Sunteți pe pagina 1din 9

1.

CoverPg Plant Customer Code Page


PA Plant Coromandel International Ltd COROMANDEL-PA
UAN 66-6700-700 1
COVER SHEET TON EC 2802
Item CND-02-500
Flash Cooler Condenser
Rev. 1
This sheet is a record of all revisions to the reference sheets listed in section 2. In case of
TECHNICAL
revision this sheet will be re-issued together with the revised reference sheets. The revision
is described in abbreviated form in section 1. However, the complete revision as shown on the
SPECIFICATION
revised reference sheets shall be considered as a firm and integral part of this specification.
Document ID Category Code Acceptance Code Status
6700-EQS-2800-EC-0004 5

1 STATUS OF REVISION

Revision Date Prepared Checked Approved Revised Pages Type of Revision

0 02-05-2018 UYP MKR MKR - Issued for Enquiry


1 18-05-2018 UYP MKR MKR 1,2,6-9 Revised based on comments received from
M/s. Coromandel and M/s. Prayon
Issued for Enquiry

2 REFERENCE SHEETS

Page Description

1 Cover Sheet
2 Design Data Sheet for Vessels
3 NozzleTable
4 Principle Sketch
5 Index of Applicable Codes and Standards (ACS)
6 General Requirements
7 Inspetion Data Sheet, Classification Group4, Page 1
8 Inspetion Data Sheet, Classification Group4, Page 2
9 Final Documentation Sheet

© 2017 tkIS India Shown on PID:


