Cement 50kg bags 6 900 5,400
2 Building sand tonnes 3 1,200 3,600
3 Ballast 1/4" tonnes 0.5 1,200 600
4 Hardcore tonnes 0.5 700 350
5 Burnt Bricks 9"X6"X4" pcs 450 6 2,700
SANITATION WARE
1 Pour flush squatting toilet pcs 1 3,500 3,500
2 Plastic nipple 3/4'' external dia pcs 1 50 50
3 Transparent hose pipe for urinal 1'' internal dia ft. 3 50 150
4 Prefabricated Plastic urinal pcs 1 1,200 1,200
VENTILATION
1 PVC Vent pipe Class B 4"x10ft pcs 0.5 1,600 800
2 PVC Vent pipe cover pcs 1 50 50
DOORS
1 Steel door with frame 2000m x 0.8m pcs 1 1,800 1,800
2 Door hinges 4" pcs 2 100 200
3 Tower bolt 4" pcs 1 100 100
4 Tower bolt 2" pcs 1 50 50
5 Screws 1 3/4'' pcs 30 5 150
ROOFING
1 Corrugated Iron Sheets 2m x 32gauge pcs 2 500 1,000
2 Roofing Timber 4"X2" ft. 45 50 2,250
3 Roofing Nails Standard kg 0.5 150 75
HAND WASHING FACILITY
1 Complete Hand washing facility 20 ltr 1 1,500 1,500.00
GENERAL
1 Wire nails 4" kg 0.5 120 60.00
2 Wire nails 2" kg 0.5 120 60.00
3 Wire nails 1 1/2'' kg 0.5 120 60.00
4 Wall-pass kg 3 150 450
5 Urine Soak pit sum 1 2,000 2,000
6 Thread seal Tape Lump pcs 1 25.00 25
7 Transport Lump sum 1 3,000 3000
Sub Total (material)
A Skilled labour Man days 5 800 4,000
B Unskilled labour Man days 5 400 2,000
Sub Total (labour)
Grant total
Technical Handbook
97
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
Item Description Size Unit Quantity Unit cost Total Contribution Subsidy
in Ksh Landlord/Lady UBSUP
CONCRETE WORKS
1 Portland Cement 50kg bags 5 900 4,500
2 Building sand tonnes 3 1,200 3,600
3 Ballast 1/4" tonnes 0.5 1,200 600
4 Hardcore tonnes 0.5 700 350
5 Quarry stone 15"X6"X8" ms 8 450 3,600
SANITATION WARE
1 Pour flush squatting toilet pcs 1 3,500 3,500
2 Plastic nipple 3/4'' external dia pcs 1 50 50
3 Transparent hose pipe for urinal 1'' internal dia ft. 3 50 150
4 Prefabricated Plastic urinal pcs 1 1,200 1,200
VENTILATION
1 PVC Vent pipe Class B 4"x10ft pcs 0.5 1,600 800
2 PVC Vent pipe cover pcs 1 50 50
DOORS
1 Steel door with frame 2000m x 0.8m pcs 1 1,800 1,800
2 Door hinges 4" pcs 2 100 200
3 Tower bolt 4" pcs 1 100 100
4 Tower bolt 2" pcs 1 50 50
5 Screws 1 3/4'' pcs 30 5 150
ROOFING
1 Corrugated Iron Sheets 2m x 32gauge pcs 2 500 1,000
2 Roofing Timber 4"X2" ft. 45 50 2,250
3 Roofing Nails Standard kg 0.5 150 75
HAND WASHING FACILITY
1 Complete Hand washing facility 20 ltr 1 1,500 1,500.00
GENERAL
1 Wire nails 4" kg 0.5 120 60.00
2 Wire nails 2" kg 0.5 120 60.00
3 Wire nails 1 1/2'' kg 0.5 120 60.00
4 Wall-pass kg 3 150 450
5 Urine Soak pit Lump sum 1 2,000 2,000
6 Thread seal Tape pcs 1 25.00 25
7 Transport Lump sum 1 3,000 3000
Sub Total (material)
A Skilled Labour Man days 5 800 4,000
B Unskilled Labour Man days 5 400 2,000
Sub Total (labour)
Total Grant
Landlords/Lady signature and date % %
WSP Tech. Manager signature and date
Technical Handbook
98
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
Item Description Size Unit Quantity Unit cost Total Contribution Subsidy
in Ksh Landlord/Lady UBSUP
CONCRETE WORKS
1 Portland Cement 50kg bags 5 900 4,500
2 Building sand tonnes 3 1,200 3,600
3 Ballast 1/4" tonnes 0.5 1,200 600
4 Hardcore tonnes 0.5 700 350
5 Concrete Bricks 15"X6"X8" ms 8 550 4,400
SANITATION WARE
1 Pour flush squatting toilet pcs 1 3,500 3,500
