MOMBASA PORT AREA ROAD DEVELOPMENT TRAINING CURRICULUM

Subject Goals
Contract Management
1
To be able to define the project scope, organisation
To identify the Consultants office/ RE/ Contractor's camp
To identify key installations
To identify quantity requirements
To perform general cost estimate
To be familirarised with components of producing a work plan
To be familiarised with project schedule - concepts and methods
To perform risk management
To perform project control

2 Site Inspection To record activities on site


To familiarise with type of plant on site
To familiarise with work methodologies
To familiarise with procedures for detection of errors

3 Materials to identify materials in use in the temporary and permanent works


to familiriarise with the origin of materials to be used in the ongoing works.
to determine sampling requirements on any given material for the works
to perform sampling on basic materials on ongoing works
to be familiar with basic test apparatus and to be able perform basic tests with the apparatus

to analyse test results for ongoing works


to interrogate test results for ongoing works

4 Survey
to perform basic setting out of ongoing works
to perform advance setting out where necessary
to confirm as built results
to perform general survey calculations
MOMBASA PORT AREA ROAD DEVELOPMENT TRAINING CURRICULUM

5 Highway to perform basic CAD drawings - cross sectrion/ gradient


to identify Design Controls and Criteria
to familiriarise with types of Cross sections and functions
To familiriase with the Type of Crown and reasons for uses
To understand implications of Right of Way considerations on ongoing works
to familiarise with the types of and properties of Horizontal curves
to familiarise with the types of Superelevation of curves
to familiarise with the properties of Vertical curves
to note the functions of Curbs, shoulders, barriers
to perform a basic design from beginning to print out

6 Structure/Drainage
To familiarise with hydraulic/hydrologic considerations for culverts, box and bridge
To identify the different types of structures on the project site
To familiriase with the planning and design process used to select the structures on site
To familiarise with material ,loads and design safety used on site
To determine suitability of the foundation
To familiarise with the different types of concrete systems to deal with tension(reinforced concrete and
prestressed)
To familiarise basic foundation/ piling / sheeting calculations for identified box on project road
To familiariset basic reinforced concrete box calculations: pier/ abutment / deck
To familiarise basic foundation calculations for identified bridge on project road
To familiarise with basic reinforced concrete bridge calculations: pier/ abutment / deck
To familiarise with basic prestressed deck bridge calculations:
To draft and detail sample pier/ deck/ abutment structural steel details
To draft and detail sample pier/ deck/ abutment reinforcement details

7 Environmental To familiriarise with Health and Safety , TMP, OHS Plan


To familiarise with Environmental issues, EMP, legal requirements
MOMBASA PORT AREA ROAD DEVELOPMENT TRAINING CURRICULUM
To familiarise with Ressettlement issues
MOMBASA PORT AREA ROAD DEVELOPMENT TRAINING CURRICULUM

Note
1 Work Hours
Normal Working hours shall be as follows:
Weekdays: Morning-8a.m to 1a.m- Afternoon -2a.m to 5p.m
Saturdays: 8a.m to 1 a.m
Application for day offs/leave should be made to the MFO

2 Deliverables by trainees shall be:


a Presentation (to be presented to the Engineer in Charge/ DPD)
monthly presentation - 15min
b Report (to be forwarded to the Engineer in Charge/ DPD)
-weekly, Monthly report
- Final
3 The site administrator shall be responsible for ensuring attendance/ reports are submitted
4 Facilitation
The Trainee shall be provided the following:
a Desktop Computer/laptop (Based on site)- to be returned after program
b Writing Material
-Pen/ Pencil
-Note Pad
-Box Folder
5 Clothing
Personal Protective Clothing(PPE)- Helmet, Reflective clothing, boots, Dust Coat
6 Transportation

a Office
The trainee shall accompany the senior engineer during inspection of site
b Site
The trainee shall work with the RE's staff and use the RE vehicles during site inspection
c Outside work hours
MOMBASA PORT AREA ROAD DEVELOPMENT TRAINING CURRICULUM
The trainee shall not be permitted use of a project vehicle outside work hours unless in the presence of a senior engineer
Week of Training Time taken location Graduate/Student Graduate Responsibility

Eng 1 Basic Intermediate Advanced


1 1day site 1 DPD/RE
1 1day site 1 RE
1 1day site 1 RE
22-24 2weeks site 1 Highways
22-24 1week office 1 Quantity Engineer
22-24 2weeks office 1 Quantity Engineer
22-24 2weeks office 1 "
22-24 2weeks office 1 "
22-24 2weeks office 1 "

1-4 4weeks site 1 RE


1-4 4weeks site 1 "
1-4 4weeks site 1 "
1-4 4weeks site 1 "

5-8 1 week site 1 Quality Engineer


5-8 4weeks site 1 "
5-8 4weeks site 1 "
5-8 4weeks site 1 "
5-8 4weeks site 1 "
5-8 1 week site 1 "
5-8 1week site 1 "

9-12 4weeks site 1 Geoditic Engineer


9-12 4weeks site 1 "
9-12 4weeks site 1 "
9-12 4weeks site 1 1 "
18-21 4weeks site 1 Highway Engineer
18-21 4weeks site 1 "
18-21 4weeks site 1 "
18-21 4weeks site 1 "
18-21 4weeks site 1 "
18-21 4weeks site 1 "
18-21 4weeks site 1 "
18-21 4weeks site 1 "
18-21 4weeks site 1 "
18-21 4weeks site 1 1 "

13-16 4week site 1 Structural/ Drainage Engineer


13-16 4week site 1 "
13-16 4week site 1 "
13-16 4week site 1 "
13-16 4week site 1 "

13-16 4week site 1 "


13-16 4week site 1 "
13-16 4week site 1 "
13-16 4week site 1 "
13-16 4week site 1 "
13-16 4week site 1 "
13-16 4week site 1 "
13-16 4week site 1 "

1-24 continous site/office Environmentalist


1-24 continous site/office Environmentalist
1-24 continous site/office Resettlement
nce of a senior engineer
MOMBASA PORT AREA ROAD DEVELOPMENT TRAINING CURRICULUM
month 1 2 3 4 5 6
Activity
week 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
1 Contract Management
Eng 1
Induction
a

Contract Manag Eng 1


b

Site Inspection Eng 1


2

Eng 1
3 Materials
Eng 2

Eng 1
4 Survey
Eng 2

Eng 1
5 Highway
Eng 2

Eng 1
6 Structure
Eng 2

Environmental/ Health Eng 1


7
and Safety and RAP Eng 2

Site Eng 1/2


Office