List of Projects in Andhra Pradesh (as on 15/05/2018)

Estimate
S. Implementing
Project Name Theme d Cost Project Status
No. agency
(Rs. Cr)
1 Upgradation of OB 1 & 2 for Iron Ore Handling - Phase 1 Port Modernization 395 VPT Completed
2 Development of WQ N (WQ-7 and WQ-8) - Vizag Port Modernization 243 VPT Completed
3 RFID system - Vizag Port Port Modernization 7 VPT Completed
Supply, Erection, Testing and commissioning of 2 HMCs of
4 Port Modernization 39 VPT Completed
capacity greater than 100MT at east quay berth - Vizag Port
5 2 to 4 laning of port road connectivity to NH – 5 (Phase II) Port Connectivity 77 VPT Completed
Upgrading B.T Road from Burmah Shell area to security gate near Department of
6 Port Connectivity 15 Completed
Sakthi Gas Plant at Kakinada Anchorage port Ports, GoAP
7 Road Connectivity of VPT to NH-16 (Phase II) Port Connectivity 77 NHAI Completed
8 Construction of coastal Berth at VPT Port Modernization 43 VPT Completed
9 Electrification of east yard revamped lines. 23.489 TKM Port Connectivity 20 VPT Completed
Rail Connectivity to South Port of Krishnapatnam Port from
10 Port Connectivity 300 Indian Railways Completed
Guduru
11 Krishnapatnam-Venkatachalam - Doubling with electrification Port Connectivity 87 Indian Railways Completed
12 Vishnupuram- Mellacheruvu New BG line Port Connectivity 378 Indian Railways Completed
Development of Kakinada Hope Island Konaseema as World Class Coastal Community AP Forest
13 70 Completed
Coastal & Eco-Tourism Circuit in Andhra Pradesh Development Department
14 Development of New EQ-10 berth - Vizag Port Modernization 55.38 VPT Completed
15 Iron Ore Handling - Phase 2 - Mechanisation of WQ 1 - Vizag Port Modernization 265 VPT DPR Prepared
Development of Passenger Jetty, Sea Plane Jetty and upgradation
16 Port Modernization 58 APTDC DPR Prepared
of existing jetty at Kakinada
2 to 4 laning of road connecting Kakinada port to NH 16 at
17 Port Connectivity 1,074 NHAI DPR Prepared
Rajanagaram in Godavri District
18 Bhadrachalam- Kovvuru New BG Line (151 Km) Port Connectivity 1,500 Indian Railways DPR Prepared
Development of Fishing Harbour in Juvvaladinne in SPSR Nellore Coastal Community Fisheries
19 242 DPR Prepared
District in the State of Andhra Pradesh. Development Department, GoAP
Direct connectivity to Mindi Yard from E.Co. Railways/ SC
20 Port Connectivity DPR Prepared
Railways 45 IPRCL
Phase 2 development of existing fishing harbour at Coastal Community Fisheries
21 Development DPR Prepared
Machilipatnam in Krishna district 252 Department, GoAP
Phase 2 development of existing fishing harbour at Nizampatnam Coastal Community Fisheries
22 Development DPR Prepared
in Guntur district 341 Department, GoAP
Coastal Community Fisheries
23 Development of fishing harbour at Vodarevu in Prakasam district Development DPR Prepared
409 Department, GoAP
Development of fishing harbour at Uppada (V) U. Kotapalli (M) in Coastal Community Fisheries
24 289 DPR Prepared
East Godavari district Development Department, GoAP
Department of
25 New Port at Machhilipatnam (Phase 1) Port Modernization 11924 DPR Prepared
Ports, GoAP
Department of
26 New Port - Bhavanapadu Port Modernization 4000 DPR Prepared
Ports, GoAP
Department of
27 Development of passenger jetties at Kakinada Port for tourism Port Modernization 100 DPR to be Prepared
Ports, GoAP
Expressway from Sanathnagar industrial cluster (Hyderabad) to
