Documente Academic
Documente Profesional
Documente Cultură
(SUMMARY SHEET)
Page 1 of 9
11. ITT C 2.2 (c) Page 17 Page 17R Clause Modified
Page 2 of 9
S. Document Clause No. /Page In place of Please read Remarks
No. No. as
12. SCC Additional Clause Page 25of 29 Page 25R of Clause Modified
46- Indemnity Bond 29
13. SCC Additional Clause Page 29of 29 Page 29R of Clause Added
62- Comprehensive 29
Annual Maintenance
Page 3 of 9
Volume - 3 (General Specification)
Page 4 of 9
6 PS Chapter 2 Page 6 of 11 Page 6R of Clause Modified
Clause 2.2.4.1 11
Page 5 of 9
24 PS Chapter 7 Page19of 36 Page19Rof Clause Modified
Clause 4.1 36
Page 6 of 9
42 PS Chapter 9A Page6of 40 Page6Rof 40 Clause Modified
Clause 1.1 (6)
43 PS Chapter 9A Page8of 40 Page8Rof 40 Clause Modified
Clause 2.1
44 PS Chapter 9A Page9of 40 Page9Rof 40 Clause Modified
Clause 2.1.5
45 PS Chapter 9A Page15of 40 Page15R Clause Modified
Clause 2.3 of 40
46 PS Chapter 9A Page22of 40 Page22Rof 40 Clause Modified
Clause 3
Page 7 of 9
61 PS Chapter 10 Page44of 76 Page44Rof 76 Clause Modified
Clause 6.2
Page 8 of 9
82 PS Chapter 14 Page 3 of 7 Page 3R of 7 Clause Modified
Clause 1
Volume-7 BOQ
Page 9 of 9
Contract NE-01, Supply, Installation, Testing and Commissioning of 25 kV Overhead Equipment (OHE), 33 kV Auxiliary Power
Supply and SCADA Systems for Elevated Corridor of Noida-Greater Noida Section (21 Stations, 29.139 RKM) and Rolling
Stock Depot at Greater Noida
1.1 GENERAL
Delhi Metro Rail Corporation (DMRC) Ltd. invites Open e-Tenders on international
competitive bidding (ICB) basis from eligible applicants from all countries and all areas, who
fulfil qualification criteria as stipulated in clause 1.1.4 of NIT, for the scope
The brief scope of the work and site information is provided in ITT clause A1.1 & Employer
Requirements (Volume –3 & Volume 4)
Last date of Seeking Clarification 05.06.2015 (Queries from bidders after due date
shall not be acknowledged)
Last date of issuing addendum 11.06.2015 19.06.2015 07.07.2015
Date & time of Submission of Tender 29.06.2015 03.07.2015 30.07.2015 @ 15:00 Hrs.
Date & time of opening of Tender 29.06.2015 03.07.2015 30.07.2015 @ 15:05 Hrs.
1.1.3 Source of Funds: This is a NON-JICA funded Contract and project shall be financed
accordingly
(ii) (a) A non-Indian firm is permitted to tender only in a joint venture or consortium
arrangement with any other Indian firm having minimum participation interest of 26% or
their wholly owned Indian subsidiary registered in India under Companies Act-1956 with
minimum 26% participation
(b) A tenderer shall submit only one bid in the same tendering process, either individually as
a tenderer or as a partner of a JV. A tenderer who submits or participates in, more than
one bid will cause all of the proposals in which the tenderer has participated to be
disqualified. No tenderer can be a subcontractor while submitting a bid individually or as
a partner of a JV in the same bidding process. A tenderer, if acting in the capacity of
subcontractor in any bid, may participate in more than one bid, but only in that capacity.
However bidders may propose vendors as per vendor approval procedure provided in
the tender documents and vendors will not be treated as subcontractors, for the
purpose of this clause only.
a. Tenderer and all partners constituting the Tenderer has been engaged by the
Employer to provide consulting services for the preparation related to procurement for
or implementation of the project;
b. Tenderer and all partners constituting the Tenderer is any associates / affiliates
(inclusive of parent firms) mentioned in subparagraph (a) above; or
c. A Tenderer and all partners constituting the Tenderer lends, or temporarily seconds
its personnel to firms or organizations which are engaged in consulting services for
the preparation related to procurement for or implementation of the project, if the
personnel would be involved in any capacity on the same project.
(iv) A firm, who has purchased the tender document in their name, can submit the tender either
as individual firm or in joint venture/Consortium. However, the lead partner in case of JV shall
be one who has experience of Viaduct/Bridge/Flyover.
(v) Any Central / State government department / public sector undertaking / other government
entity or local body must not have banned business with the tenderer (any member in case
of JV) as on the date of tender submission. Also no contract of the tenderer should have
been rescinded / terminated by DMRC after award during last 5 years due to non-
performance of the tenderer or any of JV/Consortium members. The tenderer should submit
undertaking to this effect in - Appendix 19 of Form of Tender.
(vi) Tenderer (any member in case of JV/consortium) must not have paid liquidated damages of
10% (or more) of the contract value in a contract due to delay or penalty of 10% (or more) of
the contract value due to any other reason during last five years. The tenderer should submit
undertaking to this effect in Appendix-20 of Form of Tender.
(vii) Tenderer (any member in case of JV/consortium) must not have suffered bankruptcy/
insolvency during the last 5 years. The tenderer should submit undertaking to this effect in
Appendix-21 of Form of Tender.
(viii) LEAD PARTNER/NON SUBSTANTIAL PARTNERS/CHANGE IN JV/CONSORTIUM
a. Lead partner must have a minimum of 26% participation in the JV/Consortium.
b. Partners having less than 26% participation will be termed as non-substantial
partner and will not be considered for evaluation which means that their financial
soundness and work experience shall not be considered for evaluation of
JV/Consortium.
c. In case of JV/Consortium, change in constitution or percentage participation shall
not be permitted at any stage after their submission of application otherwise the
applicant shall be treated as non-responsive.
d. The tenderer, in case of JV/Consortium, shall clearly and unambiguously define the
role and responsibilities for each substantial/non-substantial partner in the JV
agreement/ MOU submitted vide foot note (d) of Appendix 6 of Form of Tender,
providing clearly that any abrogation/subsequent re-assignment of any
responsibility by any substantive/non-substantive partner of JV/Consortium in
favour of other JV/Consortium partner or any change in constitution of partners of
JV/Consortium (without written approval of Employer) from the one given in JV
agrement/MOU at tender stage, will be treated, as ‘breach of contract condition’
and/or ‘concealment of facts’ (as the case may be), vide GCC clause 4.33.1 [a (ii)
and (iii)] and acted accordingly.
The Employer in such cases, may in its sole discretion take action under clause 4.33.1 (b)
and/or under clause 4.33.1(c) of GCC against any member(s) for failure in tenderer’s
obligation and declare that member(s) of JV/Consortium ineligible for award of any tender in
DMRC or take action to terminate the contract in part or whole under clause 13 of GCC as the
DMRC/NE-01/Vol-1/NIT Page 3R
Contract NE-01, Supply, Installation, Testing and Commissioning of 25 kV Overhead Equipment (OHE), 33 kV Auxiliary Power
Supply and SCADA Systems for Elevated Corridor of Noida-Greater Noida Section (21 Stations, 29.139 RKM) and Rolling
Stock Depot at Greater Noida
1.1.4.2 Minimum Eligibility Criteria: (All values in Indian Rupees), (1 Crore = 10 million)
Work Experience: The tenderers will be qualified only if they have completed work(s) during
last 10 years as on date of tender submission as given below:
A. General Experience:
OR
Two “similar works”** each of value INR 50 Cr or more.
OR
Three “similar works”** each of value INR 40 Cr or more.
**”Similar works” for (i) above for this contract shall be Railway/Metro/Sub-urban traction work
which shall include minimum of Supply, Installation, Testing And Commissioning of 15 kV
and above Traction (Flexible OHE) Systems .
AND
OR
Two “similar works”*** each of value INR 45 Cr or more.
OR
Three “similar works”*** each of value INR 36 Cr or more.
***”Similar works” for (ii) above for this contract shall be Electrical work which shall include
minimum of Supply, Installation, Testing And Commissioning of 11 kV and above
INDOOR Auxiliary Sub stations .
Note:- If the general experience vide (i) & (ii) is provided for the same contract
(which includes both similar works), the total eligibility criteria shall be evaluated
after adding the values of works as mentioned in each of the works of General
Experience under (i) & (ii)
Notes :
• The tenderer shall submit details of works executed by them in the Performa of
Appendix 11 & 12 of FOT for the works to be considered for qualification of work
experience criteria. Documentary proof such as completion certificates from client
clearly indicating the nature/scope of work, actual completion cost and actual date of
completion for such work should be submitted. The offers submitted without this
documentary proof shall not be evaluated. In case the work is executed for private
client, copy of work order, bill of quantities, bill wise details of payment received
certified by C.A., T.D.S certificates for all payments received and copy of final/last bill
paid by client shall also be submitted.
• Value of successfully completed portion of any ongoing work up to 31.05.2015 will also
be considered for qualification of work experience criteria.
• For completed works, value of work done shall be updated to 31.05.2015 price level
assuming 5% inflation for Indian Rupees every year and 2% for foreign currency
DMRC/NE-01/Vol-1/NIT Page 4R
• For completed works, value of work done shall be updated to 31.05.2015 price level
assuming 5% inflation for Indian Rupees every year and 2% for foreign currency
portions per year. The exchange rate of foreign currency shall be applicable 28 days
before the submission date of tender.
• In case of joint venture / Consortium, full value of the work, if done by the same joint
venture shall be considered. However, if the qualifying work(s) were done by them in
JV/Consortium having different constituents, then the value of work as per their
percentage participation in such JV/Consortium shall be considered.
B. - Financial Standing: The Tenderers will be qualified only if they have minimum financial
capabilities as below:
(i) T1 – Liquidity It is necessary that the firm can withstand cash flow that the contract will
require until payments received from the Employer. Liquidity therefore becomes an
important consideration.
This shall be seen from the balance sheets and/or from the banking reference. Net
current assets and/or documents including banking reference, should show that the
applicant has access to or has available liquid assets, lines of credit and other
financial means to meet cash flow of Rs. 13.57 Crores for this contract, net of
applicant’s commitments for other Contracts. Banking reference should contain in
clear terms the amount that bank will be in a position to lend for this work to the
applicant/member of the Joint Venture/Consortium. In case the Net Current Assets (as
seen from the Balance Sheets) are negative, only the Banking references will be
considered. Otherwise the aggregate of the Net Current Assets and submitted
Banking references will be considered for working out the Liquidity.
The banking reference should be from a Scheduled Bank in India or (in case of foreign
parties) from an international bank of repute acceptable to DMRC as per standard
performa provided in ITT as Annexure-8 Annexure 12 and it should not be more
than 3 months old as on date of submission of bids.
(ii) T2 - Profitability: Profit before Tax should be Positive in at least 2 (two) year, out of the last
five audited financial years
In Case of JV/JVA/Consortium - The profitability of only lead member shall be
evaluated.
(iii) T3 - Net Worth: Net Worth of tenderer must be positive in the latest audited financial
balance sheets.
In Case of JV/JVA/Consortium, the algebraic sum total of Net Worths of all the
members as per the latest audited balance sheets shall be considered the Net Worth of
the tenderer.
DMRC/NE-01/Vol-1/NIT Page 5R
Contract NE-01, Supply, Installation, Testing and Commissioning of 25 kV Overhead Equipment (OHE), 33 kV Auxiliary Power
Supply and SCADA Systems for Elevated Corridor of Noida-Greater Noida Section (21 Stations, 29.139 RKM) and Rolling
Stock Depot at Greater Noida
Volume 1
Notice Inviting Tender
Instructions to Tenderers (including Annexures)
Form of Tender (including Appendices)
Volume 2
General Conditions of Contracts
Special Conditions of Contract (including Schedules)
Volume 3
Employer’s Requirements – General Specifications
Volume 4
Employer’s Requirements – Particular Specifications
Volume 5
Tender Drawings
Volume 6
Condition of Contract on Safety, Health & Environment (SHE) Ver. 1.2
Volume 7
Bill of Quantities
(Soft copy shall also be provided in a CD)
1.1.6 The Tenderers may obtain further information/ clarification, if any, in respect of these tender
documents from the authority defined in the Key details above.
1.1.8 The authorized signatory of intending tenderer, as per Power of Attorney (POA), must have
valid class-III digital signature. The tender document can only be downloaded or uploaded
using Class-III digital signature of the authorized signatory.
1.1.9 Tender submissions will be made online after uploading the mandatory scanned documents
towards cost of tender documents such as Demand Draft or Pay Order or Banker’s Cheque
from a Scheduled commercial bank based in India and towards Tender Security such as Bank
Guarantee or Demand Draft or Pay Order or Banker’s Cheque from a Scheduled commercial
bank based in India and other documents as stated in the tender document.
1.1.10 All Tenderers are hereby cautioned that tenders containing any material deviation or
reservations as described in Clause. E 4.0 of “Instructions to Tenderers” and/or minor
deviation without quoting the cost of withdrawal shall be considered as non-responsive and is
DMRC/NE-01/Vol-1/NIT Page 8R
Contract NE-01, Supply, Installation, Testing and Commissioning of 25 kV Overhead Equipment (OHE), 33 kV Auxiliary Power Supply and
SCADA Systems for Elevated Corridor of Noida-Greater Noida Section (21 Stations, 29.139 RKM) and Rolling Stock Depot at Greater Noida
INSTRUCTIONS TO TENDERERS
A. General
A1. General Description of the Work
Delhi Metro Rail Corporation Limited (DMRC) has been authorised to procure works for Design,
Verification, Detail Engineering, Manufacture, Supply, Installation, Testing and Commissioning
of 25 kV Overhead Equipment (OHE), 33 kV Auxiliary Power Supply and SCADA Systems for
Elevated Corridor of Noida-Greater Noida Section (21 Stations, 29.139 RKM) and Rolling Stock
Depot at Greater Noida.
The various sections of the corridor along with the expected date of opening for carriage of
passenger for information only are as under:
RKM 9.488
RKM 10.280
Contract NE-01 " Design, Verification, detailed Engineering, Supply, Installation, Testing
and Commissioning of 25 kV Overhead Equipment (OHE), 33 kV Auxiliary Power Supply and
SCADA Systems for Elevated Corridor of Noida-Greater Noida Section (21 Stations, 29.139
RKM) and Rolling Stock Depot at Greater Noida.”
The Scope of Work for the Design and Construction of this contract is further described in the
Employer’s Requirements. (Volume 3, 4 and Bill of Quantities/Pricing Document).
A1.1.1 Not Used
A1.1.2 Not Used.
A 1.2 Not Used
A1.2.1 Not Used.
B4.1 During the tender period, the Employer may issue further instructions to Tenderers or any
modifications to existing tender documents in the form of an addendum. Such an amendment in
the form of an addendum will be uploaded on the e-tendering portal
www.tenderwizard.com/DMRC within the date given in NIT which shall be available for all the
prospective tenderers who have purchased the tender document in the tender period. In case
of delay beyond the last date of issuing addendum given in NIT, the date of submission, at its
sole discretion may be extended by DMRC under Clause D2.6 of ITT.
Without prejudice to the order of preference as specified in Clause 1.5 of General Conditions of
Contract, the provisions in such addenda shall take priority over the Invitation to Tender and
Tender Documents issued previously. Tenderers should acknowledge receipt of such addenda
and include them in the tender submittal. (In the format given in Appendix-10 of Form of
Tender)
B4.2 The Tenderer should note that there might be aspects of his Tender and/or the evaluation
documents submitted with the Tender that will necessitate clarification. It is intended that any
aspect of the said evaluation documents and any amendments or clarification which are to
have contractual effect will be incorporated into the Contract either:
(a) by way of Special Conditions of Contract to be prepared by the Employer and agreed in writing
by the Tenderer prior to and conditional upon acceptance of the Tender; or
(b) by the Tenderer submitting, at the written request of the Employer, documents which are
expressly stated to form part of the Tender, whether requested before or after submission of the
documents forming part of the Tender, identified in paragraphs C2.3(a) to C2.3(l) below, and
whether as supplements to, or amended versions of such documents.
Save as aforesaid, all such amendments or clarifications shall not have contractual effect.
Requests for clarification and the Tenderers responses shall be made in writing.
C. Preparation of Tenders
C1 Language
Tenders and all accompanying documents shall be in English. In case any accompanying
printed literature is in other languages, it shall be accompanied by an English translation. The
English version shall prevail in matters of interpretation.
Financial Package shall contain the documents referred to in paragraphs C2.2 (a); (b); & (c).
The Tenderer shall ensure that a receipt is obtained for the submission of his Tender, such
receipt being issued free of charge.
C 2.2 The Tenderer shall submit, as his Tender, the following documents, duly completed which in
the event of acceptance of the Tender, shall form part of the Contract:
(d) Appendix 3 to the Form of Tender: Outline Quality Plan (see paragraph C4 below);
(e) Appendix 4 to the Form of Tender: Outline Safety, Health & Environment Plan (see
paragraph C5 ):
(f) Appendix 5 to the Form of Tender: Contractor's Technical Proposals (see para C6);
(h) Appendix 7 to the Form of Tender: Staffing Schedules and Organisation Chart (see
paragraph C12);
(i) Appendix 8 to the Form of Tender: Power of Attorney(s) (see paragraph A4)
(j) Appendix 9 to the Form of Tender: Tender Index (See paragraph C23);
(k) Appendix 10 to the Form of Tender: Participation letter;
(l) Appendix -11 & 12 of FOT: Work Experience;
(m) Appendix- 13 of FOT: Financial Data (Financial Standing);
(n) Appendix -14 of FOT: Financial Data (Work Done);
(o) Appendix-15 of FOT: Financial Data (Commitment for Ongoing Works);
(p) Appendix -16 of FOT: Minimum Key staff requirement;
(q) Appendix -17 of FOT: Key staff Bio-data;
(r) Appendix -18 of FOT: Historical contract Non Performance.
(s) Appendix -19 of FOT: Banned Business
requirement which do not alter the basic functionality of the work or part thereof. If
there is no such minor deviation, then the tender must write “NIL” in this annexure.
Tenderer to note that such minor deviations may or may not be accepted by the
employer and the tenderer shall not have any right to any claim on this account. The
offer in pricing document shall be given without considering any deviation in tender
conditions.
Tenderers shall further note that except for deviations listed in Annexure ‘3’ of
Instructions to Tenderer, the tender shall be deemed to comply with all the
requirements in the tender documents including Employer’s Requirements, without any
extra cost to the Employer irrespective of any mention to contrary, anywhere else in the
Tender.
The tender price shall be added with the price of deviations given in “Statement of
pricing for unqualified withdrawal of conditions/qualifications and deviations
etc.” with view of bringing various bidders at par, i.e. in full compliance of tender
conditions;
(y) Annexure 4 to ITT:– Requirement for Tender’s Technical Proposals
(a) Certificate of compliance
(b) Appendix A – Statement of Deviations
(c) Appendix B – Schedule of Sub-Contractor/ Vendors
(d) Appendix C – Pricing of Unqualified withdrawal of Conditions,
Qualifications, Deviation, etc.
(e) Appendix D – Proposal for Equipment/Systems
(f) Appendix E – Undertaking for Transfer of technology
(g) Appendix F – Proforma for Submitting No Load Iron Losses and Full Load
Copper Losses Figure
(h) Appendix G – Project Organisation
(i) Appendix H – Construction Machinery usage undertaking
(j) Appendix I – Sub- Contractor undertaking
(k) Appendix J – Interface requirement undertaking
(l) Appendix K – Scope of work compliance undertaking
(z) Annexure 5 to ITT: – Tentative Project Implementation Programme (see paragraph
C8).
(aa) Annexure 6 to ITT: - Requirement of Tender Programme (see paragraph C8).
(bb) Annexure 7 to ITT: – Bank Guarantee for Tender Security (see paragraph C18).
(cc) Annexure 8 to ITT: – Confirmation of Performance Security Provider (see paragraph
F5).
(dd) Annexure 9 to ITT:– Not Used Form Of Additional Bankguarantee By Bank
(ee) Annexure 10 to ITT: – Details of Foreign Currency (see paragraph C16.1).
(ff) Annexure 11 to ITT: – Undertaking for Downloaded Tender Document
(gg) Annexure 12 to ITT: – Sample Format For Banking Reference For Liquidity
A declaration by the bidders as per Annexure -11 of ITT must be submitted stating that the
tender document has been downloaded from official website of e-tendering portal
C2.4 The Employer may get, from the Government, partial or complete waiver of taxes, royalties,
duties, Labour cess, octroi, and other levies payable to various authorities. The successful
tenderer (the contractor) shall maintain meticulous records of all the taxes and duties paid and
provide the same with each running bill. In case the waiver becomes effective, the Contractor
will be advised on the process to be followed to obtain the refund from the concerned authority.
The Contractor shall arrange for the remit of the refund to the Employer. In case of failure by
the Contractor to remit such amounts, the same shall be recovered from amounts due for
payment to the Contractor. With the tender submission, the tenderer shall submit the proof of
U.P VAT registration or shall submit an undertaking that he will get registered with U.P VAT
authorities in case of award of LOA to them.
C2.5 Tenderers shall quote all prices as per Clause 11.1.1 of GCC and clause 24 of S.C.C.
C2.7 Unless stated otherwise in the tender documents, the contract shall be for the whole of the
Works as described in the tender documents, based on the unit rates and prices in the Bill of
Quantities submitted by the Tenderer.
C2.8 The Tenderer shall fill in rates and prices for all items of the works described in the Bill of
Quantities. Items against which no rates or price is entered by the Tenderer will not be paid for
by the Employer when executed and shall be deemed to be covered by the rates for other items
and prices in the Bill of Quantities.
C2.9 The employer shall deduct at source from the bills of the contractor any amount which employer
may require by law for deposition with the statutory authorities in India. The Employer shall
further furnish to the contractor a certificate for such tax deducted at source.
C2.10 The rate for each item shall be reasonable and not unbalanced.
C2.11 If the employer so decides, he may supply some items of BOQ to the contractor as “Employer
supply items” and in such an event the Contractor shall not be allowed to claim payment for
such items. The Employer shall notify a list of such items within three months of the placement
of the Contract.
