Progress Date: 27-10-2017 FLOAT-5 PROGRESS OF WORK

Achieved / Completed Actual d


Completion
Sl Total upto
Description of Work Unit on 27 Target Date Date of
No. qty. 26- Total %
Oct as of 18/8 Start
Oct

1 M/s L & T

BATCH PLANT-Oveall
A Batch Plant-Building
1 Column Upto +9.20MLvl Lifts 48 48 48 100% 15-Jul-17
2 Silo Beams Rm 170 170 170 100% 27-Jul-17
3 Cones Erection Nos. 10 10 0 10 100% 31-Aug-17 24-Aug-17
B Cullet Buildimg
1 Deck Slab M3 35 35 35 100% 16-Aug-17 27-Jul-17
C Mixure Builing
1 Slab +3.3mLvl Cum 60 60 60 100% 27-Jul-17
2 Columns upto +9.1m Lifts 24 24 0 24 100% 24-Aug-17 18-Aug-17
3 Slab @ +9.1m Cum 68 68 0 68 100% 5-Sep-17 19-Sep-17
4 Columns upto +13.7m Lifts 28 0 0 0 0% 22-Sep-17
5 Slab @ +13.7m Cum 60 0 0 0 0% 31-Oct-17
D Sand Unloading Shed & HTU 23-Jun-17
E Big bag unloading shed 16-Mar-17
CHIMNEY
1 Chimney Slipping-1st stage Rm 13.40 13.40 13.40 100% 19-Jan-17
2 Chimney Slipping-2nd stage Rm 58.5 58.50 58.50 100% 31-Mar-17
3 Chimney Slipping-3rd stage Rm 32.62 32.62 0.00 32.62 100% 21-Aug-17 28-Aug-17
4 Corbel @ 58.5m Set 1 1 1 100% 24-Aug-17
5 Corbel @ 86.5m Set 1 1 1 100% 7-Oct-17
FLUE DUCT
1 Near Furnace Raft Cum 32.00 32.00 32.00 100% 31-Jul-17
2 Near Furnace Wall 1st Lift Lifts 2 2 2.00 100% 2-Aug-17
3 Near Furnace Wall 2nd Lift Lifts 2 2 2.00 100% 9-Aug-17
4 Near Furnace Wall 3rd Lift Lifts 2 2 2.00 100% 24-Aug-17 14-Aug-17
5 Sloped Part-1 Raft Cum 32.00 32.00 32.00 100% 31-Jul-17
6 Sloped part-1 Wall 1st Lift Lifts 2 2 2.00 100% 12-Aug-17
7 Sloped part-1 Wall 2nd Lift Lifts 2 2 2.00 100% 26-Aug-17 17-Aug-17
8 Sloped Part-2 Raft Cum 24.00 24.00 24.00 100% 8-Aug-17
9 Sloped part-2 Wall 1st Lift Lifts 2 2 2.00 100% 23-Aug-17 14-Aug-17
10 Sloped Part-3A Raft Cum 14.50 14.50 14.50 100% 18-Aug-17 15-Aug-17
11 Sloped part-3A Wall 1st Lift Lifts 2 2 2.00 100% 26-Aug-17 14-Aug-17
12 Sloped Part-3B Raft Cum 14.00 14 14.00 100% 21-Aug-17 14-Aug-17
13 Sloped part-3B Wall 1st Lift Lifts 2 2 2.00 100% 26-Aug-17 14-Aug-17
FURNACE BUIILDING
A Main Building
1 Completed
B Transformer Room (Btn. 3-5)
1 RCC Column 1st Lft Up to PB Lifts 9 9 9 100% 25-Apr-17
2 RCC-Tie Beam @ -11m Rm 48 48 48 100% 26-Jun-17
3 RCC Column 2nd Lft Up to PB @ -4.5m Lifts 9 9 9 100% 30-Jun-17
C Transformer Room (Btn. 8-9)
1 RCC Column 1st Lft Up to PB Lifts 6 6 6 100% 25-Apr-17
