PROJECT NAME:

LOCATION :
OWNER :
BILL OF MATERIALS

DISCRIPTION QTY UNIT ITEM COST


A. GENERAL REQUIREMENTS
1.0 Mobilization/Demobilization 1 LOT
SUB-TOTAL 11,500.00
2.0 Temporary Facilities and Safety and Health Program 1 LOT
SUB-TOTAL 310,500.00
3.0 Security Fences 1 LOT
SUB-TOTAL 77,625.00
B. SITEWORK
1.0 Clearing,Staking and Layout 1 LOT
SUB-TOTAL 17,250.00
2.0 Excavations 156 CU.M.
SUB-TOTAL 84,857.79
3.0 Backfilling and Compaction 233 CU.M.
SUB-TOTAL 126,410.76
4.0 Gravel Bedding 18 CU.M.
SUB-TOTAL 24,333.89
C. STRUCTURAL
1 Concrete Works
FOOTING 18 CU.M.
PEDESTAL 4 CU.M.
COMPOSITE COLUMN 22 CU.M.
FOOTING TIE BEAM 11 CU.M.
SLAB ON GRADE 43 CU.M.
2ND FLOOR SLAB 48 CU.M.
3RD FLOOR SLAB 21 CU.M.
ROOF SLAB 11 CU.M.
STAIRS 3 CU.M.
SUB-TOTAL 1,340,930.67
2.0 REBARS
FOOTING
16mmØBarX6m 135 LGTS
PEDESTAL
16mmØBarX6m 108 LGTS
10mmØBarX6m 88 LGTS
FOOTING TIE BEAM
16mmØBarX6m 150 LGTS
10mmØBarX6m 161 LGTS
SLAB ON GRADE
10mmØBarX6m 353 LGTS
2ND FLOOR SLAB
12mmØBarX6m 198 LGTS
10mmØBarX6m 361 LGTS
3RD FLOOR SLAB
12mmØBarX6m 81 LGTS
10mmØBarX6m 151 LGTS
ROOF SLAB
12mmØBarX6m 53 LGTS
10mmØBarX6m 96 LGTS
G.I. TIE WIRE #16 10 ROLL
SUB-TOTAL 724,039.43
3.0 Formworks and Scaffolding
3.1 Coco Lumbers 2"x2"x8' 1,223 LGTS
3.1 Coco Lumbers 2"x3"x8' 1,156 LGTS
3.2 plywood 1/4"x4'x8' 43 SHEET
3.2 plywood 1/2"x4'x8' 85 SHEET
3.3 Common Nail 3" 10 BOX
PROJECT NAME:
LOCATION :
OWNER :
BILL OF MATERIALS

3.4 Common Nail 2 1/2" 6 BOX


3.5 Common Nail 1 1/2" 2 BOX
3.6 Concrete Nail Assorted 1 BOX
SUB-TOTAL 455,574.92
4.0 STRUCTURAL BEAM
GROUND -2ND FLOOR COLUMN
W12X30X6M 20 LGTS
W10X30X6M 1 LGTS
2ND FLOOR- 3RD FLOOR COLIMN
W12X30X6M 20 LGTS
W10X30X6M 5 LGTS
3RD FLOOR-ROOF DECK COLIMNS
W10X30X6M 8 LGTS
2ND FLOOR FRAMING BEAMS
W10X30X6M 4 LGTS
W10X26X6M 14 LGTS
W12X26X6M 20 LGTS
W8X21X6M 4 LGTS
W8X15X6M 2 LGTS
3RD FLOOR FRAMING PLAN
W8X15X6M 12 LGTS
W8X21X6M 10 LGTS
W10X30X6M 7 LGTS
W10X22X6M 4 LGTS
W10X26X5M 1 LGTS
ROOF SLAB FRAMING PLAN
W6X12X6M 4 LGTS
W8X15X6M 5 LGTS
W8X21X6M 5 LGTS
0.8mm THK., DSND-1, 80,000psi 309 SQ.M.
200mmX350mmX16mm THK. BASE PLATE 2 PCS
200mmX350mmX20mm THK. BASE PLATE 20 PCS
20mmØ X800mmm LENGH A307 W/ BOLTS AND WASHIER 120 PCS
16mmØ X600mmm LENGH A307 W/ BOLTS AND WASHIER 12 PCS
4'x8'x16mm thk. Stiffener Plate 5 SHEET
4'x8'x15mm thk. Stair Landing 5 SHEET
4'x8'x12mm thk. SHEAR PLATE 10 SHEET
4'x8'x3mm thk. RunBase 4 SHEET
Angular Bar 50mmx50mmx6mm 70 LGTS
G.I. Pipe 4"x20'x4mm 60 LGTS
Welding Rod (N-7018) 20KG/BOX 15 BOX
Welding Rod (N-6011) 20KG/BOX 15 BOX
Oxygen Tank 200 CYL
Gas Tank 50 CYL
Rust Convertor 20 GAL
Epoxy Primier Grey 50 GAL
Laquer Thinner 20 GAL
Paint Brush 4" 50 PCS
Ruller Brush 4" 100 PCS
4" Grinding Disk 20 BOX
SUB-TOTAL 5,154,470.46