C2.12 In exceptional circumstances, when it is proved beyond reasonable doubts that the Contractor
is not able to procure any equipment / material either locally or by import, as per the
specification given in the contract documents, the Employer may permit use of equipment/
material to other design specification provided that the Contractor is able to establish that
performance of the system shall not get affected in any way. Benefit, if any, accruing due to this
change shall be passed on to the employer.
C3 Form of Tender
The Form of Tender shall be completed and signed by a duly authorised and empowered
representative of the Tenderer. If the Tenderer comprises a partnership, or a joint venture/JVA
the Form of Tender shall be signed by a person who is duly authorised by each member or
participant thereof or by authorized signatory of each member. Signatures on the Form of
Tender shall be witnessed and dated. Copies of relevant powers of attorney shall be attached.
C4 Outline Quality Plan
The Tenderer shall submit Appendix-3 of Form of Tender to form part of his Tender an Outline
Quality Plan illustrating the intended means of compliance with the Employer's Requirements
(Volume 3) and setting out in summary form an adequate basis for the development of the
more detailed document required under Clause 19 of the SCC. The Outline Quality Plan shall
C16.3 For the purpose of comparative evaluation of the offers, all tender prices will be converted to
Indian Rupees by using the Exchange (selling) rates for those currencies at the close of
business of the State Bank of India 28 days before the latest date for submission of Tenders
Any deviation in Bid security with regard to amount, validity and format shall be considered as material deviation and
bid shall be dealt accordingly. No clarification shall be sought from the bidders regarding bid security.
C18.2 Any Tender not accompanied by an acceptable Tender Security shall be rejected by the Employer considering it as
non-responsive and their Technical package shall not be opened and if opened then it will NOT be evaluated.
C18.3 The Tender Security of the successful Tenderer shall be returned upon the execution of the Contract and the receipt by
the Employer of the Performance Security in accordance with Sub-Clause 4.2 of the GCC.
C18.4 The Tender Security of the unsuccessful Tenderers shall be released after the Contract has
been signed with the successful Tenderer. The Tender Security of tenderers who fail in technical
evaluation shall be returned after opening of financial package. Tender security of the unsuccessful tenderers
in financial opening shall be released after unconditional acceptance of the Letter of Acceptance (LOA) by the
successful tenderer.
(ii) The outcome/result of the tender shall be communicated to successful tenderers and will be posted on the website. The
information about the bidding results may be made public by JICA.
(iii) After notification of award, if any unsuccessful tenderer requests in writing to DMRC asking reasons of being
unsuccessful, DMRC shall reply in writing giving brief reasons. Tenderers to note that no further correspondence on
this issue will be entertained by DMRC.
F3.3 Upon “Letter of acceptance” being signed and returned by the successful Tenderer as per Clause F3.1, the employer
will promptly notify the unsuccessful Tenderers and discharge / return their tender securities.
F3.4 In the event of award of the Contract, the following will be the sequence of events in the order given below. The Employer may
seek suitable amendments to the Contract if such amendments are desired by the Employer.
F4 Signing of Agreement
The Tenderer should note that in the event of acceptance of the Tender, the Tenderer will be required to execute the
Contract Agreement in the form specified in Special Conditions of Contract with such modifications as may be
considered necessary at the time of finalisation of the contract within a period of 30 days from the date of issue of the
Letter of Acceptance.
F5 Performance Security
F5.1 The Performance Security required in accordance with Clause 4.2 of the GCC shall be for 10% of the Contract Price
from the Scheduled commercial Bank (including Scheduled Commercial Foreign Banks) in India in the currency in
which the Contract Price is payable. The Performance Security shall be furnished to the Employer within 30 (thirty) days
of receipt of the Letter of Acceptance. The form of Performance Security provided in SCC.
The required Performance Security for the sum mentioned above may be submitted in any one of the following forms:
(a) Irrevocable bank guarantee in the prescribed format, given in Annexure-8 of Instruction to Tenderers (ITT), issued
by a Scheduled Commercial Bank based in India or from a branch in India of a Scheduled foreign bank.
(b) Bank Draft in favour of Delhi Metro Rail Corporation Ltd. payable at New Delhi from a Scheduled Commercial
Bank based in India.
(c) Fixed Deposit Receipt of a Scheduled Commercial bank / Post offices based in India duly pledged in favour of
Delhi Metro Rail Corporation Ltd.
In case of joint venture/consortium, the Performance Security is to be submitted in the name of the JV / Consortium.
However, splitting of the performance security (while ensuring the security is in the name of JV / Consortium) and its
submission by different members of the JV / Consortium for an amount proportionate to their scope of work is also
acceptable.
The Performance Guarantee should be valid for a period of 6 (six) months beyond the Defect Liability Period.
F5.2 The Tenderer has to furnish other Guarantees, Undertakings, and Warranties, in accordance with the provisions of the
General Conditions of Contract and Special Conditions of Contract.
F5.3 Failure of the successful Tenderer to comply with the requirements of paragraphs F4 and F5 shall constitute sufficient
grounds for the annulment of the award and forfeiture of the Tender Security.
CONTRACT “NE-01”
CHECK SHEET FOR TECHNICAL SUBMISSION
Documents required to be submitted along with the Technical Package
B9. The tenderer should submit an undertaking, in Appendix `E’ to Annexure `4’ that he will make
credible arrangements for ensuring availability of critical spares and technical support, during
the service life of the equipments/spares/M&P/systems commissioned. The tenderer’s technical
proposal should also explain as to how he will ensure availability of critical spares and technical
support for maintenance/up gradation during the service life of the equipment.
B10. The technical proposal should also explain the tenderer’s understanding of interfacing with
other designated contractor’s/power supply authorities/statutory authorities. (Refer
Appendix –J to Annexure ‘4’)
B11. The technical proposal should also contain the tenderer’s understanding of scope of work.
(Refer Appendix –K to Annexure ‘4’)
In case the bidder is not having this experience, he should list out the sub contractors
from which he proposes to get these works done individually. Details of the proposed
subcontractors to be furnished.
10. The expressions “the Employer”, “the Bank” and “the Contractor” hereinbefore used shall include
their respective successors and assigns.
d) a) Our liability under this Bank Guarantee shall not exceed Rs……………(Rupees………)
f) c) We are liable to pay the guarantee amount or part thereof under this Bank Guarantee
only & only if you serve upon us a written claim or demand on or before………….
In witness whereof I/We of the bank have signed and sealed this guarantee on the …………. day of
…………… (Month& year) being herewith duly authorized.
Name : ……………………………..
Designation : ……………………………..
Notes:
1. The stamp papers of appropriate value shall be purchased in the name of the
Bank, who issues the ‘Bank Guarantee’.
2. The ‘Bank Guarantee’ shall be from the Scheduled Commercial Bank based in India,
acceptable to Employer
Annexure - 11 to ITT
UNDERTAKING FOR DOWNLOADED TENDER DOCUMENT
We here by confirm that, we have downloaded / read the complete set of tender documents
(as detailed in NIT Clause 3 1.1.5)/addendum/clarifications along with the set of enclosures
hosted on e-tendering portal www.tenderwizard.com/DMRC. We confirm that we have gone
through the bid documents, addendums and clarifications for this work placed upto the date of
opening of bids on the e-tendering portal [www.tenderwizard.com/DMRC]. We confirm our
unconditional acceptance for the same and have considered for these in the submission of our
financial bid.
BANK CERTIFICATE
This is to certify that M/s .................................................... is a reputed company with a good financial
standing.
___Sd.___
Name of Bank:__________
This is to certify that M/s .................................................... who has formed a JV with M/s
.................................................... and M/s .................................................... for participating in this bid,
is a reputed company with a good financial standing.
APPENDIX-1A
Preliminary Design
KD-1 8 8 8 8
Submission
Submission of Preliminary
KD-3 8 8 8 8
Simulation Study
Submission of Final
KD-4 15 15 15 15
Simulation Study
Submission of Earthing
and Bonding scheme
KD-5 along with detailed 17 17 17 17
drawings based upon
Simulation study
Submission of Report by
Independent Agency for
KD-7 20 20 20 20
Verification (Auditing) of
design
Installation of Auxiliary
Power Supply System,
KD-9 Auxiliary Supply 84 82 63 60 63 60 63 60
Interlinking, SCADA
Sytems etc.
Testing and
Commissioning of
Auxiliary Power Supply
KD-11 87 65 65 65
System, Auxiliary Supply
Interlinking, SCADA
Sytems etc.
Testing and
Commissioning of Flexible
OHE equipments, Rigid
KD-12 93 91 72 69 72 69 72 69
OCS equipments,, SP,
SS, FP, SSP , Traction
Supply Interlinking etc
Submission of Report by
Independent Agency for
KD-13 92 90 71 68 71 68 71 68
Verification (Auditing) of
installation
Specific Construction Experience (shall be submitted separately for each work claimed for work experience)
Contract Identification
Award date
Completion date
Employer’s Name
Employer’s Address:
Telephone / Fax number:
E Mail
Role in Contract
(Individual/JV-JVA/Consortium Individual JV-JVA/Consortium Member
member)
Currency (as stated in Clients In equivalent INR at 31.05.2015 as on
Completion Cost Certificate) date of tender submission price level.
NOTE: 1. Only the value of contract as executed by the applicant/member in his own name should
be indicated. Where a work is undertaken by a group JV/JVA/Consortium, only that
portion of the contract which is undertaken by the concerned applicant/member should
be indicated and the remaining done by the other members of the group be excluded.
This is to be substantiated with documentary evidence.
2. Separate sheet for each work along with Clients Certificate to be submitted.
Name of Applicant (each member Total Number of works No. of contracts delayed,
in case of group) i.e., completed beyond the
As per clause no. 1.1.4.2 A
original date of completion
at the price level of
31.05.2015 as on date of
tender submission.
NOTE:-
1. In case the work was done as JV/JVA/Consortium, only the value of work done by the
applicant as per his Percentage participation must be given.
a). Chief Project Manager and Project Manager – Graduate having minimum 10 years of
total experience out of which 5 years should be in projects of similar nature.
b). Deputy Project Manager (DPM) - Graduate having minimum 8 years of total experience out
of which 4 years should be in projects of similar nature.
c). Design Engineer - Graduate having minimum 5 years of total experience out of which 3
years should be in Designing of projects of similar nature.
d). Station In-Charge – Graduate/Diploma having minimum 5 years of total experience out of
which 3 years should be in projects of similar nature.
e). SHE Organisation– As per the qualification and experience given in General
Instruction – 2 of DMRC SHE manual (shall include an Accident prevention Officer).
f). Civil & structural engineer– Graduate/Diploma having minimum experience of 2 years .
NOTE – Please submit the CV of above Key Personals as per Annexure 5 NIT Appendix –
17 of FOT.
The tenderer is required to confirm in Appendix-G of Annexure-4 of ITT that above minimum
requirement of experts of requisite experience and qualification will be mobilized by them for the
work in addition to semi-skilled and skilled staff.
As per the qualification and experience given in General Instruction – 2 of DMRC SHE manual
(shall include an Accident prevention Officer).
SCHEDULE - 2
PERFORMANCE SECURITY
DELETED
onfidential Page 1R of 3
Special Conditions of Contract – Schedules-2
PERFORMANCE SECURITY
(To be stamped in accordance with the Stamp Act of the Country of Issuing Bank)
To:
Barakhamba Road,
India.
WHEREAS ---------------- (Name and address of Contractor) (hereinafter called “the Contractor”)
has undertaken, in pursuance of Contract No.[Note-1] to execute and complete and
remedy any defects in the Works of the [Note 2] (hereinafter called “the Contract”)
AND WHEREAS it has been stipulated by you in the said Contract that the Contractor shall
furnish you with a Bank Guarantee by a scheduled commercial bank based in India for
the sum specified herein as security for compliance with his obligations in accordance
with the Contract.
AND WHEREAS we (Insert name and address of Bank) have agreed to give the Contractor
such a Bank Guarantee:
NOW THEREFORE we hereby affirm that we are the Guarantor and responsible to you, on
behalf of the Contractor up to a total of ------------------- (amount of Guarantee)-------------
-------- (in words), such sum being payable in the types and proportion of currencies in
which the Contract Price is payable and we hereby unconditionally, irrevocably and
without demur undertake to immediately pay you, upon your first written demand and
without cavil or argument any sum or sums within the limits of ------------ (amount of
guarantee) as aforesaid without your needing to prove or to show grounds or reasons
for your demand for the sum specified therein.
We hereby waive the necessity of your demanding the said debt from the Contractor before
presenting us with the demand.
We further agree that no change or addition to or other modification of the terms of the
contract or of the Works to be performed there under or of any of the contract
documents which may be made between you and the Contractor shall in any way
release us from any liability under the guarantee and we hereby waive notice of any
such change, addition or modification.
onfidential Page 2R of 3
Special Conditions of Contract – Schedules-2
This guarantee shall be valid for 28 days beyond the Defect Liability Period. The pendency of
any dispute or arbitration or other proceedings shall not affect this guarantee in any
manner.
----------------------------------------------------------------
ADDRESS --------------------------------------------------
DATE -------------------------------------------------------
Notes:
3. The stamp papers of appropriate value shall be purchased in the name of the
Bank, who issues the ‘Bank Guarantee’
onfidential Page 3R of 3
Contract NE - 01 Special Conditions of Contract
Page 5R of 29
Contract NE - 01 Special Conditions of Contract
Page 12 R of 29
Contract NE - 01 Special Conditions of Contract
Page 13 R of 29
Contract NE - 01 Special Conditions of Contract
Page 14 R of 29
Contract NE-01 Special Conditions of Contract
C) Change in Taxes/Duty :
The contract price shall not be adjusted to take into account any
change in taxes, duties, levies or introduction of any new tax, duty
or levy till the completion date including the date of extended period
of contract.
Page 17R of 29
Contract NE - 01 Special Conditions of Contract
The last Para of Clause 14.1 of GCC shall not be applicable in this
contract and the Contractor shall include such risks also in his
insurance cover. NOT USED
Page 21R of 29
Contract NE-01 Special Conditions of Contract
(b) The Employer may, during a period of ten years from the date
of taking-over of the whole of the Works, purchase as many
parts as required by him, at the rates indicated in the pricing
document and accepted by the Employer.
Page 24R of 29
Contract NE-01 Special Conditions of Contract
Page 25R of 29
Contract NE-01 Special Conditions of Contract
Page 29R of 29
NE Electrical Contracts - General Specification
(3) the absence of a programme date or installation period for the Contractor in a
specific area shall not prejudice the right of the Employer’s Representative to
establish a reasonable programme date or installation period for that area;
(4) the Contractor shall comply with the identified Key Dates. The Contractor
shall also comply with the Access dates identified in the; and
(5) the Contractor shall deliver all Contractor’s Equipment and Permanent Works
for stations and ventilation shafts by road and via temporary access openings
unless otherwise reviewed by the Employer’s Representative.
2.8.1 The Testing and Commissioning Programme shall be submitted as stated in the PS or
as directed by the Employer’s Representative and shall comply with the requirements
of clause 2.4.2.7 above.
2.8.2 The Contractor shall submit the Testing and Commissioning Programme that shall
fulfil all the on-Site testing and commissioning requirements of clause 9.3.2.2 below.
The Testing and Commissioning Programme shall clearly demonstrate the logic and
highlight the topics listed in the On-Site Testing and Commissioning Plan in clause
9.3.2.2 below.
2.8.3 The Testing and Commissioning Programme shall be fully detailed, with activities
individually identifying all tests for which a certificate will be issued, and shall include
activities for preparation, submittal and review of the test procedures.
2.8.4 The Testing and Commissioning Programme shall demonstrate the logical
dependencies between the individual tests of the Works, and shall also show the
interfaces and dependencies with all of the Project Contractors’ tests required to
commission the W orks and support the Commissioning Plan.
2.9.1 The Contractor shall, within 90 180 days of the Commencement Date of the W orks,
submit for review by the Employer’s Representative, a Training and Transfer of
Technology Programme covering all proposed formal training courses, delivery of
training equipment and accesses by the Employer’s personnel for informal ‘hands on’
technology transfer. The Training and Transfer of Technology Programme shall also
detail specific Transfer of Technology features as required by the Specification and
proposed by the Contractor.
2.9.2 The Training and Transfer of Technology Programme shall be developed to the
Training and Transfer of Technology Plan as required under clause 3.7.4 below.
2.9.3 The Training and Transfer of Technology Programme shall be sufficiently detailed that
the Employer can ensure the availability of staff for all the courses required under
clause 10.1.6 below.
2.9.4 The Training and Transfer of Technology Programme shall include the requirements
of Chapter 10 below, including the Training and Transfer of Technology activities of all
sub-contractors and suppliers.
Page GS 2-7R of 11
NE Electrical Contracts - General Specification
CHAPTER 9
9.1 General
9.1.1 Deleted.
9.1.2 Deleted
9.1.3 Deleted.
9.1.4 The Employer and the Employer’s Representative will bear their own costs for
attendance at witnessed inspections or tests (other than re-tests) scheduled in
accordance with the agreed W orks Programme and subject to notice in accordance
with the Specification.
9.2.1 The Manufacturing Test Plan is the Contractor’s plan for carrying out the necessary
procedures to ensure that the items presented for acceptance by the Employer and
the Employer’s Representative are in compliance with the requirements of the
Specification.
9.2.2 During the process of procurement and manufacture of the system components the
Contractor shall undertake such testing and inspection as is required by the Quality
Plan referred to in clause 5.4 above 5.6.
9.2.3 The Employer and the Employer’s Representative will not become involved in the
Contractor’s Manufacturing Tests except in respect of the following:
9.2.4 Before shipment of any items to Site the Contractor shall present the items for the first
stage of Acceptance according to the Commissioning Plan as detailed in clause 9.3
below.
9.2.5 Inspection
9.2.5.1 The Contractor shall be wholly responsible for all inward inspection of items to be
incorporated into the system as a whole.
9.2.5.2 Equipment issued by the Employer shall not be subject to Type Tests or First Article
Inspection however the Contractor shall undertake Inspection as referenced in clause
7.1 above. Should the Employer’s issued equipment be subsequently incorporated
Page GS 9-1R of 13
NE Electrical Contracts - General Specification
9.4.4.10 The Contractor shall include a complete schedule of all Partial Acceptance Tests
records and their current status within the Monthly Progress Report.
9.4.5.1 System Acceptance Tests are defined as the tests undertaken to demonstrate that the
Works in its entirety is capable of functioning in accordance with the specified
requirements in the Contract in all respects. The System Acceptance Tests are part
of the Tests on Completion to be performed by the Contractor under the Contract in
order to achieve Employer’s Taking Over of the W orks. The System Acceptance
Tests may commence before remote operations capability (if any) is fully functional,
however, the system must be satisfactorily tested remotely (if specified to have such
capability) before the System Acceptance Tests can be considered to be completed.
On satisfactory completion of the System Acceptance Tests, the tested items will be
considered available for Integrated Testing & Commissioning.
9.4.5.2 The particular requirements for System Acceptance Tests are prescribed in the PS /
TS are indicative only.
9.4.5.4 System Acceptance Tests shall comprise comprehensive testing of the assembled
installation to ensure that it operates in accordance with the requirements of the PS /
TS.
9.4.5.5 The tests shall include, but not be limited to, the following:
(1) tests of all functional and performance requirements for the system;
9.4.5.6 The System Acceptance Test Plan shall identify a comprehensive list of specifications,
standards, method statements, procedures, pass / fail criteria, sample records,
resources to be made available, drawings and records to be submitted to the
Employer’s Representative, and programme showing the dates for testing and for
submission of each test procedure.
9.4.5.7 Test procedures shall be carefully planned to ensure that the work can be executed in
the time available. If the available time is restricted, this planning shall include
contingency plans to be implemented if testing proceeds slower than anticipated or if
defects are discovered that necessitate rectification and subsequent repeat testing,
etc.
9.4.5.8 Immediately following the successful acceptance testing of the system, the Contractor
shall complete the appropriate commissioning records in the agreed format and
submit 3 signed copies to the Employer’s Representative.
9.4.5.9 The Contractor shall include a complete schedule of all System Acceptance Test
records and their current status within the Monthly Progress Report.
Page GS 9-6R of 13
NE Electrical Contracts - General Specification
9.4.6.1 Integrated Testing & Commissioning are defined as the final tests to be undertaken
before the commencement of Service Trial. The Integrated Testing & Commissioning
are part of the Tests on Completion to be performed by the Contractor under the
Contract in order to achieve Employer’s Taking Over of the W orks. The Integrated
Testing & Commissioning shall demonstrate the full compatibility between all
interfacing systems. On satisfactory completion of the Integrated Testing &
Commissioning, the tested items will be considered available for Service Trial.
9.4.6.2 The particular requirements for Integrated Testing & Commissioning are prescribed in
the PS are indicative only.
9.4.6.4 The Contractor shall co-ordinate with the Employer and the Employer’s
Representative and with all interfacing parties to ensure that the proposed test
programme and schedule truly demonstrate that the full specified performance
requirements are achieved.
9.4.6.5 The tests shall include, but shall not be limited to the following:-
(1) test of all functional and performance requirements for the system;
9.4.6.6 The Integrated Testing & Commissioning Plan shall identify a comprehensive list of
specifications, standards, method statements, procedures, pass/fail criteria, sample
records, resources to be made available, drawings and records to be submitted to the
Employer’s Representative, and a programme showing the dates for testing and for
submission of each test procedure.
9.4.6.7 Test procedures shall be carefully planned to ensure that the work can be executed in
the time available. If the available time is restricted, this planning shall include
contingency plans to be implemented if testing proceeds slower than anticipated or if
defects are discovered that necessitate rectification and subsequent repeat testing,
etc.
9.4.6.8 Immediately following the successful Integrated Testing & Commissioning of the
system or any constituent part, the Contractor shall complete the appropriate
commissioning records in the agreed format and submit 3 signed copies to the
Employer’s Representative.
9.4.6.9 The Contractor shall include a complete schedule of all Integrated Testing &
Commissioning records and their current status within the Monthly Progress Report.
9.4.7.1 Service Trial is defined as the final test of the fixed equipment, the rolling stock, and
the operational procedures including the final elements of the Tests on Completion to
demonstrate that the system in its entirety can operate satisfactorily. The Service Trial
is performed by the Employer with attendance by the Contractor under the Contract in
Page GS 9-7R of 13
NE Electrical Contracts - General Specification
between the parties, such quantities of the obsolete Spare Part as the Employer may
possess.