28 Port Connectivity 10,000 NHAI DPR to be Prepared
Vodarevu
Port led
29 Petrochemical cluster in Kakinada 4,520 MoC&F DPR to be Prepared
Industrialization
Port led
30 Development of an export based apparel cluster in central AP 3,321 APIIC DPR to be Prepared
Industrialization
Port led
31 Cement cluster in AP 24,500 DIPP DPR to be Prepared
Industrialization
Development of dedicated Machilipatnam Port Rail Connectivity
32 Port Connectivity 40 Navyuga DPR to be Prepared
from Pedana Station
Development of rail siding with number of holding lines in
33 Port Connectivity 250 Navyuga DPR to be Prepared
Machilipatnam
Port led
34 Development of CEZ in Andhra Pradesh (VCIC North) 3,000 APIIC DPR to be Prepared
Industrialization
35 4 laning of Manginapudi Beach Road connecting Machilipatnam Port Connectivity 60 NHAI DPR to be Prepared

Four lane green field road from Machilipatnam South Port to NH-
36 Port Connectivity 458 NHAI DPR to be Prepared
9 in the State of Andhra Pradesh
Four Lane green field road from Machilipatnam North Port to NH-
37 Port Connectivity 232 NHAI DPR to be Prepared
SH-46 in the State of Andhra Pradesh
Development of 7.2Km green field road connecting NH 65 to
38 Port Connectivity 175 NHAI DPR to be Prepared
Machilipatnam Port in the State of Andhra Pradesh.
Road Connectivity From Outer Harbour To Port Connectivity
39 Junction (B) at Vizag port (4 Lane road from existing East Break Port Connectivity 500 NHAI DPR to be Prepared
Waters upto Convent Junction)
Fly over bridge from Sea-horses junction area to dock area at
40 Port Connectivity 277 NHAI DPR to be Prepared
Vizag Port
Port led
41 Development of CEZ in Andhra Pradesh (VCIC Central) 3,000 APIIC DPR to be Prepared
Industrialization
Department of
42 Modernization of Infrastructure at Kakinada Anchorage Port Port Modernization 90 DPR to be Prepared
Ports, GoAP
Coastal Community Department of
43 Setting up logistics and Maritime University at Kakinada 300 DPR to be Prepared
Development Ports, GoAP
44 Bhavanapadu Port rail link Port Connectivity TBA Adani Ports DPR to be Prepared
Construction of flyover bridge (FOB) at Nathayyapalem (Mindi)
45 Port Connectivity NHAI DPR to be Prepared
on NH-16 TBA
Construction of flyover/under-pass at Vizag airport junction to
46 Port Connectivity TBA NHAI DPR to be Prepared
ensure flow of container trailers to/from MMLP setup at NH-16
Development of outer ring road from East Breakwater to
47 Port Connectivity TBA NHAI DPR to be Prepared
Sheelanagar
Formation of new road from L-Arm road Junction to
Dummulapeta Beach Road at NCS storage system including DPR under
48 Port Connectivity 50 NHAI
construction of bridge on Dummulapeta Creek at Kakinada preparation
Anchorage Port
4 laning of Kakinada Anchorage Port Uppada beach road DPR under
49 Port Connectivity 980 NHAI
connecting NH-16 in East Godavari District preparation
RoB at Dummalapeta and Old Port Area in Kakinada Deep Water DPR under
50 Port Connectivity 80 NHAI
Port & Kakinada Anchorage Port preparation
Greenfield road connecting north and south industrial cluster of DPR under
51 Port Connectivity 580 NHAI
Khandaleru Creek near Krishnapatnam port preparation
DPR under
52 4 laning of road from Nellore city to Krishnapatnam port to NH 5 Port Connectivity 300 NHAI
preparation
DPR under
53 Construction of Passenger Jetty at Baruva in Srikakulam Port Modernization 59 APTDC
