Installation Checklist

General

• Punchlist

Foundations

• Punchlist

Pusher

• Punchlist
1
2

Charging machine (Kick-in)

• Punchlist
1
2

5
6

Inclined ramps

• Punchlist
1

Lifting frame
Translation frame

Water troughs

• Punchlist
1

Fixed beams
Walking beams

• Punchlist
1

Hearth, side/charging/discharging walls and roof

• Punchlist

Final grouting

• Punchlist

Main frame
• Punchlist

Refractories

• Punchlist

Waste gas duct

• Punchlist
1

2
3

Combustion air system

• Punchlist for Combustion Air System


1

2
3

8
9

10

11

12

• Punchlist for Combustion Air System


13

14

15

16

Charging and discharging doors

• Punchlist
1

Damper
• Punchlist

Recuperator

• Punchlist

Hydraulic system

• Punchlist
1
2

Natural gas piping


• Punchlist
1

10

11

12

13

14
15

16

17

18

19

20

21

22

23

24

25

26
27

28

29

30

31

32

Coke oven gas piping


• Punchlist
1

10

11

12
13

14

15

16

17

18

19

20
21

22

23

24

Nitrogen piping
• Punchlist

Cooling water piping

• Punchlist for Indirect Cooling Water Piping


1

4
5

10

11

12

13

14

15

16

17

18

19
20

21

22

23

24

25

26

27

28

29

30
31

32

33

34

35
36

37

• Punchlist for Direct Cooling Water Piping


1

4
5

9
10

11

12

13

Compressed air piping


• Punchlist
1

9
10

11

12

13

14

15
Grease lubrication system

• Punchlist

Discharging machine (Kick-off)

• Punchlist
1

Additional
Photocells
• Punchlist
1

Scale Chute
• Punchlist
1

Stack
• Punchlist
1
Installation Checklist

• Erection drawings
• Erection manual
• Completeness of delivery

• Main reference axis drawn


• Reference levels set
• Check of foundations for compliance with drawings
• Set of levelling shims

• Steel structure alignment


• Size and location of anchors bolts
• Pusher carriage installation as per drawings
• Check of hand operated translation for proper operation
• Hydraulic cylinder installation
• First grouting (anchor bolts)
• Final alignment
• Anchor bolt tightening
• Final grouting
• Check of installation completeness as per drawings

On the pusher shall be install support for encoder or transducer, after that touch up paint shall be performed
Clips for pusher hydraulic shall be full weld according to the drawing.

arging machine (Kick-in)


• Kick-in pre-alignment
• Size and location of anchor bolts
• Installation drive shaft as per drawings
• Assembly arms as per drawing
• Alignment arms and drive shaft
• Check of hand translation for proper operation
• Drive unit installation
• Drive unit alignment
• First grouting (anchor bolts)
• Kick-in final alignment
• Anchor bolt tightening
• Final grouting
• Check of installation completeness as per drawings

Frame base for cable track is not leveling and not fix at the position (both of kick in and kick off)
Coupling between spindle and motor kick in and kick off not yet coupled

Eccentric (Fly Wheel) gap for kick in and kick out shall be regulated according to the drawing

All the rail clips must be welding, it also applicable for the shear block (stoper), and after welding it must be touch
up paint. (both of kick in and kick off)

All of support for kick-in and kick-off limit switch not yet installed as per drawing, at this moments the support
only done tack welding, it must be drilling or tapped and connect with bolt afer that shall be touch up paint.
All of support for kick-in and kick-off transducer not yet installed, after welding shall be touch up paint.

lined ramps
• Inclined ramps assembly
• Pre-alignment
• Size and location of anchors bolts
• First grouting (anchor bolts)
• Final alignment
• Anchor bolt tightening

Rust prevention for inclined ramp shall be cleaning

Tightening for anchor still not performed

• Frame assembly as per drawings


• Lower wheels installation
• Lower wheel alignment
• Lifting frame installation onto inclined ramps
• Lifting frame alignment
• Upper wheels installation
• Upper wheels alignment
• Lifting cylinder installation
• Punchlist

anslation frame
• Frame assembly as per drawings
• Sliding plate installation
• Sliding plate alignment
• Translation frame installation
• Transfer cylinder installation
• Punchlist

ater troughs
• Water troughs installation as per drawings
• Welding connections properly carried out
• Leak test (with water)

