Sunteți pe pagina 1din 7

J. Mt. Sci.

(2012) 9: 214–220
DOI: 10.1007/s11629-012-2148-5

Dam-break Flood Simulation under Various Likely


Scenarios and Mapping Using GIS: Case of a Proposed Dam
on River Yamuna, India

Mahendra S. LODHI1* and Devendra K. AGRAWAL2

1 GB Pant Institute of Himalayan Environment and Development, North-East Unit, Vivek Vihar, Itanagar - 791113,
Arunachal Pradesh, India
2 AGM – Environment, Energy Infratech Pvt. Ltd., Plot No: 145 – 146, Udyog Vihar Phase – IV, Gurgaon – 122015, India

﹡Corresponding author,e-mail: mahen29.mail@gmail.com

© Science Press and Institute of Mountain Hazards and Environment, CAS and Springer-Verlag Berlin Heidelberg 2012

Abstract: The precision modeling of dam break Introduction


floods can lead to formulation of proper emergency
action plan to minimize flood impacts within the Among the various man-made hazards, failure
economic lifetime of the assets. Application of GIS
of a storage dam is a common and disastrous
techniques in integration with hydrological modeling
hazard. Large inflow into the reservoir, seepage or
for mapping of the flood inundated areas can play a
momentous role in further minimizing the risk and
piping action through dam structure, embankment
likely damages. In the present study, dam break or slope failure, earth quake, landslides generated
analysis using DAMBRK model was performed under waves etc. are the possible reasons responsible for
various likely scenarios. Probable Maximum Flood a dam failure. Irrespective of the cause of failure it
(PMF) calculated for a return period of 1000 years is quite apparent that the elevated water waves
using deterministic approach was adopted for dam rushing down can lead to massive destruction in
break analysis of the proposed dam under various the downstream reaches. Floods due to dam failure
combinations of breach dimensions. The available are generally significantly larger than natural
downstream river cross-sections data sets were used floods as unexpected high peak in a very short
as input in the model to generate the downstream duration and presence of a moving hydraulic
flood profile. Dam break flow depths generated by the
shock/bore make it a different problem as
DAMBRK model under various combinations of
compared to other natural floods (Singh 2005).
structural failure are subsequently plotted on Digital
Elevation Model (DEM) of the downstream of dam
Flood waves resulting from dam breaks have been
site to map the likely affected area. The simulation responsible for severe losses of life and natural as
results reveals that in one particular case the flood well as man-made assets (Husain et al. 2000).
without dam may be more intense if a rainfall of Advance and efficient modeling of probable dam
significant intensity takes place. failure events can play a significant role in
safeguarding the life and valuable resources against
Keywords: Dam break analysis; DAMBRK; GIS; such man-made disasters. The predictive data on
Flood mapping; Hydropower; India hypothetical flood events such as flood flows, flow
velocities, depths and flood wave arrival times at
specific locations downstream of the dam become
somewhat the most important pieces of
Received: 24 March 2011
information for disaster preparedness (Kho et al.
Accepted: 25 December 2011

