Sunteți pe pagina 1din 6

JOB SAFETY ANALYSIS Date:

Contractor Name: Project Plant Location:


Sub-Tier Contractor Name:
Prepared By:
Project: Project No.: Contract/PO No.:
Location (e.g., building, area, etc.):
Work Scope/Description: Excavate to a depth greater than five feet
Specific Work Location(s):
Name Primary/Phone # Secondary/Phone #
Contractor Contact Person(s):
Alcoa SPA:
Plant Emergency No.:
Prejob Walkthrough Conducted: Yes No
KNOWN OR POTENTIAL HAZARDS
Yes No Reference Yes No Reference
1. Hazardous Waste
√ • 29 CFR 1910.120 17. Noise Exposure √ „ ASP.653.3002
Operations
ASP.653.3000
2. Confined Space √ • „ ASP.653.3010 18. Temperature Extremes
/.3003
3. Hot Work √ • ASP.653.2308 19. Hoisting & Rigging √ „ ASP.653.2202
20. Ergonomics:
Repetitive Motion /
4. Roof Work • „ ASP.653.2321 √ ASP.653.3011
Awkward Positions /
Same Position (s)
5. Fall Hazards (> 6 ft) √ • „ ASP.653.2001 21. Biological ASP.653.2102
22. Insects / Varmints /
6. Excavation/Trenching √ • „ ASP.653.2311 ASP.653.2102
Vermin
7. Scaffolds / Ladders √ • „ ASP.653.2302/2303 23. Signs and Barricades ASP.653.2300
24. Location Specific
8. Aerial Lifts √ • „ ASP.653.2205 Emergency √ ASP.653.1007
Response Plan
9. Heavy Equipment √ „ ASP.653.2200 Series 25. Air Effluent Discharges • ASP.653.4003
26. Water/Liquid Effluent
10. Lock and Tag √ • „ ASP.653.2315 • ASP.653.4004
Discharges
11. Site/Vehicle Traffic ASP.653.1005/.2300 27. Fatality Prevention √ ASP.653.1400
12. Electrical Hazards √ • „ ASP.653.2309/.2310 28. Associated w/Significant ASP.653.4000
13. Asbestos Work √ • „ ASP.653.3001 Environmental Aspects? Series
14. Lead Work √ • „ ASP.653.3005 √ = Requires formal/special training
15. Hazardous
√ ASP.653.2100/.3007 • = Requires a permit/form/report
Materials/MSDS
16. Respiratory Hazards √ ASP.653.3008 „ = Requires certification or Competent/Qualified Person
SPECIFIC HAZARD ANALYSIS AND SAFE WORK REQUIREMENTS
Known and/or potential hazards are further evaluated, and specific measures are identified on subsequent pages. This discussion must include
identification of the work activity, the specific hazards present, and the safe work requirements/controls (including a hazards assessment for PPE)
to be used to alleviate/control the hazard(s).
MINIMUM DRESS/PPE REQUIREMENTS: hard hats, safety glasses, electrical hazard-rated metatarsal boots with hard toes, and long pants
and shirt with sleeves made of 100% cotton or wool (or cotton/blend).
REVIEW
KNOWN AND/OR POTENTIAL HAZARDS ARE FURTHER EVALUATED, AND SPECIFIC CONTROL MEASURES
ARE IDENTIFIED ON SUBSEQUENT PAGES

Project Engineer Date Alcoa Single Point Accountable Date

Contractor Supervision Date (Optional) Date

S-AF-059 19 Aug 04
JOB SAFETY ANALYSIS Project:
(Continuation Page) Contract/P.O./Release No.:
Work Activity Hazards Present Required Safety Measures/PPE
Excavations requires a competent person be
appointed. This competent person is
responsible for proper execution of the
excavation process. (ASP.653.2311)

Complete all site required forms and


notifications. Obtain prints and notify utilities
companies or owners of intended excavation.
Use "Call Before You Dig" agency or provide
for alternative methods of underground
obstruction location. This process must be as
positive as feasible. Area scanning or hand
probing and hand digging until utilities are
visibly located is required. All underground
utilities and obstructions should be surface
marked per standard marking codes listed in
ASP.653.2311.

1. Locating underground utilities and Slips trips and falls walking in general area of Review general terrain and identified surface
obstructions prior to digging intended excavation. conditions. Look for ruts, larges rocks and
uneven terrain.

A. Scanning with electronic equipment. Trips and falls, strain from lifting heavy If focus on instrument distracts excessivly from
instruments. attension to terrain, have an assistant help spot
various hazards in area. If lifting or pushing
scanning instruments of heavier weights, get
help with movements to avoid strains.

B. Probing with metal tipped fiberglass rods. Slips trips and falls walking in general area of Review general terrain and identified surface
intended excavation. conditions. Look for ruts, larges rocks and
uneven terrain.

Back strains, hand injury from probing rod Avoid excessive force attempting to penetrate
deeper with rods. Wear leather gloves to avoid
blisters and other hand injuries.

2. Mobilizing digging equipment.


(9) Heavy Equipment - competent person Struck by mobile equipment All workers are to wear reflective traffic vests
required as appropriate. The competent person is
responsible for determining need. Barricade
work area and permit only excavation
personnel in the area.

Struck by site vehicles. Restrict outside vehicular traffic in the job site.
(11) Site Vehicle Traffic Use flaggers and a specific traffic route if
necessary.

Reminder: visually confirm proper clearances


from electrical lines in the area.

