S.A.Reddi, Fellow Indian National Academy of Engineering
Introduction Pre-cast RC bored piles of to bouldery strata Despite best
2.5m diameter was first successfully efforts, the well only went down by Bridge foundations are the most realized in India for the old Thana 35.25 m after three seasons and at complicated and difficult to Creek Bridge constructed in 1960s. extra cost! The well was plugged at construct. Unexpected difficulties For the 13 Km long Saudi–Baharain RL 32.075 m and 5 nos 1.5 m dia cause delays, extra costs and Causeway large diameter pre-cast RCC bored piles (25-35m) were revision of designs due to altered pre-stressed bored piles were provided to anchor the well, one in situations. Loss of human lives was adopted. By 2005, piles of 2-3 m the middle through the dredge hole normal rather than exception. In the dia, upto 120m deep are extensively and 4 outside at the four corners. Sixties, more than 50 lives were used in the rest of the world. These Further a launching apron of crated lost due to the accident during new techniques eliminate boulder 3 m thick was laid making pneumatic sinking operations for complicated weather-dependent a circle of 60 m dia around the well foundations of Mahanadi bridge and risky operations in water. They well, at RL 61.00. These extra works in Orissa. For Kali Bridge at Karwar have reduced the delays caused further delay in the comp- in Karnataka, pneumatic sinking considerably and minimized the letion of the substructure works. was required for inspection of the technical and financial risks. The founding surface of the wells. Apart Well foundations on development of modern techniques from delays and extra costs, large sloping rock: has considerably reduced quantities number of workers suffered caisson disease. Due to difficulties in well of materials used for foundations Brahmaputra Bridge at as well as energy consumption and sinking, two contractors left the job Jogighopa (2.28 km) environmental impacts. and the third took more than 5 The wells of main span were 11 m years to complete the well Well Foundation x 17 m double ‘D’ type. Foundations foundations. Alternative construction 17 & 18 were resting on hard rock techniques and equipments have Problems at at steep incline of almost 1:1 slope. emerged. With the introduction of It was not possible to rest the advanced piling equipment, large Brahmaputra Bridge foundations partially on two types diameter piles up to 3.5 m dia are at Tezpur of strata. Hence to found these easily realized at a fast rate, with a The bridge was more than 3 km wells, 1500 mm dia anchor piles, significant reduction in cost and long with 26 spans of 120 m and 2 12 nos for each foundation were material quantities. Bridges shore spans of 70 m each, founded provided through the body of the elsewhere are now constructed with on 12m dia Wells. Sinking well No.2 steining, extending to about 10 m pile foundations. to full depth was not possible due below the cutting edge.
148 NBM&CW SEPTEMBER 2010
Additional cost was several The calculated maximum scour crores. Effective use of Pile depth was 36 m below water level. Foundations - Jamuna River The soil strata were sandy up to Bridge in Bangladesh (figs.2 about 30 m followed by hard stiff &3). clay. During construction, the wells A 4.8 km long, four lane started tilting and the problems road bridge with 100 m spans continued right through the sinking. was constructed in the 1990s Despite extensive chiseling, the rate on the Jamuna river of sinking was painfully slow. (Brahmaputra in India). The Well 2 - The founding level was foundation design was 64.7 m below the water level. challenging. Very deep wells The rate of sinking through clay are extremely slow to construct, was about 1.5 - 2 cm/hr. 3500 costly, increasing the total cost. crane hours were used to sink Various alternatives were the well. considered including caissons, Well 17 - The well shifted by 1.86 driven precast piles and driven m. The piers were to be retained steel tubular piles. The only at the original position; resulting viable option was large in excessive moments in the well. Figure 1: Brahmaputra bridge foundations No. 17 & 18 diameter tubular steel piles To counter the moments driven at a rake (fig.2). The counterweight was provided in the piles were fabricated in Korea, form of a dummy well sunk to a shipped to site and installed depth of 20 m in the adjacent by hydraulic hammer. The area and connected to the main diameter of the piles ranged well through a common well cap. between 2.5 and 3.15 m and Well 32 - The well shifted by the steel tubes were filled with 1150 mm. A similar solution as in concrete. Maximum pile length well 17 was adopted. was 72 m below bed level. Well 4 - During concreting of During one working season curb, sand leaked from the island from October 1995 to June and the entire curb tilted and sank 