WO#33 PROVISION OF DEDICATE IRT LINE FROM TK-253 TO MAB-HCR IN MAA

Activity ID Activity Name Original Start Finish 2019 2


Duration
A S Oct N D an

WO#33 PROVISION OF D
DEDICATE IRT LINE FROM TK-253 TO MAB-HCR IN M 378 27-Oct-18 A 10-Jan-20

MILESTONES 0 10-Jan-20 10-Jan-20

MS155 Work Order Completion 0 10-Jan-20

GENERAL ACTIVTIES 0

INITIATION 0
MOBILIZATION 0
SUBMISSIONS OF DOCUMENT
DOCUME 0
PMS 0
WORK PROGRAMME 0
PMS & "S" Curve 0
METHOD STATEMENTS & P
PROCEDURES 0
PAINTING & BLASTING PROCEDURE
PRO 0
WPS 0
ITP 0
HYDROTEST PROCEDURE 0
METHOD STATEMENT 0
PROCUREMENT 372 27-Oct-18 A 03-Jan-20

HANDING OVER FREE ISSUE


ISSU MATERIAL 0
PREFABRICATION 30 27-Oct-18 A 15-Aug-19
A2390 Blasting & Pre fabrication of piping material 30 27-Oct-18 A 15-Aug-19
KCCEC MATERIAL 357 13-Nov-18 A 03-Jan-20
PSV 134 14-Jul-19 A 03-Jan-20
A2640 Approval of Technical specification 10 14-Jul-19 A 15-Aug-19
A2580 Manufacturing ( 21 weeks ) 147 16-Aug-19 01-Jan-20
A2590 Delivery & Inspection at Site 2 01-Jan-20 03-Jan-20
OMRON RELAY 242 13-Nov-18 A 21-Aug-19
P3030 Placement of PO 14 13-Nov-18 A 10-Aug-19
P3040 Manufacturing 5 11-Aug-19 15-Aug-19
P3050 Delivery & Inspection at Site 5 17-Aug-19 21-Aug-19
DCS VENDOR ASSITANCE 30 05-Aug-19 08-Sep-19
P3055 Submission & approval of Data sheets 30 05-Aug-19 08-Sep-19

CONSTRUCTION 203 27-Apr-19 A 07-Jan-20

EXISTING LINE ( NEAR TK 4


459 TO NEAR TK 511 ) 0
TIE IN ( Existing Line Tie In ) TK 511 (tie in ) 0

Actual Level of Effort Remaining Work Date Revision Checked Approved


Page 1 of 2
05-Aug- Work schedule ( Balance activitie
Actual Work Critical Remainin...
WO#33 PROVISION OF DEDICATE IRT LINE FROM TK-253 TO MAB-HCR IN MAA
Activity ID Activity Name Original Start Finish 2019 2
Duration
A S Oct N D an
NEW LINE ( SWITCH GATE T
TO TK 511) 77 16-May-19 A 18-Aug-19
A1910 Fit-up & welding of field joints ( New line ) 5 16-May-19 A 14-Aug-19
A1930 NDT for field joints 2 14-Aug-19 17-Aug-19
A1940 Paint touch up 2 17-Aug-19 18-Aug-19
NEAR TK 459 TO TK 253 98 27-Apr-19 A 22-Sep-19
A1020 Erection of scaffolding 8 27-Apr-19 A 18-Aug-19
A1040 Installation of prefabricated pipes ( New line ) 12 01-May-19 A 22-Aug-19
A1050 Fit-up & welding of field joints 34 02-May-19 A 15-Sep-19
A1070 NDT for field joints ( New line ) 16 06-May-19 A 17-Sep-19
A1030 Dismantlle of scaffolding 4 17-Sep-19 22-Sep-19
A1100 paint touch up ( New line ) 4 17-Sep-19 22-Sep-19
A1035 Repair / Rectification of existing pipe supports ( if required ) and Pipe support 12 08-Sep-19 22-Sep-19
TIE IN ( new Line ) 7 22-Sep-19 30-Sep-19
A1765 Site prepration ( permit Authorization , necessary arrangements) 1 22-Sep-19 22-Sep-19

A1770 Fabrication / Testing / Cross check for tie in pipes 2 22-Sep-19 24-Sep-19

A1790 Cold Cutting 1 24-Sep-19 25-Sep-19


A1820 Welding of Tie in pipe 2 25-Sep-19 26-Sep-19

A1830 NDT 1 26-Sep-19 28-Sep-19


A1840 Hydrotest ( Complete line ) 2 28-Sep-19 30-Sep-19
PSV & MOV INSTALLATION 98 16-Sep-19 07-Jan-20
A2480 Installation of MOV 2 16-Sep-19 17-Sep-19
A2410 Bolting & Tightening of flanges 1 17-Sep-19 18-Sep-19
A2470 MOV feed back point & graphic Configuration 2 17-Sep-19 19-Sep-19

A2490 MOV Testing & Commissioning 2 17-Sep-19 19-Sep-19


A2600 Installation of PSV 2 04-Jan-20 05-Jan-20
A2610 Bolting & Tightening of flanges 1 05-Jan-20 06-Jan-20
A2620 PSV Testing & Commissioning 2 06-Jan-20 07-Jan-20

COMPLETION & HANDOVER


HANDO 110 22-Sep-19 10-Jan-20

H100 Punch Points 5 25-Sep-19 30-Sep-19

H110 As built and finals issue of documents 14 22-Sep-19 06-Oct-19


H105 Handover 3 07-Jan-20 10-Jan-20

Actual Level of Effort Remaining Work Date Revision Checked Approved


Page 2 of 2
05-Aug- Work schedule ( Balance activitie
Actual Work Critical Remainin...