2 RCC-Tie Beam @ -11m Rm 30 30 30 100% 10-Jul-17
3 RCC Colimn 2nd Lft Up to PB @ -4.5m Lifts 6 6 0 6 100% 5-Aug-17
D Gas Preparation Room
1 RCC Column 1st Lift Nos. 6 6 6 100% 1-May-17
2 RCC Column upto -4.5m level Nos. 6 6 6 100% 17-Jul-17 18-Aug-17
3 Plinth Beams @ -4.5m Level Rm 28 28 0 28 100% 8-Aug-17 5-Oct-17
4 RCC Slab Cum 40 40 0 40 99% 9-Oct-17
E Peripheral Drains (N,S W sides)
1 Completed Rm 180 180 180 100% 19-Jun-17
FLOAT
1 Plinth Beam RM 1345 1345 0 1345 100% 29-Dec-16
2 Column 2 nd Lift-Upto Roof Slab Nos 173 173 173 100% 5-Jan-17
3 Slab @ 0.0m Level Nos 6 6 6 100% 12-Feb-17
4 Column Above 0.0 m slab Lifts 152 152 152 100% 16-Aug-17 16-Mar-17
5 Equipement Column Lifts 96 96 96 100% 30-Aug-17 19-Apr-17
6 Slab @ 4.70 M lvl Nos 6 6 6 100% 21-Aug-17 5-May-17
7 Cols upto 5.6m with Bolt Fixing Nos 36 36 36 100% 25-Aug-17 25-Jun-17
8 SFRC Flooring (Z-1&2) Part 9 9 0 9 100% 25-Aug-17 3-Aug-17
9 Grade Slab Flooring (Z-3) Part 2 2 0 2 100% 6-Oct-17
10 Tweel Platform(zone 3) Part 1 1 0 1 100% 11-Oct-17
11 Blower Foundation Nos. 3 3 0 3 100% 28-Aug-17
LEHR (KSV + SRC)
1 Excavation for footing Nos 116 116 116 100% 13-Sep-16
2 PCC Nos 116 116 116 100% 14-Oct-16
3 RCC for footing Nos 116 116 116 100% 22-Nov-16
4 Column 1st Lift Nos 125 125 125 100% 17-Dec-16
5 Plinth Beam RM 1490 1490 1490 100% 29-Dec-16
6 Column above PB 1st Lift Nos 125 125 125 100% 23-Jan-17
7 Column above PB 2nd Lift Nos 125 125 125 100% 23-Jan-17
8 Slab @ 0.0m Lvl Nos 4 4 0 4 100% 11-Sep-17 2-May-17
9 Pedestal +1m Lvl Nos 80 80 0 80 100% 18-Sep-17 6-Jul-17
10 Cable Trench RCC Raft Rm 160 160 0 160 100% 3-Aug-17
11 Cable Trench RCC Wall 1st lift Rm 293 293 0 293 100% 5-Aug-17
12 Cable Trench RCC Wall 2nd lift Rm 194 194 0 194 100% 17-Aug-17
13 DG Foundation No 3 3 0 3 100% 5-Aug-17
14 DG Stack Foundation Raft No 1 1 0 1 100% 18-Aug-17
15 DG Stack Pedestal 1st Lift No 1 1 0 1 100% 25-Aug-17
16 DG Stack Pedestal 2nd Lift No 1 1 1 100% 27-Aug-17
17 Flooring @ -4.5m Sqm 3320 1675 220 1895 57% 14-Sep-17
WARE HOUSE
1 Plinth Beam Rm 468 468 468 100% 11-Feb-16
2 PCC for Flooring Sqm 30085 28464 181 28464 95% 25-Sep-17 23-Jan-17
3 SFRC Flooring Sqm 30085 28302 0 28302 94% 30-Sep-17 3-Mar-17
4 PCC in Tunnel Sqm 1892 1892 0 1892 100% 3-Mar-17