2 Plastic nipple 3/4'' external dia pcs 1 50 50
3 Transparent hose pipe for urinal 1'' internal dia ft. 3 50 150
4 Prefabricated Plastic urinal pcs 1 1,200 1,200
VENTILATION
1 PVC Vent pipe Class B 4"x10ft pcs 0.5 1,600 800
2 PVC Vent pipe cover pcs 1 50 50
DOORS
1 Steel door with frame 2000m x 0.8m pcs 1 1,800 1,800
2 Door hinges 4" pcs 2 100 200
3 Tower bolt 4" pcs 1 100 100
4 Tower bolt 2" pcs 1 50 50
5 Screws 1 3/4'' pcs 30 5 150
ROOFING
1 Corrugated Iron Sheets 2m x 32gauge pcs 2 500 1,000
2 Roofing Timber 4"X2" ft. 45 50 2,250
3 Roofing Nails Standard kg 0.5 150 75
HAND WASHING FACILITY
1 Complete Hand washing facility 20 ltr 1 1,500 1,500.00
GENERAL
1 Wire nails 4" kg 0.5 120 60.00
2 Wire nails 2" kg 0.5 120 60.00
3 Wire nails 1 1/2'' kg 0.5 120 60.00
4 Wall-pass kg 3 150 450
5 Urine Soak pit Lump sum 1 2,000 2,000
6 Thread seal Tape pcs 1 25.00 25
7 Transport Lump sum 1 3,000 3000
Sub Total (material)
A Skilled Labour Man days 5 800 4,000
B Unskilled Labour Man days 5 400 2,000
Sub Total (labour)
Total Grant
Landlords/Lady signature and date % %
WSP Tech. Manager signature and date
Technical Handbook
99
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
Item Description Size Unit Quantity Unit cost Total Contribution Subsidy
in Ksh Landlord/Lady UBSUP
CONCRETE WORKS
1 Portland Cement 50kg bags 5
2 Building sand tonnes 3
3 Ballast 1/4" tonnes 0,5
4 Hardcore tonnes 0,5
5 Quarry stone 15"X6"X8" sm 3
SANITATION WARE
1 Pour flush sitting toilet pcs 1
2 Plastic nipple 3/4'' external dia pcs 1
3 Transparent hose pipe for urinal 1'' internal dia ft. 6
4 Prefabricated Plastic urinal pcs 1
VENTILATION
1 PVC Vent pipe Class B 4"x10ft pcs 0,5
2 PVC Vent pipe cover pcs 1
ROOFING
1 Corrugated iron sheets 2m x 32gauge pcs 8
2 Iron sheet clips Standard kg 3
HAND WASHING FACILITY
1 Complete hand washing facility 20 ltr 1
GENERAL
1 PPR Pipe 3/4" pcs 7
2 Elbow 3/4" pcs 6
3 Tee 3/4" pcs 21
4 Pop rivets kg 2
5 Transport Lump sum 1
Sub Total (material)
A Skilled labour Man days 3
B Unskilled labour Man days 3
Sub Total (labour)
Grant total
Landlords/Lady signature and date % %
WSP Tech. Manager signature and date
Technical Handbook
100
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
Item Description Size Unit Quantity Unit cost Total Contribution Subsidy
in Ksh Landlord/Lady UBSUP
CONCRETE WORKS
1 Portland Cement 50kg bags 5
2 Building sand tonnes 3
3 Ballast 1/4" tonnes 0,5
4 Hardcore tonnes 0,5
5 Quarry stone 15"X6"X8" sm 3
SANITATION WARE
1 Pour flush sitting toilet pcs 1
2 Plastic nipple 3/4'' external dia pcs 1
3 Transparent hose pipe for urinal 1'' internal dia ft. 6
4 Prefabricated Plastic urinal pcs 1
VENTILATION
1 PVC Vent pipe Class B 4"x10ft pcs 0,5
2 PVC Vent pipe cover pcs 1
ROOFING
1 Corrugated iron sheets 2m x 32gauge pcs 8
2 Iron sheet crips Standard kg 3
HAND WASHING FACILITY
1 Complete hand washing facility 20 ltr 1
GENERAL
1 Steel square tube 3/4" gauge 16 no 8
2 Door bushes no 4
4 pop rivets kg 2
5 Transport Lamp sum 1
Technical Handbook
101
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
Item Description Size Unit Quantity Unit cost Total Contribution Subsidy
in Ksh Landlord/Lady UBSUP
CONCRETE WORKS
1 Portland Cement 50kg bags 4
2 Building sand tones 1
3 Ballast 1/4" tones 1
4 Hardcore tones 1