1996 all the 121 main work by 4.5 m. A new sheet pile piles plus two full scale trial cofferdam had to be erected and piles were driven. a new well curb was cast. The Figure 2: Pile foundations for Jamuna bridge This optimization resulted total delay was one month. in overall reduction in the Well 9 - the total height of the bridge costs by more than steining except last 2 m was 50%. This solution also completed with 7.5 m balance reduced the use of resources sinking. Due to presence of stiff (concrete and steel) clay, 8 m sump was made to considerably and was facilitate sinking. After several beneficial to environmental weeks, the well suddenly jumped Figure 3: Completed view of the Jamuna bridge impact. The piles were by about 9 m with the top of installed in 8 months; the well steining below water level. Work Due to the steep incline, part of foundations of three bridges across resumed after monsoon. A the cutting edge was resting on the the same river constructed in India temporary RC cofferdam was rock while the other parts were have taken 3-5 years each to constructed and the sunk well overhanging. In order to contain the complete. dewatered to expose and build bottom plug, two rows of jet grouted up further steining. Time loss: piles were introduced around the Damages During about 6 months. periphery of the well steining which Construction - Ganga Wells 3 & 4 -Wells were sunk by acted as curtain wall (fig.1). 1500 about 44 and 37 m before the dia piles also driven up to hard Bridge at Bhagalpur (4.6 monsoon season in 1996. The rock along the periphery through km) wells were toppled due to scour the steining. The completion of the The well foundations consist of and disappeared during the project was extended by 3 years. single circular wells 11.6 m dia. floods. Based on a number of
150 NBM&CW SEPTEMBER 2010
trial bores well No.3 was found total height of steining except last 2 An Expensive tilted along the bridge axis. Well m was concreted. The well was in No.4 was found on the upstream the final stages of steining, with Solution Indeed !! side along the direction of current. about 7.5 m to reach the founding The completion was delayed by These wells weighing up to level. As the well was stuck up in more than one season as the 9900 t could not be restored and stiff clay, efforts were made to sink solution was based on an Expert were abandoned. New wells were the well by creating a sump of about Committee investigation and report. cast and sunk by changing the 8 m below the cutting edge. All of a This led to delay in finalization of span arrangement. Floating sudden the well sank suddenly by the designs and drawings for the caissons were used. about 9 m and the top of steining foundation well and necessity of Extra cost and time - The cost on was below the water level by about issuing variation orders to cover the completion was Rs.106 cr against 3.5 m. Rectification measures were items of cut-off walls and bed accepted tender cost of Rs.55 cr! very expensive and time consuming. protection works which were not The time overrun was 5 years! Ganga bridge at Varanasi: Very envisaged in the original contract. stiff clay was encountered at 25 m Tilts and Shifts in Well below and sinking of well Ganga Bridge, Patna Foundations - Vasai foundations No. 3 and 5 was very The 5.6 km long bridge comprises Creek Bridges Near difficult, did not move for three of 46 spans of 120 m each resting months. Then well No.3 jumped by on 56 m deep well foundations Mumbai several meters without any warning (12m dia.). Two of the wells in the Bassein Creek road bridge near when two workers and one midstream (Nos. 41 and 45) Mumbai (1970) faced problems of supervisor were taking sump encountered artesian conditions heavy tilting of the well foundations. sounding. The tragic accident killed during the final stages of sinking Two of the foundations no.4 & 6 all the three people. The well No.5 There was continuous sand tilted very heavily and all attempt to also jumped by about 5 m and blowing filling the dredge hole to 5- correct the tile failed. The was submerged in the water by 6 m above the cutting edge. Months foundations were abandoned and 1m. of efforts to sink the well proved the design of the bridge was futile. A technical advisory committee changed to accommodate new Artesian Conditions took about a year for arriving at a foundations and longer spans. The During Construction of solution. Temporary steel cofferdam project was delayed by six years with termination of the first contract, Well Foundations was built enveloping the well and an artificial head of about 6 m of arbitration, litigation. Nepal Bridge (Kohalpur / water was created to counter act Despite previous histories of Mahakali Section ) the sand bubbling. Delay: two years two bridges built across the same Artesian conditions were creek that faced problems with well