13.3.1 The quantity of Spare Parts to be supplied by the Contractor to the Employer shall be
determined in accordance with the formulae described in clauses or for particular items as
detailed in the PS. Deleted
13.3.2 Notwithstanding the quantities defined in the PS or by the following formulae the quantity
of Spare Parts shall be sufficient for the full operation of the Permanent W orks for the first
two 5 years following the expiry of the Defects Liability Period for the works ("Contract
Spares').
13.3.3 The Contractor shall supply and deliver the Contract Spares on or before completion of the
Systems Acceptance Test.
13.3.4 Deleted
13.3.5 Deleted
13.3.6 Deleted
13.3.7 Deleted
13.4.1 In addition to the Contract Spares, the Contractor shall keep on the Site ,under his
own custody throughout the installation, erection and commissioning periods,
sufficient stocks of Spare Parts to enable immediate replacement of any item in the
Permanent W orks found to be defective or in any way in non-conformance with the
Specification during the installation, erection and commissioning period
("Commissioning Spares").
13.4.2 The Contractor shall supply and deliver the Commissioning Spares on or before the
commencement of any Partial Acceptance Tests (PAT) or as defined in the PS.
13.4.3 Deleted
13.4.4 The Contractor shall not be entitled to use any of the Contract Spares to replace any
item in the Permanent Works during the installation, erection and commissioning
periods.
13.5.1 In addition to the Contract Spares, the Contractor shall keep sufficient stocks of Spare
Parts, in his own custody in an off-site location in Delhi/NCR throughout the Defects
Liability Periods to enable rapid replacement of any item in the Permanent Works
found to require replacement as part of the Contractor's obligations during the Defects
Liability Periods ('Defects Liability Spares").
Page: GS 13-4R of 7
NE Electrical Contracts - General Specification
13.5.2 The Contractor shall supply and deliver the Defects Liability Spares on or before the
commencement of the Service Trial. Deleted
13.5.3 The Contractor shall submit to the Employer’s Representative for review a list of all
Defects Liability Spares that shall be maintained by the Contractor during the Defects
Liability Periods.
13.5.4 The Contractor shall not be entitled to use any of the Contract Spares to replace any
item in the Permanent W orks during the Defects Liability Periods.
13.6.1 The Special Tools and Test Equipment (together with the relevant calibration
certificates) required to carry out all the functions described in the Operation and
Maintenance Manual or as required by the PS shall be suitably packed and identified
in accordance with Chapter 8 above, consigned to the Employer by the Contractor and
delivered to the Employer in accordance with the Employer’s Representative's
instructions not later than the date scheduled for stage commissioning. The extent of
supply shall include protective carrying cases as may be appropriate for the storage
and use of each item.
13.6.2 All Special Tools and Test Equipment shall be supplied with Operation and
Maintenance Manuals, complete diagrams, schematics, assembly and connection
drawings, calibration instructions and circuit diagrams/descriptions for future
maintenance.
13.6.3 W here the Contractor has used the Special Tools and Test Equipment for installation
and commissioning of the Permanent W orks, he shall refurbish and re-calibrate each
item to the satisfaction of the Employer’s Representative prior to handover to the
Employer, accompanied by the Certificate of Calibration traceable to a recognised
International or National standard.
13.6.4 W here any item of Special Tools and Test Equipment is provided by the Contractor, it
shall be accompanied by drawings, manuals and full operating instructions to enable
them to be used by suitably skilled (but not necessarily specially trained) personnel in
a non-hazardous manner and to achieve the desired result in terms of accuracy and
quality.
13.6.5 The Contractor shall provide the means and instructions which describe the
parameters of each item of Special Tools and Test Equipment that are critical to their
proper methods of use and which enable the Employer's staff using the Special Tools
and Test Equipment to achieve the proper performance and operation. Such means
and instructions shall include, but not be limited to, any routine checking or re-
calibration needs for the Special Tool and Test Equipment itself.
13.7 Coding and Tagging of Spare Parts and Special Tools and Test
Equipment
13.7.1 All Spare Parts and Special Tools and Test Equipment to be delivered to the Employer
shall each carry a tag suitably marked, bar-coded (as directed by the Employer’s
Representative) and numbered.
Page: GS 13-5R of 7
NE Electrical Contracts - General Specification
APPENDIX 9
WORKS AREAS
NOT APPLICABLE
1. Works Areas
(b) Deleted.
(c) Deleted.
(d) Deleted.
(e) Prior to the W orks Area Handover Dates for returning any W orks Area, the
Contractor shall carry out the following works:
(i) construct all Permanent W orks within the area, to the extent defined
in this Appendix, in accordance with the requirements of the Contract,
(ii) reinstate the area to the condition as close as possible to its condition
when it was taken over,
(iii) form the area to the approved lines and levels and carry out such
other works as may be required by the Employer's Representative,
∗ End of Appendix 9 ∗
15.4.1 The Contractor’s offices, sheds, stores, mess rooms, latrines and other
accommodation on the Site shall be maintained in a clean, stable and secure
condition. Living accommodation shall not be provided on the Site unless stated in the
Contract or having been reviewed without objection by the Employer’s Representative.
The Contractor's personnel shall not be allowed to live on the Site.
15.4.2 The Contractor shall provide and maintain all necessary offices, sheds, stores, mess
rooms, latrines and other accommodation and remove the same from the Site on the
Employer’s Taking Over of the Works. These shall be to the satisfaction of the
Employer’s Representative and shall be kept in a clean and sanitary condition. No
structure shall be erected by the Contractor within the Site without the written consent
of the Employer’s Representative and such consent will not relieve the Contractor of
the responsibility of siting temporary structures clear of the Works.
15.4.3 A copy of the plan showing the extent and position of all offices, stores, sheds, etc.
shall be prepared by the Contractor and retained for inspection in the Site office.
15.4.4 Deleted
15.4.5 The Contractor shall not erect or operate canteen and kitchen facilities on the Site
except with the consent of the Employer’s Representative and, where appropriate, the
Relevant Authorities. Any such facilities shall, in particular but without limitation,
conform to all regulations and standards to the extent required by the concerned city
authorities of GNCTD/UP..
15.5.1 Temporary clean drinking water, wash room with water, electricity, telephone,
emergency transportation (Passenger vehicle) sewerage and drainage facilities shall
be provided for the Employer’s Representative’s accommodation and for the
Contractor’s use in carrying out the Works. The Contractor shall make all
arrangements with and obtain the necessary approvals from the Relevant Authorities
for the facilities.
15.5.2 If, under the Contract, the Contractor is provided with Site utilities and access by any
Other Contractor under the attendance of the same or another Other Contractor, the
Contractor shall ensure that all requirements in terms of use of such facilities, their
upkeep and maintenance, etc. are properly observed. If the facilities provided under
such attendance are insufficient for the Contractor’s bona fide needs, the Contractor
shall be solely responsible for providing such additional facilities he may require for the
execution of the Works.
15.5.3 Access roads and parking areas shall be provided within the Site as required and shall
be maintained in a clean, passable and stable condition.
15.6.2 The accommodation for Employer’s Representative shall include furniture, fan, air
conditioner, drinking water facilities and suitable communication facilities.
Page: GS 15-2R of 5
Contract NE-01-Introduction & Project Overview
Revenue
Sr.
Section Operating Dates
No.
(ROD)
1. Sector 71 Sector 137
2. Sector 142 Sector 149 Refer Appendix I
3. Knowledge Park II Depot Station of FOT
4 Greater Noida Rolling Stock Depot
However, the alignment of above Corridors, number of stations and ROD may change
during design and construction stage.
In the event of a conflict between this Specification and any other standards or
specification quoted herein, the requirements of this Specification shall prevail.
The order of precedence, with item a) having the highest priority, is:
a) Particular Specification
b) General Specification
c) Indian Railway Standards
d) Indian Standards
e) International Standards referenced herein.
f) Other International Standards
g) Other National Standards.
Taking into account the technical and other data contained in the Bid document, the Bidder
shall verify the ratings, quantities of equipment etc as specified herein and if the Bidder
considers any additional equipment, equipment of higher capacities and higher ratings for the
systems and sub-systems or any other additions necessary for the complete, safe and reliable
operable power supply system, he shall include such
1. General
A general description of the broad scope of work, relating to works covered in this
Tender, is given below. It shall, however, be clearly understood that the description is
for the purpose of general guidance only and is not exclusive. For complete
appreciation of the Scope, the Specifications, Drawings and other relevant
paragraphs of the Tender documents shall be referred to.
Chapter 2 Page 3 R of 11
2. SCOPE
2.1. General
In general, NE-01 Contractor is responsible for all works relating to Traction
Overhead Equipment, 33 kV Power Distribution Network, Auxiliary Substations and
SCADA in the various Corridors, except for certain items of work which are
specifically excluded from the NE-01 Contractor’s Scope and which would be carried
out by other Contractors/Agencies.
2.2.1.2 Depots
In addition, supply and erection of OHE in the following Metro Car Maintenance
Depot (generally referred to as ‘Depots’), shall also be within the scope of NE-01
Contract.
a) Greater Noida Rolling Stock Depot
Chapter 2 Page 4 R of 11
2.2.2 Switching Stations
2. 2. 2 .2
Tentatively, the Switching Stations are located near the following Stations,
in various Corridors.
Sw itching Stations
Sr.
Name of Corridor
No. FP SP SSP SS Total
1 1 6 3 13
Noida- Greater Noida
2.2.3 .1
All works, including civil and general electrical works relating to AMS Room and
33 kV Switchgear and auxiliaries, in the Auxiliary Main Substations in the RSS
premises, are within the RSS Contractor’s scope of work. However, supply and
erection of 33 kV cables from the outgoing 33 kV Switchgear panels in the AMS
Room to the 33 kV Switchgear panels in the designated ASS in the relevant
corridor, is within the NE-01 Contractor’s Scope of Work.
Chapter 2 Page 5 R of 11
2.2.4 Auxiliary Substations (ASS)
2.2.4 .1 The fo llo win g works shall form p art of this Tender:
Design, Supply, erection, testing and commissioning of all equipments at all
Elevated ASS’s, including, but not limited to,
- 33 kV / 415 V transformers
- 33 kV Switchgear
- 33 kV and Control Cables
- 33 kV Cables inside the ASS
- All control cables required for ASS
- All LT cables reuqired for interconnection of equipments etc in the ASS
(excluding those required for connection from 415V side of Auxiliary
Transformer)
- All measuring and protective devices
- Batteries and battery chargers
- Cable paths and earthing
- Safety equipment and
all other items required for successful and satisfactory working of the ASS, at all
ASS’s.
2.2.4 .2 Tentatively , the following lis t sho ws the number o f A SS’s in the
Noida-Greate r Noida Corridors
Sr. ASS’s
Remarks
No. Name of Corridor Elevated Underground
1 Noida- Greater Noida 21 Nil
(At Elevated stations, there is one ASS at every station which has two loops)
The Control and Monitoring System covered under this Bid, is required to supervise,
control and acquire the various specified data from the ‘Controlled
Chapter 2 Page 6 R of 11
3. DOCUMENTS AND MANUALS
The contractor shall have to supply, in his own language and in English language, all
the following drawings and documents according to the time table defined below
which may be modified according to the contractual planning of the equipment
supply.
Under no circumstance may the various detail modifications required for perfecting of
the installations and requested within 1 month after supply of the drawings entitle the
manufacturer to delay the delivery or to ask for a price increase of his supply.
For the whole equipment of the OCC room, a detailed study defining:
- the layout of the part of the room under its responsibility
- the dimensions, colours and perspectives views of the console
- The appearance of the mimic panel with the monitoring devices
- The dimensions of the desk.
Chapter 2 Page 8 R of 11
4. SUMMARY
The work to be performed on the Noida-Greater Noida Corridors shall include but not
be limited to:
- Design, Supply, installation, testing and commissioning of 25kV flexible AC
Over Head Electrification System and approx. 100 meter ROCS on viaduct
and in the Depot;
- Design, Supply, installation, testing and commissioning of 25 kV OHE in
Ramps for smooth transition from Depot to Elevated Section and vice-versa.
- Design, Supply, installation, testing and commissioning of Switching Stations,
for supply of traction power to rolling stock with necessary protection of the
line and the depot;
- Design, Supply and installation of a duplicate 25 kV feeder from TSS to Feed
FP’s in Elevated Sections,
- Design, Supply and installation of a duplicate 33 kV Auxiliary Power Network
- Supply, installation, testing and commissioning of 33kV/415-Volt Auxiliary
Substation.
- Design, Supply, installation, testing and commissioning of Control &
Monitoring for traction and auxiliary power supply, and necessary interface
with OCC (Operation Control Centre);
- Provision of track bonding and earthing system including BEC;
- Provision of all the construction drawings, documents, and as-built drawings
required to supply, install, test and commission the above installations.
- Supply of spare parts, tools and equipment for Traction Electrification, Power
Supply, C&M Systems;
- Deal and resolve in co-ordination with the employer/Employer’s Engineer the
Interface with other Contractors to ensure timely completion of the Works;
- Ensure Technology Transfer and Training to Employer’s staff.
Chapter 2 Page 11 R of 11
Contract NE-01– Particular Specification – Interfaces
10. Cable dropping from via-duct NE-01 will provide drawings. Provide opening in viaduct.
to ground for 25 and 33kV 1.
cables traction return C&M
cables and LT cables, at
Feeding Posts or other
locations
NE-01 will lay the cables from the ASS MDB (provided by the
Station E&M), provide the necessary luminaires and control gear.
13. Approx. 100 metre ROCS NE-01contractor will prepare list of segments requiring Will arrange to strengthen the A list of segments on which
strengthening, to receive ROCS masts, anchors etc. based on concerned segments and provide ROCS masts/anchors are
available track plans. NE-01 Contractor will verify at site. If holding down bolts (as per drg required to be placed, in
there are any changes in the track layout plans, NE-01 provided by the DDC). accordance with the Layout
Contractor will interface with viaduct contractor to further Plans, will be issued to the
add segments to the list (wherever segments are not cast) or successful bidder, along with
modify ROCS design etc. to suit available strengthened the Layout Plans. The
segments. Contractor shall thereupon
interface with the Viaduct
Contractor to assess the status
of casting/erection of segments
and take appropriate action to
ensure compatibility
Chapter 3 Page 14 R of 42
Table 6.3
Interfacing with E & M Contractors in Stations (E&M)
Chapter 3 Page20 R of 42
Table 8.3
Interfacing with E & M Contractors in Depots (EMD)
4. Connection of Return NE-01 will prepare typical connection Will supply and install impedance This corridor will be installed with
Conductor to rail, drawings showing connection between RC bonds and make connection of the axle counter. Track circuit will not
through impedance and Rail through Impedance Bond. NE-01 cable to Impedance Bond. be used. So the impedance bond
Bonds. will supply and install cables and connect and return conductor connection
them to RC side. not required.
Chapter 3 Page31 R of 42
Signalling cable details NE-01 will 'model' the signalling cables Will furnish to NE-01 specifications
for Electromagnetic suitably for EMC study. The NE-01 and of signalling cables and their
Compatibility (EMC) NS01 Contractors shall perform a joint locations.
study and develop the EMC Management
5. Plans using such data as the emission
characteristics susceptibility levels, filter
characteristics , physical layout and
construction of their equipment taking
into consideration variation in component
characteristics with frequencies. The study
shall demonstrate compatibility or
highlight areas.
NE-01 and NS01 contractors shall co-
ordinate for any information concerning
EMI/EMC in the OHE & Other structures
and jointly develop a test plan detailing
how the EMC of OHE and S&T system
will be verified, taking into the
consideration the study conducted.
6 Normal and short circuit DD13B(T) NE-01 will advise to SIG (NS01)
currents levels in the
OHE
7 Location of Track SIG (NS01) will give details to NE-
Circuits 01
8 Bonding and Earthing NE-01 will Design Bonding and Earthing
Plan Plan to suit track-circuiting axle counter
details furnished by SIG (NS01)
Chapter 3 Page31A of 42
9 Rail Continuity Bonds NE-01 will provide Rail continuity bonds, If required, the continuity bonds ,
according to finalised bonding plan and in NE-01 contractor will provide and
co-ordination with SIG (NS01). install the rail continuity bonds.
10 Impedance Bonds & NE-01 will provide TCPMM for earth SIG will supply and install This corridor will be installed with
TCPMM continuity. Impedance bonds at finalised axle counter , Track circuit will not
locations. be used , so the impedance bond
and return conductor connection
not required .
11 Cross Bonds NE-01 will provide cross bonds, according to
finalised bonding plan and in co-ordination
with SIG (NS01).
12 Insulated Rail Joints SIG will provide details regarding NS-01 contractor doesn’t require
locations of insulated rail joints on the insulated Rails joints. If
the required NE-01 contractor will
main line and in the Depot/yard. provide and install the rail
continuity bonds.
13 Signal Locations SIG (NS01) will provide chainages
of signal posts, to NE-01
14 OHE mast locations NE-01 will provide Layout Plans of OHE SIG (NS01) will ensure that signals
showing mast locations, wire staggers etc, to are mounted in locations where they
SIG. are not hidden by OHE masts or
other hardware
15 Electrical Clearances NE-01 will provide Layout Plans of OHE to SIG (NS01) shall coordinate with
SIG (NS01). NE-01 to ensure minimum safe
clearances between any signalling
field installation and the live OHE
part.
Chapter 3 Page32 R of 42
16 Power Supply NE-01 will advise to SIG (NS01) the SIG (NS01) will ensure Train
Protection System and protection relay settings. Control and Signalling systems
trip settings are designed suitably.
17 CBTC NE-01 will interact with the Signalling SIG (NS01) will advised NE-01 ,
Contractor and will advise NE-01 of the details of the CBTC system
special steps, if any, required to be taken proposed to be adopted in Line8
by the NE-01 and also list out special steps, if
any, required to be taken on the
Power side.
Chapter 3 Page32A of 42
Table 11.2
Interfacing Requirement with Telecom Contractor (TEL)
Chapter 3 Page34 R of 42
4. Laying of C&M Supply and install Control and Provide space (approx 10cm2) in the S&T
cables Monitoring ( C&M ) cables in the cable supports
S&T cable trough between each
traction switching station and the
nearest Station Control Room
5. SCADA NE-01 will advise section wise E 1 Will provide Ethernet channels ( normally 2 NE-01 contractor is required to
requirements or LAN channel SCADA Mbps) from TER of station to TER of OCC. interface TEL contractor for
requirements to TEL channel allocations.
6. Furniture at OCC NE-01 will provide the Desk and ____ ____
Chairs for the operators.
7. Electromagnetic NE-01 will give details of the TEL will coordinate jointly with NE-01 to Traction & Telecom contractor
Compatibility EMC study carried out by ensure compatibility. shall jointly develop a plan
NE-01 detailing how EMC of OHE
traction system and Telecom
system will be taken care of ,
taking into consideration the
study conducted.
Chapter 3 Page35 R of 42
8. Traction The Traction Contractor shall
Currents advise the S&T Contractor of
the normal and worst case short
circuit current levels which
need to be taken in to account
by Telecommunication
Contractors in their design to
take care of EMI/EMC affects.
9. Earthing The Traction & Telecom
Contractors shall interface and
coordinate for connection of the
Telecom field equipments on the
via-duct and on the platform to
the Buried Earth Conductor
/Earth Conductor. The
Connecting jumper cable for
this shall be provided and
installed by the Telecom
contractor.
10. Physical The Traction & Telecom
Interface contractors shall coordinate for
ensuring the minimum safe
distance between any
Telecommunication
field/platform installation and
the live OHE contact point for
the purpose of human safety
apart from EMC/EMI
consideration.
Chapter 3 Page35A of 42
Contract NE-01 – Particular Specification – Definition and Lists
Chapter 7 Page 7 R of 36
Contract NE-01 – Particular Specification – Definition and Lists
72 NE-01-T-OH-TYPI-1033-0 Typical Drawing Showing Connection of OPC and BEC to Rail/Connecting Plate
Chapter 7 Page 8 R of 36
Contract NE-01 – Particular Specification – Definition and Lists
80 NE-01-T-OH-TYPI-1041-0 Typical Drawing Showing Earthing and Bonding for Switching devices on Masts
SCADA DRAWINGS
INTERFACE DRAWINGS
87 NE-01-T-IN-OHPS-1001-0 General Arrangement of Suspension of OHE/OPC/RC from Platform Shed Roof Trusses
General Arrangement of OHE Masts on Parapets
88 NE-01-T-IN-OHPS-1002-0
Chapter 7 Page 9 R of 36
Contract NE-01 – Particular Specification – Definition and Lists
94 NE-01-T-IN-OHPS-1008-0 Typical Drawing Showing Earthing Arrangements for Metallic Masses at Stations
Chapter 7 Page 10 R of 36
Contract NE-01 – Particular Specification – Definition and Lists
4.1 GENERAL
The following list indicates the description and quantities of requirement of
Spare parts, to be supplied by the Contractor. The Contractor shall deliver
these spare parts, at the same time as of handing over the first lot of erected
equipment , if not earlier in phased manner.
Traction Equipments (25 kV)
S.No. Description Unit Quantities
1 25 kV Manually Operated Isolator Nos 1 2
2 25 kV Circuit Breaker Nos 1 2
3 25 kV Interrupter Nos 1 2
4 Spare Components of 25 kV Interrupter
4.1 Control Card Set Nos 3
4.2 L- pad Nos 3
4.3 Connector Nos 10
4.4 Panel Locks Nos 10
4.5 Castell Lock Set Nos 10
4.6 Set of Indication Lamp Nos 5
5 Spare Components of 25 kV Isolator
5.1 Earthing heel Nos 2
5.2 Male & Female contact set Nos 4
5.3 Bimetallic Strip Nos 20
6 25 kV Voltage transformer (Line indication Type Nos 2
30MVA 30VA)
SCADA
Note: Additional list of Spares of OHE, PSI and SCADA is also mentioned in Chapter
13 along with above mentioned spare list.