Plant Customer Code UAN Page
PA Plant Coromandel International Ltd COROMANDEL-PA 66-6700-700 2
DESIGN DATA SHEET FOR VESSELS TON EC 2802
Flash Cooler Condenser Item CND-02-500
Rev Rev Rev. 1
1 Quantity operat./stand-by 1 -- 19 Nominal volume m³ ~9.3
2 Position (H)orizontal/(V)ertical V 20 Shell diameter, outside mm
3 Process fluid 1) 21 Shell diameter, inside mm 1200 ( Refer Sketch)
4 22 Height (Length) of shell,cyl. mm 8200 ( Refer Sketch)
5 Physical condition G+L 23 Width mm
6 Class of hazard 24 Max.fill.lev.in oper.cond. % / mm
7 Density solid/bulk kg/m³ 25 Material (process side) CSRL
8 Density liquid kg/m³ 1000 26 Surf.-treatm./coat. (proc.side)
9 Density vapour/gas kg/m³ 0.17 27 Internal Lining 5mm Rubber lining or FRP 3)
10 pH-Value 28 Insulation (type)
11 H2-partial pressure kg/cm2 a 29 Internals Sprayer (Ref Sketch)
12 Max. operating temp. °C 30
13 Max. operating pressure kg/cm2 g 31 Heating/cooling device
14 Operating temperature °C 65 32 Heat transfer area m2
15 Operating pressure kg/cm2 a 0.259 33 H. T. area (jacket)
16 Design Temperature °C 105 34 H. T. area (Coil)
17 Design Pressure( Internal) kg/cm2 g Full Vacuum / Full of Liquid 2) 35
18 MDMT °C 15 36
37 01 Remarks:
1)Water vapours and non-condensable gases with traces of H3PO4, H2SiF6, H2SO4 & Acidic cooling water.
2) Mechanical Design to take into account the condition of the rubber vulcanization including the vessel full filling with hot water if vulcanization with hot water is
chosen.
3) Rubber lining of Hard Rubber (Hardness 78 +/- 5 shore D) suitable for Vacuum service. Spark test to be done after (By rubber lining applicator) Rubber Lining &
painting.
4) Gas: 22040 kg/h ; liquid: 1554 m³/h (nominal flows)
Abbreviations for physical condition: (S)olid, (L)iquid, (G)as, (V)apour
43 Design code ASME Sec.VIII Div.1, Edn.2017 65 Part Material Remarks
44 "ACS Page 6" 66 01 Shell IS 2062 Gr.E250BR 6)
45 Corros. allow., for calcul. mm 3.0 67 Head SA 516 Gr.70 6)
46 Joint efficiency 0.85 / 1 2) 68 01 Cone IS 2062 Gr.E250BR 6)
47 Seismic factor As per GES 69 01 Supports IS 2062 Gr.E250BR 6)
48 Wind loads acc. to As per GES 70 01 Clips directly welded IS 2062 Gr.E250BR 6)
49 Inspection by Client / TPIA 71 01 Nozzle flanges SA 105/IS 2062 Gr.E250BR 6)
50 Test pressure kg/cm2 g 3) 72 01 Nozzle pipes SA 106 Gr.B/IS2062 Gr.E250BR 6)
51 Heat treatment Acc. to code 73 01 Internals welded IS 2062 Gr.E250BR 6)
52 Nondestructive test Acc. to code/ IDS/ ESA-AD6(M) 74 01 Internals removable Polypropylene/IS 2062 Gr.250BR 6),8)
53 Derusting 4) 75 Bolts/Nuts outside SA 193 GR.B7/ SA 194 GR.2H 6)
54 Painting 4) 76 Bolts/Nuts inside -
55 Pickling - 77 Gaskets outside 6 Thk. Rubber
56 Insulation mm 78 Gaskets Inside -
57 Weight, delivery kg 4700 1) 79 Gaskets Jacket OutSide -
58 Weight, with process fluid kg 14600 1) 80 01 Manhole Davit IS 2062 Gr.E250BR
59 Weight, water-filled kg 14700 1) 81 Sprayer Polypropylene 6)
60 Wind Shear (Kg) 82 01 Lifting lugs/trunnions IS 2062 Gr.E250BR 6)
61 Wind Moment (Kgm) 83 01 Anchor Bolts IS 2062 Gr.E250BR By Others
62 Seismic Shear (Kg) 84 Nameplate bracket SS304
63 Seismic Moment (Kgm) 85 Jacket Shell / Dish End -
64 Fire Proofing 86 Baffles/Jacket Closure -
87 Remarks:
1) Weights & Loads to be checked and confirmed by Manufacturer.Indicated weights are preliminary.
2) Joint Effeciency : For Shell : 0.85(10% Spot + all 'T' Joints) & For Dish End : 1.00 (Full Radiography)
3) Testing to be done in Full of Liquid.
4) Surface preparation & primer painting for external CS parts shall be as per System 1 of Technical Specification for painting.
5) Gasket :- Rubber.
6) All materials shall be delivered with test certificates as per EN 10204 listed below:
a) Pressure bearing components & internal / external attachments welded to pressure parts - type 3.1
b) Stainless Steel removable internals - 3.1 & Carbon Steel removable internals - 2.2
7) Refer Sketch for more detail.
8) Gas inlet insert in Polypropylene or Carbon Steel lined with 5 mm Hard Rubber.

