PROYEK ANANTARA UBUD - BALI

AREA : LANTAI PONDASI


SCHEDULE OF : CONCRETE STRUCTURE WORKS
CONC & REINF. IN : COLUMNS VILLA
f'c = 25 Mpa
CHECK
Type Height Size Coloum Thickness Length Area Re-bar Remark Main
Concrete
No. Grid Line SLAB TYPE BEAM TYPE Height Bruto Wide High Slab Netto Formwork Ratio
Sengkang Ties Tul. Utama Total QTY DIA. Overlap WEIGHT
Column S/DS Beam m m m m m m3 m2 (kg/m3)
Level PC -Ground

1 2 / A K2 S0 G4 0.40 1.20 0.50 0.40 - 1.20 0.24 2.16 13.24 7.64 55.90 76.79 319.95 14 16 1.330 55.90
2 2 / B K6 S11 G4 0.40 4.20 0.50 0.40 0.12 4.08 0.82 7.34 47.45 25.99 122.19 195.63 239.74 14 16 1.330 122.19
3 2 / C K2 S11 G4 0.40 4.20 0.50 0.40 0.12 4.08 0.82 7.34 47.45 25.99 122.19 195.63 239.74 14 16 1.330 122.19
4 3 / A K3 S11 G4 0.40 4.20 0.40 0.40 0.12 4.08 0.65 6.53 42.15 23.90 69.82 135.87 208.13 8 16 1.330 69.82
5 3 / B K7 S11 G4 0.40 4.20 0.40 0.40 0.12 4.08 0.65 6.53 42.15 23.90 69.82 135.87 208.13 8 16 1.330 69.82
6 3 / C K8 S11 G4 0.40 4.20 0.40 0.40 0.12 4.08 0.65 6.53 42.15 23.90 69.82 135.87 208.13 8 16 1.330 69.82

7 3" / A K4 S11 G4 0.40 4.67 0.40 0.40 0.12 4.55 0.73 7.28 47.05 28.11 62.57 137.74 189.28 8 16 0.288 62.57
8 3" / B K4 S11 G4 0.40 4.67 0.40 0.40 0.12 4.55 0.73 7.28 47.05 28.11 62.57 137.74 189.28 8 16 0.288 62.57
9 3" / C K4 S11 G4 0.40 4.67 0.40 0.40 0.12 4.55 0.73 7.28 47.05 28.11 62.57 137.74 189.28 8 16 0.288 62.57

6.01 58.26 1,288.86


Sengkang Ties REKAP PER DIA
JUMLAH ZONE QTY JUMLAH ZONE Length 10 13 16 19 22 25 29 32
DIA. JML Length WEIGHT JML DIA. WEIGHT
A B C D H V A B C D H V 0.6165 1.0419 1.5782 2.2256 2.9839 3.8531 5.1848 6.3130

10 4 2 4 2 12 1.79 13.24 1 1 4 2 2 2 10 10 0.670 0.570 7.64 20.89 - 55.90 - - - - -


10 4 10 19 10 43 1.79 47.45 1 1 4 10 10 10 34 10 0.670 0.570 25.99 73.44 - 122.19 - - - - -
10 4 10 19 10 43 1.79 47.45 1 1 4 10 10 10 34 10 0.670 0.570 25.99 73.44 - 122.19 - - - - -
10 4 10 19 10 43 1.59 42.15 1 1 4 10 10 10 34 10 0.570 0.570 23.90 66.05 - 69.82 - - - - -
10 4 10 19 10 43 1.59 42.15 1 1 4 10 10 10 34 10 0.570 0.570 23.90 66.05 - 69.82 - - - - -
10 4 10 19 10 43 1.59 42.15 1 1 4 10 10 10 34 10 0.570 0.570 23.90 66.05 - 69.82 - - - - -

10 4 11 22 11 48 1.59 47.05 1 1 4 11 11 11 40 10 0.570 0.570 28.11 75.16 - 62.57 - - - - -


10 4 11 22 11 48 1.59 47.05 1 1 4 11 11 11 40 10 0.570 0.570 28.11 75.16 - 62.57 - - - - -
10 4 11 22 11 48 1.59 47.05 1 1 4 11 11 11 40 10 0.570 0.570 28.11 75.16 - 62.57 - - - - -

591.40 - 697.46 - - - - -
PROYEK ANANTARA UBUD - BALI

AREA : LANTAI PONDASI


SCHEDULE OF : CONCRETE STRUCTURE WORKS
CONC & REINF. IN : COLUMNS VILLA
f'c = 25 Mpa
CHECK
Type Height Size Coloum Thickness Length Area Re-bar Remark Main
Concrete
No. Grid Line SLAB TYPE BEAM TYPE Height Bruto Wide High Slab Netto Formwork Ratio
Sengkang Ties Tul. Utama Total QTY DIA. Overlap WEIGHT
Column S/DS Beam m m m m m m3 m2 (kg/m3)
Level PC - Ground