Scraper still using intermittent and tack weld, it shall fixed

• Reference axis drawn (with piano wire)


• Fixed beams installation as per drawings
• Fixed beams alignment
• Bolt tightening
• Punchlist

alking beams
• Walking beams installation as per drawings
• Walking beams alignment
• Cover plate installation as per drawings

arth, side/charging/discharging walls and roof


• Hearth installation as per drawings
• Size and location of anchor bolts
• Hearth alignment
• First grouting (anchor bolts)
• Walls installation as per drawings
• Roof beams installation
• Walls alignment
• Final grouting
• Anchor bolts tightening
• Inspection charging/discharging frames doors installation as per drawings

• Inclined ramps
• Columns
• Hearth
• Water troughs heads

• Reference axis drawn (with piano wire)


• Steel structure installation as per drawings
• Steel structure alignment
• Size and location of anchor bolts
• Grouting
• Anchors bolt tightening
• Check of installation completeness as per drawings
• Refractories installation as per drawings

aste gas duct


• Reference axis drawn (with piano wire)
• Steel structure alignment
• Size and location of anchor bolts
• Grouting
• Anchors bolt tightening
• Duct installation as per drawings

Tightening anchors still not perform, including square washer.

Waste gas duct flange must be installed with fiber gasket, before that refractory executor company shall cleaning
area with grinding machine.
Bolt and nut for critical part waste gas duct support still using material 8.8, it shall change to material 10.9 as per
drawing, 44ea x 16 part

mbustion air system


• Burners installation as per drawings
• Recuperator installation as per drawings
• Combustion air fan installation as per drawings
• Main ducts and zone manifolds installation as per drawings
• Burners pipe connections to zone manifolds as per drawings
• Air ducts bolt connections final tightening
• Instrumentation installation as per drawings
• Air duct thermal insulation as per drawings
Punchlist for Combustion Air System
Support COA on number S-158 and S-159 are not touched the pipe so the pipe is hangging on support

Support COA on number S-131, the gap for guide are needed to repair, because the guide is too large
Support COA on number S-125, the gap for guide are needed to repair, because the guide is too wide

The guide for support COA pipe on number S-118 are does not exist

Support COA on number S-141 was apply intermitent weld to the pipe

The Stifener for support on number S-189 is cut

The support for COA on number S-112 which have a design fixed point support are installed with guide support in
actual

There is have a addition support and guide for combution air manifold as shown on the picure but there is
notthing in the assembly drawing
General Comment:
1. Some of support for COA are does not yet weld or tack weld to the pipe

General Comment:
2. Some COA pipes on zone 7 and 8 are not yet weld due to repair for burner position and verticality, it also
applicable for COA flange for burner (40ea)

General Comment:
3. Gasket for COA are not suitable (cannot withstand for high temperature)

Tapping for Thermocouple for COA manifold is sufficient for tapping caused by steel structure, minimun distance
are 700mm

Punchlist for Combustion Air System


40 flange burner for combustion air inlet for zone 7 and zone 8 are not welding due to late of supply from SMS, at
this moment flange already on site. However flange installation waiting repair at refractory roof conceide with re-
alignment for top/radiant burner (12ea).

On site, piping installation which mark on the drawing still not installed (using half coupling 1/4")

Installation of insulation still not start, Material presence on site

Handrail shall installed properly, it shall modificate since it interfere with combustion air piping. All handrail must
be installed with out exception.

arging and discharging doors


• Installation of doors with lifting/lowering devices as per drawings
Support for hydraulic charging door weld to structure, it shall be give bolt connection as per drawing. (make a
hole for bolting connectiong)

Chain for charging door still not setting, it shall follow dimension from the drawing

Missing installation of bolt on the discharging door

Spray on discharging door miss for 1 piece, it shall installed as per drawing

• Damper and relevant frame installation as per drawings


• Check of hand rotation
• Check of installation completeness
• Leverage adjustment

• Visual inspection of housing refractory lining for proper execution


• Housing internal lower side properly filled with rock-wool
• Gasket properly installed on housing top-hole
• Recuperator installation as per drawings
• Housing exhaust gas duct inside lower side sealing with refractory brick

draulic system
• Location of hydraulic unit as per drawings
• Hydraulic unit properly fastened by expansion bolts
• System pipe installation as per drawings
• Pipe brackets installation as per drawings
• NDT of pipe welded joints
• Pressure test of system piping
• Pickling of system piping
• Flushing of system piping
• Instruments installation as per drawings