© 2017 tkIS India


Plant Customer Code Page
UAN 66-6700-700
3.NozTable

PA Plant Coromandel International Ltd COROMANDEL-PA 3


NOZZLETABLE TON EC 2802
Flash Cooler Condenser Item CND-02-500
Rev Rev. 1
Nozzle Designation NPS Class Standard Flange Flange Pipe dimension Remarks
Symbol mm ASME Type Facing mm
1 N1 Gas Inlet 1000 150 B16.47 Ser.B SO FF 7)
2 N2 Water Inlet 250 150 B16.5 SO FF with dip pipe & sprayer
3 N3 Water Inlet 250 150 B16.5 SO FF with dip pipe & sprayer
4 N4 Water Inlet 250 150 B16.5 SO FF with dip pipe & sprayer
5 N5 Water Inlet 250 150 B16.5 SO FF with dip pipe & sprayer
6 N2A Insert Nozzle for N2 350 150 B16.5 SO FF 5) with Blind
7 N3A Insert Nozzle for N3 350 150 B16.5 SO FF 5) with Blind
8 N4A Insert Nozzle for N4 350 150 B16.5 SO FF 5) with Blind
9 N5A Insert Nozzle for N5 350 150 B16.5 SO FF 5) with Blind
10 N6 Gas Outlet 250 150 B16.5 SO FF
11 N7 Water Outlet 600 150 B16.5 SO FF
12 M1 Manhole with cover 600 150 B16.5 SO FF 4),6) with Davit
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51 Remarks:
1) Nozzle Projections: Nozzles<= 300NB : 200mm; Nozzles>300NB : 250mm.
2) Flange face finish - As per GES of Pressure Vessel.
3) Nozzle pipes shall be seamless upto 12“ size for CS and 6“ size for SS. Nozzle pipes exceeding above limits may be fabricated from plate with 100
% radiography. MOC of fabricated neck shall be same as shell / head.
4) M1 shall be placed in front of Nozzle N1.
5) N2A, N3A, N4A & N5A Dia. should allow the Removal of Sprayer.
6) With Gasket Fastners and applicable spares.
7) N1 axis must beset at 500mm below gas outlet nozzle of Flash Cooler Pre-condenser (EC 2801).

© 2017 tkIS India


Plant Customer Code Page
UAN 66-6700-700
4.Sketch

PA Plant Coromandel International Ltd COROMANDEL-PA 4


PRINCIPLE SKETCH TON EC 2802
Flash Cooler Condenser Item CND-02-500
Rev Rev. 1

© 2017 tkIS India


Plant Customer Code Page
UAN 66-6700-700
5.ACS

PA Plant Coromandel International Ltd COROMANDEL-PA 5


INDEX OF APPLICABLE CODES AND STANDARDS (ACS) TON EC 2802
Flash Cooler Condenser Item CND-02-500
Rev Rev. 1
1 1 DESIGN CODES
2 X ASME-Code Section VIII, Division 1, Edition 2017
3 ASME-Code Section VIII, Division 2, Edition 2017
4 EN 13121 Edition 2008, Addendum 2010
5 TEMA Standards, Class R, Edition 9th , 2007
6 TEMA Standards, Class C, Edition 9th , 2007
7 API Standard 650, 12th Edition 2013 Addenda 2016
8 AD 2000-Merkblätter
9 Manufacturer's Standard
10 IBR - 10th Edition
11 2 REFERENCE STANDARDS
12 X 6700-EQS-0000-EC-0001 General Engineering Specification for Pressure Vessels
13 6700-EQS-0000-EC-0002 General Engineering Specification for Atmospheric Vessels
14 6700-EQS-0000-EC-0003 General Engineering Specification for FRP Vessels
15 6700-EQS-0000-EC-0004 General Engineering Specification for Heat Exchangers
16 6700-EQS-0000-EC-0005 General Engineering Specification for Storage Tanks
17 X 6700-EQS-0000-EC-0006 General Engineering Specification for Rubber Lined Equipment
18 X 6700-EQS-0000-EC-0007 Technical Specification for Painting
19 6700-EQS-0000-EC-0008 Technical Specification for Insulation
20 X PIN LES-EQS-0011 Summary of Engineering & Final Documents" 1)
21
22
23 X ES 10 MS-ST-01 Packing Instructions - Fabricated Equipment 1)
24 UN V416-03 Part 1(M) Pickling & Passivation - Technical Specification 1)
25 X ESA 09 AU-ST-02 (M) Additional Loads on Nozzles General Specificati 1)
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55 3 CLASSIFICATION GROUP and LEAKAGE CLASS
56 X Vessel Group 4
57 Heat Exchanger Shell Side Group Tube Side Group Leakage class
58 Not Applicable
59 4 FATIGUE LOADING
60 Design No. of load cycles from kg/cm² g to kg/cm² g
61 Remarks:
1) These documents are enclosed with General Engineering Specification for Pressure Vessels.
2) Line 17: Rubber lining application & testing shall be as per rubber lined GES.