S-AF-059 19 Aug 04
JOB SAFETY ANALYSIS Project:
(Continuation Page) Contract/P.O./Release No.:
Work Activity Hazards Present Required Safety Measures/PPE
3. Dig trench.
(6) Begin digging. Striking underground utilities or other Observe marked locations of underground
significant obstructions. utilities if marked. Excavate by hand when
within five (5) feet in any direction of known
underground obstructions.
NOTE: Follow attached matrix to determine
exact methods of safe excation according to
extent of utility location.

1. Non-energized obstruction 1. Hand digging not required. May machine


e.g. foundation, rock excavate.

2. Abandoned utilities / process lines. 2. Hand digging not required (upon


Verification required. verification) Machine digging per competent
[ Unless verified, must be treated as energized ] person evaluation and JSA/STA.

3. Active utilities 3.Hand digging required to visually establish


e.g. storm water lines, sanitary lines location. Machine digging per competent
person evaluation and JSA/STA.

4. Electrical duct bank 4. Hand digging required to visually establish


location. Machine digging allowed after visual
location based upon JSA/STA.

5. Active, energized utilities. 5. Hand digging required when within 5 ft. of


e.g. air, gas, steam, process line, electrical utility. Machine digging allowed within two
(conduit and direct bury cable) feet after visual identification and deenergized
based upon competent person evaluation and
JSA/STA.

Excavate trench to proper depth. Cave ins from unsupported sides of trench After reaching a depth of five feet, a certified
and inspected trench box shall be in place in the
excavation prior to anyone working in the
trench. The trench box must rest within two
feet of the bottom of the trench. All work shall
be performed within the confines of the
protective shield (trench box). All access and
egress to and from the trench shall also be
accomplished within the confines of the trench
box. Ladders used for access must be tied off.
At no time will anyone be permitted to be in an
unprotected area of the excavation.
The competent person shall inspect the
installation of the protective barrier and the
conditions of the trench prior to enterg and
daily before each shift thereafter or after a rain
storm. Any water accumulation in the trench
shall be kept at a minimum by portable pumps.
Competent person shall monitor the water level
and determine when safe limits have been
exceeded.

Barricade the swing radius of the excavator to


prevent struck by or crushed between injuries at
the rear of the equipment.
Spoil pile shall be placed at least two feet from
the edge of the trench. Operator shall place
spoils as far back from the edge as possible and
slope the pile away from the excavation.

Site traffic shall be prohibited from entering the


excavation area. If traffic can not be kept
S-AF-059 a 04
19 Aug
significant distance from the site, flaggers,
Jersey barriers or stop logs shall be placed to
prevent approach.
JOB SAFETY ANALYSIS Project:
(Continuation Page) Contract/P.O./Release No.:
Work Activity Hazards Present Required Safety Measures/PPE
Falling into eight foot depth trench Anyone working within six feet of the edge of
the trench if exposed to a fall >6 ft. Protection
from falling into trench must be provided. At a
minimum, barricades shall be erected six feet
from the edge of the trench. Anyone within the
six foot boundary must be protected. Methods
of fall protection can be: OSHA approved
railing or fall restraint by tethering workers so
that they cannot approach the trench close
enough to fall in. Attachment must only be
withstand four times the anticipated load a
person would exert walking to the trench or
leaning to see in.

The trench must be barricaded with substantial,


highly visible methods when left unattended.

Provide a walkway or bridge with standard


guardrails if employees must cross over the
excavation

5. Noise exposure Hearing loss from constant exposure to sound Wear ear plugs whenever close to operating
levels above 85 db. heavy equipment.

Site emergency response Need for trench rescue or EMS Call plant emergency number for all emergency
response needs. Plant protection is coverage
for trench rescue, they must be contacted daily
to advise of trenching activities.

6. Hazardous chemicals Chemical burns, poisoning, dermatitus and All chemicals brought on site must have a
other injuries from exposure. MSDS readily accessable to all workers on the
job. Workers must be trained on the hazards
and how to protect against them.

7. General PPE requirements. Hard hat, ANSI Z87.1 approved safety glasses,
steel toed safety boots, long trousers and shirts
with a minimum five inch sleeve.

8. Fatality prevention Fatality Prevention: Workers are instructed to be aware of their


While performing all construction activities, surroundings. Report any and all concerns to
personnel could be struck by falling objects, their immediate supervisor. Workers are
moving crane loads, vehicle and mobile trained to recognize hazards and coordinate the
equipment traffic, fall from heights, use of administrative controls, engineering
electrocution, drowning, loss of oxygen in controls, PPE, or evaluate another way to
confined space causing fatal injuries. perform the task which will lesson or eliminate
the hazards and potential for fatality. All
conmtractors have received Alcoa Fatality
Prevention Orientation.
Thoroughly review all JSA's, STA's and
associated work plans with all crew members.

S-AF-059 19 Aug 04
JOB SAFETY ANALYSIS Project:
(Continuation Page) Contract/P.O./Release No.:
Work Activity Hazards Present Required Safety Measures/PPE

S-AF-059 19 Aug 04
PREJOB SAFETY PLANNING SIGNOFF

I have read the attached Prejob plan, (and attachments) and understand the hazards and controls associated with this job.

Job Safety Analysis JSA review Task Specific JSA review Employee Safety and Health
Orientation
Energized Electrical Work Fall Protection Work Plan Respiratory/Lead work plan
Permit
Hoisting & Rigging Prelift Confined Space Pre-Entry Meeting Lead Compliance Plan
Lock/Tag/Verify
Other (specify):
Company Name:
Project Number: Project Location:

Date ID No. (optional) Name (Print) Signature

Person Conducting Briefing

Print Name Title Signature

S-AF-073 21 Jun 07

S-ar putea să vă placă și