Cracking of Well Steining encountered during soil foundations, the same were again investigations for the Shivganga During Construction adopted for another Vasai Creek bridge (8 spans of 32 m). At Cracking of well steining is one of Bridge. During construction, heavy locations P-4 and P-5 artesian head the serious problems faced many tilting of wells was observed. The of about 4.3 m was encountered at times in the construction of well corrective measures for one well about 17 m below ground level. foundations, resulting in time and alone took almost two years The well was redesigned with cost overruns. The causes are delaying completion of the foundation terminating above the usually: foundations; costing about Rs. 2 artesian layer, resulting in shallow 1. Blasting, Dewatering crores. foundations resting on clay. Due to 2. Insufficient steining thickness founding the wells at shallow depth, 3. Jumping due to excessive sump Sudden Jumping of Wells it was necessary to provide 4. Sand blows During Sinking adequate bed protection so as to 5. Surcharge due to dumping Sometimes the well sinks suddenly prevent scour. The bed protection dredge material close to well. due to excessive sump or weak consisted of : 6. Failure of cutting edges. soil layer and the steining Upstream and downstream When such cracking occurs, at disappears below water level, aprons least one season is lost for the making it difficult to continue further Cut-off walls, upstream & investigation, developing remedial work on the well steining. downstream measures, approvals of the same In one of the well foundations Concrete floor etc. In the last 45 years, the author in a bridge across river Ganga, the is aware of more then 200 cases 152 NBM&CW SEPTEMBER 2010 Analysis by the Federal Highway Administration (FHWA), USA More than 100,000 bridges would be constructed during the next two decades. Foundations represent about 30% or more of the cost of the highway bridges. The predominant type of foundation Figure 5: Pasighat Bridge, Boulder system used for the highway Figure 4: Pasighat Bridge, AP dredged during well sinking bridges in the US is pile. Many bridges can tolerate significant of bridges constructed by various beginning of sinking. After 15 years magnitudes of a total and differential construction agencies, where the of struggle to pneumatically sink vertical settlement without becoming dredge hole of well has to be filled the wells to RL – 50 m, the seriously over-stressed with concrete due to cracks in designed founding level was steining. drastically raised by 22m in 2002. Appreciation During well sinking of Tapi The Indian Bridge Engineers are by Major Bridges and large mentally tuned to Bridge, Maharashtra, hard strata was met. Due to blasting, extensive (Worldwide) on Pile providing well foundations for bridges as a reflect action; whereas cracks developed in steinings New Foundations steinings had to be constructed it is very necessary to analyze the Su Tong Bridge, China : The 6 km inside the wells. The original comparative merits and demerits, long Cable-stay bridge crosses contract period was four years. construction time frame and cost of Yangtze river near Shangai will carry Attempts were made for five years construction of bridges with well/ a six lane highway with emergency to sink the wells. Work was pile foundations before finally lanes, with a record 1088 m main suspended for five years for want choosing the type of foundation. An span and 300 m high concrete of decision to revise the founding analysis of the history of well pylons. Each tower is supported on level. An expert committee ultimately foundations during the last five 131 cast-in-situ bored piles 120 m recommended raising the decades indicates innumerable long and 2.7 m diameter. Due to foundation level of wells by more difficulties, delays and cost overruns strong currents, significant scour is than 20m The bridge was in a majority of the cases. expected around the foundations, completed after fourteen years. The Realization of well foundations and suitable scour protection is contractor suffered losses due to requires special skills and provided around the pylons. The the delays. The owner suffered experience which are gradually central span has a clearance of 62 substantial losses due to time dwindling. m for container ships to pass overrun. Delay: 10 years. Developments have taken place through. The bridge used 200,000 t in respect of large diameter pile Extraordinary Delays in of steel, 1 million cum of concrete. foundations as well as equipment Stonecutters Bridge, Hong Construction of Well Kong: The 1600 m long for the same. The time and cost Foundations Pasighat advantages of opting for pile Stonecutters Bridge Hong Kong with foundations have been amply Bidge, Arunachal cable-stay span of 1018 m is one demonstrated worldwide and to a of the longest in the world. The