© 2017 tkIS India


Plant Customer Code Page
UAN 66-6700-700
6.GenReq

PA Plant Coromandel International Ltd COROMANDEL-PA 6


GENERAL REQUIREMENTS TON EC 2802
Flash Cooler Condenser Item CND-02-500
Rev Rev. 1
1 General
2 X Stress analysis shall be performed by the manufacturer in accordance with design specifications
3 X Specified wall thicknesses are min.values and shall be increased if required by stress calculation at no extra cost & delivery to client.
4 01 X Nozzle necks shall not be less DN80 /3" for CSRL equipment.
5 Bolts, nuts and gaskets for joints with tapped holes have to be supplied by the vessel manufacturer.
6
7 Supplies shall include the following items
8 Base ring template
9 X Clips and pads for ladders and plattforms
10 Clips for davits
11 X Davits for manholes
12 X Clips and pads for pipe supports
13 Supports for insulation
14 Supports for fireproofing insulation acc. to UN 2000 - 05 part 4
15 01 X Additional 2 sets of gaskets for flanges with blind flanges and companion flanges.
16 01 X Additional 10% stud / nuts (Min.-2 Nos. per joint) for flanges being supplied with blind flange / companion flange as spare
17 X Lifting lugs for erection
18 Lifting trunnions for erection
19 X 2 separate earthing connections to be provided 180 degree apart
20 All internals like agitator baffles and its supports, dip-pipes, Cooling coils/it's support etc except agitator shaft/blades assembly .
21 1 Set(100%) of glasses and gaskets for Sight glass/ Light glass nozzles as spare.
22 X All removable internals shall be sized such that they shall pass through manhole.
23 Platforms and ladders plus bolts and nuts, as spare
24 01 Mendatory two years O&M and commissioning spare list to be provided by vendor with unit rates.
25 Bolts, nuts and gaskets for connecting piping
26 Connection plate with studs and nuts
27 Lifting lugs on channels and bonnets
28 X Nameplate bracket, Name Plate including engraving
29 Tailing lug,Internal Tray support ring, Bolting bars & all welded attachement to shell
30 X For applicable standards see page ' index of applicable Codes and standards'
31 Support for fireproofing according to UN 2004-02
32 Additional requirements for heat exchangers
33 Tubes to be welded into tube sheet and tested according to UN V416-02 part 1,Leakage class
34 Tubes to be expanded after welding
35 Tubes to be fixed by expansion
36 Expansion with grooves in tube sheet holes
37 Tube bundle to be equipped with 2 slide rails
38 Tube bundle to be equipped with sealing strips
39 For stacked heat exchangers an experimental assembly and pressure test shall be performed
40 Protection device for expansion bellows
41
42 Pulling Lugs for tube bundle
43 Jackscrews and jack bosses according to UN 2100 - 03 part 2
44 Tube holes in baffles and support plates to be max. 0.4 mm over outer diameter of tubes
45 Holes' diameter in tube sheet according to standard fit
46
47
48 01 Remarks:
1) Shop fabricated equipment : Vendor's scope of work includes design, procurement of material, fabrication, inspection, testing & painting.
2) Mechanical design, material & worksmanship guarantee for equipment is by equipment manufacturer.
3) Vendor to give nozzle price list for nozzles 1" to 24" (150#, 300#) with & without blind flange as per ASME B16.5.
4) Hydrotest/Pneumatic test shall be done with service gasket only & after test it shall be replaced with new one. In addition to these, 2 new gaskets
shall be supplied as spare as mentioned in Line 15 .
5) Vendor to give unit rates ( per kg) for clips for ladder, platform, pipe supports etc as applicable.
6) Vendor to give unit rates ( per kg) for ladder, Platform, pipe supports etc as applicable.
8) Plates equal to or greater than 12 mm thickness shall be ultrasonically tested for lamination defects as per ESA-AD6(M).
9) Forging equal to or greater than 40 mm thickness shall be 100% ultrasonically tested as per ESA-AD6(M).
10) Equipment shall be rubber lined by tkIS approved vendor. Equipment shall be painted clearly on visible area in black & 150mm height lettering as
" RUBBER LINED ITEM - NO WELDING PERMITTED"
11) Shop fabricated equipment: cardboard of sufficient thickness to be used to avoid damaged of nozzle rubber lining during transportation.