5 RCC in Cullet Tunnel raft Sqm 1892 1892 1892 100% 25-Mar-17
6 RCC Wall in Tunnel Rm 498 498 498 100% 14-Aug-17 1-Jun-17
7 Loading Bay Raft Nos 6 3 0 3 50% 20-Jul-17
8 Loading Bay Wall Final Lift Lifts 12 6 0 6 50% 24-Jul-17
9 Tunnel Columns Nos 29 29 0 29 100% 12-Jul-17
10 Tunnel Top slab Sqm 1412 1412 0 1412 100% 1-Aug-17
11 Retaining Wall Along Grid-99, Raft Rm 66 37.0 0 37.0 56% 27-Aug-17
12 Retaining Wall Along Grid-99 Rm 66 25.5 0 25.5 39% 30-Aug-17
13 Optical Lab Plinth Beam Rm 96 36.0 0 36.0 38% 19-Oct-17
14 Optical Lab Column upto +0.05m slab Nos 28 0.0 0 0.0 0%
15 Optical Lab +0.05m Slab Nos 1 0.0 0 0.0 0%
16 Optical Lab upto +4.2m Column Nos 28 0.0 6 6.0 21%
17 Optical Lab +4.2m Slab Nos 1 0.0 0 0.0 0%
18 Retaining wall Raft Along Grid 63 Rm 17 4.0 0 4.0 24%
19 Retaining Wall Along Grid 63 Rm 17 0.0 0 0.0 0%
20 MCC Room CL2 Raft Nos 1 1.0 0 1.0 100% 10-Oct-17
21 MCC Room CL2 Column Nos 12 6.0 0 6.0 50%
22 MCC Room CL2 Slab Nos 1 0.0 0 0.0 0%
CULLET YARD
1 North Side PCC Rm 153 57 0 57 37% 3-Aug-17 19-Sep-17
2 North Side Raft Rm 153 55 0 55 36% 3-Aug-17 23-Sep-17
3 North Side Wall 1st Lift Rm 153 53 0 53 35% 28-Aug-17 6-Oct-11
3 North Side Wall 2nd Lift Rm 153 51 0 51 33% 13-Oct-17
4 East Side Raft Rm 59 6 0 6 10% 14-Aug-17 23-Sep-17
5 East Side Wall 1st Lift Rm 59 6 0 6 10% 5-Sep-17 3-Oct-17
6 South Side Raft Rm 186 112 0 112 60% 21-Aug-17 20-Aug-17
7 South Side Wall 1st Lift Rm 186 104 0 104 56% 15-Sep-17 28-Aug-17
8 South Side Wall 2nd Lift Rm 186 42 37 79 42% 15-Sep-17 28-Aug-17
9 South Side Wall 3rd Lift Rm 186 42 0 42 23% 15-Sep-17 9-Sep-17
10 West Side Raft Rm 59 7 0 7 12% 15-Sep-17 17-Oct-17
2 M/s SRC
A CONVEYOR BELT FDN. 22-Feb-17
B Access Bridge - 1&2
a Part-1 11-Feb-17
b Part-2 5-May-17
C Access Bridge - 27-29
a Part-1 10-Mar-17
b Part-2 5-May-17
D Cooling Towers
a CT-1- CKTA
1 Column - 1 lift Nos 30 30 30 100% 30-Jul-17
2 Column -2 lift Nos 30 30 30 100% 19-Aug-17 13-Aug-17
3 RCC Beam Rm 333 333 333 100% 30-Aug-17 15-Aug-17
b CT-2-CKTB
1 RCC Beam Rm 155 155 155 100% 16-Aug-17 5-Aug-17
E Retaining Wall in Cooling Tower Area
1 Excavation Rm 100 100 100 100% 19-Jun-17
2 PCC for Raft Rm 100 100 100 100% 19-Jun-17
3 RCC for Raft Rm 100 100 100 100% 22-Jun-17
4 Wall RCC Rm 100 100 100 100% 30-Jun-17
F IW/RW Tank Foundation 19-Apr-17
G Tank foundation -Surge Tank 13-Apr-17
