Documente Academic
Documente Profesional
Documente Cultură
10.1 Introduction
A pile cap is defined as a concrete block cast on the head of a group of piles, to
transmit the load from the structure to the group of piles. Generally, pile cap
transfers the load form the structures to a pile group, then the load further
transfers to firm soil.
External pressures on a pile are likely to be greatest near the ground surface.
Ground stability increases with depth and pressure. The top of the pile
therefore, is more vulnerable to movement and stress than the base of the pile.
Pile caps are thus incorporated in order to tie the pile heads together so that
individual pile movement and settlement is greatly reduced. Thus stability of
the pile group is greatly increased.
1. To distribute a single load equally over the pile group and thus over a
greater area of bearing potential,
The C.G. of piles should be placed as far as possible in the C.G. of loads
transmitted from the structure to the group of piles.
Initial Layout:
The simplest pile layout is one without batter piles. Such a layout should be
used if the magnitude of lateral forces is small. Since all piles do not carry an
equal portion of the load, axial pile capacity can be reduced to 70 percent of
the computed value to provide a good starting point to determine an initial
layout. In this case, the designer begins by dividing the largest vertical load on
the structure by the reduced pile capacity to obtain the approximate number
of pile. If there are large applied lateral forces, then batter piles are usually
required. Piles with flat batters 2.5 (V) to 1 (H), provide greater resistance to
lateral loads and the less resistance to vertical loads. Piles with steep batters 5
(V) to 1 (H) provide greater vertical resistance and less lateral resistance.
Final Layout:
After the preliminary layout was developed remaining load cases should be
investigated and the layout revised to provide an efficient layout. The goal
should be to produce a pile layout in which most piles are loaded as near to
capacity as practical for the critical loading cases with tips located at the same
elevation for the various pile groups within a given monolith. Adjustments to
the initial layout by the addition deletion, or relocation of piles within the
layout grid system may be required. Generally, revisions to the pile batters
will not be required because they were optimized during the initial pile layout.
The designer is cautioned that the founding of piles at various elevations or in
different strata may result in monolith instability and differential settlement.
1. Design must satisfy the punching shear in the vicinity of the individual
piles or shafts
3. The bearing force between the individual piles or shafts and the caps
must not exceed the capacity of either element.
• Pile Cap Reinforcement
The amount of pile cap reinforcement is governed by:
To a great extent the design and calculation (load analysis) of pile foundations
is carried out using computer software. For some special cases, calculations
can be carried out using the following methods
For a simple understanding of the method, let us assume that the following
conditions are satisfied:
3. Each pile receives the load only vertically (i.e. axially applied );
Ix = Io + A . X2
بإهمال Ioلصغر قيمته ،وحذف الحد ( Aحيث ( )Aمساحة مقطع الخازوق ) من المعادلة ،نجد أن
حمولة الخازوق الناتجة عن العزوم المطبقة على القيمة هى المبينة فى المعادلة :
Eccentricity of load
) ( Single
Eccentricity of load
)( Double
Graphical Method
Installation error:
Until now we have been calculating theoretical force distribution on piles.
However during installation of piles slight changes in position do occur and
piles may miss their designed locations.
So the designer must compare theoretical and the actual load distribution as a
result of misalignment after pile installation.
Deviation of the piles
Thus, the pile cap should be large enough to accommodate those piles which
have deviated from the intended position. The pile cap should extend for a
distance of 100 to 150 mm outside the outer face of the piles in the group.
The pile head at cutoff elevation shall be within 50 mm of plan locations for
bent caps supported by piles, and shall be within 150mm of plan locations for
all piles capped below final grade. The as – driven centroid of load of any pile
group at cutoff elevation shall be within 5% of the plan location of the
designed centroid of load.
No pile shall be nearer than 100mm from any edge of the cap. Any increase in
size of cap to meet this edge distance requirement shall be at the Contractor’s
expense.
Piles shall be installed so that the axial alignment of the top 3m of the pile is
within 2% of the specified alignment. For piles that cannot be inspected
internally after installation, an alignment check shall be made before
installing the last 1.5m of pile, or after installation is completed provided the
exposed portion of the pile is not less than 1.5m in length. The Engineer may
require that driving be stopped in order to check the pile alignment. Aligned
section on a misaligned section shall not be permitted.
• If the pile group is analyzed with a rigid base, then a separate analysis is
needed to determine the stresses in the pile cap.
• There are many methods for designing pile caps from which we could
mention the following:
1- Circulage Method
2- Beam Method
3- FEM methods
• Circulage method can only be used when the column is loaded with an
axial force and piles are arranged on the circumference of a circle. Piles are
not allowed to carry horizontal forces in this case.
The strut-and-tie model should be considered for the design of deep footings
and pile caps or other situations in which the distance between the centres of
applied load and the supporting reactions is less than about twice the member
thickness.
Struts and ties in a pile cap
The main reinforcement (As) can then be calculated from the following
relation:
Design Procedure:
A- Required Data:
2- Column dimensions
B- Design Steps:
Notes:
9- Details of reinforcement:
Plane
10.4.3 FEM Method
Grid used for FLAC 3D analysis of pile groups (After Poulos, 2001)
10.5 Grade Beams
• Grade beams are required for all deep foundations subject to seismic loads.
For seismic design, they must resist a horizontal load equal to 10% of the
column vertical load.
• Grade beams must be designed without the support of the underlying soil.
• Ground beams should not be confused with capping beams. Capping beams
perform the same function as pile caps. However, the function of a ground
beam is to connect adjacent pile caps to ensure stability of the foundation
and to ensure stability against lateral forces.
• Ground beams are designed to connect a group of pile caps in a continuous
manner.
• The top and bottom reinforcement of a ground beam are usually made equal
to overcome lateral forces or settlement of one pile cap relative to the
adjacent one.
• Ground beams may also require shear reinforcement in the form of binders.
• The depth of the ground beam is usually more than 1/15 of the span. The
width of the beam depends on design requirements.
Ground beams can also be designed to transmit loads from walls to pile caps.