© 2017 tkIS India


7.Gr4.IDSPg1 Plant Customer Code Page
PA Plant Coromandel International Ltd COROMANDEL-PA UAN 66-6700-700 7
INSPETION DATA SHEET, CLASSIFICATION GROUP4, PAGE 1 for Pressure Vessels and Heat Exchangers TON EC 2802
Classification Group No. 4 Item CND-02-500
Flash Cooler Condenser ASME CODE Rev. 1
1 The tests indicated are minimum requirements. They have to be performed in addition to the tests specified in the codes and standards.
2 In case of discrepancies between the inspection data sheet (IDS) and the workshop documents approved by EPCM Contractor,
3 the latter shall apply. The manufacturer shall be responsible that the required tests are performed and that the inspector
4 is invited in due time to witness the tests. The manufacturer shall try to perform as many individual tests as possible on the
5 same day, provided that the fabrication process permits such a procedure.
6 Inspection by
7 Manuf. Client/TPIA
8 PRE INSPECTION MEETING (PIM) - only if requested by tkIS or Client  
9 MATERIAL TEST AT SEMI FINISHED PRODUCTS
10 In accordance with design code  
11
12
13
14 EXAMINATION OF WELD EDGES
15 In accordance with design code  
16
17
18
19
20 WELDING
21 Welding and testing schedule on form UF V360-21 part 1 or approved schedule of manufacturer  
22 Welding Procedure Specification (WPS) and Procedure Qualification Record (PQR) in acc. with to applicable design code  
23
24
25 HEAT TREATMENT (if required)
26 Visual and dimensional check before PWHT  
27 MP of temporary welds before PWHT  
28 Heat treatment plan and record  
29
30 NONDESTRUCTIVE TESTS prior to pressure test (after final heat treatment)
31 RT, UT, MT, PT in accordance with design code  
32 PT: 100% weld ring gasket, first and top layer of fillet seam and closing seams  
33 Visual and dimensional check before pressure test in case of no PWHT  
34
35
36
37 NONDESTRUCTIVE TESTS after pressure test
38 only if specified in design code or other referenced standards / specifications
39
40
41 FINAL INSPECTION
42 Visual check, inside and outside  
43 Dimensional check; report and / or "as built" drawing with required and actual main dimensions  
44 Completeness check  
45 Record of production test plates  
46 Leakage test nozzle reinforcements / lining  
47 Pressure test ( for pressure test on shell sides of heat exchangers, otherwise )  / 
48 Material certificate compare with marking / picture of marking  
49 Pickling, passivation, blasting- if required, check of performance  
50 Drying, cleanliness, inside and outside  
51 Painting / corrosion protection, if required  
52 Data of nameplate correspondence with drawing  
53 Documentation, submit at final inspection  
54
55 SYMBOL EXPLANATION
56  Holding Point, Fabrication stop until inspection has been performed or written release note is given
57  Advice of inspection, Fabrication may be continued if inspector is not present after invitation issued in due time
58  Examination with test report
59  Review of test report
60  Test Respectively Execution
61
62 LS = Longitudinal seam MT = Magnetic particle examination DDS = Design Data Sheet
63 CS = Circumferential seam PT = Liquid penetrant examination t = Wall thickness
64 NCS = Shell-nozzle seam UT = Ultrasonic examination DN = Nominal pipe size (NPS)
E_IDS41A.XLS

