1.0. INSTALLATION COST FOR A 3.

3 KW SOLAR ARRAY SUPPORT STRUCTURE PER CELL SITE


QUOTATION DATE: 10.12.2018 PLS QUOTATION NUMBER: Q_01
CUSTOMER: JOB REFERENCE:

S/N PART NO. & DESCRIPTION QUANTITY UNIT PRICE EXTENSION NOTES: RECOMMENDATION
(N) (N)
1. (4 × 4)" /2.5mm THICK GALVANISED 6 SHEAR NUT
HOLLOW SQUARE PIPE
2. (2 × 2)" /2.5mm THICK GALVANISED 4
HOLLOW SQUARE PIPE
3. 4”/ 2.5mm THICK GALVANISED ANGLE 6
IRON
4. M18 FOUNDATION STUD AND NUT 16
5. 1FT2 GALVANISED FOUNDATION PLATE 4
6. M13 SHEAR NUT 50
7. M13 2” BOLT 50
8. 1" 140
M13 2 BOLT
9. 6mm2 PURE Cu WIRE (TWIN) SPECIAL 50m
SOLAR CABLE (ARMORED)
10. 4mm2 EARTH WIRE 1 ROLL
11. 25mm2 FLEX TRUNK PIPE 15m
12. CABLE TIE 2 THESE ITEMS ARE REQUIRED FOR EVERY
13. 50A DC MCB AND CASE 2 SITE INSTALLATION.
14. CEMENT (+quickset kit) 2 BAG
15. WELDING ELECTRODE 2 PACK
16. GRINDING STONE 2
17. M13 DRILL BITS 2 PACKET
18. PETROL FOR WELDING MACHINE 15 LTRS
19. INSTALLATION, LOGISTICS & MISC.
20. GRAND TOTAL
2.0. OTHER CRITICAL ITEMS TO ENABLE ON SITE FABRICATION FOR THREE (3) SITES SIMULTANEOUS INSTALLATION FOR 75
SITES:

QUOTATION DATE: 10.09.2018 PLS QUOTATION NUMBER: Q_02


CUSTOMER: JOB REFERENCE:

S/N PART NO. & DESCRIPTION QUANTITY UNIT PRICE EXTENSION NOTES: RECOMMENDATION
(N) (N)
1. 250 amps START AND WELDING 3 ITEMS PRESENTED HERE ARE NOT A PER
MACHINE SITE BASIS, RATHER THEY ARE
2. ANGLE GRINDER MACHINE 3 EQUIPMENTS USED SO THAT A MINIMUM
3. DRILLING MACHINE 3 OF THREE (3) SITES INSTALLATION TO BE
4. PORTABLE COLLAPSIBLE LADDER 3 RUN CONCURRENTLY.
TOTAL=
3.0. BRIEF ON SCHEDULE OF ACTIVITIES FOR THE INSTALLATION OF A 3.3KW SOLAR ARRAY AND SUPPORT STRUCTURE

DAY NATURE OF ACTIVITY NO. OF STAFF AND DESIGNATION


REQUIRED ON SITE DAILY
1 Deployment of 10nos 300 watts monocrystalline solar modules and the structural 1) Lead Engineer (1)
members alongside accessories for installation 2) Solar Engineer (3)
3) Electrical Technicians (3)
2 Setting out of plan, taking ground measurements, pegging, marking of foundation 1) Lead Engineer (1)
stand positions, digging/excavating of foundation trenches of solar support structure 2) Solar Engineers (3)
and concrete cast of foundation studs. 3) Electrical Technicians (3)
As the concrete cast is allowed to set, Structural fabrication will begin; measurement of 4) Brick Layer/Mason (2)
support structure members, cutting to dimension and drilling of holes for bolts to
fasten solar modules.
3 Setting into position base of support structure as concrete mix must have considerably 1) Lead Engineer (1)
cured (depending on weather conditions and geographical location). 2) Solar Engineers (3)
Welding of foundation plates to (4 × 2)" 2mm galvanized H channel (support structure 3) Electrical Technicians (3)
base) and(4 × 2)” 2mm galvanized U channel (paulines) and unto the 2” 2mm square 4) Welder (1)
pipe (web bracing) to ensure maximum support and rigidity. Coating of all structural
members with red oxide paint for anti-corrosion measure and subsequently with
aluminum paint to give it a required ecstatic’s.
The solar modules are then installed and fastened with the help of M8 shear nuts and 2
inch bolts for security.
Electrical connections are then made and cables neatly trunked for safety. Power is
routed via a 50A DC circuit breaker and then terminated at the power distribution
panel. Proper earth/ground connections are equipotentially bonded. Preliminary
testing is carried out.
4 Testing and Commissioning 1) Lead Engineer (1)
2) Solar Engineers (3)
3) Electrical Technicians (3)