D. ROOFING AND TRANSMITHY


1.1 Colored Roof & Assessories 153 SQ.M.
1.2 C-Purlins 120 LGTS
1.3 C-Channel 320 LGTS
1.4 Welding Rod 6011 (20KG) 10 BOX
1.5 welding Rod 7018 (20KG) 10 BOX
1.6 Grinding Disk 4" 5 BOX
1.7 Primier Epoxy Grey 10 GAL
PROJECT NAME:
LOCATION :
OWNER :
BILL OF MATERIALS

1.8 Thinner 10 GAL


1.9 Babby Ruller 50 PCS
1.10 Paint Brush 2" 20 PCS
SUB-TOTAL 2,068,512.19
E. MASONRY /CIVIL WORKS
1. CHB LAYING, LINTEL BEAM, STIFFINER COLUMNS AND WALL FOOTING
1.0 6" CHB 3,406 PCS
1.1 4" CHB 3,232 PCS
1.2 Screened Sand 41 CU.M.
1.3 Fine Sand 47 CU.M.
1.4 Cement (Holcem) 1,104 BAGS
1.5 10mmØBarX6m 740 LGTS
1.6 12mmØBarX6m 75 LGTS
1.7 G.I. Tie Wire #16 3 roll
1.8 Concrete Topping 15 CU.M.
1.9 3/4 GRAVEL 16 CU.M.
SUB-TOTAL 1,038,287.16
F. ELECTRICAL WORKS
1.0 Service Entrance Wire
h. 22.0 mm2 THHN 100 L.M.
i. 14.0 mm2 THHN 50 L.M.
1.1 Power Distribution and lighting System Wire
a. 3.5 mm THHN #12 20 BOX
b. 5.5 mm THHN #10 25 BOX
c. 8.0 mm THHN #8 12 BOX
1.2 Conduits, Pipes & Accessories
a. 1" PVC Pipe 40 PCS
b. 1/2" PVC Pipe 250 PCS
c. 3/4" PVC Pipe 364 PCS
d. RSC Pipe Entrance Cap 1" dia. 6 PCS
i. RSC Pipe 25mm dia x 3mts 12 PCS
j. Utility Box 2"x4" 29 PCS
k. Junction Box 4'x4' 125 PCS
l. Electrical Tape (Big) 70 PCS
m. Telephone Wire 12 BOX
n. Cable Wire 12 BOX
1.3 Panel Boards & Circuit Breaker
a. Main Distribution Panel 2 Holes Bolt-on 100AT/1200AF 1 PCS
g. Typ. Panel Board 12 Branches Bolt-on 60AT/50AF 2 PCS
FIXTURES
1. Square / Circular Pin Light 170 PCS
2. Wall Lamp 10 PCS
Chandelier 10 PCS
Roof Light 4 PCS
4. Outlet 2 Gang 3 PCS
5. Outlet 1 Gang 46 PCS
6. Switch Single 14 PCS
7. Switch Double 23 PCS
8. Switch Three Way 3 PCS
9. Switch Three 8 PCS
SUB-TOTAL 1,088,477.93
G. SANITARY / PLUMBING WORKS
1.0 Sanitary and Ventline
1.1 PVC Pipe Series 1000 (Neltex) 95 PCS
c. 4" dia. PVC Pipe 11 PCS
d. 3" dia. PVC Pipe 5 PCS
e. 2" dia. PVC Pipe 6 PCS
f. 4" dia. PVC Coupling 4 PCS
PROJECT NAME:
LOCATION :
OWNER :
BILL OF MATERIALS