65 AS = Attachment seam RT = Radiographic examination HAZ = Heat affected zone


66 TS = T-Joints DK = Leakage class acc. to UN V416-02 part 1
67 continued on sheet E_IDS42 line 68
 © 2017 tkIS India
8.Gr4.IDSPg2 Plant Customer Code Page
PA Plant Coromandel International Ltd COROMANDEL-PA UAN 66-6700-700 8
INSPETION DATA SHEET, CLASSIFICATION GROUP4, PAGE 2 for Pressure Vessels and Heat Exchangers TON EC 2802
Classification Group No. 4 Item CND-02-500
Flash Cooler Condenser ASME CODE Rev. 1
68 Continued from sheet E_IDS41, line 67
69
70
71
72 SPECIAL REQUIREMENTS FOR HEAT EXCHANGERS and SPECIAL TESTS
73 Inspection by
74 Manuf. Client/TPIA
75 HEAT EXCHANGER TUBES FOR HEAT EXCHANGERS AND COILS
76 Tests of tubes according to ESA-AD6(M) para. 10  
77 Depending on DK and material Eddy Current -, UT- and Pressure Test may be required
78 TUBE-TO-TUBESHEET JOINTS test acc. to UN V416-02 part 1 (DK class acc. to DDS)
79 Tube-to-tubesheet test specimen, if required acc. to UN V416-02 part 1  /2)
80 Start of tube to tubesheet welding  /2)
81 Leak test with air / bubble formation agent 1st pass 1)  /2)
82 PT 1st pass 100% 1)  /2)
83 Leak test top pass (prior to tube expansion and PT)  /2)
84 PT top pass (prior to expansion and prior to heat treatment), 100%  /2)
85 PT top pass (after expansion and after heat treatment), 100%  /2)
86 1) Leak and PT test after 1st pass may be skipped based on agreement with tkIS in case of welding both passes in one run.
87 2)  for DK 1 and DK 2,  for DK 3
88 OTHER TESTS FOR HEAT EXCHANGERS
89 Visual examination of shell inside (before bundle insertion)  
90 Check of tolerance for drillholes in tubesheets and baffle plates  
91 Inspection of tube bundle  /2)
92 Insertion of tube bundle  /2)
93 Measuring of tube expansion on 5%, min. on 10 tubes per tubesheet, (if expansion is specified)  /2)
94 Hydrostatic test, tube side  
95 Hydrostatic test, shell side  
96 Assembly check of stacked heat exchangers  
97 PT: Transition radius channel to tubesheet after pressure test  
98 PT or MT: cold bent tubes after annealing  
99 RT: 2% of tube to tubesheet welds but not less than 5 welds on each tubesheet  
100 for cooling water and / or corrosive acids on shell- and / or tubeside.
101 In case that any inadmissible defect is found by this RT inspection the scope of testing shall be increased to 25 %.
102 If within this increased scope any further inadmissible defect is found then the testing scope shall finally be 100%
103 BFU type heat exchangers: Check of longitudinal gasket assembly  
104
105 SPECIAL TESTS
106 UT: Weld overlays and clad material  
107 Copper sulphate test or equivalent test: weld overlay and welds on clad material  
108 PT: Weld overlay and welds on clad material  
109 UT: Clad plates after forming  
110 Examination of surface preparation prior to lining or coating (rubber lining, synthetic resin, coating) acc.to applicable standards  
111 Examination of lined or coated surfaces (rubber lining, synthetic resin, coating) according to applicable standards  
112 Hardness test when using metal gasket: flange face and gasket  
113
114 SPECIAL TESTS (if specified in DDS and / or engineering spec.)
115 Positive Material Identification (PMI)  
116 Leakage test with helium / NH3 (vacuum test)  
117
118 SYMBOL EXPLANATION
119  Holding Point, Fabrication stop until inspection has been performed or written release note is given
120  Advice of inspection, Fabrication may be continued if inspector is not present after invitation issued in due time
121  Examination with test report
122  Review of test report
123  Test respectively execution
124
125
126 LS = Longitudinal seam MT = Magnetic particle examination DDS = Design Data Sheet
127 CS = Circumferential seam PT = Liquid penetrant examination t = Wall thickness
128 NCS = Shell-nozzle seam UT = Ultrasonic examination DN = Nominal pipe size (NPS)
129 AS = Attachment seam RT = Radiographic examination HAZ = Heat affected zone
130 TS = T-Joints DK = Leakage class acc. to UN V416-02 part 1
131
132
133
134
© 2017 tkIS India
Plant Customer Code Page
UAN 66-6700-700
9.Add4