214
J. Mt. Sci. (2012) 9: 214–220

2009). In order to predict the magnitude and through the valley cross-sections.
extent of such floods, computerized mathematical If a disaster cannot be avoided, individual and
simulation models are being recognized as social structure preparedness may be of great help
powerful tools worldwide. in reducing risk and vulnerability. Past experiences
shows that the time between the occurrence of a
breach and discharge of the dam reservoir ranges
1 Methods and Materials from 15 minutes to 5 hours (Seker et al. 2003).
Thus a precision modeling of dam break floods can
1.1 Modeling of dam break flow lead to formulation of proper emergency action
plan to minimize flood impacts within the
Ritter (1892) attempted very first for the economic lifetime of the assets. To make the people
analytical solution of dam break problems for a aware and resilient against dam break floods, a
horizontal frictionless rectangular channel and now flood hazard map can be a comprehensive mode of
a day’s different flood and reservoir routing proving all these details at one place. Application of
methods and procedures are available in literature. Geographical Information System (GIS) techniques
Till now several researchers have developed one in integration of hydrological modeling can result
dimensional and two dimensional models vital maps depicting valuable and reliable
(Katopodes 1984; Hromadka 1985; Akanbi et al. information on future risk assessment and their
1988; Zhao et al. 1996; Hicks et al. 1997; Sarma management. In the present study, an effort has
1999; Zoppou et al. 2000; Sanders 2001; been made to plot the model generated flooding
Macchione et al. 2004), for simulating dam break elevations under various combinations of possible
flood (Mimi et al. 2006). In addition to this, a flood hazard on Digital Elevation Model (DEM) of
number of professional and user friendly software the downstream river stretch. The dam under study
viz. UNET (HEC 1995), MIKE-11 (Danish is a part of Vyasi hydroelectric power project which
Hydraulics Institute), DAMBRK (NWS), RUBICON, is proposed on river Yamun in Uttarakhand state of
FLDWAV etc. have been developed for simplifying India (Figure 1). The proposed hydropower project
the cumbersome process of carrying out the dam is planned to have a capacity of 120 MW. The
break analysis routing. The choice of a model probable maximum flood calculated for a return
depends upon the prevailing ground situations and period of 1000 years using deterministic approach
the availability of the data sets. was adopted for carrying out dam failure analysis
All these dam break models are categorized of the proposed dam under various combinations
into two groups i.e., the simple empirical models
and the sophisticated ones requiring high-level
computer skills. Among these, the BOSS DAMBRK
(originally developed by NWS) model has been
widely used (Nayak et al. 2004; Wahl 1997). The
BOSS DAMBRK is advanced, easy-to-use one-
dimensional hydrodynamic flood routing software
and is commonly used for dynamic flood routing,
dam safety analysis and reservoir spillway analysis.
The DAMBRK model simulates the failure of a dam,
computes the resultant outflow hydrograph and
also simulates movement of the dam break flood
wave through the downstream river valley. It
utilizes hydrodynamic theory to predict the dam
break wave formation and its downstream
progression (User’s Manual 1991). After computing
the hydrograph of the reservoir outflow, the
flooding elevations in the downstream valley is Figure 1 Location map of the Vyasi Hydropower Dam
determined by routing the outflow hydrograph and its catchment in Yamuna basin

215
J. Mt. Sci. (2012) 9: 214–220

of breach dimensions and time of occurrence using characteristics, etc.), downstream river cross-
the available data sets of natural downstream river sections and channel roughness characteristics. In
cross-sections. present study, these basic data sets were acquired
from the project proponent’s document (Revised
Detailed Project Report of Lakhwar-Vyasi
Table 1 Salient features of the project hydropower project 2006) and remaining few
Dam parameters such as roughness coefficient etc., were
Top of dam EL. 634 m assumed based on the river valley characteristics,
River bed level at dam site EL. 584 m technical help from DAMBRK User’s manual was
Expected deepest foundation level EL. 548 m also taken. The inflow hydrograph considered in
Upstream slope 0.3:1 the present analysis is Probable Maximum Flood
Downstream Slope 0.65:1
(PMF) hydrograph (Figure 2) with 1000 yr return
Reservoir
period having a peak of 8850 cubic metre per
Maximum water level (MWL) EL. 631.5 m
Full Reservoir Level (FRL) EL. 360 m
second (cumec). The PMF was estimated by
Gross Storage at FRL 12.6 Mm3 deterministic approach using hydrograph method
Dead Storage at Minimum Drawdown by convolution of 1-day unit hydrograph computed
9.12 Mm3
Level (MDDL) from the observed flood hydrograph of 1988. The
Reservoir area at FRL 70.4 ha reservoir’s storage volume was estimated in terms
Live Storage 3.48 Mm3 of Elevation-Area capacity as presented in Table 2.
Hydrology
Catchment area 2100 km2
Free Draining Catchment 13.6137 km2
Designed Flood 8850 Cumec
Maximum Annual Runoff (1998-99) 37637 Mm3
Average Annual Runoff 2318 Mm3