NOTE:
1.Total cost of the above mentioned spares have to be quoted in cost centre MC- spares
(Sub –Clause MC-1)
2. All the above mentioned spares shall be available with the contractor before
commitioning (ie Key Date –KD-11)
Chapter 7 Page 23 R of 36
Contract NE-01 – Particular Specification – Definition and Lists
Spares Management is to be linked with ‘product Life Cycle’ (PLC). Contractor will be
able to supply spares as per various stages of PLC. The optimum support to product
will be available and spares management is to be matched with manufacture’s phasing
out and obsolescence policy.
I. Current
II. Active
III. Mature
IV. Limited
II. Active :- In this stage of PLC, the supplied product has passed a sufficient
duration in market. Comprehensive support to the product in terms of spares
availability and their manufacturing should be available.
III. Mature:- At this stage, a product of better technology has been developed which
is gradually replacing the supplied product. The manufacturer will classify which
spares are covered under this stage of PLC. At this stage the spares will be
classified as follows:
a) Usual spares ie. Which of those of the spares which were available in
“Current” and “Active” stage of PLC are available at this stage.
b) Spares as “Exchange Modular” which are of updated technology and
compatible to components of offered products.
c) Spares required for repairing of selected modules.
During “Mature” stage the product is fully supported with usual spares/
exchange modules/ repairing modules for a sufficient duration before it goes
into the last stage of “PLC” ie. “Limited Stage”.
Chapter 7 Page 24 R of 36
Contract NE-01 – Particular Specification – Definition and Lists
IV. Limited:- Here the new product has covered the market to a great extent. The
product supplied by the manufacturer is approaching obsolescence stage. At this stage
spares will be classified as follows:
In view of the above , it is required to know that the product being offered
/being supplied is in which stage of Product Life Cycle which will govern the
requirement of spares. Accordingly, following uniform policy for spares is to
be followed.
Note:
1. If any additional spares, from the ones mentioned above are required during
the DLP/AMC period the same will be arranged by the contractor, without any
Extra Payments.
2. For spares/ tools & plants required during DLP/AMC, (mentioned in Ch-13, Vol-
4), nothing extra shall be paid separately to the contractor. The list given in ch-
13 is not exhaustive & contractor shall arrange to keep spares as per actual
requirement.
3. The requirement given above is indicative and minimum in nature (for guidance
purpose only). Prior approval of Engineer-in-Charge will have to be taken
before supply of spares, Tools & Test Equipment along with details regarding
the make & model no. of items specified above.
Chapter 7 Page 25 R of 36
Contract NE-01 – Particular Specification – Definition and Lists
6.1 GENERAL
I. CONSUMABLE SPARES
(i) The ‘consumable spares’ shall include items such as
lubricants, oils, greases, sealants, filter Medias, gaskets, lamps
and wearable parts etc. whose declared life is less than one
year. This will not include the consumables like Diesel Salt etc.
required for operation of the equipment.
(ii) The Tenderer shall provide a recommended unpriced list of
‘consumable’ spares in Annexure-1 as noted above for
maintenance and repairs of equipment in technical package.
Any consumable item if required but not included in the above
recommended list by the tenderer will be deemed to have been
included and shall be supplied as per the provisions of this
contract without any extra financial implication to the Employer.
Contractor will be required to supply the requisite quantity of
spares, as required irrespective of the quantities indicated by the
contractor in the recommended list. Employer’s decision in
determining any particular item(s) as consumable in line with
above guideline will be final and binding. In case any changes
are required in the supply of consumables on account of
changes at design stage, the contractor shall have to supply the
required consumables also.
(iii) List of consumable spares furnished in the technical package
shall be updated during the execution of Contract and following
information as minimum shall be provided.
(a) Names, addresses, telephone numbers and other
particulars of manufacturers and their local representatives;
(b) Modules and Part Numbers
(c) Full description of spares including a note whether it is
sealed unit or an assembly or sub-assembly which can be
broken down into component parts;
(d) Quantity installed in the system;
(e) Expected consumption rates;
(f) Overall dimensions and weight including minimum packing
(if any) for shelf space purposes;
Chapter 7 Page 26 R of 36
Contract NE-01 – Particular Specification – Definition and Lists
Chapter 7 Page 27 R of 36
Contract NE-01 – Particular Specification – Definition and Lists
(iii) The Contractor shall generally not be entitled to use any of the
Employer's spare parts during the installation, erection and
commissioning periods or during the Defects Liability Period.
(iv) Contractor shall not be permitted to remove any working/healthy
equipment / components / sub-systems / systems for any reason
whatsoever without specific approval in writing from DMRC’s
Engineer or Engineer’s authorised representative.
(v) Spares as per the agreed list shall be supplied atleast three
months before ROD. Stocks of such spares as available in
Contractor stores will be jointly checked with Engineer every
three months. Certificate by Engineer confirming availability of
the spares in contractor stores / in Depots as per agreed list will
be a pre-requisite for release of interim payments of the
Contractor. However, this condition will not be applicable for six
months before the expected expiry of the DLP period.
(vi) The Contractor shall include the price of this item in cost of DLP
in their financial bid. This will be part of tender evaluation while
assessing the L-1 bidder.
IV. Mandatory spares
(i) The Contractor shall supply the Mandatory Spares as listed in
the Annexure-3 of this Chapter of Employer’s Requirements.
The Spares shall be supplied at the location nominated by the
Engineer. The price of these spares shall be quoted at actual
and will also be part of the evaluation for assessing L-1 bidder.
(ii) No change in quoted price of any spare will be allowed even
when there is change in design of any equipment/sub-system
during the execution of the contract.
(iii) Contractor will furnish complete details during contract execution
(detailed design stage) as noted below for the listed spares;
(a) Names, addresses, telephone numbers and other
particulars of manufacturers and their local representatives;
(b) Models and part numbers
(c) Full description of spares including a note whether it is
sealed unit or an assembly or sub-assembly, which can be
broken down into component parts;
(d) Quantity installed in the system;
(e) Overall dimensions and weight including minimum packing
(if any) for shelf space purposes;
(f) Designed and shelf life;
Chapter 7 Page 28 R of 36
Contract NE-01 – Particular Specification – Definition and Lists
Chapter 7 Page 29 R of 36
Contract NE-01 – Particular Specification – Definition and Lists
Chapter 7 Page 30 R of 36
Contract NE-01 – Particular Specification – Definition and Lists
Chapter 7 Page 31 R of 36
Contract NE-01 – Particular Specification – Definition and Lists
6.4 The relevant list of the spares mentioned above shall be submitted in the
technical bids after blanking the prices, where applicable. The financial bid
shall have the price details.
6.5 Contractor shall submit technical specifications of the items used in this
project for the purpose of purchasing. Engineer’s views, if any, shall be
suitably incorporated.
Annexure-1
Total
Chapter 7 Page 32 R of 36
Contract NE-01 – Particular Specification – Definition and Lists
Annexure-2
Unit Exchange Spares
Total
Chapter 7 Page 33 R of 36
Contract NE-01 – Particular Specification – Definition and Lists
Annexure-3
Mandatory Spares
Unit Price Total Amount
S.No
Item Quantity Foreign Foreign
. INR INR
Currency Currency
1
2
3
4
5
6
7
8
9
10
Total
Chapter 7 Page34 R of 36
Contract NE-01 – Particular Specification – Definition and Lists
Annexure-4
Chapter 7 Page 35 R of 36
Contract NE-01 – Particular Specification – Definition and Lists
Annexure-5
Chapter 7 Page36 R of 36
Contract NE-01– Particular Specification – Civil Works at Power Supply
Installations
4. ALONG VIADUCT
4.1 GENERAL
The NE-01Contractor may be required to carry out certain works, which are more in
the nature of civil works, along the Viaduct. For this purpose, he will maintain
suitable interface with the Viaduct Contractor. The indicative list of such works is as
follows:
• Buried Earth Conductor (BEC) shall be connected to the girders by means of
flexible copper Al/ACSR conductors cables, the connection being
established to the terminal/s provided on the girder.
• At Integral Transverse Link (ITL), it will be necessary to lay adequate number
of Ø60mm HDPE pipes to carry the cables required for establishing the
connection
• Power sockets (16A) will require to be provided along the Viaduct, on one
side only, at an approximate spacing of 50m.
Sockets shall be placed every 25 50 meters. They shall be 16 A rated current with 5
pins/ 3 phases plus neutral plus earth. They shall ensure a protection of IP 65. Not
more than 2 sockets will be operated in one circuit at any time. That is to say, the
cable should be designed for carrying a continuous rated current of 32A, after
considering the derating factors as applicable.
The cable along the via duct should be of the same cross section( min. 25 sq. mm.)
throughout.
Chapter 8 Page 6 R of 9
5. AT AUXILIARY SUBSTATIONS (ASS)
5.1 GENERAL
The ASS rooms at stations are constructed by the Station Building Contractor (SBC).
The SBC shall complete the ASS room including the final finished floor. The NE-
01Contractor will have to do the following Civil works :
Chapter 8 Page 8 R of 9
Contract NE-01-Preliminary Design and Simulation
1. The key design criteria that the Contractor shall adhere to are addressed in the following paragraphs.
It should be noted that any design criterion is subject to change, subsequent to review, in the interest of
enhancing the System-wide performance, cost and safety. The Contractor/Designer shall ensure that
the designs proposed are similar and compatible to the design already adopted for DMRC Projects.
0
(1) Temperature Minimum Temperature (ambient) (-)0.6 C
0
Maximum design temperature (ambient) 50 C
0
Mean temperature adopted 35 C
(2) Rainfall Rains occur generally during
monsoon from June to September
and occasional showers in December
and January are also experienced.
(5) Thunder storm The region is subject to thunder during April to June.
Isoceraunic level of average 30 thunderstorms per year as
per IS 2309 may be considered.
(6) Nature of atmosphere The pollution content as recorded during year 2004 and 2005
in Delhi at a busy intersection is as under.
SPM 1651μg/m3
SO2 14 μg/m3
NO2 115 μg/m3
RSPM 507 μg/m3
The expected pollution levels in future are likely to be higher than these figures. The
atmospheric conditions described above are for estimation. Designer/Contractor shall obtain
the relevant details of NOIDA for the design. The pollution level in this contract will be treated
as extreme polluted conditions. The equipment and their technical characteristics shall be
selected which are suitable for extreme polluted conditions in India(Eg. creepage distance of
2
1600 mm in case of insulator and mass of zinc coating of 1000g/m in case of galvanized
masts/steel parts. Portals. For zinc coating of SPS first priority will be 1000gm/m , but
2
Chapter 9A Page 6 R of 40
1) Normal system voltage - 33 kV
2) Maximum system voltage - 36 kV
3) Minimum voltage under normal - 33kV-5%
feeding
4) Minimum voltage under loss of - 33 kV-10%
any one supply
The approved SOD will be made available . Any changes in the approved SOD will also be
communicated time to time.
Flexible Catenary comprising contact wire (107 sq mm) and catenary (65 sqmm) shall be utilised with
OHE system on the elevated sections. However, tramway type OHE may be used in the depot area.
Provision of sliding type rigid OHE may be explored for use in depot inspection lines to facilitate crane
working for maintenance of air conditioners/roof equipment of the train sets.
2.1.2 Stagger
Spans and staggers shall be carefully arranged to ensure that the contact wire will never be displaced
by more than 200 mm on straight track and 300 mm on curve from the center-line of the pantograph at
any point in-span, under the worst operating conditions of the OHE System, the rolling stock and the
pantograph.
In calculating the maximum displacement of the contact wire for the stagger, the following shall be taken
into account:
• Temperature effect (i.e. the effect of stagger change due to temperature variation);
• Static and dynamic effect of track tolerances (if they are not included in pantograph
sway); and
• Erection tolerance.
The standard OHE spans adopted in Indian railway is from 27 meter to 54 meter
Chapter 9A Page 8 R of 40
(upto 67.5 depending upon the wind speed ) as per latest guidelines of RDSO .Generally in
steps of 4.5 m. Span length shall be suitably designed based on the practices followed on the
corridors of Phase-I, II, III Project.
Designer/Contractor shall proposes suitable economic design of OHE masts. Tubular masts
will be preferred on aesthetic considerations.
The Contact and catenary tension shall be 1000 Kg. The tension length and the mid point
anchor shall be so arranged that the tension loss in each half of the tension section should be
less than ±10% (contact wire) and ±12% (catenary wire) of the nominal working tension. The
tension lengths shall normally be limited to 1,500m 1120m. Individual tension lengths shall be
designed for crossovers wherever possible. Spring Type/Pulley type ATDs (standardized
design) shall be used for mainlines. Five pulleys type ATDs can be used in Depot areas.
The auto-tensioned simple overhead line system shall be such that the nominal height of the
contact wire at mid-span is lower than that at the supports to improve the current collection
quality. The amount of this pre-sag on a straight track shall be decided based on system
calculations or experimental data. On a curved track, it shall be increased to compensate for
the cant.
The maximum permissible contact wire sag, which is the difference in height between the
supports and the lowest point in the span, shall be 100mm.
The height of the contact wire above the rail level shall normally be the same at each support.
If, due to local conditions (such as the transition between main line and depot), a variation in
height is necessary, this shall be achieved with as small a gradient as practicable.
The maximum permissible gradients of the contact wire above the rail level shall not exceed
3mm/m on main lines and 10 mm/m on sidings. The relative gradient of the contact wire in
two adjacent spans shall not be greater than 1.5 mm/m on main lines and 5mm/m on sidings.
2.1.8 Clearances
The minimum electrical and mechanical clearances shown in Table shall not be infringed
under the worst operating conditions of the overhead line equipment, the rolling stock and
pantograph. The values in the right column shall be used only where it is absolutely
necessary and prior approval of Engineer as obtained upon review in each case.
Chapter 9A Page 9 R of 40
• Normally, the interlock between isolators to isolators, isolator to circuit breaker & circuit breaker
to circuit breaker shall be designed depending upon the safety and operational requirements.
33kV Cable feeders shall be provided for auxiliary power transmission from RSS to various Stations,
25kV and traction return cables will be required for feeding traction power from RSS to OHE.
There would be requirement of 415V LT Cables, Control Cables and Communication Cable in the
Project.
The cabling System shall meet the requirements of IEC and IS standards. Flame retardant low smoke
zero halogen (FRLSOH) and low smoke zero halogen (FRLS) type cables shall be proposed with XLPE
insulation and metallic sheath/ armouring as applicable for underground and elevated sections
respectively. A colour code scheme shall be used for different cables for easy of identifications.33 kV
cables for auxiliary power supply are laid in cable troughs cable brackets/ hangers on viaduct.
33 kV cables are proposed to be laid on cable brackets/ hangers on the parapet walls of viaduct.
Contractor shall be required to design the cable laying arrangement of viaduct and accordingly suggest
and interface with civil contractor. The specifications of 33kV cables to be designed accordingly keeping
into consideration of outdoor atmospheric conditions including UV rays.
The Contractor shall prepare design, technical and performance specifications for the supervisory
control and data acquisition system monitoring, Control and tele-metering of the entire Power Supply &
Traction system.
The SCADA system shall be essentially based on the power management system of master station or a
central terminal unit (CTU) installed at the operation control center (OCC) and back-up control center
(BCC) and many remote terminal units (RTU) scattered along the railway line and connected to the CTU
through line and MODEM.
The basic functions of SCADA system shall be the switching operation of the equipment at the RSS cum
Traction Sub Station (TSS) as well as auxiliary power supply stations (ASS) and switching stations e.g.
FP/SSP/SP (controlled stations) to monitor the status of equipment and to collect, store and analyze
information and data relating to traction and auxiliary power supply. The system shall monitor, record,
perform the reporting of network control and exercise the management functions of measurements &
statistical data.
The proposed SCADA system for this Corridors shall be compatible and matching with the DMRC
network system of those particular corridors in respect of speed, protocol, control & monitoring
Philosophy etc. DESIGNER shall propose an optimum solution where existing SCADA servers can be
used with addition of RTUs.
The SCADA system is to be designed in such a manner it gets integrated with existing system of DMRC
. SCADA system architecture should be based on latest technology so that it should enhance response
time, fault detection of panel and building control for restoration of system with minimal human interface.
Chapter 9A Page 15 R of 40
It should be able to calculate the amount of regenerative braking Power and energy generated by trains and the
portion of it utilized by the others trains, system and its variation w.r.t. delay in starting of train and headway of
trains, separately for UP line and DN line and also for the different sections under different Receiving sub
stations.Simulation to be carried out for different headway and time of starting of train services and train
composition in a particular corridor, to ascertain the amount of regenerative braking power and energy generated
in the system and also utilized, to reach to state of "Optimum Energy Consumption Mode" of the system.
The idea is to operate trains in a scenario where all the regenerative braking energy generated by trains is
consumed within the system by other trains and a minimum input energy is required.
Study and calculation methods and control mechanism are to be developed to achieve the above state of
“Optimum Energy Consumption Mode".
DESIGNER is required to develop the above described “Mathematical Model / Program” by using the software or
by using the results of simulation study.
The power supply arrangement proposed would give due consideration to power reliability. The scope of
DESIGNER in interacting with power supply authority is limited to technical aspects and legal/tariff negotiations
are not in his scope.
(b) Preparation of pegging plans and furnishing detailed OHE plans and cross section plans.
Based on the track plans and layout plans of stations and other structures, DESIGNER shall prepare OHE
layout plans for main line & depot, on format already adopted in phase-I,II and III. The OHE layout plans shall
be submitted as soon as sectioning diagrams are approved by Employer’s Representative. Cross section
drawings will be prepared for adequate number of typical cases (say 40 or 50), which will cover all individual
locations. DESIGNER shall, covers all locations and the location km number (mast number) is clearly marked
on the typical cross section drawings. It should also be ensured that no location is left uncovered.
DESIGNER will suitably interface with the designers/contractors of the Civil, structural, architectural, E&M,
VAC, S&T, RSS, etc and provide and collect all details as are necessary, so that all the interface issues are in
the designs and drawings are addressed.
3 Task 2
Study as per standards already adopted over in Phase-I ,II & III for limiting the induction effect to the adjoining
telecommunication circuits residential and commercial areas and recommend the design, requirement, capacity
and spacing the Booster Transformers (BT) (if required), and arrangement of return conductor and its connection
to traction rails and current flow back to substation.
DMRC is contemplating to go for reduced size RC provision in N-GN Systems without Booster Transformer.
However BT with 240 sq. mm RC will be provided between Knowledge Park II to Delta-1 Station (approx 4
km section) of Noida-Greater Noida Corridor. The details regarding the telecom cables, other cables,
telephone exchange etc. in a 200m wide corridor along the alignment, shall be obtained by DESIGNER with the
help of DMRC. Based on these and other input details, the electromagnetic compatibility study will be performed
by DESIGNER, and the requirements, sizing and specification of booster transformers and return conductors and
other details will be finalized. While doing this study, the requirements of BT, RC etc already finalized in Phase-I
and II may be used as an input data. Full and complete explanation will be submitted by DESIGNER along with
the results of EMC study. The NE01 contractor will clarify the requirement of BT based on the study report.
Chapter 9A Page 22 R of 40
DESIGNER shall update the register as required. All drawings shall be checked for compliance with design
specifications and for accuracy by the DESIGNER’s design staff and shall also be subjected to the checking
procedures as detailed in Section below.
20.6 Documents
Documents shall be prepared by the DESIGNER in accordance with the requirements issued by the
Employer’s Representative. Documents produced by the DESIGNER shall be listed as part of the Progress
Register.
The DESIGNER shall submit details and verification of all computer programs it intends for use to the
Employer’s Representative for acceptance prior to use in making calculations. These shall include the
computer program manuals, input and output printout of a typical example and previous records of its use
by the DESIGNER. The DESIGNER may also be required to perform test calculations using the program so
that the results may be compared with those obtained by other means. The Softwares should have been
used for designing similar type of installations (traction and auxiliary systems) for MRTS systems. The
Designer shall submit the credentials for the software for approval to the Employer.
21.1 General
DESIGNER Note : Document and manuals of Preliminary design for OHE,PSI & SCADA should be
submitted within 2 months of the order and for final design, to be submitted within three & half months of
the order.
shall appoint a Validating Agency for validation of the design submitted by them.Design validation shall
be done as per IEC and other relevant standards.
21.4 Certification
Certificate signed by the Project Manager of the DESIGNER or his accredited representative stating that
all drawings and documents have been checked and approved in accordance with the agreement, shall
accompany all documents and drawings issued by the DESIGNER to the Employer’s Representative for
acceptance.
Chapter 9A Page 35 R of 40
Contract NE- 01 Particular Specification for Traction Network
Name of Type of
Approx.
Sr. No. Switching Switching Remarks
Chainage
Stations Stations
1 Sector 71 SSP -
2 Sector 71 FP
3 Sector 78 SS -
4 Sector 81 SSP -
5 Sector 83 FP -
6 Sector 142 SS -
7 Sector 144 SSP -
8 Sector 147 SP -
9 Sector 153 FP -
10 Sector 149 SSP -
11 Pari Chowk SSP -
12 ALPHA -2 SS -
13 Depot Station SSP -
Note:- FP at Sector 71 has been kept for interlinking with Line-3, in case of
emergency.
Noida Sector 71 to
Depot Station
1 (Noida-Greater Noida NE-01-T-TN-TYPI-1000-0
Corridor)
Chapter 9B Page 5 R of 37
3A. BOOSTER TRANSFORMERS
3A.1 GENERAL
Booster transformers are basically two-winding transformers (1:1 ratio), with the
primary winding connected in series with the OHE and the secondary in series with a
return conductor. Since the primary winding is connected in series with the overhead
equipment, the Booster transformers are subjected to frequent and heavy short
circuits due to transient faults.
3A.2 RATING
The Booster transformers shall have a rating of 150KVA or 280 kVA, as required. The
salient technical requirements are as follows:-
The temperature rise after full load operation followed by overload, shall not exceed
o o
50 c for winding (by resistance method) over an ambient temperature of 45 c.
The Booster transformers may be oil filled type or dry cast resin type.
3A.7 Metal work and Paint-work
Painting should be suitable for salty seaside atmosphere and has to comply with IEC 60 721-2-
5 standard
Then all metal surfaces shall be painted in accordance with the rules of art with three coats of
non-metallic paint of the same quality as that used for outdoor transformers, total thickness
should not be less than 120µm and should withstand 120°C
This protection shall be fully guaranteed for five years starting from provisional taking over.