Clamp for Hydraulic pipe HY5 are not clamped


Perhaps the heater junction box damage on site, must be repairing and check if the heater is not damaged

All of hydraulic hoses must be connected after pickling

All rust which present in all of block cylinder/valve block must be cleaning and repainting

Tank must be grouted, hydraulic unit must be refurbish because some rusty due to raining on site, beside that
motor shall be tested for isolation

tural gas piping


• Piping system installation as per drawings
• Pipe brackets installation as per drawings
• NDT of pipe welded joints
• Pressure test of piping system
• (Test pressure of tightness with pressure of 1.5 times the maximum working pressure at any point)
• Flushing of piping system
• Instruments installation as per drawings

Piping connection for nitrogen gas vent on line NG-F01-0010-125 not yet installed

Piping connection for nitrogen gas vent on line NG-F01-0009-250 not yet installed

Piping connection for nitrogen gas vent on line NG-F01-0006-250 not yet installed

Piping connection for nitrogen gas vent on line NG-F01-0004-200 not yet installed

Piping connection for nitrogen gas vent on line NG-F01-0005-250 not yet installed

Piping connection for nitrogen gas vent on line NG-F01-0007-250 not yet installed

Piping connection for nitrogen gas vent on line NG-F01-0009-250 not yet installed

Piping connection for nitrogen gas vent on line NG-F01-0013-125 not yet installed

Piping connection for nitrogen gas vent on line NG-F01-0016-200 not yet installed

Piping connection for nitrogen supplay on line NG-F01-0010-125 not yet installed

Piping connection for nitrogen supplay on line NG-F01-0009-250 not yet installed

Piping connection for nitrogen supplay on line NG-F01-0006-250 not yet installed

Piping connection for nitrogen supplay on line NG-F01-0004-200 not yet installed

Piping connection for nitrogensupplay on line NG-F01-0005-250 not yet installed


Piping connection for nitrogen supplay on line NG-F01-0007-250 not yet installed

Piping connection for nitrogen supplay on line NG-F01-0009-250 not yet installed

Piping connection for nitrogen supplay on line NG-F01-0013-125 not yet installed

Piping connection for nitrogen supplay on line NG-F01-0016-200 not yet installed

Gasket for electrical pneumatic butterfly valve (21LF no.1) on line NG-F01-0005-250 not yet installed

Gasket for electrical pneumatic butterfly valve (21LF no.1 & no.2) on line NG-F01-0009-250 not yet installed

Gasket for electrical pneumatic butterfly valve (21LF no.1 & no.2) on line NG-F01-0007-250 not yet installed

Valve for PSL on liine NG-F01-0016-200 not yet installed

General Comment :
1. Check Flange Management to ensure length of bolts are proper

General Comment :
2. All of Instrumentation Equipment are not yet installed

General Comment :
3. Valve for Gasses Application not yet checked, whether use soft seat or metal seat type, since if use metal seat
all butterfly valve shall have gasket for flange connection

General Comment :
4. Some of Bolts at flange connection on are not tightening and not completed
U-Bolts for suport NG piping on line NG-F01-0009-400 as shown in the pcture are does not installed

U-Bolts for suport NG piping on line NG-F01-0012-250, NG-F01-0016-200 & NG-F01-0013-150 as shown in the
pcture are does not installed

U-Bolts for suport NG piping on line NG-F01-0004-200 as shown in the pcture are does not installed

U-Bolts for suport NG piping on line NG-F01-0003-300 as shown in the pcture are does not installed

Bolting for support natural gas station still not yet installed

Grounding still not connected to flange

ke oven gas piping


• Piping system installation as per drawings
• Pipe brackets installation as per drawings
• NDT of pipe welded joints
• Pressure test of piping system
• (Test pressure of tightness with pressure of 1.5 times the maximum working pressure at any point)
• Flushing of piping system
• Instruments installation as per drawings

Piping connection for nitrogen gas vent on line COG-F01-0009-150 not yet installed

Piping connection for nitrogen gas vent on line COG-F01-0006-350 not yet installed

Piping connection for nitrogen gas vent on line COG-F01-0004-400 not yet installed