1.2 The Vyasi hydroelectric power project

The proposed Vyasi hydroelectric project


(HEP) will have an 86 m high (above deepest
foundation) concrete gravity dam having 205 m of
top width (30o31’N, 77 o 54’E). The dam will
regulate the river flow through a 2.7 km long and 7
m diameter tunnel to the power house proposed
4.5 km downstream of the dam site. The project on Figure 2 Inflow probable maximum flood hydrograph
for Vyasi dam site (Source: Revised DPR, Lakhwar and
completion is likely to generate 425 million kWh of Vyasi Hydroelectric project, 2006)
electricity on annual basis. The project site is 66.6
km from Dehradun, the state capital of Table 2 Reservoir volume description
Uttarakhand and the site can be approached Elevation (m AMSL) Surface Area (km2)
through National Highway 123 passing through the 634.00 0.765
project area (Comprehensive EIA of Vyasi HEP 626.00 0.604
2006). The salient features of the project (Table 1) 618.00 0.438
are given below. 610.00 0.278
602.00 0.166
1.3 Data Required 594.00 0.080
586.00 0.019
For undertaking the dam break analysis, basic 584.00 0
data required for DAMBRK model are hydrological
detail (PMF hydrograph), reservoir information The reservoir cross-sections at an interval of
(Elevation-Area characteristics), dam design each 250 m were taken from the dam axis up to a
parameters (different dam elevations, spillway point along the length of river Yamuna where river

216
J. Mt. Sci. (2012) 9: 214–220

bed level is equal to FRL (Full Reservoir Level). nature of structure and acting forces, thus in order
The reservoir capacity at FRL (EL 630 m) and to simulate the possible scenario, a set of different
MDDL (EL 624.5 m) was worked out as 12.6 Mm3 values can give better estimates. To study the effect
and 9.12 Mm3 respectively. The length of Vyasi of breach dimensions, different combinations
reservoir at FRL (EL 630 m) is 4.85 km and the starting from least to worst case were considered
spread at FRL is 0.703 km2 (Revised Detailed for developing different scenarios of dam break
Project Report of Lakhwar-Vyasi hydropower failure. Further, since the concrete dams tend to
project 2006). The actual downstream river cross have a rectangular breach, therefore the breach
sections provided by the project proponents up to side slopes are assumed zero. The time of breach
reach length of 5.65 km at every 500m interval formation in such cases is usually small therefore;
have been used for conducting the analysis. the time of breach formation was taken as 0.1 hr
Additional river cross-sections were generated for all the scenarios. The roughness coefficients of
through GIS using DEM up to a downstream reach the river bed material were taken as 0.05 at the
length of 26.5 km. The DEM for the catchment area dam section and 0.04 at all other river cross
was generated through standard Triangulation sections.
Irregular Network (TIN) techniques using digitized As discussed, to study the effect of breach
contours obtained from Survey of India dimension and other possible conditions of dam
topographic sheets (1:50,000 scale). failure or flood eventually, four different scenarios
were considered in this study, as described below:
Case I: No Dam (routing of peak flow only): In
2 Modelling Results this case simulation of the Probable Maximum
Flood (PMF) hydrograph was performed without
The proposed dam will be a concrete gravity considering any structure in the consideration.
dam and usually concrete gravity dams tend to Case II: With Dam Break (Breach Dimensions:
have a partial breach as one or more monolith 16.5m Depth X 125 m Width): Under this scenario,
sections formed during the construction of the dam dam break analysis was done using PMF
are forced apart by the escaping water. The final hydrograph considering relatively small breach
breach dimensions and time of breach formation dimensions (16.5 m depth and 125 m width).
are most important parameters in calculating the Case III: With Dam Break (Breach Dimensions:
flood hydrograph. At the same time these 41.25m Depth X 125 m Width): Under this case,
parameter are uncertain depending upon the dam break analysis was performed considering

Figure 3 Flood crest profile plot for PMF hydrograph under four different cases (I-IV)