PA Plant Coromandel InCOROMANDEL-PA 9


FINAL DOCUMENTATION SHEET TON EC 2802
Flash Cooler Condenser Item CND-02-500
Rev Rev. 1
1 The following engineering and final documents shall be furnished by the manufacturer :
2 Version and delivery date shall be as specified.
3
4 1.0 For engineering and approval Quantity
5 Sr. Documents Reprodu- Copy Version Deliver
cible y Date
6 1 Assembly drawing - arrangement drawing 4 II B
7 2 Foundation plan - load plan 4 II B
8 3 Workshop drawing with part list 4 II B
9 4 Engineering data and specifications 4 II B
10 5 Piping plan or piping diagram
11 6 Electrical diagrams
12 7 Delivery schedule for equipment 4 II D
13 8 Sketch for equipment transport 4 II 2)
14 9 Erection instructions 4 II 2)
15 10 Stress analysis (for review) 4 II B
16 11 Material status report 4 II B
17 12
18 13 Documents bearing Uhde notes shall be resubmitted As indicated above C
19 2.0 Spare parts
20 1 Quotation for 2 year (s) operation A
21 2 Spare parts list with itemized drawings or sketches
22
23 3.0 Final documents
24 1 “As built” version of documents listed under 1.0 1 4 II G
25 2 Spare parts list with itemized drawings or sketches
26 3 Erection instructions 4 II G
27 4 Table of lubricants and lubrication schedule
28 5 Test certificates for explosion proof items of equipment

29 6 Summary of antifriction bearings


30 7 Stress analysis 4 II G
31 8
32 4.0 Inspection
33 1 Shop inspection certificate / Hydro-static test Certificate 4 II E
34 2 Material certificate to EN 10204 / 3.1 A - 3.1 B - 3.1 C 4 II E
35 3 Inspection reports issued by inspection authority such as TÜV 4 II F
36 4 Inspection reports, stress relieving diagrams, etc. 4 II E
37 5 Inspection reports issued by statutory authorities
38 5.0 Explana
39 I Lettering or wording A To be submitted with quotation
40 in German B 2 weeks after order placement
41 II Lettering or wording C 2 weeks after return of documents
42 in English D 2 weeks after order placement, , thereafter monthly
43 III Lettering or wording E Not later than date of final inspection
44 in German & English F 2 weeks after final inspection; to be submitted with shipping
45 IV Lettering or wording Documents if the equipment has to be shipped abroad
46 in German & G After release, but not later than 2 weeks
47 Prior to the final inspection
48
49 6.0 Remarks

50 1) Standard size DIN A4 and smaller on white sheets, larger sizes on transparent paper (plastic sheets).
51 2) 3 months after order placement or two weeks before final shipment, whichever is earlier.
52 3) CD-ROM containing electronic copies of all drawings/sketches & documents shall be submitted by vendor
along with final documentation.

© 2017 tkIS India

S-ar putea să vă placă și