SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP.
ITP # ACTIVITY #:
ACCEPTED
USACE INSPECTION LEVEL QC DEPARTMENT INSPECTION LEVEL
REJECTED
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
As per approved
A1 Pre-Installation Survey/UTM Coordinate system Method Statement
for DC/RIC Work
Work area reference points shall be marked out as per the shop drawing. As per the
A3
Acceptable allowance of 25cm approved dwg.
As per the
A4 Location of Testing Points (Pre/Post CPT)/UTM Coordinate system
approved dwg.
ISO 9001-2015
A5 Calibration of survey instrument must be 6 months validity
Clause 9 Part 9.1
As per the
A6 Spacing of DC Compaction /Compaction points/Levelling
approved dwg.
REMARKS:
REFERENCE DOCUMENTS:
1.MS for DC/RIC Compaction Work
2. ASTM D5778
3.Project Specification
QC Engineer
Performed
Work / Rework May Proceed
Name, Initials and Date: Inspection
Page 1 of 1
ROYAL SAUDI LAND FORCES ARTILLERY BRIGADE
ROYAL SAUDI LAND FORCES ARTILLERY BRIGADE Al Yamama Company for Trading and Contracting
LOCATION / DISCRIPTION
DAMMAM, KINGDOM OF SAUDI ARABIA
SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP.
ITP #: ACTIVITY #:
ACCEPTED
USACE INSPECTION LEVEL CONTRACTOR INSPECTION LEVEL
REJECTED
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP. DATE
No.
As per approved
A1 Machine technician Qualification (TUV) Method Statement
for DC/RIC Work
As per approved
A5 Test result submittal in Final Report. Method Statement
for DC/RIC Work
REMARKS:
REFERENCE DOCUMENTS:
1. Method Statement
2. ASTM D5778
3. ISO 22476-1
Al Yamama Co. / Third-Party Client
Construction Department representative USACE Representative
Work is Complete and Ready for Inspection: QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date:
QC Engineer
Performed Inspection Work / Rework May Proceed
Name, Initials and Date:
Page 1 of 1