5 Burnt Bricks 9"X6"X4" pcs 150
6 BRC Mesh (commercial) Medium gauge ms 2
7 Shuttering Timber 6"x1" ft 60
8 Poles for shuttering 3ft x dia 3" pcs 2
9 Poles for Scaffolding 8ft x dia 3" pcs 2
10 Y8 Reinforcement pars 12m pcs 1
SANITATION WARE
1 Plastic squatting pan pcs 1
2 Plastic nipple 3/4'' external dia pcs 1
3 Transparent hose pipe for Squatting Pan 1'' internal dia ft 6
VENTILATION
1 PVC Vent pipe Class B 4"x10ft pcs 1
2 PVC Vent pipe cover pcs 1
DOORS
Steel door panels and steel frame painted
1 75cm X 80cm pcs 2
black with 2no. hinges and a wedge
Transport Item 1
Sub Total (material)
A Skilled Labour Man days 2
B Unskilled Labour Man days 2
Sub Total (labour)
Total Grant
Technical Handbook
102
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
BILL OF QUANTITIES (BoQ) for double vaultr Urine Diverting Dry Toilet (UDDT)
Building Material: Quarry Stones
Name and Tel. of Landlord/land lady:
Name and Tel. of Owner:
Location / District:
Code & UTM coordinates:
CONCRETE WORKS
1 Portland Cement 50kg bags
2 Building sand tones
3 Ballast 1/4" tones
4 Hardcore tones
5 Quarry stones 6"X6"X12" pcs
6 BRC Mesh (commercial) Medium gauge ms
7 Shuttering Timber 6"x1" ft
8 Poles for shuttering 3ft x dia 3" pcs
9 Poles for Scaffolding 8ft x dia 3" pcs
10 Y8 Reinforcement pars 12m pcs
SANITATION WARE
1 Plastic squatting pan pcs
2 Plastic nipple 3/4'' external dia pcs
3 Transparent hose pipe for Squatting Pan 1'' internal dia ft
VENTILATION
1 PVC Vent pipe Class B 4"x10ft pcs
2 PVC Vent pipe cover pcs
DOORS
Steel door panels and steel frame painted black
1 75cm X 80cm pcs
with 2no. hinges and a wedge
Transport Item
Sub Total (material)
A Skilled Labour Man days
B Unskilled Labour Man days
Sub Total (labour)
Total Grant
Landlords/Lady signature and date
Technical Handbook
103
et (UDDT)
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
4
1
1
1
72
2
60
2
2
1
1
1
6
1
1
2
2
% %
Technical Handbook
104
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
BILL OF QUANTITIES (BoQ) Quadruple Vaults Urine Diverting Dry Toilet (UDDT)
Building Material: Burnt Clay Bricks
Name and Tel. of Landlord/land lady:
Name and Tel. of Owner:
Location / District:
Code & UTM coordinates:
Item Description Size Unit Quantity Unit cost Total Contribution Subsidy
in Ksh Landlord/Lady UBSUP
CONCRETE WORKS
1 Portland Cement 50kg bags 7
2 Building sand tonnes 2
3 Ballast 1/4" tonnes 1
4 Hardcore tonnes 1
5 Burnt Bricks 9"X6"X4" pcs 270
6 BRC Mesh (commercial) Medium gauge ms 4
7 Shuttering Timber 6"x1" ft 110
8 Poles for shuttering 3ft x dia 3" pcs 4
9 Poles for Scaffolding 8ft x dia 3" pcs 4
10 Y8 Reinforcement pars 12m pcs 2
SANITATION WARE
1 Plastic squatting pan pcs 2
2 Plastic nipple 3/4'' external dia pcs 2
3 Transparent hose pipe for Squatting Pan 1'' internal dia ft 10
VENTILATION
1 PVC Vent pipe Class B 4"x10ft pcs 1
2 PVC Vent pipe cover pcs 2
DOORS
Steel door panels and steel frame painted
1 75cm X 80cm pcs 4
black with 2no. Hinges and a wedge
Transport Item 1
Sub Total (material)
A Skilled Labour Man days 3
B Unskilled Labour Man days 3
Sub Total (labour)
Total Grant
Technical Handbook
105
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
BILL OF QUANTITIES (BoQ) for Quadruple Vaultr Urine Diverting Dry Toilet (UDDT)
Building Material: Quarry Stones