217
J. Mt. Sci. (2012) 9: 214–220

relatively large breach formation (41.25m depth at each cross-section within the stretch of 26.5 km
and 125m width). are given in Table 3, and presented in Figure 4 as
Case IV: Without Dam Break (Overtopping): well. The results give clear understanding of
The occurrence of operational gate failure or flooding elevations and lateral spread of flood.
spillway blockages can result in a range of different Flood inundation plot shows that the flood wave
overtopping depths that can lead to dam failure. If confines itself within the valley section of the river.
the upstream pool elevation continues to rise The results further indicate that at the fifth cross-
during a flood event, the dam may experience section (i.e. 8.2 km in downstream) the flooding
overtopping due to a combination of wave depths, in all the four scenarios achieves the same
overtopping and overflow due to the high static elevation level and further downstream the waves
pool elevation. are following the similar trend and elevations as
that of normal flood wave without dam scenario.
3 Discussion At the 5th cross-section i.e., 8.2 km
downstream from the proposed Vyasi dam site, the
3.1 Flood inundation elevation difference between flooding water level resulting
from that particular event of dam failure and flood
The flood crests profile (Figure 3) was plotted level without dam (Case-I) are the same and this
for all the four likely scenarios. The flooding depths suggests that the hazardous effect of dam break

Figure 4 River Cross-section and flooding elevations for the Probable Maximum Flood
(PMF) hydrograph under different cases

218
J. Mt. Sci. (2012) 9: 214–220

would be felt up to this location only. Further down failure in addition to the case of flood inundation
below, the flooding of almost similar magnitude without dam was considered. The results indicated
would take place whether the dam exist or not. In that, no human settlement is likely to be
other words, it can be understood from the results submerged as a result of dam failure in this 8.2 km
that in a particular scenario of flood event a storage stretch; although an additional area of 4.69 km2 is
structure like a dam may not always be made likely to be submerged in large breaching.
responsible for a flood disaster, as the natural
event itself can cause a flood of equal magnitude in
downstream. This might be a true case with 4 Conclusion
reference to the small dams built at the outlet of a
large catchment area. For reducing the threats of dam induced floods
it is essential to understand the characteristics of
3.2 Flood inundation mapping probable flood in realistic manner. Large man-
made storage structures like dam always possess a
To map the spatial spread of the flooding risk of devastating floods in the downstream;
water in downstream area of the dam, the plotting however a natural rainfall event of high magnitude
of flooding elevation on Digital Elevation Model can also create a huge flood hazard, where a
(DEM) was done using GIS. For defining the likely storage structure has no role to play. Assessment of
impact zone, a 5 km lateral stretch on both the such probable scenarios along with dam break
banks of river Yamuna in the downstream of the flood simulations can provide us with better
proposed dam was considered. On the base layer, understanding and preparedness of such floods.
human settlements, roads network, etc. were Following the same hypothesis, this study was
superimposed. Using these layers in conjunction attempted, simulating the probable maximum
with the results of dam break analysis, the flooding flood hydrograph in four different cases. The
elevations of different reaches were plotted on the simulation of PMF under ‘No dam’, ‘Dam break
DEM and inundation map was prepared (Figure 5). with small breach’, ‘Dam break with large breach’
For the purpose of this analysis, additional area and ‘Without dam break but overtopping’ was
that is likely to be inundated in worst case of dam performed. The result shows that the flooding