H Pump foundation (Cooling tower area)
1 PCC Nos 7 7 7 100% 19-Sep-17
2 Footing concrete Nos 7 7 7 100% 21-Sep-17
3 Pedestal Nos 7 7 7 100% 22-Sep-17
I External Pipe Rack (Module 1 to 6)
1 Excavation Nos 32 32 32 100% 20-Aug-17 7-Mar-17
2 PCC Nos 32 32 32 100% 21-Aug-17 10-Mar-17
3 Footing concrete Nos 32 32 32 100% 24-Aug-17 25-Mar-17
4 Pedestal 1st lift Nos 78 78 78 100% 27-Aug-17 1-Apr-17
5 Pedestal 2 nd lift with bolt Nos 78 78 0 78 100% 30-Aug-17 6-May-17
J External pipe rack (Module 7 to 12)
1 Excavation Nos 26 15 0 15 58% 8-Aug-17
2 PCC Nos 26 15 0 15 58% 8-Aug-17
3 Footing concrete Nos 26 4 0 4 15% 10-Aug-17
4 Pedestal 1st lift Nos 60 22 4 26 43% 18-Aug-17
5 Pedestal 2 nd lift with bolt Nos 60 12 4 16 27% 27-Aug-17
K External pipe rack (Module 13 & 14 )
1 Excavation Nos 5 2 0 2 40% 15-Sep-17
2 PCC Nos 5 2 0 2 40% 15-Sep-19
3 Footing concrete Nos 5 2 0 2 40% 21-Sep-17
4 Pedestal 1st lift Nos 16 6 0 6 38% 25-Sep-17
5 Pedestal 2 nd lift with bolt Nos 16 6 0 6 38% 25-Sep-17
L Pipe Sleepers
1 Excavation Nos 18 0 0 0 0%
2 PCC Nos 18 0 0 0 0%
3 Footing concrete Nos 18 0 0 0 0%
4 Pedestal 1st lift Nos 18 0 0 0 0%
5 Pedestal 2 nd lift with bolt Nos 18 0 0 0 0%
M OCL Tunnel 20-Apr-17
N HFO Tank 12-May-17
O Compressor Room
1 Excavation No 29 29 0 29 100% 27-Jun-17
2 PCC No 29 29 0 29 100% 29-Jun-17
3 Footing No 29 29 0 29 100% 30-Jun-17
4 Column upto Plinth Beam No 27 27 0 27 100% 6-Jul-17
5 Receiver foundation Pedestal No 2 2 0 2 100% 9-Sep-17
6 Pinth Beam concrete RM 226 226 226 100% 9-Sep-17
7 Column upto +0.700M Level Beam and Slab Lifts 66 66 0 66 100% 11-Sep-17
8 Beam and Slab at +0.700M Level No 1 1 0 1 100% 9-Oct-17
9 RC Kerb Wall Rm 86
10 Column upto +1.300m level Tie beam Lifts 2
11 Column upto +2.500m level Tie beam Lifts 15
12 Tie beam @ +2.500m Level No 1
13 Column upto +3.375m Level Lifts 2
P ESP Building
1 Excavation No 22 7 0 7 32% 31-Aug-17
2 PCC No 22 7 0 7 32% 31-Aug-17
3 Footing concrete No 22 7 0 7 32% 1-Sep-17
4 Pedestal 1st Lift No 39 21 2 23 59% 4-Sep-17
5 Pedestal 2nd Lift No 39 19 0 19 49% 18-Sep-17
Q Fire Pump Room
1 Excavation No 10 5 0 5 50% 25-Oct-17
2 PCC No 10 0 3 3 30%
3 Footing concrete No 10 0 0 0 0%
4 Pedestal 1st Lift No 10 0 0 0 0%
5 Pedestal 2nd Lift with bolts No 10 0 0 0 0%
Q M/s L & T
WTP