preparation
DPR under
54 Construction of Tourism Passenger Jetty at Manginapudi, Krishna Port Modernization 74 APTDC
preparation
Construction of Tourism Passenger Jetty at Kothapatnam, DPR under
55 Port Modernization 62 APTDC
Prakasam preparation
DPR under
56 Construction of Tourism Passenger Jetty at Maypadu, SPS Nellore Port Modernization 58 APTDC
preparation
DPR under
57 Construction of a passenger Jetty at Bheemunipatnam Port Modernization 79 APTDC
preparation
DPR under
58 Construction of a passenger Jetty at Kalingapatnam Port Modernization 48 APTDC
preparation
Flyover/RoB over ADB road (Kakinada Deep water port from DPR under
59 Port Connectivity 350 NHAI
Kumbhabhishek Temple to fishing Harbour) at Kakinada preparation
Up grading of existing R&B road from Chilakaru cross (NH-16) to DPR under
60 Port Connectivity 300 NHAI
Power Plants preparation
Greenfield bypass road connecting Gangavaram port in DPR under
61 Port Connectivity 80 NHAI
Visakhapatnam District (Lanes to be specified) preparation
Four lane Beach Road connecting Gangavaram Port to the SEZ
DPR under
62 proposed at Achuthapuram in Visakhapatnam District in the Port Connectivity 138 NHAI
preparation
State of Andhra Pradesh
4 to 6 laning of road connecting to NH16 at Gajuwaka to DPR under
63 Port Connectivity 50 NHAI
Gangavaram Port preparation
DPR under
64 4 lane road to Krishnapatnam Port from Naidupeta in AP Port Connectivity 670 NHAI
preparation
DPR under
65 Electrification of VPT railway lines 45.143 TKM Port Connectivity 20 IPRCL
preparation
DPR under
66 Various Signalling works at VPT Port Connectivity 24 IPRCL
preparation
4 to 6 laning of road connecting VPT East breakwater to Sheela DPR under
67 Port Connectivity TBA NHAI
Nagar Junction preparation
DPR under
68 Four lane coastal road from Gangavaram Port to Vizag Port Port Connectivity TBA NHAI
preparation
4 laning of Varagali Road from Chillakur Cross to Chintawaram DPR under
69 Port Connectivity 332.87 NHAI
Package II Km 0.000 To Km 16.450 in AP preparation
Under
70 Container scanners - Vizag Port Port Modernization 30 VPT
Implementation
Providing a direct connection between OEC and Western Sector Under
71 Port Connectivity 20 IPRCL
jointing at NAD Curve from E.Co. Rly. Implementation
Centre of Excellence in Maritime & Shipbuilding (CEMS) - AP Coastal Community Under
72 574 IRS
(18 out of 24 Labs in AP) Development Implementation
Under
73 Extension of line No. 11 to 15 to full length at R&D yard. Port Connectivity 18 IPRCL
Implementation
Greenfield Electronics manufacturing Cluster in Renigunta and Port led Under
74 9706.75 MeitY
Yerpdeu Mandal, Chittor District, Tirupati, AP Industrialization Implementation
Conversion of existing berths EQ-2, EQ-3, EQ-4 and part of EQ-5 Under
75 Port Modernization 182 VPT
into two numbers of berths - Vizag Implementation
Under
76 Development of New Berth EQ 1A - Vizag Port Modernization 313 VPT
Implementation
Upgradation of the hinterland road From Naidupeta (in Nellore Under
77 Port Connectivity 3,000 NHAI
District of AP) to Krishnagiri (in TN) Implementation
Develop NW4 (from Vijayawada to Galagali on Krishna river) Under
78 Port Connectivity 7,002 IWAI
Kakinada- Vijayawada - Muktyala, Vijayawada to Thada Implementation
2 to 4 laning of road connecting Achampeta Junction to joining Under
79 Port Connectivity 300 MoRTH