Pradesh, 703 m long bridge is founded on 3.0 m dia limited extent in India. Piles up to a The project started in 1987 and the diameter of 3m and depth of up to piles, up to 90 m deep, socketted construction of well foundations 120m have been realized for a into rock. Bandra Worli Sea Link continued for the next 20 years! As number of major bridges Mumbai: The sea link consists of per the design, based on worldwide, with cost saving of up to 5.6 km long, 8-laned bridge with misleading soil data, six wells were 40% when compared to well cable stayed portion of 600 m. The to be sunk to about 50 m below foundations. bridge is founded on 1.5 m bed. The actual strata met with There is currently no restriction diameter bored piles. Concrete for during sinking were hard in the IRC Code regarding use of the piles is M50 grade and for pile conglomerate with densely pile foundation. However, many caps is M60. Silica fume and fly compacted and very large boulders Owners impose restrictions in the ash are used for concrete (fig.6) were found right from the tender documents, without any preparation. 154 NBM&CW SEPTEMBER 2010 segments. This was made possible by an high early strength concrete which enabled pre- stressing at 60 hours after concreting. Fe500 steel reinforcement bars were used for the first time in India in a cantilever construction bridge. The huge Bearings with anchors were located among highly congested reinforcement; normal concrete Figure 6: Chenab Bridge at Akhnoor-Longest Span Cantilever PSC Bridge, eliminated wells placement, vibration was impossible. Special Conbextra justification. The example cited sunk wells and go for a scheme Grout replaced normal High above concerning the problems of with longer central span, eliminating Strength Concrete below bearings. well foundations amply justifies a the water foundations altogether. Self–compacting concrete (S.C.C) second look on the choice of With a 160m central span, both the was used for the first time for foundations. In fact, the use of well main pier foundations were located concrete below the bearings. foundations for bridges should be in the dry on the banks, resting on Segments on both sides of the an exception rather than the rule. raft foundations. These foundations Pier were concreted simultaneously were completed in months instead balancing the weights. When the Chenab River Bridge at of decades earlier in unsuccessful 22nd segments were facing each Akhnoor Near Jammu attempts to sink wells in water. The other and the shuttering of the 23rd abutments consist of hollow box segment i.e. the linking segment The project was started in the early and piers consist of hollow was to have been placed there was Seventies. A .scheme for a 231m rectangular section on raft no level difference and the levels long bridge with 5 spans foundations. matched on both tips to the nearest (3x46+2x46.5) upstream of existing The superstructure was millimeter both in plan (centre line) steel bridge was originally designed and constructed as a as well as in elevation. This was conceived. The scheme involved continuous cantilever of 280m possible because every day the construction of five well foundations length, with a central span of 160m levels were maintained by a team in the volatile Chenab River, to be (longest in India at the time). Two of surveyors with the help of total sunk through difficult strata – hard pairs of cantilever gantries were station. These levels were sent to conglomerate, in spite of deployed. The bridge with the new the Design consultant who insurmountable difficulties layout eliminating well foundations monitored these personally. In fact, elsewhere under similar was completed in 20 months after the concreting of each pair of circumstances. Two successive Other Records: The Chenab segments the levels as actually contracts and 30 years later, the bridge deck was constructed with measured and as envisaged by the impossibility of sinking wells the shortest time cycle of 6 days designer fitted almost like a ‘T’. through such strata was realized. consistently achieved for the This proves that the parameters Based on lateral thinking, it construction of each pair of fixed by the Design consultant and was decided to abandon the partly the parameters as actually achieved during execution were complimenting each other. The cables were so placed that almost all the cables were straight and without any curve. Thus prestressing results were exactly as shown in approved drawings both in terms of extension and gauge pressure. Figure 7: Chenab Bridge, Giant Figure 8: Chenab Bridge Hydraulic Earthquake The author was Value Bearings Dampers Engineering Consultant for the Fast Track Project.
Transactions of the American Society of Civil Engineers, vol. LXVIII, Sept. 1910
The New York Tunnel Extension of the Pennsylvania Railroad.
The East River Tunnels. Paper No. 1159