Documente Academic
Documente Profesional
Documente Cultură
Bored Piles
Reaction
System Secant
Load Test Piles
RESOURCE
PILING
Contiguous
Bored Pile Kentledge
Wall Load Test
Ancillary
Services
3
Achievements
• Over 30 years of Piling (since 1981)
• >489 piling projects completed
• Grade L6 (unlimited piling contracts value)
• Largest & deepest piles: Ø2.5m & 92m
• Largest Kentledge in Singapore: 5,700 ton
• Largest Reaction test in Singapore: 7,652 ton
Mitram Gopal –
HSE Executive (Keller)
Members Donald Choo – Plant Mngr
Design solution
Schedule of project
•Schedule was
developed to plan and
monitor progress of the
progress
•Corrective actions
were taken when Implementation
deadlines were not met
•Overall progress was
Oasis Hotel Review
in line with plan
ROOT CAUSE ANALYSIS
Root cause analysis
The Ishikawa model along with the 5 Why model were
used to postulate the cause of the accident at Gilstead
road.
Explosive
Statnamic is an 2 main difficulties with O- Estimated cost of steel Estimated cost for a
explosive test. There cells are in terms of the plates for a 7,068 ton 7,068 ton Reaction
are inherent risks design (accurate Kentledge test is S$7.8 load test is S$0.78.
with the handling placement of the O-cell in million. This is a huge
explosive material the pile) and quality of investment. Hence this is the
especially with construction (especially preferred option
increase of test with the concrete just
loads. below the O-cell).
Current Capacity Limitations
However, reactions systems capacities have so far been in the range of 1,500
tons to 2,000 tons. Hence the Reaction System load test would need to be re-
designed to allow test of more than 4,000 tons.
Test Pile
Reaction
Piles
BENEFITS
Height reduction
-
15000
A 7,068 ton Kentledge using
concrete blocks (left) would
3750
require employees to work at a
maximum height of 21.2 m
whereas a Reaction load test of
5250
the same capacity would
require employees to work at a
much reduced 6.4 m.
16,500
21,145mm
21.2m
7500
838
912
1400
2176
1300
835
6.4m
338 760
381
2000 Pile
Head
5400 3350 3350 5400
Toppling zone
15000
3750
5250
16,500
21,145mm
Height:
Height:
7500
21.2m
6.4m
838
912
1400
1300
2176
835
338 760
381
2000 Pile
Head
5400 3350 3350 5400
78.6m
Toppling
Height Lifts Traffic Cost
Zone
An example of the completed setup (a 7,652 ton) load test using the Reaction System at
Ophir road, Singapore.
EXPANDABILITY
Projects completed
Project Test Load Done on
Oasis Hotel @ Peck 5380t 2012 Aug.
Seah St.
M+S Project @ Ophir 7652t 2012 Nov.
Road
7652t 2012 Nov.
6240t 2013 Feb.
5046t 2013 Apr.
Intangible results
o Workers morale = Improved
o Safety awareness = Improved
o Public perception = Improved