Sunteți pe pagina 1din 9

Well Foundations

for Bridges are Obsolete!!!


S.A.Reddi, Fellow Indian National Academy of Engineering

Introduction Pre-cast RC bored piles of to bouldery strata Despite best


2.5m diameter was first successfully efforts, the well only went down by
Bridge foundations are the most
realized in India for the old Thana 35.25 m after three seasons and at
complicated and difficult to
Creek Bridge constructed in 1960s. extra cost! The well was plugged at
construct. Unexpected difficulties
For the 13 Km long Saudi–Baharain RL 32.075 m and 5 nos 1.5 m dia
cause delays, extra costs and
Causeway large diameter pre-cast RCC bored piles (25-35m) were
revision of designs due to altered
pre-stressed bored piles were provided to anchor the well, one in
situations. Loss of human lives was
adopted. By 2005, piles of 2-3 m the middle through the dredge hole
normal rather than exception. In the
dia, upto 120m deep are extensively and 4 outside at the four corners.
Sixties, more than 50 lives were
used in the rest of the world. These Further a launching apron of crated
lost due to the accident during
new techniques eliminate boulder 3 m thick was laid making
pneumatic sinking operations for
complicated weather-dependent a circle of 60 m dia around the
well foundations of Mahanadi bridge
and risky operations in water. They well, at RL 61.00. These extra works
in Orissa. For Kali Bridge at Karwar
have reduced the delays caused further delay in the comp-
in Karnataka, pneumatic sinking
considerably and minimized the letion of the substructure works.
was required for inspection of the
technical and financial risks. The
founding surface of the wells. Apart Well foundations on
development of modern techniques
from delays and extra costs, large sloping rock:
has considerably reduced quantities
number of workers suffered caisson
disease. Due to difficulties in well
of materials used for foundations Brahmaputra Bridge at
as well as energy consumption and
sinking, two contractors left the job Jogighopa (2.28 km)
environmental impacts.
and the third took more than 5 The wells of main span were 11 m
years to complete the well Well Foundation x 17 m double ‘D’ type. Foundations
foundations. Alternative construction 17 & 18 were resting on hard rock
techniques and equipments have Problems at at steep incline of almost 1:1 slope.
emerged. With the introduction of It was not possible to rest the
advanced piling equipment, large
Brahmaputra Bridge
foundations partially on two types
diameter piles up to 3.5 m dia are at Tezpur of strata. Hence to found these
easily realized at a fast rate, with a The bridge was more than 3 km wells, 1500 mm dia anchor piles,
significant reduction in cost and long with 26 spans of 120 m and 2 12 nos for each foundation were
material quantities. Bridges shore spans of 70 m each, founded provided through the body of the
elsewhere are now constructed with on 12m dia Wells. Sinking well No.2 steining, extending to about 10 m
pile foundations. to full depth was not possible due below the cutting edge.