1 1 / A K1 S11 G2 0.40 9.32 0.60 0.40 0.12 9.20 2.21 18.40 116.55 60.31 267.01 443.87 201.03 16 16 1.254 267.01
2 1 / B K5 S11 G2 0.40 9.32 0.60 0.40 0.12 9.20 2.21 18.40 116.55 60.31 267.01 443.87 201.03 16 16 1.254 267.01
3 1 / C K1 S11 G2 0.40 9.32 0.60 0.40 0.12 9.20 2.21 18.40 116.55 60.31 267.01 443.87 201.03 16 16 1.254 267.01

6.62 55.20 1,331.60


Sengkang Ties REKAP PER DIA
JUMLAH ZONE QTY JUMLAH ZONE Length 10 13 16 19 22 25 29 32
DIA. JML Length WEIGHT JML DIA. WEIGHT
A B C D H V A B C D H V 0.6165 1.0419 1.5782 2.2256 2.9839 3.8531 5.1848 6.3130

10 4 23 45 23 95 1.99 116.55 1 1 4 23 23 23 73 10 0.770 0.570 60.31 176.86 - 267.01 - - - - -


10 4 23 45 23 95 1.99 116.55 1 1 4 23 23 23 73 10 0.770 0.570 60.31 176.86 - 267.01 - - - - -
10 4 23 45 23 95 1.99 116.55 1 1 4 23 23 23 73 10 0.770 0.570 60.31 176.86 - 267.01 - - - - -

530.57 - 801.04 - - - - -
KEBUTUHAN DRAINASE PROCESS BUILDING
PROYEK PABRIK FABRIKASI BAJA MAJALENGKA

Panjang Volume
Panjang
Drainase
No Type Drainase Drainase Drainase Keterangan
Precast
(m) (m) (bh)

1 Drainase 50 x 60 1283.500 1.200 1,070 U-Ditch Standard


2 Cover Drainase 50 x 60 0.600 2,140 Heavy Duty

3 Drainase 50 x 70 196.000 1.200 164 U-Ditch Standard


4 Cover Drainase 50 x 70 0.600 328 Heavy Duty

5 Drainase 50 x 80 361.000 1.200 304 U-Ditch Standard


6 Cover Drainase 50 x 80 0.600 608 Heavy Duty

7 Drainase 60 x 80 361.000 1.200 304 U-Ditch Standard


8 Cover Drainase 60 x 80 0.600 608 Heavy Duty

Norte :
Harga sudah termasuk PPh
Pembayaran menggunakan fasilitas SCF plafond 180 hari BNI, dengan biaya bunga SCF menjadi beban Vendor
Harga Delivered Duty Paid, Site Majalengka
Sertakan kemampuan produksi perhari, dengan target barang mulai onsite dan terpasang pada 07 September 20
Sertakan ketersediaan barang ready stock pada pabrik
N DRAINASE PROCESS BUILDING
RIK FABRIKASI BAJA MAJALENGKA

PT. Beton Elemindo Perkasa


Harsat Material Total Price
NOTE
IDR IDR

- U DITCH-DRYCAST-K350
- CU 500 HD-DRYCAST-K350

- U DITCH-DRYCAST-K350
- CU 500 HD-DRYCAST-K350

UKURAN TIDAK TERSEDIA


UKURAN TIDAK TERSEDIA

- U DITCH-DRYCAST-K350
- CU 600 HD-DRYCAST-K350

Total = -

ngan biaya bunga SCF menjadi beban Vendor

ai onsite dan terpasang pada 07 September 2019


KEBUTUHAN DRAINASE PROCESS BUILDING
PROYEK PABRIK FABRIKASI BAJA MAJALENGKA

Panjang Volume
Panjang
Drainase
No Type Drainase Drainase Drainase Keterangan
Precast
(m) (m) (bh)

1 Drainase 50 x 60 1283.500 1.200 1,070 U-Ditch Standard


2 Cover Drainase 50 x 60 0.600 2,140 Heavy Duty

3 Drainase 50 x 70 203.000 1.200 170 U-Ditch Standard


4 Cover Drainase 50 x 70 0.600 340 Heavy Duty

5 Drainase 50 x 80 352.000 1.200 297 U-Ditch Standard


6 Cover Drainase 50 x 80 0.600 594 Heavy Duty

7 Drainase 60 x 80 352.000 1.200 297 U-Ditch Standard


8 Cover Drainase 60 x 80 0.600 594 Heavy Duty

Norte :
Harga sudah termasuk PPh
Pembayaran menggunakan fasilitas SCF plafond 180 hari BNI, dengan biaya bunga SCF menjadi beban Vendor
Harga Delivered Duty Paid, Site Majalengka
Sertakan kemampuan produksi perhari, dengan target barang mulai onsite dan terpasang pada 07 September 2019
Sertakan ketersediaan barang ready stock pada pabrik
ROCESS BUILDING
BAJA MAJALENGKA

PT. Beton Elemindo Perkasa


Harsat Material Total Price
NOTE
IDR IDR

- U DITCH-DRYCAST-K350
- CU 500 HD-DRYCAST-K350

- U DITCH-DRYCAST-K350
- CU 500 HD-DRYCAST-K350

UKURAN TIDAK TERSEDIA


UKURAN TIDAK TERSEDIA

- U DITCH-DRYCAST-K350
- CU 600 HD-DRYCAST-K350

Total = -

CF menjadi beban Vendor

ang pada 07 September 2019