Name and Tel. of Landlord/land lady:
Name and Tel. of Owner:
Location / District:
Code & UTM coordinates:
Item Description Size Unit Quantity Unit cost Total Contribution Subsidy
in Ksh Landlord/Lady UBSUP
CONCRETE WORKS
1 Portland Cement 50kg bags 7
2 Building sand tonnes 2
3 Ballast 1/4" tonnes 1
4 Hardcore tonnes 1
5 Quarry stones 6"X6"X12" ms 5
6 BRC Mesh (commercial) Medium gauge ms 4
7 Shuttering Timber 6"x1" ft 110
8 Poles for shuttering 3ft x dia 3" pcs 4
9 Poles for Scaffolding 8ft x dia 3" pcs 4
10 Y8 Reinforcement pars 12m pcs 2
SANITATION WARE
1 Plastic squatting pan pcs 2
2 Plastic nipple 3/4'' external dia pcs 2
3 Transparent hose pipe for Squatting Pan 1'' internal dia ft 10
VENTILATION
1 PVC Vent pipe Class B 4"x10ft pcs 1
2 PVC Vent pipe cover pcs 2
DOORS
Steel door panels and steel frame painted black
1 75cm X 80cm pcs 4
with 2no. Hinges and a wedge
Transport Item 1
Sub Total (material)
A Skilled Labour Man days 3
B Unskilled Labour Man days 3
Sub Total (labour)
Total Grant
Landlords/Lady signature and date % %
Technical Handbook
106
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
BILL OF QUANTITIES (BoQ) Quadruple Vaults Urine Diverting Dry Toilet (UDDT)
Building Material: Burnt Clay Bricks
Name and Tel. of Landlord/land lady:
Name and Tel. of Owner:
Location / District:
Code & UTM coordinates:
Item Description Size Unit Quantity Unit cost Total Contribution Subsidy
in Ksh Landlord/Lady UBSUP
CONCRETE WORKS
1 Portland Cement 50kg bags 7
2 Building sand tonnes 2
3 Ballast 1/4" tonnes 1
4 Hardcore tonnes 1
5 Burnt Bricks 9"X6"X4" pcs 270
6 BRC Mesh (commercial) Medium gauge ms 4
7 Shuttering Timber 6"x1" ft 110
8 Poles for shuttering 3ft x dia 3" pcs 4
9 Poles for Scaffolding 8ft x dia 3" pcs 4
10 Y8 Reinforcement pars 12m pcs 2
SANITATION WARE
1 Plastic squatting pan pcs 2
2 Plastic nipple 3/4'' external dia pcs 2
3 Transparent hose pipe for Squatting Pan 1'' internal dia ft 10
VENTILATION
1 PVC Vent pipe Class B 4"x10ft pcs 1
2 PVC Vent pipe cover pcs 2
DOORS
Steel door panels and steel frame painted
1 75cm X 80cm pcs 4
black with 2no. Hinges and a wedge
Transport Item 1
Sub Total (material)
A Skilled Labour Man days 3
B Unskilled Labour Man days 3
Sub Total (labour)
Total Grant
Technical Handbook
107
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
Item Description Size Unit Quantity Unit cost Total Contribution Subsidy
in Ksh Landlord/Lady UBSUP
CONCRETE WORKS
1 Portland Cement 50kg bags 4
2 Building sand tones 1
3 Ballast 1/4" tones 1
4 Hardcore tones 1
5 Burnt Bricks 9"X6"X4" pcs 150
6 BRC Mesh (commercial) Medium gauge ms 2
7 Shuttering Timber 6"x1" ft 60
8 Poles for shuttering 3ft x dia 3" pcs 2
9 Poles for Scaffolding 8ft x dia 3" pcs 2
10 Y8 Reinforcement pars 12m pcs 1
SANITATION WARE
1 Plastic squatting pan pcs 1
2 Plastic nipple 3/4'' external dia pcs 1
3 Transparent hose pipe for Squatting Pan 1'' internal dia ft 6
VENTILATION
1 PVC Vent pipe Class B 4"x10ft pcs 1
2 PVC Vent pipe cover pcs 1
DOORS
Steel door panels and steel frame painted
1 75cm X 80cm pcs 2
black with 2no. hinges and a wedge
Transport Item 1
Excavation Item 1
A Skilled Labour Man days 2
B Unskilled Labour Man days 2
Sub Total (labour)
Total Grant
Technical Handbook
108