h. 2" dia. PVC Coupling 20 PCS


i. 4" dia. PVC Elbow 6 PCS
j. 3" dia. PVC Elbow 50 PCS
k. 2" dia. PVC Elbow 16 PCS
l. 4" dia. PVC Pipe Clean Out 27 PCS
m. 2" dia. PVC P-Trap 5 PCS
n. 4"x4" dia. Pipe Wye 8 PCS
o. 4"x2" dia. Wye Reducer 8 PCS
p. Neltex Solvent Cement 400cc 15 CAN
4" DIA pvc elbow 90° 5 PCS
3" DIA pvc elbow 90° 5 PCS
2" DIA pvc elbow 90° 5 PCS
2.0 Waterline Pipes
2.1 PPR Pipe
c. PN 20 Pipe, Fusion 25Ø 8 PCS
d. PN 20 Pipe, Fusion 20Ø 15 PCS
g. Elbow 90 25Ø 20 PCS
h. Elbow 90 20Ø 12 PCS
k. Tee Equal 25Ø 27 PCS
l. Tee Equal 20Ø 27 PCS
o. Tee Unequal 25Øx 20Ø 17 PCS
r. Coupling 25Ø 20 PCS
s. Coupling 20Ø 20 PCS
t. Elbow Female Adaptor 25Ø 19 PCS
w. Gate Valve 20Ø 15 PCS
x. Consumables 1 LOT
PLUMBING FIXTURES
1. WC, Lavatory, Soap Holder & Tissue Holder 39 PCS
2. Shower 7 PCS
3. Kitchen Sink 5 PCS
4. Floor Drain 4" 25 PCS
5. Fauset 31 PCS
SUB-TOTAL 3,048,706.35
H. CEILING WORKS
1.0 Ficem Board 3/16" Hardiflex 4'x8' 234 PCS
1.1 Metal Double Furring 50mmx5m 1,543 PCS
1.2 Metal Carrying Channel 50mmx5m 219 PCS
1.3 Metal Wall Angle 50mmx5m 198 PCS
1.4 Black Screw 1" 25,000 PCS
1.5 Blind Rivets 1/8"x1/2" 25,000 PCS
1.6 Concrete Nail 1" 2 BOX

SUB-TOTAL 1,092,401.10

I. PAINTING WORKS
1.1 Latex Paint White (Boysen) 127 GAL
1.2 Semi-Gloss Latex Paint White (Boysen) 127 GAL
1.3 Water Proofing Paint (Boysen) 50 GAL
1.4 Paint Thinner 20 GAL
1.5 Polytuff 100 CAN
1.6 Skim Coat 120 BAGS
1.7 Sand Paper # 400 400 PCS
1.8 Sand Paper # 100 400 PCS
1.9 Paint Brush # 2 50 PCS
2.0 Paint Brush # 3 50 PCS
2.1 Roller 7" 150 PCS
PROJECT NAME:
LOCATION :
OWNER :
BILL OF MATERIALS

2.2 Rag 300 KGS


2.3 Spatula 3" 120 PCS
SUB-TOTAL 572,871.40
J. FINISHES
1.0 TILING 124 s.m.
SUB-TOTAL 1,926,186.75
2.0 WOODEN DOORS AND HARDWARES 51 SQ.M.
SUB-TOTAL 395,887.50
3.0 GLASS DOORS AND WINDOWS AND ACCESSORIES 138 SQ.M.
SUB-TOTAL 1,178,176.73
4.0 STAIR (Floor Tiles & Railing) 1 LOT
SUB-TOTAL 388,125.00
5.O TUBULARS, RAILINGS AND ARCH. FIXTURES 1 LOT
SUB-TOTAL 465,750.00
K. KITCHEN CABINET & WALK-IN CLOSET 1 LOT
SUB-TOTAL 776,250.00
L. WALL FINISHES 1 LOT
SUB-TOTAL 931,500.00

TOTAL 23,298,625.00