Should any noticeable deterioration by rust or corrosion appear before this time elapses, the
contractor shall be responsible for repainting at his own expense and for renewing his
guarantee for the work performed.
The painting and preserving of panels for transformer protection should be of similar
standards with that of other control and relay panels provided in the control room.
NOTE: Booster Transformer will be provided only from Knowledge Park-II to Delta 1 Station
(approx. 4km section)
Chapter 9B Page 31 R of 37
The equipment shall be capable of withstanding intensive use without
alteration, and of performing its duty even after extended idle period.
The Cable laying & also for 25 kV cable & 3.3 kV Cable shall be followed as
specified in Clause 5.7 of Chapter 11A – Auxiliary Network.
The entire equipment will be designed for operation in hot weather, according
to the climatic conditions defined in General Specifications.
The equipment will be sturdy and properly treated against corrosion. This
protection shall be suited to the various environmental conditions encountered
in the various parts of the network.
The 3.3 kV cable shall be 191.9/3.3 kV , grade single core, 240 sq mm strandard
copper conductor, XLPE insulated , copper wire screened, tape armouring , PVC
sheathed cables. It shall conform to IEC 60502 Part 1 latest for construction and for
testing. The nominal thickness of insulation for 3.3 kV cables shall not be less than
2.0 mm as per IEC 60502 part 1. Relevant specifications given above for 25 kV cable
shall apply to return cable also.
Chapter 9B Page 34 R of 37
Contract-NE-01: Specification forTraction Overhead Equipment
1.5.1 Temperature
1.5.2 Humidity
1.5.4 Pollution
1.5.5 Earthquake
Zone 5
Chapter 10 Page 11 R of 76
2 BASIC DESIGN CRITERIA
2.1 BASIC PARAMETERS
2.1.1 The Overhead Equipment (OHE) is designed taking into account the following basic
parameters.
: 1 in 9 / 1 in 7
• Types of Points and Crossings
• Curves
a) Minimum radius of curvature on Main line
: 200 m
b) Minimum radius of curvature in
depot/workshop/carshed :
• Gradient
a) Maximum gradient of track on main line :
b) Maximum gradient of track in 3%
depot/workshop/carshed
:
4%
Chapter 10 Page 12 R of 76
2.4 Conductor Tensions
2.4.1 The use of a higher conductor tension of 1000 kgf in the Messenger and contact wire
ensures a better current collection performance. The mechanical interaction between
the contact wire and the pantograph plays an important role in the phenomenon of
current collection. The pantograph exerts an upward pressure on the contact wire,
which tends to hog the contact wire. At the same time, the contact wire tends to sag
by its own unsupported weight and the pre-sag provided. The sag of the contact wire
will depend upon the tension in the contact wire. The net result of this pantograph -
contact wire interaction will play a vital role in the flow of current from the contact wire
to the pantograph. A combination of higher tension in the contact wire and a
specified pre-sag, helps to contribute better current collection at higher design
speeds.
2.5.1 The following table indicates the speed potentials of different ranges of OHE, along
with their possible applicability.
Chapter 10 Page 19 R of 76
Description Fully regulated OHE Unregulated OHE Single
regulated
contact
wire
Mechanical stress 1000 kgf 1000 kgf 1000 kgf at kgf at 35ºC 1000
of cables/wire 35 ºC kgf
Maximum NA 3‰ NA 6‰ 10‰
permissible
gradient of contact
wire
Maximum NA 1.5 ‰ NA 3‰ 5‰
permissible
transition gradient
of Contact Wire
Maximum speed 60 kmph 80 kmph
100kmph
Works for OHE connection to existing facilities in Therefore on such locations one more
cantilever to be provided on the OHE masts and adjustment to be made for getting
clearance of 200 mm between in-run & outrun wires. In addition, OPC & RC wires are to be
extended by splicing and to be anchored on mast.
Chapter 10 Page 20 R of 76
5 Sector 83 FP -
6 Sector 142 SS -
8 Sector 147 SP -
9
Sector 153 FP -
12 ALPHA 2 SS -
The Traction Sectioning Diagrams of the corridor are shown in the list given below.
The single phase traction power from 2 adjacent Substations may have a phase
difference between them. In order to segregate the power supply feeds from
adjacent Substations, Neutral Sections are provided on the flexible OHE in front of
Sectioning Posts. Normally, the OHE on either side of the Neutral Section will not
be bridged.
3.5.1 At locations of Sectioning Posts (SP), Short Neutral Section Assembly shall be
provided, whose general arrangement is shown in DRG. No. NE-01-T-OH-TYPI-
1042-0.
Chapter 10 Page 22 R of 76
ANCHOR INTERMEDIATE AXLE INTERMEDIATE ANCHOR
0.20m
Usual way for
Running Trains
Common Zone
Anchor Raising
Span Span
Fig. 5/4: Reversed un-insulated Overlap by means of 4 spans
5.3.4 The details of arrangements, including values of staggers adopted, are shown in the
Drawing NE-01-T-OH-TYPI-1006-0.
5.4.1 As mentioned earlier, the Messenger wire and contact wire are each given a tension
of 1000kgf. This tension has to be maintained at this value, irrespective of the
variations in the atmospheric temperatures. This is achieved by providing
Automatic Tensioning Devices (ATD), on either end of each tension length. When
the tension length is 560 m or less, ATD could be provided at one end and the
other end of the tension length could be fixed without an ATD. This will be termed
as a half-tension-length and is provided depending upon the exigencies in the
layout of OHE. Normally the tension length is varying between 850 m and 1120 m
and ATD's are provided at either end of the tension length. The ATD’s used shall
be either of 5 pulley block type or of spring type. Normally 5 pulley block type ATD
shall be provided on the viaduct & inside the depot. However, at critical location,
where any remote possibility of ATD falling down accidently on the traffic below
the road; Spring type ATD shall be provided. Spring type ATD shall also be
provided on the ramps, where there is limited height available for counterweight
movement. Use of spring type ATD shall be approximately 50% of the total
number of ATDs, used overall in the system. However actual will worked out
during detailed design stage.
5.4.2 The scope will also include temperature marking on the masts.
Chapter 10 Page 31 R of 76
TOHE Termination arrangement
Drg.No. NE-01-T-OH-TYPI-1010-0
Return conductor termination
Drg.No.NE-01-T-OH-TYPI-1011-0-
Arrangement
R-1
GA of Anchor on Parapets
Drg.No.NE-01-T-IN-OHPS-1003-0
GA of Guy rod assembly
Drg.No. NE-01-T-OH-TYPI-1012-0
5.6.3 However, in the case of Reduced Return conductor and OPC, it might also be
possible to anchor the concerned conductor to a mast, designed to take the load
without the use of a guy rod. That is to say, since the normal tensions in the
Return conductor, OPC and anti-creep wires are only of the order of 400 kgf at
35ºC, the structures on which these are anchored, could, if required, be designed
as self-anchoring masts.
5.7.1The location of obligatory structures to support the catenary system of the main line
and that of the turn-out equipment, together with their arrangement on the
cantilevers, is of vital importance. Basically, the arrangement has to ensure.
• That the current collection is smooth and without any sparking, and
Chapter 10 Page 39 R of 76
6.1 Equipment With Head Spans
At stations, return conductor will be laid down in brackets along the platforms in order
to avoid the current problems of short circuit between return conductor and
messenger wire caused by birds. RC shall be taken through super mast at all the
sensitive locations such as at double cantilever assembly, BT’s, BM’s etc.
Return conductor support should be hot dip galvanised as per the RDSO
specification No. ETI/OHE/13(4/84).The galvanization shall not be less than
1000gm/m2. The first priority of galvanization shall not be less than
1000gm/m2, but it may be accepted for SPS as 610 gm/m2 as per
availability at vendor.
In place where BT is not provided the reduced size of RC will be provided in a suitable
clamp at the back side of the mast ie. away from the track on viaduct. In platform the
RC will be suspended in the drop arm provided by civil contractor at station canopy.
Chapter 10 Page 44 R of 76
6.3 Overhead Protection Conductor Supports
At feeding posts, OPC shall be taken through parapet of viaduct. At all switching
posts locations OPC should either be taken on cross arm/super mast away from
track or it should be taken through viaduct.
These are the small part of the steel as per the drawing no. NE-01-T-OH-TYPI-1016-
0(sheet 6/9). This shall be provided in the OHE mast for the provision of multiple
bracket. Normally these items are required at the location of overlap mast, obligatory
structure. Theses should be made of steel and confirm to Bureau of Indian Standard
specification IS: 2062, IS: 800 and IS: 808 all latest versions and it should be hot dip
galvanised as per the RDSO specification No. ETI/OHE/13(4/84).The galvanization
shall not be less than 1000gm/m2. The first priority of galvanization shall not
be less than 1000gm/m2, but it may be accepted for SPS as 610 gm/m2 as
per availability at vendor.
6.5 Arrangement for catenary system/overhead conductors from under the roof
at stations
These are the small part of the steel as per the drawing no. NE-01-T-OH-TYPI-
1004-0 (Sheet-3/3). This is also known as DA in Indian railway. The DA should be
Rolled Steel Joists (RSJ) or Broad Flange Beams (BFB) type. The DA should confirm
to Bureau of Indian Standard specification IS: 2062, IS: 800 and IS: 808 all latest
versions and it should be hot dip galvanised as per the RDSO specification No.
ETI/OHE/13(4/84).The galvanization shall not be less than 1000gm/m2.
Chapter 10 Page 45 R of 76
7 Overhead Catenary System
The contact wire shall be of 150 sq mm 107 sq. mm hard drawn grooved, round
copper conductor, diameter 13.8 12.24 mm. The contact wire should be drawn out of
continuous cast rods of minimum diameter of 21 mm. Contact wire shall conform to
latest RDSO specification ETI/OHE/76(6/97).
OR
The contact wire shall be 150 sq mm flat bottom /107 sq mm round bottom Silver
Bearing Grooved Copper Conductor. Contact wire shall confirm to latest RDSO
specification TI/SPC/OHE/CW(Cu-Ag)0100(07/2010) or specification approved by
DMRC.
The salient features of the contact wire are in Table 1.
Note: Silver bearing copper contact wire should be used in main line as
adjustable price and copper contact wire should be used in depot.
.
The Messenger wire shall be of Cadmium copper, diameter 10.5 mm, consisting of
19 strands, each of 2.1 mm diameter. The nominal cross section of the Messenger
wire is 65 sq. mm. The messenger wire shall conform to Indian Railways' RDSO
specification No. ETI/OHE/50 (Latest Revision)
In stations the messenger wire will be protected with an insulated cover in order to
avoid that birds can touch messenger wire and return cable at the same time.
Chapter 10 Page 46 R of 76
7.3 Return Conductor
BT shall not be provided only from Knowledge Park-II to Delta 1 Station
(approx. 4 km section) in Noida – Greater Noida Corridor. 240 sq. mm
return conductor (All aluminium conductor) shall be provided in BT area.
However reduced size RC shall be provided which shall be 93.3 sq. mm, ACSR
conductor, where BT is not provided.
Reduced size RC will be supported in OHE mast along the track except in stations
where it will be laid down under platform at DA provided by the civil contractor. A
feeding posts and switching posts locations reduced size RC will be taken through
parapet of viaduct by means of super mast/ suitable arrangement .
All aluminium conductor (SPIDER) consisting of 19 strands each of 3.99 mm
diameter with nominal cross section of 240 sq.mm . The overall diameter of RC is
19.95 mm. The SPIDER conductor shall confirm to Bureau of Indian Standard
specification IS: 398 (part-I) latest version.
OPC will be supported in OHE mast along the track except in stations where will be
laid down under platform by means of brackets. At Feeding posts and switching
posts locations OPC will be taken through parapet of viaduct by means of brackets.
Chapter 10 Page 47 R of 76
- 262 sq mm feeder of Electrolytic copper, consisting of 37 strands each of 3.0mm
diameter, with a nominal cross section of 262 sq mm and diameter of 21.0 mm.
Insulated sleeve shall be also provided on Return conductor (240 sq. mm)
under portal location and station area in the section of 4 Km where Booster
transformer to be installed.
Chapter 10 Page 51 R of 76
8.2 A DISC INSULATORS
8.3.1 Section insulators are deployed when it is necessary to electrically separate one
section of the OHE from another. The normal section insulator assembly consists
of a Tensioning Insulator (9 tonne) on the catenary wire and an arrangement
involving copper runners and sectioning insulator on the contact wire. The above
arrangement provides the necessary insulation between adjacent sections of the
OHE.
8.3.2 Section Insulators specially designed to meet the following requirements, are used
on the OHE.
- Light weight
- Less maintenance. The skids do not require frequent checks and adjustments
thereby permitting the Section Insulators to be left unattended for long periods.
8.3.3 The use of section insulator has been restricted to places in Main lines where
insulated overlap assembly is not possible and in sidings and depot lines.
8.4.4 Section Insulator should be used at least 5 years in any metro/railway system
8.4.5 The Contractor should give 5 years warranty for section insulator.
8.4.6 The Section Insulator should meet the RDSO specification
TI/SPC/OHE/LWTSI/0060 or latest versions are proposed to be used.
OR
Any other design which has been used in the past of DMRC may be consider the
8.4.7 JG 2202 (Galland make) or similar light weight section insulator can be
considered for cross-over.
It has to be ensured that old section insulators even in wet condition
perform satisfactory in service. Contractor shall give undertaking for this.
Chapter 10 Page 55 R of 76
uprights. OHE’s relating to intermediate tracks shall be supported by means of
drop-arm attached from underside of such portal. A typical general arrangement of
cantilevers on Drop arm is shown in drawing no.NE-01-T-OH-TYPI-1004-0.
9.2.4 For portal, only factory fabricated galvanised uprights of portal with base plate shall
be erected.
The Portal shall be hot dip galvanized in accordance with Indian Railway’s
RDSO specification ETI/OHE/13(4/84), latest version. The galvanization shall
not be less than 1000gm/m2.
Chapter 10 Page 59 R of 76
defined in terms of maximum permissible pressure which could be withstood by them.
10.4.2 Three types of soil are taken into account
a) Normal Soil
: Maximum permissible pressure is 0.11Mpa to
0.22MPa
10.5.1 Concrete for foundations shall be of nominal mix of grade M-15 obtained by mixing
cement, coarse aggregate, fine aggregate and water in accordance with
proportions given in Table 9 of IS:456-2000.Latest Version.
10.5.2 For grouting, muffing and embedding of structures, in foundations and for cable
trenches at switching stations, nominal mix concrete M-20 shall be used, in
accordance with IS:456-2000. Latest Version.
Concrete Poles shall be grouted with dry sand. The core hole after sand grouting
shall be sealed with a 10cm layer of Bitumen before Muffing is provided to prevent
any ingress of water in to the Core hole.
10.6.1Use of concrete anchor blocks shall be in accordance with Indian Railway's RDSO
drawings and specifications.
Chapter 10 Page 62 R of 76
13A ELECTROMAGNETIC INTERFERENCE
13A.1 GENERAL
13A.2.2 The Booster Transformer’s are mounted on gantries fixed on parapet walls
of the viaduct/ or on ground at grade. A typical general arrangement of
Booster Transformer on viaduct is shown in NE -T-IN-OHPS-1004-0.
13A.3.2 The technical details of the Return Conductor are indicated in Clause 7.3.
* The number and capacity of the transformers are tentative and is subject to
confirmation.
- All other items required for successful and satisfactory working of the ASS,
at all elevated ASS’s shall be within the scope of this Tender.
33 /25 kV, single phase, 2 MVA transformer will be installed in Rolling stock
depot for 25 kV traction power supply inside Depot. Apart from this, 25 kV
supply tapped from main line will also be available at Feeding Post of Depot.
There will be provision of Automatic Switched Neutral Section (ASNS) at
depot entry and exit lines of Depot. This ASNS will be normally kept bridged
by Circuit Breaker. To segregate the fault of Main line & Depot OHE
necessary Circuit Breaker will be provided accordingly. Normally the feed to
the Depot will be through 25 kV OHE which is coming from the Depot station
(last commercial halt station). Only in emergencies 25 kV supply will be
extended to rolling stock depot from 33 /25 kV transformer.
- There shall be two nos ASS in Rolling stock depot at Greater Noida.
The transformer capacity and utility of these are as follows:
The Employer may call upon NE-01 Contractor to provide suitable manning
staff in the ASS’s / AMS already commissioned and handed over to the
Employer, for manning the installations, before commencement of the
Revenue operation of the line. NE-01 Contractor shall provide the necessary
staff team for the purpose. The staff team deployed at the ASS’s / AMS shall
be thoroughly conversant and
i. The Primary Protection for the cable faults between two stations shall be pilot wire
differential protection (87L) which will trip the respective MVCB on either end of the
faulty section of the cable.
Advantages of keeping the pilot wire protection is that it does not require any current
or time grading as it works on the difference of current in the zone between the two
pilot wire relays. NE-01 contractor will supply & install armoured pilot wire cable.
3.4.4.2 The Transformers feeder breakers (i.e. MVCB-1/2) should be provided with the
following protections:
a. Transformer differential protection (87T)(For UG Only)
b. Restricted Earth Fault protection(64NP)(For UG Only)
c. Over Current Protection and Earth Fault Protection (50/51/50N/51N)
d. Mechanical Door Limit Switch (Castle Key Arrangement) (33)
e. Winding Temperature Indicator (49T).
a. The ASS relay timings should be synchronized with the RTUs of the
concerned ASS.
During Defect Liability Period /Annual Maintenance contract, Contractor shall depute dedicated
manpower round the clock in shifts prescribed in Table 1 at designated place
as agreed by employer for attending breakdowns and preventive maintenance activities.
This shall be read in conjunction with Clause 23 (Sub clause 10) of SCC applicable for DLP and AMC
as well.
This excludes the responsibility of the contractor during DLP defined in Tender
Documents.
Table 1
No. of persons to be
S. No. Staff Designation Min. Qualification
deployed
Degree with 5 yrs. Experience of
1 Sr. Engineer 1
similar nature
Degree with 3 years similar Exp./
2 Field Engineer 1 per shift
Diploma with 5 years similar Exp.
3 Skilled 3 per shift ITI with 3yrs. Similar Exp.
4 Un-skilled 2 per shift -
Contractor shall set-up OHE Depot, corresponding stores, repair shops, which includes furniture,
material racks staff cup-boards, tools instruments, material handling instruments, communication
instruments, material consumable etc. in addition to proper upkeep of all the installations and vehicles
in OHE.
Chapter 13 Page 3R of 45
SCOPE OF WORK FOR DLP/AMC of PSI & SCADA
During Defect Liability Period /Annual Maintenance contract, Contractor shall depute dedicated
manpower round the clock in shifts prescribed in Table 1 at designated place as agreed by employer
for attending breakdowns and preventive maintenance activities.
This shall be read in conjunction with Clause 23 (Sub clause 10) of SCC applicable for DLP and AMC
as well.
The following requirement is in addition to the responsibility of the contractor during DLP defined in
Tender Documents.
Table 1
No. of persons to
S. No. Staff Designation Min. Qualification
be deployed
Degree with 5 yrs. Experience of
1 Sr. Engineer 1
similar nature
Degree with 3 years similar Exp./
2 Field Engineer 1 per shift
Diploma with 5 years similar Exp.
3 Skilled 3 per shift ITI with 3yrs. Similar Exp.
4 Un-skilled 1 per shift -
Contractor shall set-up PSI Depot, corresponding stores, repair shops, which includes furniture,
material racks staff cup-boards, tools, instruments, material handling instruments, communication
instruments, material consumable etc. in addition to proper upkeep of all the installations in PSI.
Manpower mentioned above shall be able to perform duties as follows:
a. Duties and Responsibilities of Sr. Engineer (PSI)
Sr. Engineer (PSI) is the field in-charge of all the PSI installations including stores working under him
and directly responsible for the safe and efficient maintenance of Traction as well as Auxiliary power
supply installations at ASS’s including traction switching stations, SCADA installations etc. in his
jurisdiction. He must be thoroughly conversant with all technical details of the equipments under his
charge including their rating, trend of power demand and also correct method of their operation
andmaintenance.
In particular he/she shall responsible: -
1. To supervise the preventive and corrective maintenance of installations under his charge
accordance with the standard and prescribed schedules to keep them fully serviceable all
times and in a state of good repair .To ensure proper record of preventive and corrective
maintenance of installations in his control and submit monthly report to Employer with
completion and next due dates(Equipment wise);
1. Earthquake Sensor
The requirement of Earthquake Censor is to detect even feeble earthquake and
generate an alarm on the OCC. The objective is that the earthquake can be detected
and alarm to be generated on the OCC to take a decision to stop the train operation
resolution 0.05g)
1.2.1 Sensor
Chapter 14 Page 3R of 7
Contract NE-01– Particular Specification – Miscellaneous
Connectivity - Ethernet
The signals of Earthquake sensor should be integrated in OCC through RTU via the SCADA
System. Each Earthquake sensor shall be provided with the necessary auxiliary contacts
and internal wiring to permit remote control and indication.
Chapter 14 Page 4R of 7
C. Milestone Payment Schedule (MPS)
1 The MPS completed by the Contractor shall set out the maximum cumulative amount for all Cost
Centres for all Sections put together in relation to each month for which payment may be sought
in accordance with Sub-Clause 11.4 of the GCC. This information should also be presented in a
tabular form. Monthly Cash Flows for the Contract will form part of the Pricing Document.
2 The MPS covers the period which will commence on the first day of the calendar month next
after the month containing the Commencement Date of the Works as per the Contract. The first
application for interim payment may be made not earlier than during the month following the
calendar month next after the month containing the Commencement Date of the Works, such
first application relating to the first month (i.e. month 1) of the MPS.
3 The price shall not be unbalanced therefore, for the statement-C, the price quoted in the Cost
Center-C (Installation and Site Testing) and Cost Center-D (System Acceptance Tests,
Integrated Testing and Commissioning) shall not be less than 15% and 10% of the price quoted
in the Cost Center-B (Manufacture and Delivery).
D. Tender Total
1 The Tender Total submitted by the Tenderer shall be in the format shown in the Pricing
Document.
2 The Pricing Document contains Sections, Cost Centres under each Section, and Milestones under
each Cost Centre. The Sections, Cost Centres and Milestones have been prepared to indicate the
extent of detail required in the Tender. The Tenderer shall prepare and complete documents, in
this format, as being his Tender and submit as part of the Financial Package.
