Metal Reinf.

For 2nd Floor Beam


Dimension = 0.20 x 0.30 Conc. Cover = 0.04
Stirrups Spacing = 3.00 @ 0.05 diam. Bar = 0.01
3.00 @ 0.10
Rest @ 0.20
LT = 108.85
# of Main Reinf. Beam = 6
L Of Stirrups = 0.88
# stirrups/6 m = 7
784
T# 6m RSB = = 131 pcs 16mm Ø 6m RSB
6

T# Stirrups = 424.00
# 6m RSB = 424 = 63 pcs 10mm Ø 6m RSB
7

Form Works
Plywood Form
P = 2(a+b) + 0.10
TB
P = 0.80
AT = 87.08
87.08
# plywood = = 31 pcs - 1/4" x 4' x 8'
2.88
2"x2" Wood Frame
# bdft = 31 x 25.06
# bdft = 776.86
776.86
Total pcs = = 167 pcs - 2" x 2" x 14' Good Lumber
4.67

For Two Way Slab


Slab Form
AT = 81.82 m2
81.82
# plywood = = 29 pcs - 1/4" x 4' x 8'
2.88

Scaffoldings
# bdft = 82 x 9.10
# bdft = 745 bdft
745
Total pcs = = 107 pcs - 2" x3" x 14' Good Lumber
7
Metal Reinf.
AT = 81.82
Spacing of S &B Bars = 0.10
Spacing of TB = 0.20
Spacing of CB = 0.20

# 6m RSB = 81.82 x 4.37


# 6m RSB = 358 pcs 12mm Ø 6m RSB

# kg Tie Wire = 81.82 x 0.59


# kg Tie Wire = 49 kg tie wire # 16 G.I. wire

Metal Reinforcement

Dimension of C1 = 0.25 x 0.25


Dimension of C2 = 0.40 x 0.20
Number of CB on C1 = 6
Number of C1 = 10
Number of C2 = 14
Second Storey Height = 2.80
Concrete CoverNETE 0.040
Concrete CoverETE 0.075
# of Main Reinf. C1 = 4
# of Main Reinf. C2 = 6
Dimension Roof Beam = 0.30 x 0.20
Lateral Spacing Column = 2@ 0.05
3@ 0.10
3@ 0.15
Rest = 4@ 0.20

For Column
Main Reinforcement

C1 L1 = 134.40 m
C2 L2 = 282.24 m
LT = 416.64 m
417
T# 6m RSB = = 70 pcs 16mm Ø 6m RSB
6

Lateral Ties
C1 LLT = 0.88 m
6.00
# of LLT/6 = = 6.82
0.88
T# of LT = 200
200
# 6m RSB = = 29 pcs 10mm Ø 6m RSB
7

LTiewire = 240.00
240.00
T# kg = = 5 kg tie wire # 16 G.I. wire
53

C1 LLT = 1.08 m
6
# of LLT/6 = = 5.56
# of LLT/6 = = 5.56
1.08
T# of LT = 280
280
# 6m RSB = = 47 pcs 10mm Ø 6m RSB
6

LTiewire = 504
504
T# kg = = 10 kg tie wire # 16 G.I. wire
53
Concrete Hollow Blocks

Roof Beam Thickness = 0.30


Second Storey Height = 2.80
Total length of W2 = 60.3 m
WLADDITIONAL = 25.1 m
Additonal Wall Height = 0.9 m
Doors:
# SET
1 D1 = 2.10 x 1.00 = 2.10
4 D2 = 2.10 x 0.80 = 6.72
2 D3 = 2.10 x 0.70 = 2.94
Windows: =
1 W1 = 1.20 x 1.00 = 1.20
5 W2 = 1.20 x 1.20 = 7.20
1 W3 = 1.20 x 0.60 = 0.72
1 W4 = 0.60 x 0.60 = 0.36

Total Area of W2 = 152.10 m2

Number of CHB for W2:


CHB = 152.10 x 12.50
= 1902 pcs

Metal Reinf. For Wall


AT = 152.10
for Vert. Reinf.
L = 152.10 x 2.13
L = 323.98 m
for Hor. Reinf.
L = 152.10 x 2.15
L = 327.02 m
LT = 651.00
651.00
# 6mm RSB = = 109 pcs 12mm Ø 6m RSB
6
# kg Tie Wire = 152 x 0.026
# kg Tie Wire = 4 kg tie wire # 16 G.I. wire

Cement Mortar
W2
CHB = 1902.00 pcs
Convert to unit of 100 = 1902.00
= 19.02
100

Class B Misture , 40kg Cement in Bag for 15 x 20 x 40 CHB

Cement: 19.02 x 8.104 = 154.14 bags


Sand: 19.02 x 0.675 = 12.84 m3

Frorm Works
Plywood Form
P = 2(a+b) + 0.20
C1 P = 1.20
C2 P = 1.40
AT = 79.00
79.00
# plywood = = 28 pcs - 1/4" x 4' x 8' Ordinary Plywood
2.88
2"x2" Wood Frame
# bdft = 28.00 x 29.67 bdft
# bdft = 830.76

Total # 2"x2" Wood Frame


T# bdft = 830.76
Total pcs = 830.76
4.67
Total pcs = 178 pcs - 2" x 2" x 14' Good Lumber

Scaffolding for Column


LT = 60.00
Vertical Support
# bdft = 60.00 x 7
# bdft = 420.00 bdft
420.00
Total pcs =
7
Total pcs = 60 pcs - 2" x 3" x 14' Good Lumber
Horizontal Support
# bdft = 60.00 x 21
# bdft = 1260.00
Total pcs = 1260.00
7
Total pcs = 180 pcs - 2" x 2" x 14' Good Lumber
Diagonal Brace
# bdft = 60.00 x 12
# bdft = 702.00
Total pcs = 702.00
4.67
Total pcs = 151 pcs - 2" x 2" x 14' Good Lumber
CONCRETE COLUMN

Beam Thickness = 0.30


First Storey Height = 2.80
Number of C1 = 10
Number of C2 = 14.00
C1 Dimensions of C1 = 0.25 x 0.25
C2 Dimensions of C1 = 0.40 x 0.20
Volume of C1 = 1.56 m3
Volume of C2 = 2.80 m3
Total Volume of CS = 4.36 m3

Class A Mixture, 40kg Cement in Bag

Cement: 4.36 x 9.00 = 39.26 bags


Sand: 4.36 x 0.50 = 2.18 m3
Gravel: 4.36 x 1.00 = 4.36 m3

Concrete Works
2nd Floor Beam
VTOTAL = 6.53 m3
Class A Mixture, 40kg Cement in Bag

Cement: 6.53 x 9.00 = 58.78 bags


Sand: 6.53 x 0.50 = 3.27 m3
Gravel: 6.53 x 1.00 = 6.53 m3

Sanitary Works
Installation of Sanitary Pipes
PVC Sizes
LT 4"Ø = 13 m
13
# pcs 4"Ø x 20' = = 1 pcs 4"Ø x 20' PVC Pipe
20
PVC Elbows
# pcs 1"Ø = 3 pcs 1"Ø PVC Pipe
# pcs 4"Ø = 4 pcs 4"Ø PVC Pipe
PVC Tee
# pcs 1"Ø = 3 pcs 1"Ø PVC Pipe

2nd Floor Slab


AT = 81.82
Thickness of Slab = 0.125
VTOTAL = 10.23
Class A Mixture, 40kg Cement in Bag

Cement: 10.23 x 9.00 = 92.05 bags


Sand: 10.23 x 0.50 = 5.11 m3
Gravel: 10.23 x 1.00 = 10.23 m3

Ceiling Joist
AT = 81.82
2"x2", 0.4m x 0.6m spacing
# bdft = 81.82 x 5.373
# bdft = 439.62
Total pcs = 439.62
4.67
Total pcs = 95 pcs - 2" x 2" x 14' Good Lumber
Ceiling Board
AT = 81.82
2"x2", 0.4m x 0.6m spacing
Total pcs = 81.82
2.88
Total pcs = 29 pcs - 1/4" x 4' x 8' Marine Plywood