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
BILL OF QUANTITIES (BoQ) for double vaultr Urine Diverting Dry Toilet (UDDT)
Building Material: Quarry Stones
Name and Tel. of Landlord/land lady:
Name and Tel. of Owner:
Location / District:
Code & UTM coordinates:
Item Description Size Unit Quantity Unit cost Total Contribution Subsidy
in Ksh Landlord/Lady UBSUP
CONCRETE WORKS
1 Portland Cement 50kg bags 4
2 Building sand tones 1
3 Ballast 1/4" tones 1
4 Hardcore tones 1
5 Quarry stones 15"X6"X8" ms 4
6 BRC Mesh (commercial) Medium gauge ms 2
7 Shuttering Timber 6"x1" ft 60
8 Poles for shuttering 3ft x dia 3" pcs 2
9 Poles for Scaffolding 8ft x dia 3" pcs 2
10 Y8 Reinforcement pars 12m pcs 1
SANITATION WARE
1 Plastic squatting pan pcs 1
2 Plastic nipple 3/4'' external dia pcs 1
3 Transparent hose pipe for Squatting Pan 1'' internal dia ft 6
VENTILATION
1 PVC Vent pipe Class B 4"x10ft pcs 1
2 PVC Vent pipe cover pcs 1
DOORS
Steel door panels and steel frame painted
1 75cm X 80cm pcs 2
black with 2no. hinges and a wedge
Transport Item 1
Excavation Item 1
A Skilled Labour Man days 2
B Unskilled Labour Man days 2
Sub Total (labour)
Total Grant
Landlords/Lady signature and date % %
WSP Tech. Manager signature and date
Technical Handbook
109
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
BILL OF QUANTITIES (BoQ) for double Vault Urine Diverting Dry Toilet (UDDT)
Building Material: Concrete Bricks
Name and Tel. of Landlord/land lady:
Name and Tel. of Owner:
Location / District:
Code & UTM coordinates:
Item Description Size Unit Quantity Unit cost Total Contribution Subsidy
in Ksh Landlord/Lady UBSUP
CONCRETE WORKS
1 Portland Cement 50kg bags 4
2 Building sand tonnes 1
3 Ballast 1/4" tonnes 1
4 Hardcore tonnes 1
5 Concrete bricks 15"X6"X8" ms 4
6 BRC Mesh (commercial) Medium gauge ms 2
7 Shuttering Timber 6"x1" ft 60
8 Poles for shuttering 3ft x dia 3" pcs 2
9 Poles for Scaffolding 8ft x dia 3" pcs 2
10 Y8 Reinforcement pars 12m pcs 1
SANITATION WARE
1 Plastic squatting pan pcs 1
2 Plastic nipple 3/4'' external dia pcs 1
3 Transparent hose pipe for Squatting Pan 1'' internal dia ft 6
VENTILATION
1 PVC Vent pipe Class B 4"x10ft pcs 1
2 PVC Vent pipe cover pcs 1
DOORS
Steel door panels and steel frame painted
1 75cm X 80cm pcs 2
black with 2no. hinges and a wedge
Transport Item 1
Excavation Item 1
Sub Total (material)
A Skilled Labour Man days 2
B Unskilled Labour Man days 2
Sub Total (labour)
Total Grant
Technical Handbook
110
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
Technical Handbook
111
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
1 Cement bags 3
2 Fine River Sand kg 250
3 Ballast 3/4''x 1/2'' kg 12,5
4 Concrete blocks or quarry stones 15"X6"X8" feet 60
8 PVC pipe 6'' length 0,2
9 PVC elbow ,45 ° 6'' pcs 1
10 Excavation item 1
11 Transport item 1
12 Labour (skilled) man days 1
13 Labour (un skilled) man days 1
Total Grant
Landlords/Lady signature and date
WSP Tech. Manager signature and date
Technical Handbook
112
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
Total Grant
WSP Tech. Manager signature and date
Technical Handbook
113
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
Technical Handbook
114
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
Technical Handbook
115