Items/Milestones against which no rate or sum is entered by the Tenderer, whether quantities
are stated or not, shall be regarded as covered by other rates in the pricing document.
3 The Pricing Document completed and submitted by the Tenderer, as part of his Tender, should
use an indexing and page numbering system such that its extent and completeness is clearly
evident.
E. Currency
1 Section Totals, Cost Centre Totals and Milestone amounts shall be indicated in Indian Rupees
and in a foreign currency as per clause C16.1, wherever required.
F. Milestones
Manning of Commissioned ASS
Contractor to Quote all-inclusive man-day charges
considering 4224 man-days. Any change in the man-
days (above/below 4224 mandays ) shall be adjusted
on pro rata rates quoted.
The staff team deployed at the ASS's shall be thoroughly
conversant and competent to operate the various
switchgear and systems and shall be able to provide
auxiliary power, if so desired by DMRC, to other
Agencies working in the Station area or elsewhere and
also to provide power shut-downs of the commissioned
C1-12 systems, if so directed by DMRC.
A period of 8 hours of deployment of one staff should
be considered as 1 man-day.
The quoted amount shall cover the approval of the
supervisors and replacement as required by the
Employer, employment of approved staff including
salaries, overtime, airfares, lodging allowances, their
office expenditure, telephone/mobile bills, local travel
costs to and from site, training materials, income tax
and other taxes deducted at source.
The contractor shall be responsible for the compliance
of all the labour laws irrespective of rates quoted.
a RTU
b Control and Monitoring Cable, cable paths etc
c Any other item(s) considered necessary to comply with the
Scope of Work
C3-10 Manning of Commissioned ASS
Contractor to Quote all-inclusive man-day charges considering
5940 man-days. Any change in the man-days (above/below
5940 mandays ) shall be adjusted on pro rata rates quoted.
The staff team deployed at the ASS's shall be thoroughly
conversant and competent to operate the various switchgear
and systems and shall be able to provide auxiliary power, if so
desired by DMRC, to other Agencies working in the Station area
or elsewhere and also to provide power shut-downs of the
commissioned systems, if so directed by DMRC.
A period of 8 hours of deployment of one staff should be
considered as 1 man-day.
The quoted amount shall cover the approval of the supervisors
and replacement as required by the Employer, employment of
approved staff including salaries, overtime, airfares, lodging
allowances, their office expenditure, telephone/mobile bills,
local travel costs to and from site, training materials, income tax
and other taxes deducted at source.
The contractor shall be responsible for the compliance of all the
labour laws irrespective of rates quoted.
Statement No. F
Optional Items
NAME OF THE FIRM 0
Note:-
1. Employer may award the Comprehensive AMC to the successful tenderer for 3 years beyond DLP at these rates.
2. The cost of spare parts, T&P required for maintenance during AMC period beyond DLP will be deemed to be inclusive in the
prices for AMC indicated in this Statement . Nothing extra will be paid for such spare parts.
3. This statement will be considered for tender evaluation while assessing the L-1 bidder.
4. Payment for AMC will be made on quarterly basis on completion of maintenance obligations by the Contractor.
5. Scope of maintenance work will be as per details provided in the Scope of Maintenance during DLP and AMC
6. The Contractor to quote prices as per Clause 24 of SCC.
7. Service tax shall be inclusive in the above price
8. Employer reserves the right to enter into a separate Comprehensive AMC contract for further 5 Years, beyond 3 Years
Comprehensive AMC , considering the Price quoted for "3rd Year" above as Po subject to Escalation / Price Adjustment
based on IEEMA formula provided in Schedule 10 of SCC.
9. The Consortium member responsible for the Manufacturing and Supply of the equipment shall also be the contracting
agency (either as an individual or JV. / Consortium Member) for the Supplementary Contract for Comprehensive AMC
as well as for Long-term Comprehensive AMC
Contract NE-01 – Appendix 1 to Pricing Document
(1) It shall be obligatory for the Contractor to obtain Notice of ‘No Objection’ from the Engineer for the selection
of the vendors for all items of work, even if the name of the vendor is specified in the Contractor’s Technical
Submission and the works to be done including purchase of materials and equipment is in accordance with
the Standards specified in the Contract.
(2) Vendor to be selected who are capable to provide good after sales services available in Delhi NCR during
DLP and thereafter.
(3) The contractor shall send a proposal after ensuring that what he proposes at least meets the specifications
both, the quality and safety standard of the stipulated makes, the proposed product should be a proven one.
He shall also stand full guarantee to his proposal and if at any stage it is found that the material is not
suitable or meeting the tender requirement, the contractor shall replace the material with alternate vendor
without any additional cost to DMRC. The alternate makes can be used only after an approval accorded by
the Employer, whose decision will be final in the matter.
(4) The approval of any equipment or product to be used shall be done in two stages:-
(a) Stage-I
• Assessment of capability of proposed Vendor to supply a particular equipment or product,
with quality and performance requirements, as required by Specifications as well as other
contract conditions. The proposed product should be a proven product in service for at
least 3 years.
• Assessment of the financial and functional strength of the Vendor to supply the requisite
quantity of equipment and product as per delivery schedule acceptable to contractor and
engineer to deliver the project in time.
(b) Stage-II
Stage-II called as Technical Submission Approval Stage, selection of Equipment or product from
the equipment / products manufactured / supplied by the approved vendor will be done. This stage
includes thorough technical assessments about the conformance of the offered equipment / product
to the Specifications and other requirements.
(c) To obtain Vendor Approval the Contractor must apply with the following documents to the Engineer
(i) Company Profile and Experience of the Vendor.
(ii) Clause wise compliance of the relevant Clauses of Specifications.
(iii) Details of supplies / orders executed in last ten years for the type of equipment / product
offered. Supplies / orders executed for Metro Systems shall be specifically mentioned.
(iv) Details of the facilities available at the Works / Manufacturing Unit where the proposed
equipment / product shall be manufactured.
(v) ISO 9000 Certification for the Works / Manufacturing Unit where the proposed equipment /
product shall be manufactured (The Works / Manufacturing Unit where the proposed
equipment / product shall be manufactured must have ISO 9000 Certification).
(vi) Proof regarding compliance to Manufacturer’s Qualifications. The offered products must be
proven in service.
(vii) Audited Financial Statements of the Vendor for the last three years.
(viii) Type test certificates/ Performance certificate from laboratories for the proposed type of
equipment / products to establish the technical capability of the vendor (In case, specific
requirements are mentioned in the relevant sections of Specifications with regard to type
testing, same shall also be complied additionally).
(ix) The vendor shall not have been blacklisted by any Govt. Agency in India.
(x) Any other item as required by Employer / Employer’s Representative.
Page 1 of 9
Contract NE-01 – Appendix 1 to Pricing Document
(d) Contractor must certify the check list provided that vendor Proposal is complete and all the above
documents are available in the Vendor Proposal. In addition, the Contractor must check / certify
compliance to the Specifications before forwarding the same.
(e) Incomplete Vendor Proposal will not be treated as a submission and will be returned.
(f) Engineer will give Approval to the Vendor Proposal (received complete with all the documents
mentioned above) expeditiously.
(g) Technical submission shall be accompanied with the calculations / other technical documents to
justify the selection of any particular model of equipment / product, detailed technical features /
parameters of the selected product, type test certificates from the laboratories for the offered
products, any other document required by the Engineer.
(h) Engineer will give Approval to the Technical Proposal (received complete with all the documents
mentioned above) expeditiously.
(5) It may be noted that Approval of Vendors as per Point (3) above shall only be done by Employer / Engineer
after the award of the work. Vendor submissions shall not be evaluated during the tender evaluation.
Conditional Tender offers received from Tenderers with particular Vendors for supply of equipment/
products will not be evaluated during evaluation and will be dealt with after award of the work.
(6) It may further be noted that Employer / Engineer shall be under no obligation to accept equipment /
products manufactured by the successful Tenderer, unless it meets the entire criterion mentioned above.
All sub-systems, equipments and major components etc. (hereinafter referred as ‘sub-systems’) shall be
state-of-art and of proven design. The contractor shall ensure that the equipments/systems proposed for
elevated/at grade/underground sections shall be as far as possible, similar to the ones approved for Phase-
I/Phase-II/Phase-III lines.
Proposed Systems/ sub-systems shall have been in use and have established their satisfactory
performance and reliability on at least Two mass rapid transit systems (including Railway or Airports) in
revenue service either outside the country of origin at an average in two different countries or in DMRC.
Systems/ Sub-systems/ components used in DMRC do not get automatically qualified for use unless
specifically approved by the Engineer for this project. If required by the Engineer, Contractor shall provide
certificate of satisfactory performance from the Metro operators. Where similar System/ Sub-systems of a
different rating are already proven in service as per the above criteria then the supply shall be based on
such sub-systems.
All ‘sub systems’ shall be procured from the approved vendors and sourced from only such manufacturing
units that have supplied the sub-systems that fulfill the proven design requirements as above.
In case the contractor proposes to use systems or sub-system(s) that do not fulfill the above said criteria
then the contractor shall furnish sufficient information to prove the basic soundness and reliability of the
offered systems and sub-system(s) for review of the Engineer.
The Engineer’s decision on contractor’s proposal shall be final and binding.
For sourcing the equipment from indigenous manufacturing facilities, following conditions shall be
complied:-
Page 2 of 9
Contract NE-01 – Appendix 1 to Pricing Document
(i) In case the vendor uses his own facilities for indigenization after part supply of equipment from the
approved manufacturing unit, no change in design, component type/make, quality standards, manufacture
procedure, etc. shall be made without specific approval of the Engineer.
(ii) In case OEM wants to use manufacturing facilities in India (other than his own) for items for which the OEM
has been approved, it shall enter into an agreement with such selected Indian equipment manufacturer and
obtain prior approval from DMRC. No change in composition, rating, type, model no., manufacturing
process, quality standards, design, etc. and make of the components used in assemblies/sub-assemblies of
such equipment as manufactured by the approved parent vendor shall be made without specific approval of
the Engineer.
(iii) In case OEM wishes to change/make/type specifications, etc. of any sub-components for supplies to be
sourced from Indian facility, specific prior approval of the Engineer shall be obtained for changes made,
model, specification, etc. Responsibility for obtaining such prior approval shall rest solely with the
contractor.
Format for submitting the vendor approval request shall be given to the contractor during initial stages
(sample format enclosed) and approved format shall be followed throughout the contract.
Page 3 of 9
Contract NE-01 – Appendix 1 to Pricing Document
Page 4 of 9
Contract NE-01 – Appendix 1 to Pricing Document
Page 5 of 9
Contract NE-01 – Appendix 1 to Pricing Document
Page 6 of 9
Contract NE-01 – Appendix 1 to Pricing Document
Page 7 of 9
Contract NE-01 – Appendix 1 to Pricing Document
CONFIRMATIONS :-
B The equipment proposed is proven one and has been in service for last __ years.
C The proposed equipment will be compatible with the main equipment / machinery.
D The proposed equipment performance will not affected by EMI / EMC effects of 25 kV single phase OHE.
(Report of EMI / EMC study is enclosed, if applicable).
Page 8 of 9
Contract NE-01 – Appendix 1 to Pricing Document
E The capability of the Vendor / Sub-Contractor has been duly verified by us, as per the contract requirements
and we confirm that the Vendor / Sub-Contractor will meet all the contractual requirements.
F Sub-Contractor will ensure payment of minimum wages and proper Workmen Compensation Policy &
Insurance Policy and compliance of other statutory provisions
G Sub-contractor will ensure compliance to all applicable tax laws.
H Sub-Contractor's / vendor's warranty and other documents as required by employer's requirements and
contract conditions shall be submitted by us on approval of the proposed Sub-Contractor / Vendor.
I We hereby confirm that on approval copy of the agreement between the main contractor and Vendor / Sub-
Contractor will be submitted to DMRC for ensuring after sales support during DLP / AMC and for support for
supply of spare parts for 10 years beyond the DLP.
J We confirm that Electrical Sub-Contractor (if applicable) shall be allowed to execute the work only if they
possess Electrical License and a copy of the same will be submitted to DMRC , prior to commencement of
work at site.
K We undertake to propose suitable alternative if DMRC does not find the proposed Vendor / Sub-Contractor
capable or the proposed Vendor / Sub-Contractor fails to comply with the delivery schedule at NO extra cost
to DMRC.
L Manufacturer has given the details of orders in hand vis a vis spare production capacity and the same are
enclosed herewith. We confirm that the Vendor is capable of complying with the delivery schedule so as to
meet the key dates of the Contract.
M The vendors engineer shall be involved during the installation, testing, commissioning of the equipment at
site and certify that these activities has been carried out as per the manufacture’s recommendations.
All the statements, information and answers given above are true and no information has been suppressed.
In case of any information being found incorrect or misleading, DMRC will be at liberty to take suitable
action as considered appropriate.
( )
Date : Name &
Signature of the
Place : Authorized
Signatory of the
Main Contractor
with Company
Seal
Page 9 of 9
Statement A – TENDER TOTAL
(THIS DOCUMENT IS TO BE PREPARED AND COMPLETED BY THE TENDERER)
Amount
Stateme Amount in Indian Rupees
Description of Statement in Foreign Currency
nt No.
USD EURO YEN INR
C Corridor Cost Centres
F Optional Items
TENDER TOTAL
Rupees ( IN FIGURES)
Rupees ( IN WORDS )
Instructions to Tenderers
Annexure 4
(To be submitted with financial bid)
Key date affected by each condition, Increase or Decrease for unqualified withdrawal of each
Item Condition, Qualification, Deviation, etc
qualification, deviation, etc. conditions, qualification, deviation etc
Note:
In connecting this appendix, the Tenderer shall show every key date that will be affected by each condition, qualification, deviation, etc., included in his Financial
Package for the unqualified withdrawal of that condition, qualification, deviation, etc.
1. We hereby confirm that the pricing for unconditional withdrawal of the above deviations has been given in the financial bid.
2.We hereby confirm that all implicit and explicit deviations, comments and remarks mentioned elsewhere in our proposal shall be treated as NULL and VOID and
stand withdrawn.
3. We hereby confirm that but for the deviations noted in this Appendix our offer is fully and truly compliant.
4. All deviations have been listed and priced in the financial proposal and deviations not priced will be treated as null and void and stand withdrawn at nil price
DELHI METRO RAIL CORPORATION LIMITED
TENDER DOCUMENTS
VOLUME 7
Pricing Document
Clause
A Apportionment of Fixed Lump Sum Price to Cost Centres & Milestones
B Milestones Achievement Periods
C Milestone Payment Schedule (MPS)
D Tender Total
E Currency
F Milestones
General Requirements
This Part of the Contract is a fixed Lump Sum Price Contract for “Supply, Installation, Testing and
Commissioning of 25 kV Overhead Equipment (OHE), 33 kV Auxiliary Power Supply and SCADA
Systems for Elevated Corridor of Noida-Greater Noida Section (21 Stations, 29.139 RKM) and
Rolling Stock Depot at Greater Noida”.
Apportionment of Fixed Lump Sum Price to Sections and to Cost Centres and Milestones under
A.
each Section.
1 The whole of Works including design is divided into Sections, primarily on geographical basis.
Each Section is divided into the various Cost Centres named according to their general scope of
work.
2 The fixed Lump Sum price for the whole of Works shall be apportioned by the Tenderer amongst
the various sections. The apportioned amount for each Section will be further distributed among
various Cost Centres included in that Section, separately for foreign currency and for the Rupee
portion. The apportioned amount for each Cost Centre will be further distributed amongst
various Milestones included in that Cost Centre, separately for the Foreign Currency and the
Rupee Portion.
3 The sum of amounts shown against Milestones in a Cost Centre is the Cost Centre total that is to
be carried forward to the Section Summary. The division of the respective Cost Centre totals
between Indian Currency and Foreign currency shall be shown in the said Summary. The Section
Summary will be carried forward to the Tender Total.
4 The scope and extent of the Works are to be ascertained by reference to the Contract
Documents as a whole and shall not be limited in any manner whatsoever by the descriptions of
the Cost Centres under each Section or of the Milestones under each Cost Centre, as given in the
Appendices to the Pricing document.
5 Not used.
Contract Package NE-01 Pricing Document
1 The Milestones under each Cost Centre shall identify verifiable steps towards the completion of
the work within that Cost Centre under a Section. The Tenderer shall indicate the periods (in
weeks from the Commencement Date of the Works) within which he shall achieve each
Milestone.
Page 2 of 4
Contract Package NE-01 Pricing Document
1 The MPS completed by the Contractor shall set out the maximum cumulative amount for all Cost
Centres for all Sections put together in relation to each month for which payment may be sought
in accordance with Sub-Clause 11.4 of the GCC. This information should also be presented in a
tabular form. Monthly Cash Flows for the Contract will form part of the Pricing Document.
2 The MPS covers the period which will commence on the first day of the calendar month next
after the month containing the Commencement Date of the Works as per the Contract. The first
application for interim payment may be made not earlier than during the month following the
calendar month next after the month containing the Commencement Date of the Works, such
first application relating to the first month (i.e. month 1) of the MPS.
3 The price shall not be unbalanced therefore, for the statement-C, the price quoted in the Cost
Center-C (Installation and Site Testing) and Cost Center-D (System Acceptance Tests,
Integrated Testing and Commissioning) shall not be less than 15% and 10% of the price quoted
in the Cost Center-B (Manufacture and Delivery).
D. Tender Total
1 The Tender Total submitted by the Tenderer shall be in the format shown in the Pricing
Document.
2 The Pricing Document contains Sections, Cost Centres under each Section, and Milestones under
each Cost Centre. The Sections, Cost Centres and Milestones have been prepared to indicate the
extent of detail required in the Tender. The Tenderer shall prepare and complete documents, in
this format, as being his Tender and submit as part of the Financial Package.
Items/Milestones against which no rate or sum is entered by the Tenderer, whether quantities
are stated or not, shall be regarded as covered by other rates in the pricing document.
3 The Pricing Document completed and submitted by the Tenderer, as part of his Tender, should
use an indexing and page numbering system such that its extent and completeness is clearly
evident.
E. Currency
1 Section Totals, Cost Centre Totals and Milestone amounts shall be indicated in Indian Rupees
and in a foreign currency as per clause C16.1, wherever required.
F. Milestones
Page 3 of 4
Contract Package NE-01 Pricing Document
1 Cost Centres under each Section are fixed and shall not be changed by the Tenderer. The Cost
Centres represent the major items of the Works for which the Employer will pay the Contractor,
and the Tenderer shall ensure that he has allowed for all his costs he requires for the Contract to
meet the Employer’s Requirements.
2 If during the course of execution, it becomes necessary, to meet the Employer’s Requirements
(as indicated in these Tender Documents), to add more Milestones in a Cost Centre, the Lump
Sum Price of the whole of Works, which will remain unaltered, will be reapportioned amongst
the Sections, and further redistributed under the Cost Centres in each Sections and the
Milestones in each Cost Centre. The liability of the Employer will be limited to the fixed Lump
sum Price already accepted and the Contractor will have no right to claim any thing over and
above the fixed Lump Sum price for any such addition of Milestones in any Cost Centre. The
decision of the Employer will be final and binding in such matters and will not be subject to
Conciliation or Arbitration.
4 Contractor is allowed to claim the lump sum cost of supply milestones in the cost centres B1, B2,
B3 and B4 for each currency portion separately after certifying that all the materials considered
in the currency portion of the milestone has been supplied.
Page 4 of 4
BRIEF DESCRIPTION OF CORRIDOR
The work of Noida-Greater Noida corridor has been divided in to four different sections:-
(CH:19318 to CH:
N3 Knowledge Park II – Depot Station 28689.3) 6 December, 2017
RKM 9.371
*Tenderer shall ascertain the length of corridor for the works in particular section from the Alignment drawings. Any change up to plus/minus 0.5 km in the alignment of the overall
corridor shall not be considered as a variation.
Contract Package NE-01 Pricing Document
Statement A
Tender Total
Amount
Stateme Description of Statement Amount in Indian Rupees
in Foreign Currency
nt No.
USD EURO YEN INR
C Corridor Cost Centres
F Optional Items
TENDER TOTAL
Rupees ( IN FIGURES)
Rupees ( IN WORDS )
Supply, Installation, Testing and Commissioning of 25 kV Overhead Equipment (OHE), 33 kV Auxiliary Power Supply and
SCADA
Systems for Elevated Corridor of Noida-Greater Noida Section
(21 Stations, 29.139 RKM) and Rolling Stock Depot at Greater Noida
Statement B
Section Summaries
Cost Amount
Description of Cost Centres Amount in Indian Rupees
Centres in Foreign Currency
USD EURO YEN INR
MA Preliminaries and General Requirements
MB Training
MC Spares
MD Not Used
ME Manuals
Amount
Adjustment Prices for Additional Items Amount in Indian Rupees
in Foreign Currency
USD EURO YEN INR
TOTAL CARRIED TO TENDER TOTAL
Amount
in Foreign Currency Amount in Indian Rupees
Total Price of Cost Centers
Page 2 of 2
Supply, Installation, Testing and Commissioning of 25 kV Overhead
Equipment (OHE), 33 kV Auxiliary Power Supply and SCADA
Systems for Elevated Corridor of Noida-Greater Noida Section
(21 Stations, 29.139 RKM) and Rolling Stock Depot at Greater Noida
Corridor N (Sector 71 to Depot Station including Rolling Stock Depot at Greater Noida)
Corridor N (Sector 71 to Depot Station including Rolling Stock Depot at Greater Noida)
This Cost Centre comprises all those obligations and ongoing activities throughout the Contract not associated
directly with any other Cost Centre.
This Cost Centre A comprises all activities relating to the detailed design of 25 kV Overhead Equipment (OHE)
including FP, SP, SSP & SS etc, 33 kV Auxiliary Power Supply,Viaduct Lighting System, SCADA Systems, Earthquake
and Wind Speed Sensing and Warning Systems for Elevated Corridor of Noida-Greater Noida Section (21 Stations,
29.139 RKM) and Rolling Stock Depot at Greater Noida.
Any other item(s) considered necessary to comply with the Scope of Work.