Straircase
Metal Reinforcement
LT = 48.61
48.61
#6mm RSB = = 9 pcs 10mm Ø 6m RSB
6
LTiewire = 219
219
T# kg = = 4 kg tie wire # 16 G.I. wire
53
Stair Slab
AT = 8.50 m2
Thickness of Slab = 0.125 m
VTOTAL = 1.06 m3
Class A Mixture, 40kg Cement in Bag

Cement: 1.06 x 9.00 = 9.56 bags


Sand: 1.06 x 0.50 = 0.53 m3
Gravel: 1.06 x 1.00 = 1.06 m3

Electrical Works
Installation of Wires
Sizes
LT of 2.0 mm = 87 m 2.0mm TW
LT of 3.50.mm = 40 m 2.0mm TW
Installation of Switches & Outlets
Single Gang Switch
# pcs = 7
Two Gang Switch
# pcs = 9
Three Gang Switch
# pcs = 3
Convenience Outlet
# pcs = 28
Lighting Outlet
# pcs = 51

Metal Reinf. For Roof Beam


Dimension = 0.20 x 0.30
Stirrups Spacing = 3.00 @ 0.05
3.00 @ 0.10
Rest @ 0.20
LT = 85.70 m
# of Main Reinf. Beam = 6
L of stirrups = 0.88
# stirrups/6 m = 7
617
T# 6m RSB = = 103 pcs 16mm Ø 6m RSB
6

T# Stirrups = 381.00
381
# 6m RSB = = 56 pcs 10mm Ø 6m RSB
7

Form Works
Plywood Form
P = 2(a+b) + 0.10
TB
P = 0.80 m
AT = 68.56 m2
68.56
# plywood = = 24 pcs - 1/4" x 4' x 8'
2.88
2"x2" Wood Frame
# bdft = 24 x 25.06
# bdft = 601.44
601.44
Total pcs = = 129 pcs - 2" x 2" x 14' Good Lumber
4.67
Concrete Works
2nd Floor Beam
VTOTAL = 6.53
Class A Mixture, 40kg Cement in Bag

Cement: 6.53 x 9.00 = 58.78 bags


Sand: 6.53 x 0.50 = 3.27 m3
Gravel: 6.53 x 1.00 = 6.53 m3

W2
Area = 152.10 x 2
Area = 304.20 m2

Class B Misture , 40kg Cement for 16mm plaster thickness

Cement: 304.204 x 0.192 = 58.41 bags


Sand: 304.204 x 0.160 = 48.67 m3
PROJECT : TWO BEDROOM RESIDENTIAL BUILDING
OWNER: MR. DIXIE DISTOR
LOCATION: SAPANG I , TERNATE, CAVITE

SUMMARY OF BILL OF MATERIALS

1.CIVIL/STRUCURAL WORKS Php203,874.00 PhP


2. ROOFING MATERIALS Php77,260.00 PhP
3. PLUMBING PIPES AND FITTINGS Php22,168.00 PhP
4. PLUMBING FIXTURES AND ACCESSORIES Php8,532.00 PhP
5. FLOOR AND OTHER INTERIOR WORKS Php3,450.00 PhP
6. ELECTRICAL MATERIALS Php13,578.25 PhP
7. PAINTING MATERIALS Php20,865.00 PhP
8. DOORS AND WINDOWS Php37,480.00 PhP

TOTAL COST OF MATERIALS Php387,207.25


LABOR (35% MATERIAL COST) Php135,522.54 PhP
CONTINGENCIES ( 15% MATERIAL COST) Php58,081.09 PhP
VAT (2% MATERIALS COST) Php7,744.15 PhP

TOTAL PROJECT COST Php588,555.02 PhP