Piping connection for nitrogen gas vent on line COG-F01-0002-350 not yet installed

Piping connection for nitrogen gas vent on line COG-F01-0003-350 not yet installed

Piping connection for nitrogen gas vent on line COG-F01-0005-400 not yet installed

Piping connection for nitrogen gas vent on line COG-F01-0007-400 not yet installed

Piping connection for nitrogen gas vent on line COG-F01-00011-150 not yet installed

Piping connection for nitrogen gas vent on line COG-F01-0012-250 not yet installed

Piping connection for nitrogen supply on line COG-F01-0007-400 not yet installed

Piping connection for nitrogen supply on line COG-F01-0011-150 not yet installed

Piping connection for nitrogen supply on line COG-F01-0012-250 not yet installed
General Comment :
1. Check Flange Management to ensure length of bolts are proper

General Comment :
2. All of Instrumentation Equipment are not yet installed

General Comment :
3. Valve for Gasses Application not yet checked, whether use soft seat or metal seat type, since if use metal seat
all butterfly valve shall have gasket for flange connection

General Comments :
4. Some of Bolts at flange connection are not tightening and not completed

Supports for COG Piping on line COG-F01-0010-500 as shown in the picture does not exist

Supports for COG Piping on line COG-F01-0008-400 as shown in the picture does not exist

U-Bolts for supports COG Piping on line COG-F01-0003-350 as shown in the picture does not installed

U-Bolts for supports COG Piping on line COG-F01-0002-350 as shown in the picture does not installed
U- Bolts for Supports COG Piping on line COG-F01-0006-350 & COG-F01-0009-150 as shown in the picture does
not installed proper and should be repaired

Supports for COG piping on line COG-F01-0009-150 are moved as shown in the picture

Handwheel of butterfly valve must be turned 180 degree due to interfere with column

Valve for main control valve have missing bolt

rogen piping
• System piping installation as per drawings
• Pipe brackets installation as per drawings
• NDT of pipe welded joints
• Pressure test of system piping
• Flushing of system piping
• Instruments installation as per drawings

oling water piping


• System piping installation as per drawings
• Pipe brackets installation as per drawings
• NDT of pipe welded joints
• Pressure test of system piping
• Flushing of system piping
• Instruments installation as per drawings
unchlist for Indirect Cooling Water Piping
All Instrument not yet installed, including flow around reheating furnace doors

Handwheel for Butterfly Valve (21AZ) on line EW1-F00-0001-300 not yet installed

Gasket (2ea) for Check Valve (21AU) on line EW1-F00-0001-300 not yet installed

Magnetic flow control on line IC1-F00-0002-400 instalation are reverse for directional
General Comment for Gasket : We Shall Check Data Sheet for Butterfly with Wafer Type, if refer to API 609
Category A, Valve installation doesn't need gasket

Butterfly valve (21AL) at supply line fixed beam IC1-F01-0027-125 Change to Globe Valve (Circuit F1)

Butterfly valve (21AL) at supply line fixed beam IC1-F01-0025-125 Change to Globe Valve (Circuit F2)

Butterfly valve (21AL) at supply line fixed beam IC1-F01-0021-125 Change to Globe Valve and Reverse for
Direction (Circuit F3)

Butterfly valve (21AL) at supply line fixed beam IC1-F01-0019-125 Change to Globe Valve and Reverse for
Direction (Circuit F4)

Butterfly valve (21AL) at supply line fixed beam IC1-F01-0015-125 Change to Globe Valve and Reverse for
Direction (Circuit F5)

Magnetic Flowmeter at return line fixed beam IC1-F01-0019-125 reverse for directional and bolts not completed
yet installed (Circuit F6)

Magnetic Flowmeter at return line fixed beam IC1-F01-0028-125 reverse for directional (Circuit F1)

Magnetic Flowmeter at return line fixed beam IC1-F01-0026-125 reverse for directional (Circuit F2)

General Comment :
1. We Shall Check Data Sheet for Butterfly with Wafer Type, if refer to API 609 Category A, Valve installation
doesn't need gasket
2. Some of Plugs for Low/Bottom pocket of pipe are loss

Hose at return line movable beam M1 IC1-F01-0038-100 is reverse for directional, it makes check valve blocked
(4ea)

Hose at return line movable beam M2 IC1-F01-0040-100 is reverse for directional, it makes check valve blocked
(4ea)