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
Technical Handbook
116
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
6.1.16.14 BoQ drying bed
6.1.16.14 BoQ
6.1.16.14 BoQ
ddrying
rying
bbed
ed
6.1.16.15
6.1.16.15 BoQ
composting
BoQ composition bed bed
6.1.16.15 BoQ
composting
bed
Technical Handbook
117
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
October
2012
Technical Handbook
118
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
When: This instruction is meant for fundi constructing a concrete panel double vault toilet.
For whom: Fundi and supervisors constructing the toilets.
Aim: To guarantee the quality of the construction works and minimise the construction time.
Tools/equipment needed: Jembe, crowbar (Tarimbo), shovel/spade, metal sheet, bucket, Karai, mortar board, cement
trowel, spirit level, hosepipe, tape measure 5m, manila string (roll), masons hammer, hack
saw, welding machine, generator (optional).
Materials needed: PVC glue, 6 steel nails, 12x50 mm steel nails, 12x100 mm nails, 24x roofing nails with washers, 2 bags
cement, 300kg sand, 600kg ballast.
Toilet components:
Posts: 3x l =3300mm, 2x l=3000mm, 2x l=1200mm;
Panels: 5x 1300 x 300 x 25, 1xvent panel 1300 x 300 x 25,
18x 1100 x 300 x 25, 2x 750 x 300 x 25, 8x 450 x300 x 25;
Slabs: 1x vault slab 1550 x 1350 x 50 mm (2 sections),
1x pan slab 1475 x 1275 x 50 mm (2 sections)
Other components: 1 x squatting pan (plastic with 2 covers), 1x steps,
1x main door, 2x steel vault doors 600 x 600mm,
4x wall plate brackets 100 x 100 x 75 mm with prongs (steel), 1xPVC vent pipe, 2 PVC
100mm elbows,
1 PVC vent pipe cowl 100 mm, 2xtimbers 1450 x 100 x 75mm (wall plates), 3 timbers 1800 x
50 x 50mm (purlins), 3x corrugated steel sheets 1500 x 700mm.
Technical Handbook
119
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
Introduction
WARNING
Always use the required personal protection measures.
Technical Handbook
120
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
Steps
3. Site preparation
2. Dig 6 holes
4. Placing posts
Technical Handbook
121
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
Note
Ensure that the two slab halfs are firmly in contact. There should be no gap in between the
two halfs.
Note
Ensure that the grooves are facing the INSIDE of the toilet. If placed wrongly, panels can not be
placed later on.
Post 2 (medium)
• Add concrete to the bottom of the
corner hole diagonally opposite the
first post to a depth of 200mm.
• Place a 3000 mm long rear post into
the hole.
• Add concrete around the post,
100mm deep at a time, tamping it
down with a crowbar. Continue up to
ground level.
5. Place post
Technical Handbook
122
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
Post 3, 4 & 5
• Install a long post (3)in the front right
1
5
4
3
corner.
• Install the last 3300mm (4) long front
post in the right of thecentre hole
together with a1200mm (5) short
post at the left in the same manner
as above.
2
1. Place
post
6.3,
4Place
&5
post 3, 4 &5
Note
Ensure that the top of the short post is exactly 600 mm above the base slab. If it is higher, the slab of
the toilet will not fit. If it is lower, there will be a gap under the slab.
Post 6 & 7
• Install the last 3000mm (6) long rear 1
5
4
3
post in the rear left corner.