Page 2 of 2
Corridor N (Sector 71 to Depot Station including Rolling Stock Depot at Greater Noida)
NAME OF BIDDER 0
A3 Schedule of materials
A4 "As-built Drawings"
(SCADA Systems)
A25
Schedule of materials
A26
Contract Package NE-01 Pricing Document
"As-built Drawings"
A27
Any other item(s) considered necessary to comply
with the Scope of Work
A28
Page 2 of 2
Corridor N Sector 71 to Depot Station including Rolling Stock Depot at Greater Noida
This Cost Centre comprises all those obligations and ongoing activities
throughout the Contract not associated directly with any other Cost Centre.
This includes but is not limited to receipt/ delivery of following equipment for
Sections N1 after type test, factory acceptance test, provision of Indemnity
Bond and proof of insurance:
Delivery of equipment for the Flexible OHE for Sections N1 (Sector 71 – Sector
137 RKM 9.488) at Contractor’s premises in Delhi/NCR.
Page 2 of 2
Corridor N Sector 71 to Depot Station including Rolling Stock Depot at Greater Noida
NAME OF BIDDER 0
a Masts/Portals
c Contact Wire
f Cantilever Assembly
Page 2 of 6
Contract Package NE-01 Pricing Document
Page 3 of 6
Contract Package NE-01 Pricing Document
a Transformers
Page 4 of 6
Contract Package NE-01 Pricing Document
c 33 kV Cables
Any change up to plus/minus 0.5 Rkm in the alignment of
the overall corridor shall not be considered as a variation.
Any further change in this length shall be adjusted for the
d LV Cables
g Protection Relays
Page 5 of 6
Contract Package NE-01 Pricing Document
b 33 kV Cables
Contractor to Quote considering the distance between
the cable terminations (RSS end & ASS end) as 0.5 RKm.
Any change in this length (above/below 0.5 Rkm) shall be
c Protection Relays
b 33 kV Cables
Contractor to Quote considering the distance between
the cable terminations (Sector 71 to Line-3 Extension end)
as 0.5 RKm. Any change in this length (above/below 0.5
c Protection Relays
a RTU
Page 6 of 6
Corridor N Sector 71 to Depot Station including Rolling Stock Depot at
Page 2 of 2
Corridor N Sector 71 to Depot Station including Rolling Stock Depot at Greater Noida
NAME OF BIDDER 0
a Masts/Portals
c Contact Wire
f Cantilever Assembly
Page 2 of 14
Contract Package NE-01 Pricing Document
Page 3 of 14
Contract Package NE-01 Pricing Document
Page 4 of 14
Contract Package NE-01 Pricing Document
Page 5 of 14
Contract Package NE-01 Pricing Document
Page 6 of 14
Contract Package NE-01 Pricing Document
Page 7 of 14
Contract Package NE-01 Pricing Document
a Earthing Assembly
Page 8 of 14
Contract Package NE-01 Pricing Document
a Transformers
Page 9 of 14
Contract Package NE-01 Pricing Document
g Protection Relays
Page 10 of 14
Contract Package NE-01 Pricing Document
c Protection Relays
c Protection Relays
Page 11 of 14
Contract Package NE-01 Pricing Document
Page 12 of 14
Contract Package NE-01 Pricing Document
a RTU
Page 13 of 14
Contract Package NE-01 Pricing Document
Page 14 of 14
Corridor N Sector 71 to Depot Station including Rolling Stock Depot at
This Cost Centre comprises all those obligations and ongoing activities
throughout the Contract not associated directly with any other Cost
Centre.
Page 2 of 2
Corridor N Sector 71 to Depot Station including Rolling Stock Depot at Greater Noida
NAME OF BIDDER 0
This Cost Centre comprises all those obligations and ongoing activities
throughout the Contract not associated directly with any other Cost Centre.
This includes but is not limited to receipt/ delivery of following equipment for
Sections N2 after type test, factory acceptance test, provision of Indemnity
Bond and proof of insurance:
Delivery of equipment for the Flexible OHE for Section N2 (Sector 142 –
Sector 149 RKM 10.180) at Contractor’s premises in Delhi/NCR.
Delivery of equipment for the e- Rigid OCS for Section N2 (Sector 142 –
Sector 149 RKM 0.100) at Contractor’s premises in Delhi/NCR.
Delivery of equipment for the SCADA Systems for Section N2 (Sector 142 –
Sector 149 RKM 10 280) at Contractor’s premises in Delhi/NCR
Corridor N Sector 71 to Depot Station including Rolling Stock Depot at Greater Noida
NAME OF BIDDER 0
a Masts/Portals
c Contact Wire
f Cantilever Assembly
h Neutral Section
B2-2 Delivery of following major equipments for the e-Rigid OCS for
Section N2 (Sector 142 – Sector 149 RKM 0.100) at Contractor’s
premises in Delhi/NCR
Contractor to quote considering 0.100 RKM. Any change in the
a Masts/Portals including Support Structures
c Contact Wire
d Insulators
Page 2 of 5
Contract Package NE-01 Pricing Document
Page 3 of 5
Contract Package NE-01 Pricing Document
a Transformers
c 33 kV Cables
Any change up to plus/minus 0.5 Rkm in the alignment of the
overall corridor shall not be considered as a variation. Any
further change in this length shall be adjusted for the
d LV Cables
Page 4 of 5
Contract Package NE-01 Pricing Document
g Protection Relays
b 33 kV Cables
Contractor to Quote considering the distance between the
cable terminations (RSS end & ASS end) as 0.5 RKm. Any
change in this length (above/below 0.5 Rkm) shall be adjusted
c Protection Relays
a RTU
Page 5 of 5
Corridor N Sector 71 to Depot Station including Rolling Stock Depot at Greater Noida
This Cost Centre comprises all those obligations and ongoing activities
throughout the Contract not associated directly with any other Cost Centre.
This includes but is not limited to Delivery to Site from Contractor's premises in
Delhi, Submission of Installation Plan, Installation Drawings, inspection of
equipment and Site preparations, Pre- installation tests, Installation of
equipment, Post-installation tests, energisation and any other item(s)
considered necessary to comply with the scope of work for:
Page 2 of 3
Contract Package NE-01 Pricing Document
Page 3 of 3
Corridor N Sector 71 to Depot Station including Rolling Stock Depot at Greater Noida
NAME OF BIDDER 0
Apportioned Amount
MILE WORK DESCRIPTION Weeks for completion
Amount in Foreign Currency
STONE MILESTONE ACTIVITY Amount in of Milestone from
NO. USD EURO YEN Indian Rupees Commencement Date
• Obta i n the ”Noti ce of No Objecti on” or “Noti ce of No
Objecti on s ubject to ” from the Engi neer for ea ch of:
C2-1 Del i very to Si te from Contra ctor's premi s es i n Del hi /NCR,
Ins ta l l a ti on a nd Tes ti ng (i ncl udes pre-i ns ta l l a ti on tes ts
a nd pos t i ns ta l l a ti on tes ts ) a nd energi s a ti on of a l l
equi pment for the Fl exi bl e OHE for Secti on N2 (Sector 142
– Sector 149 RKM 10.180)
Any change up to plus/minus 0.5 Rkm in the alignment of the
overall corridor shall not be considered as a variation. Any
further change in this length shall be adjusted for the additional
plus/minus length on pro rata rates quoted.
Ma s ts /Porta l s
a
b Ga l va ni s ed Steel pa rts (Termi na ti on As s embl y,
Supporti ng Arra ngement, Anti Creep As s embl y, Guy Rod
As s embl y, Pl a tes a nd Boa rds , Sa fety Screen Pa nel etc)
Conta ct Wi re
c
d Overhea d wi res a nd Conductors (Mes s enger Wi res ,
Feeder Wi re, Dropper As s embl y, Jumper As s embl y,Bri dl e
Wi re, Ins ul a ti ng Covers etc)
e
f Ca nti l ever As s embl y
ATD a nd i ts As s embl y
g
h Neutra l Secti on
Contra ct Pa cka ge NE-01 Pri ci ng Document
c Conta ct Wi re
d Ins ul a tors
Pa ge 2 of 4
Contra ct Pa cka ge NE-01 Pri ci ng Document
Pa ge 3 of 4
Contra ct Pa cka ge NE-01 Pri ci ng Document
a Ea rthi ng As s embl y
a Tra ns formers
c 33 kV Ca bl es , Ca bl e Pa th
Any change up to plus/minus 0.5 Rkm in the alignment of the
overall corridor shall not be considered as a variation. Any
further change in this length shall be adjusted for the additional
plus/minus length on pro rata rates quoted.
d LV Ca bl e, ca bl e pa ths
g Protecti on Rel a ys
b 33 kV Ca bl es , Ca bl e Pa th
Contractor to Quote considering the distance between the cable
terminations (RSS end & ASS end) as 0.5 Rkm. Any change in
this length (above/below 0.5 Rkm) shall be adjusted on pro
rata rates quoted.
c Protecti on Rel a ys
a RTU
Pa ge 4 of 4
Corridor N Sector 71 to Depot Station including Rolling Stock Depot at Greater Noida
This Cost Centre comprises all those obligations and ongoing activities
throughout the Contract not associated directly with any other Cost Centre.
Service Trials.
Contract Package NE-01 Pricing Document
Page 2 of 2
Corridor N Sector 71 to Depot Station including Rolling Stock Depot at Greater Noida
NAME OF BIDDER 0
Page 2 of 3
Contract Package NE-01 Pricing Document
Page 3 of 3
Corridor N Sector 71 to Depot Station including Rolling Stock Depot at Greater Noida
This Cost Centre comprises all those obligations and ongoing activities throughout the Contract not associated directly with any other Cost Centre.
This includes but is not limited to receipt/ delivery of following equipment for Sections N3 after type test, factory acceptance test, provision of Indemnity Bond and proof of
insurance:
Delivery of equipment for the Flexible OHE for Section N3 (Knowledge Park II – Depot Station RKM 9.371) at Contractor’s premises in Delhi/NCR.
Delivery of equipment for the Sub-Sectioning (SS) at Alpha 2 station at Contractor’s premises in Delhi/NCR.
Delivery of equipment for the Sub-Sectioning and Paralleling Post (SSP) at Pari Chowk Station at Contractor’s premises in Delhi/NCR.
Delivery of equipment for the Sub-Sectioning and Paralleling Post (SSP) at Depot Station at Contractor’s premises in Delhi/NCR.
Delivery of equipments for Traction Supply Feeding arrangements to Rolling Stock Depot from Depot Station at Contractor’s premises in Delhi/NCR.
Delivery of equipment for Earthing & Bonding including Thermosetting weld & cables, Buried Earth Conductor (BEC), Return Conductor, Earthing
Cables,Clamps/Connectors, etc. for N3 (Knowledge Park II – Depot Station RKM 9.371) of the corridor at Contractor’s premises in Delhi/NCR.
Delivery of equipment for the Auxiliary Power Supply System for Sections N3 (Knowledge Park II – Depot Station RKM 9.371) at Contractor’s premises in Delhi/NCR.
Delivery of 33 kV Cables and other equipments (for feeding auxiliary power to Rolling StockDepot from Depot Station) at Contractor’s premises in Delhi/NCR
considering 0.5 km of distance.
Delivery of equipment for the SCADA Systems for Section N3 (Knowledge Park II – Depot Station RKM 9.371) at Contractor’s premises in Delhi/NCR.
Corridor N Sector 71 to Depot Station including Rolling Stock Depot at Greater Noida
Section N3 (Knowledge Park II – Depot Station RKM 9.371)
a Masts/Portals
a Earthing Assembly
b Buried Earth Conductor, Return Conductor, Overhead
Protection Conductor and clamps, connecions.
c Thermosetting Welds , ITL and Cables
d Any other item(s) considered necessary to comply with the
Scope of Work
B3-7 Delivery of following major equipment for the Auxiliary Power
Supply System for Sections N3 (Knowledge Park II – Depot
Station RKM 9.371) at Contractor’s premises in Delhi/NCR.
a Transformers
b Switchgears with CT, PT
c 33 kV Cables
Any change up to plus/minus 0.5 Rkm in the alignment of the
overall corridor shall not be considered as a variation. Any
further change in this length shall be adjusted for the
additional plus/minus length on pro rata rates quoted.
d LV Cables
e Viaduct Lights, Sockets and Fittings
f Auxiliary Supply System (ACDB, DCDB, Battery Bank, Battery
Charger, Earthing arrangements etc)
g Protection Relays
h Any other item(s) considered necessary to comply with the
Scope of Work
B3-8 Delivery of following major equipments for feeding auxiliary
power to Rolling Stock Depot from Depot Station at
Contractor’s premises in Delhi/NCR.
a Switchgears with CT, PT
b 33 kV Cables
c Protection Relays
d Any other item(s) considered necessary to comply with the
Scope of Work
B3-9 Delivery of following major equipment for the SCADA Systems
for Section N3 (Knowledge Park II – Depot Station RKM 9.371)
at Contractor’s premises in Delhi/NCR.
a RTU
b Control and Monitoring Cables etc
c Any other item(s) considered necessary to comply with the
Scope of Work
Contract Package NE-01 Pricing Document
Page 2 of 2
Corridor N Sector 71 to Depot Station including Rolling Stock Depot at Greater
Page 2 of 3
Contract Package NE-01 Pricing Document
Page 3 of 3
Corridor N Sector 71 to Depot Station including Rolling Stock Depot at Greater Noida
a Masts/Portals
b Galvanised Steel parts(Termination Assembly, Supporting
Arrangement, Anti Creep Assembly, Guy Rod Assembly, Plates
and Boards, Safety Screen Panel etc)
Contact Wire
c
d Overhead wires and Conductors (Messenger Wires, Feeder Wire,
Dropper Assembly, Jumper Assembly,Bridle Wire, Insulating
Covers etc)
Insulators, Section Insulators
e
f Cantilever Assembly
Page 2 of 5
Contract Package NE-01 Pricing Document
a Earthing Assembly
b Buried Earth Conductor, Return Conductor, Overhead Protection
Conductor and clamps, connecions.
c Thermosetting Welds , ITL and Cable, cable paths.
d Any other item(s) considered necessary to comply with the
Scope of Work
Page 3 of 5
Contract Package NE-01 Pricing Document
a Transformers
b Switchgears with CT, PT
c 33 kV Cables, Cable Path
Any change up to plus/minus 0.5 Rkm in the alignment of the
overall corridor shall not be considered as a variation. Any
further change in this length shall be adjusted for the
additional plus/minus length on pro rata rates quoted.
Page 4 of 5
Contract Package NE-01 Pricing Document
a RTU
b Control and Monitoring Cable, cable paths etc
c Any other item(s) considered necessary to comply with the
Scope of Work
C3-10 Manning of Commissioned ASS
Contractor to Quote all-inclusive man-day charges considering
5940 man-days. Any change in the man-days (above/below
5940 mandays ) shall be adjusted on pro rata rates quoted.
The staff team deployed at the ASS's shall be thoroughly
conversant and competent to operate the various switchgear
and systems and shall be able to provide auxiliary power, if so
desired by DMRC, to other Agencies working in the Station area
or elsewhere and also to provide power shut-downs of the
commissioned systems, if so directed by DMRC.
A period of 8 hours of deployment of one staff should be
considered as 1 man-day.
The quoted amount shall cover the approval of the supervisors
and replacement as required by the Employer, employment of
approved staff including salaries, overtime, airfares, lodging
allowances, their office expenditure, telephone/mobile bills,
local travel costs to and from site, training materials, income tax
and other taxes deducted at source.
The contractor shall be responsible for the compliance of all the
labour laws irrespective of rates quoted.
Page 5 of 5
Corridor N Sector 71 to Depot Station including Rolling Stock Depot at Greater
Service Trials.
Safety certification, in the approved format, for opening the section for
revenue operation, including for traction power.
Page 2 of 3
Contract Package NE-01 Pricing Document
Page 3 of 3
Corridor N Sector 71 to Depot Station including Rolling Stock Depot at Greater Noida
D3-8 Any other item(s) considered necessary to comply with the Scope
of Work.
COST CENTRE TOTAL CARRIED TO SECTION SUMMARY
Page 2 of 2
Corridor N Sector 71 to Depot Station including Rolling Stock Depot at
a Masts/Portals
b Galvanised Steel parts(Termination Assembly, Supporting
Arrangement, Anti Creep Assembly, Guy Rod Assembly, Plates
and Boards, Safety Screen Panel etc)
c Contact Wire
d Overhead wires and Conductors (Messenger Wires, Feeder
Wire, Dropper Assembly, Jumper Assembly,Bridle Wire,
Insulating Covers etc).
e Insulators, Section Insulators
f Cantilever Assembly
g ATD and its Assembly
h Foundation
i Neutral Section
j Any other item(s) considered necessary to comply with the
Scope of Work
B4-2 Delivery of following major equipment for the Sectioning
arrangements for proper operation of Rolling Stock for Section
N4 (Rolling Stock Depot at Greater Noida TKM 15) at
Contractor’s premises in Delhi/NCR.
a Circuit Breakers, Interruptors, Isolators
b Capacitive Voltage Sensor, PT, CT
c Traction Cables/Feeders/Jumpers and connection assemblies
a Transformer
b Circuit Breakers, Interruptors, Isolators
c Capacitive Voltage Sensor, PT, CT
d Traction and Auxiliary Cables/Feeders/Jumpers and connection
assemblies
e Any other item(s) considered necessary to comply with the
Scope of Work
B4-4 Delivery of following major equipment for Earthing & Bonding
including Thermosetting weld & cables, BEC, Return Conductor,
Return Cables, Earth Wire, Clamps and Connectors etc. for
Section N4 (Rolling Stock Depot at Greater Noida TKM 15) at
Contractor’s premises in Delhi/NCR
Any change up to plus/minus 0.5 Tkm in the alignment of the
overall corridor shall not be considered as a variation. Any
further change in this length shall be adjusted for the
additional plus/minus length on pro rata rates quoted.
a Earthing Assembly
b Buried Earth Conductor, Return Conductor, Overhead
Protection Conductor and clamps, connections.
c Thermosetting Welds , ITL and Cables
d Any other item(s) considered necessary to comply with the
Scope of Work
B4-5 Delivery of following major equipment for the Auxiliary Power
Supply System for for Section N4 (Rolling Stock Depot at
Greater Noida TKM 15) at Contractor’s premises in Delhi/NCR.
a Transformers
b Switchgears with CT, PT
c 33 kV Cables
Contractor to quote considering the distance between the
cable terminations ( Depot Sation end and Depot ASS) as 0.5
Rkm. Any change up to plus/minus 0.5 Rkm in the alignment of
the overall corridor shall not be considered as a variation. Any
further change in this length shall be adjusted for the
additional plus/minus length on pro rata rates quoted.
d LV Cables
e Viaduct Lights, Sockets and Fittings
f Auxiliary Supply System (ACDB, DCDB, Battery Bank, Battery
Charger, Earthing arrangements etc)
g Protection Relays
h Any other item(s) considered necessary to comply with the
Scope of Work
B4-6 Delivery of following major equipment for the SCADA Systems
for Section N4 (Rolling Stock Depot at Greater Noida TKM 15)
and OCC at Contractor’s premises in Delhi/NCR.
a RTU
b Control and Monitoring Cables etc
c SCADA Server+ Workstation + Printer etc.
d SCADA and other Softwares
e VDU
f Auxiliary Power Supply System
g Any other item(s) considered necessary to comply with the
Scope of Work
B4-7 Delivery of equipments for the Earthquake and Wind Speed
Sensing and Warning System for Section N4 (Rolling Stock
Depot at Greater Noida TKM 15) and Associated Arrangements
at OCC at Contractor’s premises in Delhi/NCR.
This Cost Centre comprises all those obligations and ongoing activities
throughout the Contract not associated directly with any other Cost Centre.
This includes but is not limited to Delivery to Site from Contractor's premises in
Delhi, Submission of Installation Plan, Installation Drawings, inspection of
equipment and Site preparations, Pre- installation tests, Installation of
equipment, Post-installation tests, energisation and any other item(s)
considered necessary to comply with the scope of work for:
Page 2 of 3
Contract Package NE-01 Pricing Document
Page 3 of 3
Corridor N Sector 71 to Depot Station including Rolling Stock Depot at Greater Noida
a Masts/Portals
f Cantilever Assembly
Contract Package NE-01 Pricing Document
h Foundation
i Neutral Section
a Transformer
Page 2 of 5
Contract Package NE-01 Pricing Document
a Earthing Assembly
a Transformers
Page 3 of 5
Contract Package NE-01 Pricing Document
a RTU
b Control and Monitoring Cable, cable paths etc
c SCADA Server+ Workstation + Printer etc.
d SCADA and other Softwares
e VDU
f Auxiliary Power Supply System
g Any other item(s) considered necessary to comply with the
Scope of Work
C4-7 Delivery to Site from Contractor's premises in Delhi/NCR,
Installation and Testing (includes pre-installation tests and
post installation tests) and energisation of all equipment
for the Earthquake and Wind Speed Sensing and Warning
System for Section N4 (Rolling Stock Depot at Greater
Noida TKM 15) and Associated Arrangements at OCC.
Page 4 of 5
Contract Package NE-01 Pricing Document
Page 5 of 5
Corridor N Sector 71 to Depot Station including Rolling Stock Depot at Greater
Page 2 of 3
Contract Package NE-01 Pricing Document
D4-8 Any other item(s) considered necessary to comply with the Scope
of Work.
COST CENTRE TOTAL CARRIED TO SECTION SUMMARY
Page 3 of 3
Supply, Installation, Testing and Commissioning of 25 kV Overhead Equipment (OHE), 33 kV Auxiliary Power Supply and SCADA Systems for Elevated
Corridor of Noida-Greater Noida Section (21 Stations, 29.139 RKM) and Rolling Stock Depot at Greater Noida
Corridor N (Sector 71 to Depot Station including Rolling Stock Depot at Greater Noida)
This Cost Centre comprises all those obligations and on going activities throughout the Contract not associated directly with any other Cost Centre.
Corridor N (Sector 71 to Depot Station including Rolling Stock Depot at Greater Noida)
NAME OF BIDDER 0
Apportioned Amount
MILE STONE WORK DESCRIPTION Weeks for completion
Amount in Foreign Currency
NO. MILESTONE ACTIVITY Amount in of Milestone from
USD EURO YEN Indian Rupees Commencement Date
Obtain the ”Notice of No Objection” or “Notice of No Objection
subject to…” from the Engineer for:
Page 2 of 5
Contract Package NE-01 Pricing Document
Corridor N (Sector 71 to Depot Station including Rolling Stock Depot at Greater Noida)
This Cost Centre comprises all those obligations and ongoing activities throughout the Contract not associated directly with any other Cost Centre.