Hose at return line movable beam M5 IC1-F01-0034-65 is reverse for directional, it makes check valve blocked
(3ea)

Hose at return line movable beam M4 IC1-F01-0044-100 is reverse for directional, it makes check valve blocked
(4ea)

Hose at return line movable beam M6 IC1-F01-0032-65 is reverse for directional, it makes check valve blocked
(3ea)
Magnetic Flowmeter at return line movable beam M6 IC1-F01-0032-65 reverse for directional

Magnetic Flowmeter at return line movable beam M3 IC1-F01-0042-100 reverse for directional

Magnetic Flowmeter at return line movable beam M4 IC1-F01-0044-100 reverse for directional

Globe Valve at return line movable beam M6 IC1-F01-0032-65 reverse for directional

Globe Valve (21AH) at return line top panel cooling IC1-F01-0012-065 reverse for direction

Globe Valve (21AH) at return line discharging door IC1-F01-0010-065 reverse for direction

Globe Valve (21AH) at return line discharging door IC1-F01-0008-065 reverse for direction

Hose at inlet line Discharging door IC1-F01-0007-065 reverse for direction (Cause by check valve position)

Hose at return line Discharging door IC1-F01-0008-065 reverse for direction (Cause by check valve position)

PT on mine pipe line IC4-F0001-080 are not tapping yet

Wrong placement on TE (30.21) it must be installed at line IC4-F00-0001-080 (inlet line) the actual is installed at
line IC4-F00-0002-080 (return line)
Supports for Indirect Water Piping on line IC1-F00-0001-400 and IC1-F00-0002-400 as shown in the picture does
not exist

Supports position for Indirect Water Piping on line IC1-F01-0023-065 as shown in the picture are moved and U
bolt not yet installed

Supports for Indirect Water Piping on line IC1-F01-0017-065 as shown in the picture not yet installed

Supports for Indirect Water Piping on line IC1-F01-0023-065 as shown in the picture are not yet installed U-Bolts

Supports for Indirect Water Piping on line IC1-F01-0024-065 as shown in the picture not yet installed
Supports for Indirect Water Piping on line IC1-F01-0018-065 as shown in the picture not yet installed

Supports position for Indirect Water Piping on line IC1-F01-0024-065 as shown in the picture are moved and U
bolt not yet installed

Punchlist for Direct Cooling Water Piping


Butterfly valve (21AH) for Direct Water piping on line DC2-F01-0007-100, bolts is not completed

Valve (21AB) for Direct Water piping on line DC2-F01-0013-100 and DC2-F01-0015-100 (which used to open and
close the water flow for water through) is not yet installed

Drain valve (21AG) for Direct cooling piping on line DC2-F01-0008-080 and DC2-F01-0006-080 (which used to
drain water from water through) the bolts is not completed

Butterfly valve (21AF) for direct cooling piping on line DC2-F01-0029-065 (which used to flushing the slope piping
line), bolts is not completed
Drain valve (21AG) for Direct cooling piping on line DC2-F01-0008-080 and DC2-F01-0010-080 (which used to
drain water from water through), is so rusty

General Comment:
1. All of instrumentation equipment are not yet installed

2. Check some of bolts at flange or valve connection are not tightening and completed

U-Bolts for supports DC Piping on line DC2-F00-0005-150 as shown in the picture does not installed

Some of U-Bolts (10 Pcs) for supports DC Piping on line DC2-F00-0003-050 as shown in the picture are does not
installed yet, and Cap at the end of pipe are not welding
Union For DC2 which used to supply to water trough is not connected (as shown on the picture)

Direc water piping line DC2-F01-0011-025 (which used to supply water from treatment to water trough) is not get
in to the water trough

General Comment:
1. Tapping pipe for DN 20 on Direct Water cooling line DC2-F00-0003-080 which used to roll table cooling charging
side (cold roller table) are not yet installed, it also applicable for discharging roller table (hot roller table)

General Comment:
2. The Hose which used to connect water through below bearing cold roll table and slope pipe are not yet
installed

mpressed air piping


• System piping installation as per drawings
• Pipe brackets installation as per drawings
• NDT of pipe welded joints
• Instruments installation as per drawings
• System piping pressure test
• System piping flushing

Support number SC 226 for line CAD-F00-0002-050 and line NGP-F00-0001-032 not yet installed