Note
Ensure that all posts are exactly vertical and adjust if necessary! If the posts are not vertical, panels
will not fit or will fall out of the toilet.
IMPORTANT
Leave the concrete to set for a week. During this period moist the concrete with water in the morn-
ing, noon and evening.
Technical Handbook
123
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
5. Inserting panels
Note
Place panels with the thick part at the bottom and the smooth part facing outwards.
WARNING
• Panels are very heavy. Be careful not to jam your fingers.
• Panels break easily. Treat them with care.
Technical Handbook
124
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
Note
Ensure that all the gaps in the base panel joint and between panels and post are sealed with a mix of
1:5 cement:sand and appropriate water.
Technical Handbook
125
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
Technical Handbook
126
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
Technical Handbook
127
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
Note
Ensure the groves in the mabati run from front to rear. Otherwise water will run off in the wrong
direction.
Technical Handbook
128
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
END OF PROCEDURE
Technical Handbook
129
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
February
2013
Prepared by UBSUP team
Technical Handbook
130
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
Technical Handbook
131
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
Introduction
1. Concrete vault
Preparation
1. Collected all the tools and materials needed.
2. To prevent any delays, check if all the required components are on site.
Safety regulations
WARNING
Always use the required personal protection measures.
Technical Handbook
132
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
Steps
3. Site preparation
23 .Dig 5 holes
4. Placing posts
Note
Ensure that:
1. the grooves in the post are facing the INSIDE of the vault. If placed wrongly, panels can not
be placed later on.
2. the post is placed vertically. If placed wrongly, panels will not fit or will fall out after con-
struction.
3. Ensure that the top of the short post is exactly 630 mm above ground level. If it is higher,
the slab of the toilet will not fit. If it is lower, there will be a gap under the slab.
Technical Handbook
133
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
Post 2
• Add concrete to the bottom of the 1
5
3
corner hole diagonally opposite the
first post to a depth of 200mm.
• Place post into the hole.
• Ensure that the distance between
post 1 and 2 is exactly 2260mm (cen-
tre to centre)
• Add concrete around the post,
100mm deep at a time, tamping it
down with a crowbar. Continue up to 4
2
ground level.
25. Measurement between post 3 and 4
Post 3, 4 and 5
Post 3.
• Ensure that the distance between
post 1 and 3 and post 2 and 3 is ex-
actly 1600mm (centre to centre)
Post 4.
• Ensure that the distance between
post 3 and 4 is exactly 2260mm (cen-
tre to centre)
Post 5
• Ensure that the distance between 26. Placing post 3, 4 and 5
post 1 and 5 and post 3 and 5 is ex-
actly 800mm (centre to centre)
Note
Ensure that all posts are exactly vertical and adjust if necessary! If the posts are not vertical, panels
will not fit or will fall out of the toilet.
IMPORTANT
Leave the concrete to set for a week. During this period moist the concrete with water in the morn-
ing, noon and evening.
5. Inserting panels
Note
Place panels with the thick part at the bottom and the smooth part facing outwards.
Technical Handbook
134
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
WARNING
• Panels are very heavy. Be careful not to jam your fingers.
• Panels break easily. Treat them with care.
Note
Ensure that all the gaps in the base panel joint and between panels and post are sealed with a mix of
1:5 cement:sand and appropriate water.
Technical Handbook
135
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
Note
Ensure the vault doors close tight on the base slab and that all panels are seated firmly on
each other. Any holes will result in leaking of the vault and consequently pollution of the
environment.
Technical Handbook
136
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
8. Odor trap
Technical Handbook
137
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
9. Cleaning up
END OF PROCEDURE
Technical Handbook
138
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
Technical Handbook
139
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
step 3 step 4
Remove
excess Clean the
water toilet
from mop. floor.
step 5 step 6
step 7 step 8
clean Wash your
inside of hands
toilet.
Water Services Trust Fund P.O. Box 49699-00100 Nairobi 1st Flr CIC Plaza, Mara Rd
Tel: 2720696/2729017-9 Email: info@wstfkenya.org www. wstfkenya.org
Technical Handbook
140
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
Technical Handbook
141
UBSUP
Up-scaling Basic Sanitation for the Urban Poor
Technical Handbook
142