NH 16 at Kathipudi in East Godavri District in AP Implementation
Greenfield Electronics manufacturing Cluster in Cherivi Village, Port led Under
80 1604.41 MeitY
Satyavedu Mandal, Chittor District, Tirupati, AP Industrialization Implementation
Upgradation of the proposed NH-67 From Bellary (Karnataka) to Under
81 Port Connectivity 2,440 MoRTH
Krishnapatnam (Andhra Pradesh) Implementation
Under
82 Upgrading of NH 65 from Vijayawada to the Machilipatnam Port Port Connectivity 1,087 NHAI
Implementation
Greenfield Electronics manufacturing Cluster in Vikruthamala Port led Under
83 5719.8 MeitY
Village, Yerpadu Mandal, Chittor District, Tirupati, AP Industrialization Implementation
Under
84 Decongesting RV line - 2nd line Raipur - Titlagarh (203 Km) Port Connectivity 758 Indian Railways
Implementation
Port led Under
85 Power Cluster in AP (Krishnapatnam) 37428 Ministry of Power
Industrialization Implementation
4 to 6 laning of road connecting Krishnapatnam Port to NH 5 in Under
86 Port Connectivity 315 NHAI
SPSR Nellore District of Andhra Pradesh Implementation
Under
87 Rail Obulavaripalle-Venkatachalam (95 km) Port Connectivity 1,825 Indian Railways
Implementation
Under
88 Construction of passenger jetty at Bhavani island, Krishna district Port Modernization 22 APTDC
Implementation
Connection of dead end line at North of R&D yard to Eastern Grid Under
89 Port Connectivity 13 IPRCL
(Third line) from E.Co.Rlys. Implementation
Under
90 Upgrading of NH 216 from 2 lane to 4 lane Digamarru to Ongole Port Connectivity 3,731 MoRTH
Implementation
Road connecting Vizag Port from Sheela Nagar junction to
Under
91 Anakapalli-Sabbavaram/Pendurti - Anandapuram road i.e. NH-16 Port Connectivity 2,352 NHAI
Implementation
(Former NH-5)
Port-based Mega food processing park in Kakinada (Godavari Port led Under
92 123 MoFPI
Mega Aqua Food park) Industrialization Implementation
Development of Coastal Tourism Circuit in Sri Potti Sri Ramulu Coastal Community Under
93 60 APTDC
(SPSR) Nellore under Swadesh Darshan Scheme Development Implementation
Under
94 Doubling of Vijayawada- Machilipatnam Railway line Port Connectivity 550 Indian Railways
Implementation
Under
95 Phase II of Multi Model Logistics Hub - Vizag Port Port Connectivity 262 VPT
Implementation
Port led Under
96 APIIC Mega Food Park 125.25 MoFPI
Industrialization Implementation

Doubling of line Vijaywada-Gudivada- Bhimavaram-Narasapur, Under


97 Port Connectivity 1,504 Indian Railways
Gudivada-Machlipatnam and Bhimavaram-Nidadavolu (221 km) Implementation

Under
98 Kotipalli- Narsapur New BG Line (57.21 Km) Port Connectivity 2,120 Indian Railways
Implementation
Coastal Districts Skill Development Program - Phase I (Andhra Coastal Community Under
99 0.28 MoRD (DDU-GKY)
Pradesh) Development Implementation
Construction of grade separator from H-7 area to Port
100 Port Connectivity 60 NHAI Under Tendering
connectivity Road by passing Convent Junction - Vizag Port
101 Extension of existing container terminal at VPT on DBFOT basis Port Modernization 633 VPT Under Tendering
Coastal Districts Skill Development Program - Phase 2 (Andhra Coastal Community
102 6 MoRD (DDU-GKY) Under Tendering
Pradesh) Development
103 Additional Oil Jetty (OR3) alongwith OR1 and OR2 at Vizag Port Modernization 168 VPT Under Tendering
104 New Port - Kakinada SEZ (KSEZ) Port Modernization 2123 GMR Under Tendering