Support number SC 228 for line CAD-F00-0002-050 and line NGP-F00-0001-032 not yet installed

Support number SB 244 for line CAD-F00-0001-065 and line NGP-F00-0001-029 not yet installed

Support number SC 238 for line CAD-F00-0001-065 not yet installed

Support number SC 233 for line CAD-F00-0001-066 not yet installed

Support number SA 292 for line CAD-F00-0002-050 don't have a U-bolt

Support number SC 243 for line CAD-F00-0002-050 don't have a U-bolt

Support number SB 249, SB 248, SB 247, SB 246, & SB 245 for line CAD-F00-0001-065 and line NGP-F00-0001-029
are don't have a nut and not yet tighten

Support number SA 001 for line NGV-F-032 are don't have a nut
Support number SC 237 for line CAD-F00-0002-050 are moved as shown in the drawing

Installation for pneumatic valve not yet finish

Piping for compressed air strainer not installed correctly and bending, shall add more support

Installation for piping for air to photocell not yet finished

Support for compressed air piping in scale chute area not use standard from SMS, the thickness is too thin, must
be dismantling and reinstall according with SMS Standard

General Comment:
1. Should be check the tightening of nuts in U-bolts support
ease lubrication system
• System piping installation as per drawings
• Pipe brackets installation as per drawings
• Instruments installation as per drawings

scharging machine (Kick-off)


• Kick-off pre-alignment
• Size and location of anchor bolts
• Installation drive shaft as per drawings
• Assembly arms as per drawing
• Alignment arms and drive shaft
• Check of hand translation for proper operation
• Drive unit installation
• Drive unit alignment
• First grouting (anchor bolts)
• Kick-off final alignment
• Anchor bolt tightening
• Final grouting
• Check of installation completeness as per drawings

Support for Puller is not install in fix position

• Size and location of anchor bolts


• Anchor bolt tightening
• Final grouting
• Check of installation completeness as per drawings
Some of support for side wall photocells should be installed according to the drawing, material already on site
and has been open package inspection.

Some of support for roller table photocells should be installed according to the drawing, material already on site
and has been open package inspection.

Support and pipe for /water/air box must fix in the position, also for electrical cable, installed the panel and
support for camera on the furnace still not completed

Window to check furnace burner is clash with flange of combustion air, it shall modificate
Installation for pneumatic cylinder cover are wrong, it shall be change to the right one

Installation for plateform not yet completed, lighting, electrical and safety stairs still not yet installed, bolt for
stack 4 to 5 and 5 to 6 still not tightening with dynamometric wrench. Stack still out of verticallity which is 30mm
and AFI still not resubmit to Owner.
Progress or AFI Photo

Not yet

to be clarified
to be clarified
to be clarified
Not yet completed
Already completed
Already completed
Already completed
to be clarified
Already completed
Support for instruments not yet installed

Pusher\1521_0045_a1_2a.pdf
Pusher\1521_0030_a1_1a_Pusher.pdf

Yes
Yes
Yes
Yes
Yes
Not yet
Yes
Yes
Yes
Yes
Yes
Yes
Not Yet

Kick In\1521_0033_a3_0a.pdf
Kick In\1521_0033_a3_0a.pdf

Kick In\1521_0033_a3_0a.pdf

Kick In\1521_0036_a1_1a.pdf

Kick In\1521_0035_a1_1a.pdf
Kick In\1521_0038_a1_1a.pdf

Already completed
Already completed
Already completed
Already completed
Already completed
Already completed
-

Already completed
Already completed
Already completed
Already completed
Already completed
Already completed
Already completed
Already completed
-

Already completed
Already completed
Already completed
Already completed
Already completed
-

Yes
Welding for scraper still intermittent
Not yet

Yes
Yes
to be clarified
AFI still not submit to Owner
-

Yes
Yes
Yes
-

Yes
Yes
to be clarified
Yes
Not yet completed
Yes
Not yet
Yes
to be clarified
Not yet

Yes
Yes
Yes
to be clarified

to be clarified
NDT still not finished
to be clarified (AFI)
Yes
Yes
Not all nuts using tension
Not yet
Still on progress

Not yet
to be clarified (check AFI)
Yes
Yes
Yes
Gasket not installed yet, and bolt for critical part still 8.8
Not yet complete for zone 7 and 8
Still on progress, waiting fabrication for OHC 3 (underslug)
Yes
Some pipeline have re-routing and shortage for bolt and gasket
Not yet
Not yet
Not yet
Not yet