148 NBM&CW SEPTEMBER 2010


Additional cost was several The calculated maximum scour
crores. Effective use of Pile depth was 36 m below water level.
Foundations - Jamuna River The soil strata were sandy up to
Bridge in Bangladesh (figs.2 about 30 m followed by hard stiff
&3). clay. During construction, the wells
A 4.8 km long, four lane started tilting and the problems
road bridge with 100 m spans continued right through the sinking.
was constructed in the 1990s Despite extensive chiseling, the rate
on the Jamuna river of sinking was painfully slow.
(Brahmaputra in India). The Well 2 - The founding level was
foundation design was 64.7 m below the water level.
challenging. Very deep wells The rate of sinking through clay
are extremely slow to construct, was about 1.5 - 2 cm/hr. 3500
costly, increasing the total cost. crane hours were used to sink
Various alternatives were the well.
considered including caissons, Well 17 - The well shifted by 1.86
driven precast piles and driven m. The piers were to be retained
steel tubular piles. The only at the original position; resulting
viable option was large in excessive moments in the well.
Figure 1: Brahmaputra bridge foundations
No. 17 & 18 diameter tubular steel piles To counter the moments
driven at a rake (fig.2). The counterweight was provided in the
piles were fabricated in Korea, form of a dummy well sunk to a
shipped to site and installed depth of 20 m in the adjacent
by hydraulic hammer. The area and connected to the main
diameter of the piles ranged well through a common well cap.
between 2.5 and 3.15 m and Well 32 - The well shifted by
the steel tubes were filled with 1150 mm. A similar solution as in
concrete. Maximum pile length well 17 was adopted.
was 72 m below bed level. Well 4 - During concreting of
During one working season curb, sand leaked from the island
from October 1995 to June and the entire curb tilted and sank
1996 all the 121 main work by 4.5 m. A new sheet pile
piles plus two full scale trial cofferdam had to be erected and
piles were driven. a new well curb was cast. The
Figure 2: Pile foundations for Jamuna bridge
This optimization resulted total delay was one month.
in overall reduction in the Well 9 - the total height of the
bridge costs by more than steining except last 2 m was
50%. This solution also completed with 7.5 m balance
reduced the use of resources sinking. Due to presence of stiff
(concrete and steel) clay, 8 m sump was made to
considerably and was facilitate sinking. After several
beneficial to environmental weeks, the well suddenly jumped
Figure 3: Completed view of the Jamuna bridge
impact. The piles were by about 9 m with the top of
installed in 8 months; the well steining below water level. Work
Due to the steep incline, part of
foundations of three bridges across resumed after monsoon. A
the cutting edge was resting on the
the same river constructed in India temporary RC cofferdam was
rock while the other parts were
have taken 3-5 years each to constructed and the sunk well
overhanging. In order to contain the
complete. dewatered to expose and build
bottom plug, two rows of jet grouted up further steining. Time loss:
piles were introduced around the Damages During about 6 months.
periphery of the well steining which
Construction - Ganga Wells 3 & 4 -Wells were sunk by
acted as curtain wall (fig.1). 1500
about 44 and 37 m before the
dia piles also driven up to hard Bridge at Bhagalpur (4.6
monsoon season in 1996. The
rock along the periphery through km) wells were toppled due to scour
the steining. The completion of the The well foundations consist of and disappeared during the
project was extended by 3 years. single circular wells 11.6 m dia. floods. Based on a number of

