Registered problem and Long Term Corrective Long Term Corrective Long Term Corrective
Short Term Corrective Action developed but not Action implemented. Action confirmed effective.
Action in place in house. implemented. Monitoring/evaluating Problem closed.
effectiveness.
Prepare for Problem Solving - Is an Emergency Response Action Needed?
Does the problem warrant/require an 8D? If (If needed document actions in Action Item Table)
0 so comment why and proceed.
Quality Mr. Shrikanth Sherigar Micro & Macro Inspection, Quality Head
Customer Handling, Metallurgy
Part Number(s):
10.50 mm dia. coil
Customer(s): M/s. NHB Bearings Ltd., Amalsad
List all of the data and documents that might help you to
define the problem more exactly? 1. In-coming Material Inspection Report
2B Flatness and size variation observed through out the coil. Size observed in the range of 9.35 to
9.85 mm dia.
Note on Diagram(s) circle the most likely contributors (3 max) from each side.
4B 5 – Why Analysis
Why - Why for Generation: Why - Why for Non-Detection:
Ask – Why did this happen? Ask – Why did this happen?
Ask – Why did this happen? Ask – Why did this happen?
Action Plan - Based on the team’s discussions. Begin to complete the Root Cause
Action Plan to verify and validate the root causes and test the escape point. Document this on
4C the Action Item Table.
5 Identify Solutions – Solutions that address and correct the root cause.
Solutions determined to be the best of all the alternatives. Document and verify the
Permanent Corrective Action (PCA) in the Action Item Table.
Sample to be forwarded to supplier for their futuristic analysis and Corrective &
Preventive Action
Validation - Implement and validate to ensure that corrective action does “what it is
6 supposed to do.” Detect any undesirable side effects. Document this on the Action Item Table.
Return to root cause analysis, if necessary.
Completion Date
Document Accountability
Planned Actual
Flow Charts
Control Plans
Design FMEA
Process FMEA
Gauges/MMD/IMTE
PPAP
Manufacturing Forms
Inspection Forms
8
Registered problem and Short Long Term Corrective Action Long Term Corrective Action Long Term Corrective Action confirmed
Term Corrective Action in place in developed but not implemented. implemented. Monitoring/evaluating effective. Problem closed.
house. effectiveness.
Note: Copy this page and attach as often as necessary