1521_u051_a3_1l_Comb Air Piping Support

1521_u051_a3_1l_Comb Air Piping Support


1521_u051_a3_1l_Comb Air Piping Support

1521_u051_a3_1l_Comb Air Piping Support

1521_u051_a3_1l_Comb Air Piping Support

1521_u051_a4_1l

1521_u051_a4_1l

1521_u051_a4_1l
1521_u051_a3_1l_Comb Air Piping Support

1521_u051_a3_1l_Comb Air Piping Support

1521_u051_a6_1l
Support Ubication Combustion Air\1521_u051_a4_1l.pdf

P&ID Combustion Air\1521_u050_a13_1a.pdf

Not yet
Charging Doors\1521_u044_a1_1a_Lifting Charging Door.pdf

Charging Doors\1521_u044_a1_1a_Lifting Charging Door.pdf

Still on progress
Not yet
Not yet
Not yet

Not yet
Not yet
Not yet
Not yet
Not yet

Already completed
Not yet done
Not as per reference drawing
Not yet complete for support
only 10%
Not yet
Not yet
Not yet
Not yet complete for instruments
Almost done
Not yet complete for support
only 10%
Not yet done
Not yet done
Not yet done
Not yet complete for FT (Flow Transducer)

1521_u077_a1_0a_Nat Gas Piping Diagram

1521_u077_a1_0a_Nat Gas Piping Diagram


same as above

1521_u077_a1_0a_Nat Gas Piping Diagram


same as above

1521_u077_a1_0a_Nat Gas Piping Diagram


same as above

1521_u077_a1_0a_Nat Gas Piping Diagram


same as above

1521_u077_a1_0a_Nat Gas Piping Diagram


same as above

1521_u077_a1_0a_Nat Gas Piping Diagram


same as above

1521_u077_a1_0a_Nat Gas Piping Diagram


same as above

1521_u077_a1_0a_Nat Gas Piping Diagram


same as above

1521_u077_a1_0a_Nat Gas Piping Diagram


same as above

1521_u077_a1_0a_Nat Gas Piping Diagram


same as above

1521_u077_a1_0a_Nat Gas Piping Diagram


same as above

1521_u077_a1_0a_Nat Gas Piping Diagram


same as above

1521_u077_a1_0a_Nat Gas Piping Diagram


same as above
1521_u077_a1_0a_Nat Gas Piping Diagram
same as above

1521_u077_a1_0a_Nat Gas Piping Diagram


same as above

1521_u077_a1_0a_Nat Gas Piping Diagram


same as above

1521_u077_a1_0a_Nat Gas Piping Diagram


same as above

1521_u077_a1_0a_Nat Gas Piping Diagram

1521_u077_a1_0a_Nat Gas Piping Diagram

1521_u077_a1_0a_Nat Gas Piping Diagram

1521_u077_a1_0a_Nat Gas Piping Diagram

1521_u077_a1_0a_Nat Gas Piping Diagram

1521_u077_a1_0a_Nat Gas Piping Diagram

1521_u077_a1_0a_Nat Gas Piping Diagram

1521_u077_a1_0a_Nat Gas Piping Diagram


1521_u057_a2_0a

1521_u057_a2_0a
same as above

1521_u057_a2_0a
same as above

1521_u057_a2_0a
same as above

Some pipeline have re-routing and shortage for bolt and gasket
Not yet complete for support
only 10%
Not yet done
Not yet done
Not yet done
Not yet complete for FT (Flow Transducer)

