QUALITY CONTROL CONTENTS

Contractor: DESIGN & CONSTRUCTION CONTRACTOR OF TAN SON NHAT – BINH


LOI – OUTER RING ROAD PROJECT AT HO CHI MINH CITY
Project: TAN SON NHAT – BINH LOI – OUTER RING ROAD
Laboratory: (LAS-XD 198) MATERIAL LABORATORY
TRAN NGUYEN CONSTRUCTION CONSULTING COMPANY (LIMITED)

Quality control system of laboratory is demonstrated in quality text following:

1> Quality handbook :


 To introduce organization systems, announce quality policy, engagement about
qualities and summarizes quality process of laboratory.
 Describe relationships, interactions between the processions of quality control
system.
 Application scope of chief of laboratory to group of test in lab, site.

2> Quality process


Sequence descriptions, work ever executive kind, include:
 Detailed outline of specified of test, sampling density, standard apply to
materials kind;
 Technical documents of project ;
 Standards of test, Technical standard;
 Forms of test documents;

3> instructions
 Present of way to perform a specific work to ensure suitability to achieve the
quality characteristics have been proposed including:
 Regulations of laboratory;
 Procedures when relate with lab;
 Regulations when use chemicals;

ÑÖÔØNG VAØNH ÑAI TAÂN SÔN NHAÁT – BÌNH LÔÏI

Phoøng thí nghieäm vaät lieäu xaây döïng (LAS-XD 198)


ĐT/Fax: …………… – Email: trannguyen_tnco@yahoo.com.vn
 Regulations when use equipments, machines in laboratory;
 Maintenance plan of equipments in lab;
 Deduction of standard of test of materials kind;
 Report use writing test data in lab and site;

4> Quality document control


 Laboratory always maintain a system of quality document control relate with
work of project to ensure document administer is effective and availability to
use.
 Chief of laboratory carry out to control compiling, modify approve and receive or
cancel quality document control, including background are from outside.
 Chief of laboratory designated person compiling and revise quality documents.
 Chief of lab approved quality procedures and instructions used equipments,
machines.
 The book, background document from outside can not be signed and control by
lab manager, used for reference only.

5> Office dispatch control


Lab manager control, indicate who is responsible and receive rights in the work,
send office dispatch, document, letter, fax and email between Investor and related
parties.

6> Quality record control


 Chief of laboratory must collect, control and store quality records to
demonstrate that quality control process has been applied and maintained. All
members of the laboratory is responsible for collecting quality records, classify
and inspect allocation work ensure that all quality records be store,
management consistent with requirements, easily understand, easy to get out
and storage time is determines appropriately
 Quality records must collect and store according with list of records by lab
manager established.
 The quality records is collected immediately at the place to carried out work by
rate of progress of project, at what time that the process or guide regulations,

ÑÖÔØNG VAØNH ÑAI TAÂN SÔN NHAÁT – BÌNH LÔÏI

Phoøng thí nghieäm vaät lieäu xaây döïng (LAS-XD 198)


ĐT/Fax: …………… – Email: trannguyen_tnco@yahoo.com.vn
accordance with technical standard of project and have sufficient these logal
factors corresponding request.
 Chief of laboratory shall specify the responsibilities and the specific works to be
done in quality control records, including : collection, storage, maintained use or
cancel quality record.

LAB MANAGER

LE VAN THAO