150 NBM&CW SEPTEMBER 2010


trial bores well No.3 was found total height of steining except last 2 An Expensive
tilted along the bridge axis. Well m was concreted. The well was in
No.4 was found on the upstream the final stages of steining, with Solution Indeed !!
side along the direction of current. about 7.5 m to reach the founding The completion was delayed by
These wells weighing up to level. As the well was stuck up in more than one season as the
9900 t could not be restored and stiff clay, efforts were made to sink solution was based on an Expert
were abandoned. New wells were the well by creating a sump of about Committee investigation and report.
cast and sunk by changing the 8 m below the cutting edge. All of a This led to delay in finalization of
span arrangement. Floating sudden the well sank suddenly by the designs and drawings for the
caissons were used. about 9 m and the top of steining foundation well and necessity of
Extra cost and time - The cost on was below the water level by about issuing variation orders to cover the
completion was Rs.106 cr against 3.5 m. Rectification measures were items of cut-off walls and bed
accepted tender cost of Rs.55 cr! very expensive and time consuming. protection works which were not
The time overrun was 5 years! Ganga bridge at Varanasi: Very envisaged in the original contract.
stiff clay was encountered at 25 m
Tilts and Shifts in Well below and sinking of well Ganga Bridge, Patna
Foundations - Vasai foundations No. 3 and 5 was very The 5.6 km long bridge comprises
Creek Bridges Near difficult, did not move for three of 46 spans of 120 m each resting
months. Then well No.3 jumped by on 56 m deep well foundations
Mumbai several meters without any warning (12m dia.). Two of the wells in the
Bassein Creek road bridge near when two workers and one midstream (Nos. 41 and 45)
Mumbai (1970) faced problems of supervisor were taking sump encountered artesian conditions
heavy tilting of the well foundations. sounding. The tragic accident killed during the final stages of sinking
Two of the foundations no.4 & 6 all the three people. The well No.5 There was continuous sand
tilted very heavily and all attempt to also jumped by about 5 m and blowing filling the dredge hole to 5-
correct the tile failed. The was submerged in the water by 6 m above the cutting edge. Months
foundations were abandoned and 1m. of efforts to sink the well proved
the design of the bridge was futile. A technical advisory committee
changed to accommodate new Artesian Conditions took about a year for arriving at a
foundations and longer spans. The During Construction of solution. Temporary steel cofferdam
project was delayed by six years
with termination of the first contract,
Well Foundations was built enveloping the well and
an artificial head of about 6 m of
arbitration, litigation. Nepal Bridge (Kohalpur / water was created to counter act
Despite previous histories of Mahakali Section ) the sand bubbling. Delay: two years
two bridges built across the same Artesian conditions were
creek that faced problems with well Cracking of Well Steining
encountered during soil
foundations, the same were again investigations for the Shivganga During Construction
adopted for another Vasai Creek bridge (8 spans of 32 m). At Cracking of well steining is one of
Bridge. During construction, heavy locations P-4 and P-5 artesian head the serious problems faced many
tilting of wells was observed. The of about 4.3 m was encountered at times in the construction of well
corrective measures for one well about 17 m below ground level. foundations, resulting in time and
alone took almost two years The well was redesigned with cost overruns. The causes are
delaying completion of the foundation terminating above the usually:
foundations; costing about Rs. 2 artesian layer, resulting in shallow 1. Blasting, Dewatering
crores. foundations resting on clay. Due to 2. Insufficient steining thickness
founding the wells at shallow depth, 3. Jumping due to excessive sump
Sudden Jumping of Wells
it was necessary to provide 4. Sand blows
During Sinking adequate bed protection so as to 5. Surcharge due to dumping
Sometimes the well sinks suddenly prevent scour. The bed protection dredge material close to well.
due to excessive sump or weak consisted of : 6. Failure of cutting edges.
soil layer and the steining Upstream and downstream When such cracking occurs, at
disappears below water level, aprons least one season is lost for the
making it difficult to continue further Cut-off walls, upstream & investigation, developing remedial
work on the well steining. downstream measures, approvals of the same
In one of the well foundations Concrete floor etc. In the last 45 years, the author
in a bridge across river Ganga, the is aware of more then 200 cases
152 NBM&CW SEPTEMBER 2010
Analysis by the Federal
Highway Administration
(FHWA), USA
More than 100,000 bridges would
be constructed during the next two
decades. Foundations represent
about 30% or more of the cost of
the highway bridges. The
predominant type of foundation
Figure 5: Pasighat Bridge, Boulder system used for the highway
Figure 4: Pasighat Bridge, AP
dredged during well sinking
bridges in the US is pile. Many
bridges can tolerate significant
of bridges constructed by various beginning of sinking. After 15 years magnitudes of a total and differential
construction agencies, where the of struggle to pneumatically sink vertical settlement without becoming
dredge hole of well has to be filled the wells to RL – 50 m, the seriously over-stressed
with concrete due to cracks in designed founding level was
steining. drastically raised by 22m in 2002. Appreciation
During well sinking of Tapi The Indian Bridge Engineers are by
Major Bridges and large mentally tuned to
Bridge, Maharashtra, hard strata
was met. Due to blasting, extensive (Worldwide) on Pile providing well foundations for
bridges as a reflect action; whereas
cracks developed in steinings New Foundations
steinings had to be constructed it is very necessary to analyze the
Su Tong Bridge, China : The 6 km
inside the wells. The original comparative merits and demerits,
long Cable-stay bridge crosses
contract period was four years. construction time frame and cost of
Yangtze river near Shangai will carry
Attempts were made for five years construction of bridges with well/
a six lane highway with emergency