1521_u102_a1_0a_Coke Gas Piping Diagram

1521_u102_a1_0a_Coke Gas Piping Diagram


same as above

1521_u102_a1_0a_Coke Gas Piping Diagram


same as above

1521_u102_a1_0a_Coke Gas Piping Diagram


same as above

1521_u102_a1_0a_Coke Gas Piping Diagram


same as above

1521_u102_a1_0a_Coke Gas Piping Diagram


same as above

1521_u102_a1_0a_Coke Gas Piping Diagram


same as above

1521_u102_a1_0a_Coke Gas Piping Diagram


same as above

1521_u102_a1_0a_Coke Gas Piping Diagram


same as above

1521_u102_a1_0a_Coke Gas Piping Diagram


same as above

1521_u102_a1_0a_Coke Gas Piping Diagram


same as above

1521_u102_a1_0a_Coke Gas Piping Diagram


same as above
1521_u102_a1_0a_Coke Gas Piping Diagram

1521_u102_a1_0a_Coke Gas Piping Diagram

1521_u102_a1_0a_Coke Gas Piping Diagram

1521_u102_a1_0a_Coke Gas Piping Diagram

1521_u119_a2_0a

1521_u119_a2_0a same as above

1521_u119_a3_0a

1521_u119_a3_0a same as above


1521_u119_a3_0a

1521_u119_a3_0a

Still on progress
Still on progress
Not yet done
Not yet done
Not yet done
Not yet done

Some pipeline have re-routing


Not yet complete for support
Not yet done
Not yet done
Not yet done
Some valves and instruments installation are reverse

1521_u083_a1_0a_Indirect Water

1521_u083_a1_0a_Indirect Water

1521_u083_a1_0a_Indirect Water

1521_u083_a1_0a_Indirect Water
1521_u083_a1_0a_Indirect Water

1521_u083_a2_0a

1521_u083_a2_0a Same as above

1521_u083_a2_0a Same as above

1521_u083_a2_0a Same as above

1521_u083_a2_0a Same as above

1521_u083_a2_0a

1521_u083_a2_0a

1521_u083_a2_0a

1521_u083_a2_0a

1521_u083_a3_0a

1521_u083_a3_0a Same as above

1521_u083_a3_0a Same as above

1521_u083_a3_0a Same as above

1521_u083_a3_0a Same as above


1521_u083_a3_0a

1521_u083_a3_0a Same as above

1521_u083_a3_0a Same as above

1521_u083_a3_0a

1521_u083_a1_0a_Indirect Water

1521_u083_a1_0a_Indirect Water

1521_u083_a1_0a_Indirect Water

1521_u083_a1_0a_Indirect Water

1521_u083_a1_0a_Indirect Water Same as above

1521_u083_a1_0a_Indirect Water

1521_u083_a1_0a_Indirect Water
1521_u061_a1_0a_Indirect Water Piping

1521_u061_a4_0a

1521_u061_a4_0a Same as above

1521_u061_a4_0a Same as above

1521_u061_a5_0a Same as above


1521_u061_a5_0a Same as above

1521_u061_a5_0a Same as above

1521_u082_a1_0a_Direct Water

1521_u082_a1_0a_Direct Water

1521_u082_a1_0a_Direct Water

1521_u082_a1_0a_Direct Water
1521_u082_a1_0a_Direct Water

1521_u082_a1_0a_Direct Water

1521_u082_a1_0a_Direct Water

1521_u060_a1_0l_Direct Water Piping -3

1521_u060_a1_0l_Direct Water Piping -1


1521_u060_a8_1a

1521_u060_a8_1a

1521_u060_a2_0a_Direct Water Piping -1

1521_u060_a2_0a_Direct Water Piping -1


Still on progress
Still on progress
Not yet, but will perform 10% only
Not yet complete
Not yet
Not yet

1521_u125_a1_0a

1521_u125_a1_0a

1521_u125_a1_0a

1521_u125_a1_0a

1521_u125_a1_0a

1521_u125_a1_0a

1521_u125_a1_0a

1521_u125_a1_0a

1521_u125_a9_0a
1521_u125_a1_0a

1521_u125_a1_0a
Yes
Not yet complete for support
To be announce

Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Not yet

Kick Off\1521_0039_a2_0a_Arm Extractor.pdf

Yes
Yes
Yes
Not yet
Photocells\1521_0160_a3_1a.pdf

Photocells\1521_0160_a2_0a.pdf
Remark Status
for your information

for your information


P&ID Combustion Air\1521_u050_a14_1a.pdf
Closed, All valve already check, all valve for gases
application using soft seat with NBR material
Closed, All valve already check, all valve for gases
application using soft seat with NBR material
- GNI not yet worked in Reheating Furnace Area

Closed, Gasket have already installed


Closed, Already check to data sheet for butterfly valve

Only for your information

Only for your information

General Comment

Closed

Closed

Closed

Closed

Closed
For Your Information
Closed
For Your Information
Closed, photocell already installed
Closed, already fixed