Figure 5 Flood inundation map in the downstream floodplain of 10km width

219
J. Mt. Sci. (2012) 9: 214–220

elevations in Case-I, (No Dam) are higher than developing small to medium dams instead of large
other two cases (II&IV) except dam break with once.
larger breach dimensions (Case-III) at second
cross-section. This interestingly reveals that an Acknowledgements
intensive rainfall event in upper catchment or
overtopping of huge amount of water through the
dam can also trigger a flood where there is no point The authors wish to express sincere thanks to
of blaming a storage structure. The plotted flooding M/s National Hydroelectric Power Corporation
elevation on DEM shows clear demarcation of area Ltd., Faridabad for providing the opportunity to
under probable submergence in all four likely work on EIA/EMP studies of the proposed project.
scenarios. Moreover, an area of 4.69 km2 under Several officials of NHPC provided greater insight
additional submergence in case of almost to the project and we thank them all in particular to
completed failure of structure, depicted on the map. Ers Ramesh Chandra, ED (Uttarakhand) and B D
The outcomes of such work might put forward a Saraf, GM (Planning), Drs (Mrs) Usha Bhatt and V
new point of consideration for development of K Bahuguna, Chief (Env), and Er K D Sah, Chief
disaster management plans particularly in case of Engineer (I/c) for their valuable support in
dam of moderate reservoir catchment area as in the undertaking the assignment. Special thanks are
present case. It is now a known fact that a large due to Director, G B Pant Institute of Himalayan
number of hydropower projects are coming up in Environment and Development for his continued
the Indian Himalayan Region, these projects are support and encouragement during the course of
serious cause of concern for floods disaster in the study. Last, but not the least, we thank all the
downstream areas. The present study may put a colleagues who directly or indirectly rendered help
positive contemplation if we think about from time to time.

References

Akanbi AA, Katapodes ND (1988) Model for flood propagation Revised DPR (2006) Revised Detailed Project Report of
on initially dry land. Journal of Hydraulic Engineering 114 (7): Lakhwar-Vyasi hydroelectric project, National Hydroelectric
689-706. Power Corporation (NHPC) Ltd, India.
BOSS DAMBRK (1991) User’s Manual. Saikia MD, Sarma AK (2006) Analysis for adopting logical
Comprehensive Environmental Impact Assessment and channel section for 1d dam break analysis in natural channels.
preparation of management plans for Vyasi hydroelectric ARPN Journal of Engineering and Applied Sciences 1(2): 46-
project (2006) GBPIHED, Kosi-Katarmal, Almora, 54.
Uttarakhand (India). Sanders BF (2001) High-resolution and non-oscillatory solution
Hicks FE, Steffler PM, et al. (1997) One dimensional dam break of the St.Venant equations in non-rectangular and non-
solutions for Variable width channel. Journal of Hydraulic prismatic channels. Journal of hydraulic Research 39 (3):
Engineering 123 (5): 464-468. 321-330.
Hromadka TV, II, Berenbrock CE, et al. (1985) A two Seker DZ, Kabdasli S, Rudvan B (2003) Risk assessment of a
dimensional dam–break flood plain model. Advances in dam-break using GIS technology. Water Science &
Water Resources 8 (1): 7-14. Technology 48(10): 89-95.
Husain SM, Rai NN (2000) One dimensional dam break flood Sarma AK (1999) A study of two-dimensional flow propagating
analysis for Kameng hydro electric project, India. from an opening in the river dike. PhD thesis, Gauhati
International seminar and workshop, Session 2: University, Assam, India.
Mathematical and physical modeling to simulate a dam-break Singh RD (2008) Real-time flood forecasting- Indian
flood, Seinäjoki, Finland, 2-5 October 2000. Experiences. In: Wheater, H. et al. (eds.), Hydrological
Katopodes ND (1984) Two dimensional Surges and shocks in modelling in Arid and Semi-Arid areas. Cambridge University
open channels. Journal of Hydraulic Division 110 (6): 794-812. Press, UK. pp 139-156.
Kho FWL, Law PL, et al. (2009) Quantitative dam break Wahl TL (1997) Predicting embankment dam breach
analysis on a reservoir earth dam. International Journal of parameters – A need Assessment. 27th IAHR Congress, San
Environmental Science and Technology 6 (2): 203-210. Francisco, California, August 10-15. (Online)
Macchione F, Viggiani G (2004) Simple modeling of dam failure Zhao DH et al. (1996) Approximate Riemann Solver in FVM for
in a natural river. Journal of Water Management (ICE) WA 2D Hydraulic Shock Wave Modeling. Journal of Hydraulic
157 (1): 53-60. Engineering 122(12): 692-702.
Nayak PC, Sudheer KP, et al. (2004) Dam Break Analysis of Zoppou C, Roberts S (2000) Numerical solution of the two
Ghodahoda project using DAMBRK model. Journal of dimensional unsteady dam break. Applied Mathematical
Applied Engineering Hydrology 17(1): 53-8. Model 24 (7): 457-475.

220

S-ar putea să vă placă și