to sink the wells. Work was pile foundations before finally
lanes, with a record 1088 m main
suspended for five years for want choosing the type of foundation. An
span and 300 m high concrete
of decision to revise the founding analysis of the history of well
pylons. Each tower is supported on
level. An expert committee ultimately foundations during the last five
131 cast-in-situ bored piles 120 m
recommended raising the decades indicates innumerable
long and 2.7 m diameter. Due to
foundation level of wells by more difficulties, delays and cost overruns
strong currents, significant scour is
than 20m The bridge was in a majority of the cases.
expected around the foundations,
completed after fourteen years. The Realization of well foundations
and suitable scour protection is
contractor suffered losses due to requires special skills and
provided around the pylons. The
the delays. The owner suffered experience which are gradually
central span has a clearance of 62
substantial losses due to time dwindling.
m for container ships to pass
overrun. Delay: 10 years. Developments have taken place
through. The bridge used 200,000 t
in respect of large diameter pile
Extraordinary Delays in of steel, 1 million cum of concrete.
foundations as well as equipment
Stonecutters Bridge, Hong
Construction of Well Kong: The 1600 m long
for the same. The time and cost
Foundations Pasighat advantages of opting for pile
Stonecutters Bridge Hong Kong with
foundations have been amply
Bidge, Arunachal cable-stay span of 1018 m is one
demonstrated worldwide and to a
of the longest in the world. The
Pradesh, 703 m long bridge is founded on 3.0 m dia
limited extent in India. Piles up to a
The project started in 1987 and the diameter of 3m and depth of up to
piles, up to 90 m deep, socketted
construction of well foundations 120m have been realized for a
into rock. Bandra Worli Sea Link
continued for the next 20 years! As number of major bridges
Mumbai: The sea link consists of
per the design, based on worldwide, with cost saving of up to
5.6 km long, 8-laned bridge with
misleading soil data, six wells were 40% when compared to well
cable stayed portion of 600 m. The
to be sunk to about 50 m below foundations.
bridge is founded on 1.5 m
bed. The actual strata met with There is currently no restriction
diameter bored piles. Concrete for
during sinking were hard in the IRC Code regarding use of
the piles is M50 grade and for pile
conglomerate with densely pile foundation. However, many
caps is M60. Silica fume and fly
compacted and very large boulders Owners impose restrictions in the
ash are used for concrete
(fig.6) were found right from the tender documents, without any
preparation.
154 NBM&CW SEPTEMBER 2010
segments. This was made
possible by an high early strength
concrete which enabled pre-
stressing at 60 hours after
concreting. Fe500 steel
reinforcement bars were used for
the first time in India in a cantilever
construction bridge. The huge
Bearings with anchors were located
among highly congested
reinforcement; normal concrete
Figure 6: Chenab Bridge at Akhnoor-Longest Span Cantilever PSC Bridge,
eliminated wells
placement, vibration was
impossible. Special Conbextra
justification. The example cited sunk wells and go for a scheme Grout replaced normal High
above concerning the problems of with longer central span, eliminating Strength Concrete below bearings.
well foundations amply justifies a the water foundations altogether. Self–compacting concrete (S.C.C)
second look on the choice of With a 160m central span, both the was used for the first time for
foundations. In fact, the use of well main pier foundations were located concrete below the bearings.
foundations for bridges should be in the dry on the banks, resting on Segments on both sides of the
an exception rather than the rule. raft foundations. These foundations Pier were concreted simultaneously
were completed in months instead balancing the weights. When the
Chenab River Bridge at of decades earlier in unsuccessful 22nd segments were facing each
Akhnoor Near Jammu attempts to sink wells in water. The other and the shuttering of the 23rd
abutments consist of hollow box segment i.e. the linking segment
The project was started in the early
and piers consist of hollow was to have been placed there was
Seventies. A .scheme for a 231m
rectangular section on raft no level difference and the levels
long bridge with 5 spans
foundations. matched on both tips to the nearest
(3x46+2x46.5) upstream of existing
The superstructure was millimeter both in plan (centre line)
steel bridge was originally
designed and constructed as a as well as in elevation. This was
conceived. The scheme involved
continuous cantilever of 280m possible because every day the
construction of five well foundations
length, with a central span of 160m levels were maintained by a team
in the volatile Chenab River, to be
(longest in India at the time). Two of surveyors with the help of total
sunk through difficult strata – hard
pairs of cantilever gantries were station. These levels were sent to
conglomerate, in spite of
deployed. The bridge with the new the Design consultant who
insurmountable difficulties
layout eliminating well foundations monitored these personally. In fact,
elsewhere under similar
was completed in 20 months after the concreting of each pair of
circumstances. Two successive
Other Records: The Chenab segments the levels as actually
contracts and 30 years later, the
bridge deck was constructed with measured and as envisaged by the
impossibility of sinking wells
the shortest time cycle of 6 days designer fitted almost like a ‘T’.
through such strata was realized.
consistently achieved for the This proves that the parameters
Based on lateral thinking, it
construction of each pair of fixed by the Design consultant and
was decided to abandon the partly
the parameters as actually achieved
during execution were
complimenting each other. The
cables were so placed that almost
all the cables were straight and
without any curve. Thus
prestressing results were exactly as
shown in approved drawings both
in terms of extension and gauge
pressure.
Figure 7: Chenab Bridge, Giant Figure 8: Chenab Bridge Hydraulic Earthquake The author was Value
Bearings Dampers Engineering Consultant for the Fast
Track Project.

158 NBM&CW SEPTEMBER 2010

S-ar putea să vă placă și