A Collection Water tank & Sludge Bed


1 Excavation No 4 4 0 4 100% 9-Sep-17
2 PCC for Raft No 1 1 0 1 100% 15-Sep-17
3 PCC for Footing No 3 3 0 3 100% 15-Sep-17
4 RCC for Raft No 1 1 0 1 100% 18-Sep-17
5 RCC for Footing No 3 3 0 3 100% 19-Sep-17
6 Collection water tank Wall 1st Lift No 1 1 0 1 100% 26-Sep-17
7 Column First Lift upto Sludge tank Raft No 3 3 0 3 100% 26-Sep-17
8 Beam and slab for Sludge Bed @ -5.150 m Lvl No 1
9 Collection Water tank Wall 2nd lift No 1

B MCC & PLC Panel Room, UF & RO Room


1 Excavation for footing No 14 9 0 9 64% 9-Sep-17
2 PCC for footing No 14 9 0 9 64% 15-Sep-17
3 RCC for footing No 14 9 0 9 64% 20-Sep-17
4 Column upto Tie beam @ -5.900m Level No 14 7 0 7 50% 21-Sep-17
5 Tie beam @ -5.900m Level No 1 0 0 0 0%
6 Column 1st Lift upto beam @ -1.650 m LvL No 14 0 0 0 0%
7 Column 2nd Lift upto beam @ -1.650 m Lvl No 14 0 0 0 0%
8 Tie beam @ -1.650m Lvl including bolt' No 1 0 0 0 0%

C Soft Water Tank


1 Excavation for Raft No 1 1 1 100% 20-Sep-17
2 PCC for Raft No 1 1 1 100% 21-Sep-17
3 RCC for Raft No 1 1 1 100% 26-Sep-17
4 Wall RCC with Bolt No 1 1 0 1 100% 27-Sep-17
5 Filling with M-sand No 1 0 0 0%
6 Sand Bitumen Top Layer No 1 0 0 0%

D Tank MMF 3&4,SBA & SAC Tank


1 Excavation for Raft No 2 2 2 100% 20-Sep-17
2 PCC for Raft No 2 2 2 100% 27-Sep-17
3 RCC for Raft No 2 2 0 2 100% 28-Sep-17
4 Pedestal 1st Lift No 16 16 0 16 100% 11-Oct-17
5 Pedestal 2nd Lift No 16 0 0 0%

E HRSCC Clarifier, Filter and Feed Tank


1 Excavation for Raft No 17 8 8 47% 10-Oct-17
2 PCC for Raft No 17 8 8 47% 15-Oct-17
3 RCC for Raft No 17 0 0 0%
4 Pedestal 1st Lift No 20 0 0 0%
5 Pedestal 2nd Lift No 20 0 0 0%
Reporting Date: 28-10-2017
Actual dates

Date of Remarks
Completion

26-Jul-17
13-Aug-17
31-Aug-17

26-Aug-17

4-Aug-17
18-Sep-17
12-Oct-17

29-Jun-17
7-Jun-17

26-Jan-17
14-Aug-17
11-Oct-17
27-Aug-17
8-Oct-17

2-Aug-17
5-Aug-17
12-Aug-17
30-Aug-17
2-Aug-17
16-Aug-17
30-Aug-17
11-Aug-17
30-Aug-17
18-Aug-17
30-Aug-17
21-Aug-17
30-Aug-17
25-Jun-17
29-Jun-17
3-Jul-17

25-Jun-17
24-Jul-17
31-Aug-17

11-Jul-17
24-Aug-17
5-Oct-17
22-Oct-17

21-Jul-17

7-Oct-17
7-Aug-17
14-Aug-17
24-Aug-17
21-Sep-17
22-Aug-17
24-Aug-17
28-Sep-17
11-Oct-17
14-Oct-17
4-Oct-17

28-Mar-17
29-Mar-17
31-Mar-17
3-Apr-17
21-Jul-17
22-Aug-17
23-Aug-17
14-Sep-17
19-Sep-17
13-Oct-17
25-Oct-17
5-Sep-17
2-Sep-17
24-Aug-17
26-Aug-17
30-Aug-17

23-May-17

5-Aug-17
17-Aug-17
13-Sep-17

22-Sep-17
22-Sep-17

14-Oct-17
3-Aug-17

28-Apr-17
10-May-17

17-Jul-17
19-Jul-17

12-Aug-17
19-Aug-17
8-Sep-17

22-Jun-17

22-Jun-17
24-Jun-17
20-Sep-17
25-Sep-17
7-Jun-17
5-Jun-17

24-Sep-17
25-Sep-17
27-Sep-17

22-Aug-17
22-Aug-17
23-Aug-17
25-Aug-17
27-Aug-17
9-Aug-17
1-Jul-17

5-Sep-17
7-Sep-17
31-Aug-17
2-Sep-17
19-Sep-17
21-Sep-17
14-Oct-17
14-Oct-17

12-Sep-17
15-Sep-17
15-Sep-17
18-Sep-17
19-Sep-17
26-Sep-17
26-Sep-17

20-Sep-17
21-Sep-17
26-Sep-17
10-Oct-17

20-Sep-17
27-Sep-17
28-Sep-17
23-Oct-17

10-Oct-17