Provision of Instructors by the Contractor for training of operating and maintenance personnel of the Employer in India
Training of operating and maintenance personnel of the Employer offshore at the Contractor’s facilities and MRTS.
Any other item(s) considered necessary to comply with the Scope of Work.
Notes:
The Tenderer shall not complete the column “Weeks for completion of Milestone from Commencement Date.
The dates for the operation of these Milestone Activities will be at the discretion of the Employer.
The travel, boarding and lodging expenses for the Employer’s trainees sent overseas will be borne by the Employer.
The monthly cash flow on the basis of which the PV is to be worked out will exclude the amount of this Cost Centre though this Cost Centre shall be included in the Section MS Summary and the Tender Total.
Page 3 of 5
Contract Package NE-01 Pricing Document
Corridor N (Sector 71 to Depot Station including Rolling Stock Depot at Greater Noida)
Page 4 of 5
Contract Package NE-01 Pricing Document
Corridor N (Sector 71 to Depot Station including Rolling Stock Depot at Greater Noida)
This Cost Centre comprises all those obligations and ongoing activities throughout the Contract not associated directly with any other Cost Centre.
This shall include but not be limited to supply of spares for complete Contract.
Any other item(s) considered necessary by the Contractor to comply with the Scope of Work.
Corridor N (Sector 71 to Depot Station including Rolling Stock Depot at Greater Noida)
NAME OF BIDDER
Apportioned Amount
MILE STONE WORK DESCRIPTION Weeks for completion
Amount in Foreign Currency
NO. MILESTONE ACTIVITY Amount in of Milestone from
USD EURO YEN Indian Rupees Commencement Date
Obtain the “Notice of No Objection” or “Notice of No Objection
Subject to ---“ from the Engineer for delivery of the following in
accordance with the Employer’s Requirements:
MC2 Any other item(s) considered necessary to comply with the Scope of
Work.
Corridor N (Sector 71 to Depot Station including Rolling Stock Depot at Greater Noida)
Not Used
Corridor N (Sector 71 to Depot Station including Rolling Stock Depot at Greater Noida)
This Cost Centre comprises all those obligations and ongoing activities throughout the Contract not associated directly with any other Cost Centre.
Traction power Distribution, Flexible OHE, e-Rigid OCS, SP, SSPs, SS, Feeding Post, Overall Earthing system, Auxiliary Power Supply System, Earth Quake and Wind Speed Sensing
and Warning System, SCADA etc. before commencement of Integrated Testing and Commissioning.
Provision of Maintenance Manuals in One Orignal and five (hard copies and in electronic format) for:
Traction power Distribution, Flexible OHE, e-Rigid OCS, SP, SSPs, SS Feeding Post, Overall Earthing system, Auxiliary Power Supply System, Earth Quake and Wind Speed Sensing and
Warning System, SCADA etc. before commencement of Integrated Testing and Commissioning.
Provision of sub-systems/systems and spare parts catalogue - (hard copies and electronic format)
Any other item(s) considered necessary to comply with the Scope of Work.
Corridor N (Sector 71 to Depot Station including Rolling Stock Depot at Greater Noida)
NAME OF BIDDER
Apportioned Amount
MILE STONE WORK DESCRIPTION Weeks for completion
Amount in Foreign Currency
NO. MILESTONE ACTIVITY Amount in of Milestone from
USD EURO YEN Indian Rupees Commencement Date
Obtain the “Notice of No Objection” or “Notice of No Objection
Subject to ---“ from the Engineer on delivery of the final Manuals for
Traction power Distribution, Flexible OHE, e-Rigid OCS, SP, SSPs, SS,
Feeding Post, Overall Earthing system, Auxiliary Power Supply
System, Earth Quake and Wind Speed Sensing and Warning System,
SCADA etc. before commencement of Integrated Testing and
Commissioning.
ME1 Operating Manuals (Original plus five hard copies) and in Electronic
Format.
ME3 Subsystems/ Systems spare parts catalogue (Original plus five hard
copies) and in Electronic Format.
ME4 Any other item(s) considered necessary to comply with the scope of
Work
COST CENTRE TOTAL CARRIED TO SECTION SUMMARY
Page 5 of 5
Supply, Installation, Testing and Commissioning of 25 kV Overhead Equipment (OHE), 33 kV Auxiliary
Power Supply and SCADA Systems for Elevated Corridor of Noida-Greater Noida Section
(21 Stations, 29.139 RKM) and Rolling Stock Depot at Greater Noida
Corridor N (Sector 71 to Depot Station including Rolling Stock Depot at Greater Noida)
Statement E
Adjustment Price for using Silver Bearing Copper Contact Wire RKM
2 instead of normal contact wire (over and above the price quoted 29.139
with normal contact wire).
Addition/Deletion Price of 25 kV Circuit Breaker Nos.
3 1
TOTAL
NOTE:
######## The price shall be an all inclusive fixed price for delivery. The price will include all associated accessories and fixtures of the respective items and all duties, taxes, etc. including tax deducted at source. Nothing extra shall be paid on account of Installation,
Testing and Commissioning etc. of the above items and the prices shall be deemed to be included in the Cost Centres C and D.
######## The prices shall be valid until the Taking over Certificate of the last Section.
######## These rates shall be considered for the purpose of comparative evaluation of Tenders.
Supply, Installation, Testing and Commissioning of 25 kV Overhead Equipment (OHE), 33 kV Auxiliary Power Supply and SCADA Systems for Elevated Corridor of Noida-Greater
Noida Section (21 Stations, 29.139 RKM) and Rolling Stock Depot at Greater Noida
Corridor N (Sector 71 to Depot Station including Rolling Stock Depot at Greater Noida)
Statement of Prices
Statement No. F
Optional Items
Note:-
1. Employer may award the Comprehensive AMC to the successful tenderer for 3 years beyond DLP at these rates.
2. The cost of spare parts, T&P required for maintenance during AMC period beyond DLP will be deemed to be inclusive in the
prices for AMC indicated in this Statement . Nothing extra will be paid for such spare parts.
3. This statement will be considered for tender evaluation while assessing the L-1 bidder.
4. Payment for AMC will be made on quarterly basis on completion of maintenance obligations by the Contractor.
5. Scope of maintenance work will be as per details provided in the Scope of Maintenance during DLP and AMC
6. The Contractor to quote prices as per Clause 24 of SCC.
7. Service tax shall be inclusive in the above price
8. Employer reserves the right to enter into a separate Comprehensive AMC contract for further 5 Years, beyond 3 Years
Comprehensive AMC , considering the Price quoted for "3rd Year" above as Po subject to Escalation / Price Adjustment
based on IEEMA formula provided in Schedule 10 of SCC.
9. The Consortium member responsible for the Manufacturing and Supply of the equipment shall also be the contracting
agency (either as an individual or JV. / Consortium Member) for the Supplementary Contract for Comprehensive AMC
as well as for Long-term Comprehensive AMC
Supply, Installation, Testing and Commissioning of 25 kV Overhead Equipment (OHE), 33 kV
Auxiliary Power Supply and SCADA Systems for Elevated Corridor of Noida-Greater Noida Section
(21 Stations, 29.139 RKM) and Rolling Stock Depot at Greater Noida
Corridor N (Sector 71 to Depot Station including Rolling Stock Depot at Greater Noida)
This Document is to be prepared by the Tenderer as per clause C. Milestone Payment Schedule
Note: The amount of Cost Centres B and D of Section Miscelleneous will not be included in the Monthly Cash Flows.
CONTRACT NE-01
Instructions to Tenderers
Annexure 4
(To be submitted with financial bid)
Key date affected by each condition, Increase or Decrease for unqualified withdrawal of each
Item Condition, Qualification, Deviation, etc
qualification, deviation, etc. conditions, qualification, deviation etc
Note:
In connecting this appendix, the Tenderer shall show every key date that will be affected by each condition, qualification, deviation, etc., included in his Financial
Package for the unqualified withdrawal of that condition, qualification, deviation, etc.
1. We hereby confirm that the pricing for unconditional withdrawal of the above deviations has been given in the financial bid.
2.We hereby confirm that all implicit and explicit deviations, comments and remarks mentioned elsewhere in our proposal shall be treated as NULL and VOID and
stand withdrawn.
3. We hereby confirm that but for the deviations noted in this Appendix our offer is fully and truly compliant.
4. All deviations have been listed and priced in the financial proposal and deviations not priced will be treated as null and void and stand withdrawn at nil price
Contract NE-01 Addendum to Volume-5 TENDER DRAWINGS
Sector 71 SSP -
2 NE-01-T-TN-S 71-1000-0 Electrical
Schematic Diagram
Sector 78 SS-
4 NE-01-T-TN-S 78-1000-0 Electrical
Schematic Diagram
Sector 81 SSP -
5 NE-01-T-TN-S 81-1000-0 Electrical
Schematic Diagram
Sector 83 FP -
6 NE-01-T-TN-S 83-1000-0 Electrical
Schematic Diagram
Sector 142 SS -
7 NE-01-T-TN-S 142-1000-0 Electrical
Schematic Diagram
Sector 147 SP -
9 NE-01-T-TN-S 147-1000-0 Electrical
Schematic Diagram
Contract NE-01 Addendum to Volume-5 TENDER DRAWINGS
Sector 153 FP -
10 NE-01-T-TN-S 153-1000-0 Electrical
Schematic Diagram
ALPHA 2 SS -
NE-01-T-TN- ALP 2-1000-
13 Electrical
0
Schematic Diagram
Auxiliary Sub
38 NE-01-T-AX-TYPI-1002-0 Station – 110V DC
Distribution
Contract NE-01 Addendum to Volume-5 TENDER DRAWINGS
Schematic Diagram
Auxiliary Sub
39 NE-01-T-AX-TYPI-1003-0 Station – ACDB-
Schematic Diagram
General
40 NE-01-T-OH-TYPI-1001-0 Arrangement of
OHE
General
Arrangement of
41 NE-01-T-OH-TYPI-1002-0
Single Cantilever
on Normal Mast
General
Arrangement of
42 NE-01-T-OH-TYPI-1003-0 Multiple
Cantilevers on
Normal Mast
General
Arrangement of
43 NE-01-T-OH-TYPI-1004-0
Cantilevers on
Drop-Arms
General
44 NE-01-T-OH-TYPI-1005-0 Arrangement of
Steel Portals
General
Arrangement of
45 NE-01-T-OH-TYPI-1006-0
Uninsulated
Overlap
Contract NE-01 Addendum to Volume-5 TENDER DRAWINGS
General
46 NE-01-T-OH-TYPI-1007-0 Arrangement of
Insulated Overlap
General
47 NE-01-T-OH-TYPI-1008-0 Arrangement of
Neutral Section
General
48 NE-01-T-OH-TYPI-1009-0 Arrangement of
Anticreeps
General
49 NE-01-T-OH-TYPI-1010-0 Arrangement of
OHE Termination
General
51 NE-01-T-OH-TYPI-1012-0 Arrangement of
Guy Rod Assembly
General
53 NE-01-T-OH-TYPI-1014-0 Arrangement of
Suspension of 2
Contract NE-01 Addendum to Volume-5 TENDER DRAWINGS
Messenger Wires
General
Arrangement of
54 NE-01-T-OH-TYPI-1015-0 OHE at Turnouts,
Crossovers and
Diamond Crossing.
General
55 NE-01-T-OH-TYPI-1016-0 Arrangement of
Top Tube Assembly
General
Arrangement of
56 NE-01-T-OH-TYPI-1017-0
Suspension of
Messenger Wire
General
Arrangement of
57 NE-01-T-OH-TYPI-1018-0
Bracket Tube
Assembly
General
Arrangement of
58 NE-01-T-OH-TYPI-1019-0
Register Arm
Assembly
General
Arrangement of
59 NE-01-T-OH-TYPI-1020-0
Steady Arm
Assembly
General
Arrangement of
60 NE-01-T-OH-TYPI-1021-0
Wind Stay
Droppers
Contract NE-01 Addendum to Volume-5 TENDER DRAWINGS
General
Arrangement of
61 NE-01-T-OH-TYPI-1022-0
Contact Wire
Registration
General
Arrangement of
Automatic
62 NE-01-T-OH-TYPI-1023-0
Tensioning Devices
(5 Pulley Block
Type)
General
63 NE-01-T-OH-TYPI-1024-0 Arrangement of
Dropper Assembly
General
64 NE-01-T-OH-TYPI-1025-0 Arrangement of
Jumper Assembly
General
Arrangement of
65 NE-01-T-OH-TYPI-1026-0
Section Insulator
Assembly
General
Arrangement of
66 NE-01-T-OH-TYPI-1027-0 Automatic
Tensioning Devices
(Gas Type ATD)
General
Arrangement of
68 NE-01-T-OH-TYPI-1029-0
Provision of
Staggers
General
69 NE-01-T-OH-TYPI-1030-0 Arrangement of
Guy Rod in Depot.
Typical Drawing
Showing Bonding
70 NE-01-T-OH-TYPI-1031-0
of OHE Structure
to Rail
Typical Drawing
Showing
71 NE-01-T-OH-TYPI-1032-0 Connection of OPC
to Rail/Connecting
Plate
Typical Drawing
Showing
Connection of OPC
72 NE-01-T-OH-TYPI-1033-0
and BEC to
Rail/Connecting
Plate
Typical Drawing
Showing
73 NE-01-T-OH-TYPI-1034-0
Connection of OPC
to Earth Pit/BEC
Typical Drawing
Showing
74 NE-01-T-OH-TYPI-1035-0 Connection
Between two
OPC’s
Contract NE-01 Addendum to Volume-5 TENDER DRAWINGS
Typical Drawing
Showing
Connection of RC
to Rail
75 NE-01-T-OH-TYPI-1036-0
Typical Drawing
75 NE-01-T-OH-TYPI-1036-0
Showing
Connection of
RC(240 sq. mm) to
Rail
Salient Technical
76 NE-01-T-OH-TYPI-1037-0 features of OHE
Structures
Salient Technical
features of Cables,
77 NE-01-T-OH-TYPI-1038-0
wires and
Conductors
Arrangement of
Bracket Assembly
78 NE-01-T-OH-TYPI-1039-0
for Tramway Type
OHE (Regulated)
Typical Drawing
Showing Cross-
79 NE-01-T-OH-TYPI-1040-0
Section of OHE
Arrangement
Typical Drawing
Showing Earthing
80 NE-01-T-OH-TYPI-1041-0 and Bonding for
Switching devices
on Masts
81 NE-01-T-OH-TYPI-1042-0 General
Arrangement of
Contract NE-01 Addendum to Volume-5 TENDER DRAWINGS
Short Neutral
Section Assembly
SCADA DRAWING
SCADA - Control
NE-01-T-CM-TYPI-
85 and Monitoring
1001-0
Block Diagram
SCADA -
NE-01-T-CM-TYPI-
86 Equipment Layout
1002-0
at OCC
INTERFACE DRAWING
General
Arrangement of
Suspension of
87 NE-01-T-IN-OHPS-1001-0
OHE/OPC/RC from
Platform Shed Roof
Trusses
88 NE-01-T-IN-OHPS-1002-0 General
Arrangement of
Contract NE-01 Addendum to Volume-5 TENDER DRAWINGS
OHE Masts on
Parapets
General
Arrangement of
89 NE-01-T-IN-OHPS-1003-0
Anchor on
Parapets
90 General
Arrangement of
Booster
Transformers on
Viaduct
General
Arrangement of
Masts on Parapet
91 NE-01-T-IN-OHPS-1005-0
for Supporting
Pole-Mounted
Equipments
Typical Drawing
Showing Earthing
92 NE-01-T-IN-OHPS-1006-0
Arrangements at
Stations
Typical Drawing
93 NE-01-T-IN-OHPS-1007-0 Showing Integral
Transverse Links
Arrangements for
Metallic Masses at
Stations
Earthing on
Viaduct - Earthing
95 NE-01-T-IN-OHPS-1009-0
Arrangement in
Piles and Piers
Earthing on
Viaduct - Earthing
96 NE-01-T-IN-OHPS-1010-0
Arrangement in
Girders
Earthing on
97 NE-01-T-IN-OHPS-1011-0 Viaduct - Earthing
on Plinth
Schematic
Arrangement of
Earthing-
98 NE-01-T-IN-TYPI-1000-0 Connection to
Buried Rails at
Traction
Substation
NE-01-T-IN- Drawing
99 NE-01-T-IN-TYPI-1001-0 Cable Tray Details
TYPI-1001-0-R-1 replaced
Line-3
3.3 kV Cable
25 kV Cable
2 3 4 5 6
1
SECTOR 71 SECTOR 50 SECTOR 78 SECTOR 101 SECTOR 81 DADRI ROAD
M
CH: 0.00 CH: 1341.2 CH: 2372.7 CH: 3511.7 CH: 4419.2 CH: 6431.9 DN LINE
UP LINE
UP LINE UP LINE
SS SSP
SECTOR 78 SECTOR 81
FP
SECTOR 71
FP
SECTOR 83
SS SSP
SECTOR 142 SECTOR 144 SP
SECTOR 147
13 14 15 16 17
M M
M M
SECTOR 153 SECTOR 146 SECTOR 149 KNOWLEDGE PARK II PARI CHOWK
NG
CH: 16024.9 CH: 17600.5 CH: 19225.9 CH: 22191.6 CH: 23288.7
SI
OS
FP
SECTOR 153 SSP SSP
SECTOR 149 PARI CHOWK
18 19 20 21
Ch: 28689.3m
End OF Track
ALPHA-1 ALPHA-2 DELTA-1 DEPOT STATION
CH: 24376.0 CH: 25908.8 CH: 27160.8 CH: 28086.0
DN LINE DN LINE DN LINE
M M
TO
AS
DE
SS
NS
PO
/S
ALPHA 2
NS
T
SSP
DEPOT STATION To Rolling
AS
NS
Stock Depot
TENDER DRAWING
/S
To Rolling
NS
Stock Depot
NOTE: The Booster Transformer shall be provided only from DELHI METRO RAIL CORPORATION LIMITED
Knowledge Park-II to DELTA-1 station (approx. 4 KM section) PROJECT :- NOIDA - GRETER NOIDA CORRDOR
TRANSFORMERS
LOCAL
33000/415 V
Indicative details
DISTRIBUTION scope of work by others
To Link Line- 3 LOCAL
PCT PCT PCT PCT PCT PCT PCT PCT PCT PCT PCT PCT PCT PCT PCT PCT PCT PCT PCT PCT PCT PCT PCT PCT PCT PCT PCT PCT PCT PCT PCT PCT PCT PCT PCT PCT PCT PCT PCT PCT PCT PCT PCT PCT PCT PCT B
For
Future
NO
TO PD TO PD TO PD
TO 415 MDB TO 415 MDB TO 415 MDB TO 415 MDB TO 415 MDB TO 415 MDB TO 415 MDB TO 415 MDB TO 415 MDB TO 415 MDB TO 415 MDB TO 415 MDB TO 415 MDB TO 415 MDB TO 415 MDB TO 415 MDB TO 415 MDB TO 415 MDB TO 415 MDB TO 415 MDB TO 415 MDB
OF ESR OF ESR OF ESR OF ESR OF ESR OF ESR OF ESR OF ESR OF ESR OF ESR OF ESR OF ESR OF ESR OF ESR OF ESR OF ESR OF ESR OF ESR OF ESR OF ESR OF ESR
SECTOR 71 SECROR 50 SECTOR 78 SECTOR 101 SECTOR 81 DADRI ROAD SECTOR 83 SECTOR 137 SECTOR 142 SECTOR 143 SECTOR 144
SECTOR 153
AMS
AUXILIARY
MAIN
TRANSFORMERS
TRANSFORMERS
LOCAL
33000/415 V
Indicative details
DISTRIBUTION scope of work by others
LOCAL
PCT PCT
Extension
A
Future
B PCT PCT PCT PCT PCT PCT PCT PCT PCT PCT PCT
PCT
PCT PCT PCT PCT PCT PCT PCT PCT PCT PCT PCT PCT PCT PCT PCT PCT PCT PCT PCT PCT PCT PCT PCT PCT PCT PCT PCT PCT PCT PCT
ITC
NO
33/25 kV 33/25 kV
1ph, 2 MVA 1ph, 2 MVA
TO 415 MDB TO 415 MDB Transformer Transformer
OF ESR OF ESR TO PD
TO 415 MDB TO 415 MDB 25 kV to Depot 25 kV to Depot
OF ESR OF ESR Feeding Post TO 415 MDB Feeding Post TO 415 MDB
TO 415 MDB TO 415 MDB TO 415 MDB TO 415 MDB TO 415 MDB TO 415 MDB TO 415 MDB TO 415 MDB TO 415 MDB TO 415 MDB TO 415 MDB TO 415 MDB TO 415 MDB TO 415 MDB TO 415 MDB TO 415 MDB TO 415 MDB
OF ESR OF ESR
OF ESR OF ESR OF ESR OF ESR OF ESR OF ESR OF ESR OF ESR OF ESR OF ESR OF ESR OF ESR OF ESR OF ESR OF ESR OF ESR OF ESR
SECTOR 147 SECTOR 153 SECTOR 146 SECTOR 149 KNOWLEDGE PARK II PARI CHOWK ALPHA 1 ALPHA 2 DELTA 1 DEPOT STATION ROLLING STOCK DEPOT ASS-1 ROLLING STOCK DEPOT ASS-2
Switchgear = 1250 A
TCT
CIRCUIT BREAKER
Station A/T = 315 KVA X 2
TCT
33/0.415
25 KV ISOLATOR(LOCALLY OPERATED)
M 25 KV ISOLATOR(MOTORIZED)
VT
VT
VT
VT
VT
VT
VT
25 KV INTERRUPTER
25 KV POTENTIAL TRANSFORMER
SM 109
SM 110
SM 111
SM 112
SM 113
SM 114
SM 115
M M M M M M M
25 KV CIRCUIT BREAKER
CURRENT TRANSFORMER
SS 108
NC
* INTERLOCKED ISOLATORS
CT CT CT
SM 101 M M SM 102
DN
MAIN LINE
UP
R-1