Sunteți pe pagina 1din 16

International Journal of Civil Engineering

https://doi.org/10.1007/s40999-018-0356-2

RESEARCH PAPER

Load Sharing and Carrying Mechanism of Piles in Non-connected Pile


Rafts Using a Numerical Approach
Alireza Saeedi Azizkandi1 · Habib Rasouli2 · Mohammad Hasan Baziar1

Received: 21 April 2018 / Revised: 23 July 2018 / Accepted: 29 August 2018


© Iran University of Science and Technology 2018

Abstract
The load response and carrying mechanism of piles in a non-connected piled raft foundation is a complex phenomenon due
to complex soil–structure interactions such as interactions among piles, subsoil, cushion, and raft. The scope of this research
includes four main components: (1) using 3D finite element modeling and verifying different models with centrifuge tests;
(2) investigating the parameters affecting the axial stiffness of a non-connected piled raft; (3) investigating the influence of
different parameters on the foundation settlement; and (4) devoting special attention to the mechanism of carrying and shar-
ing loads as well as the load–settlement behavior of non-connected piled raft foundations, in comparison with connected
piled raft foundations. Results of this research showed that in order to achieve optimal design, geotechnical designers should
consider three major factors, including axial stiffness of non-connected piled raft, settlement, and stress along the pile length.

Keywords  Non-connected piled raft · Connected piled raft · Finite element method · Load sharing of pile

1 Introduction satisfy the settlement designing criteria is lesser than those


required by conventional design approaches which count on
In the design of a piled raft foundation for structures, the raft the pile bearing capacity. Nonetheless, due to the fewer num-
alone may have an adequate factor of safety against ultimate ber of piles, the high axial forces and bending moments may
bearing capacity, but its settlement or differential settlement transfer from the pile head to the raft [5]. In other words, in
may exceed allowable values. Thus piles are used to enhance the active tectonic regions, high shear forces may develop
the settlement criteria. In the past, it was assumed that the at the pile-raft connection point [6]. For instance, during
piles in a piled raft foundation carry the entire load imposed the Hyogoken–Nanbu earthquake (1995), due to high shear
on the foundation. Davis and Poulos [1] introduced a new and bending forces, the pile cap and pile head of the Higashi
method to determine the number of piles needed to lower the Bridge and some other piled raft foundations were detached
foundation settlements to the acceptable level. Normally, few [7]. In most design codes (ASTM 1969, British Standard
long piles are needed to reduce the settlement to the accept- 1986) strong limitations have been imposed for the allowable
able amount [2, 3]. Poulos [4] also proposed an alternative stresses in the pile cap, which may lead to the uneconomi-
method for the designing of piled raft foundations called cal design of the foundation system [6]. In order to prevent
settlement reducers, in which the number of piles required to structural damage to the piled raft, piles could be used as soil
reinforcement rather than structural elements by placing an
* Alireza Saeedi Azizkandi interposed layer of granular material between the raft and
asaeedia@iust.ac.ir the subsoil to adjust stress transferring from the raft to the
Habib Rasouli piles and subsoil [8].
habib.rasouli@uts.edu.au The efficiency of non-connected piled raft foundations
Mohammad Hasan Baziar has been proven by both numerical and experimental inves-
baziar@iust.ac.ir tigation. Adding non-connected piles as settlement reducer
below a raft will reduce the differential settlement and
1
School of Civil Engineering, Iran University of Science bending moment within the raft structure [6]. Additionally,
and Technology, Tehran, Iran
increasing the length of piles and placing them in the center
2
Faculty of Engineering and Information Technology, of the raft are other effective ways to increase piled raft
University of Technology Sydney, Sydney, Australia

13
Vol.:(0123456789)
International Journal of Civil Engineering

stiffness and decrease differential settlement [6, 9]. Cush- with the connected piled rafts under vertical loading. Accu-
ion thickness, stiffness, and particle gradation can improve racy of the numerical analysis was verified by a series of
non-connected piled raft axial stiffness. Rasouli et al. [10] centrifugal tests reported by Fioravante and Giretti [15]. The
used centrifuge-modeling tests to show that choosing an effect of several parameters including length, spacing, and
appropriate particle soil grading of the cushion can improve the number of the piles, cushions, and subsoil stiffness (i.e.
the axial stiffness of non-connected piled raft. The previous Young’s modulus) were considered chiefly to investigate the
studies revealed that a cushion layer with higher stiffness and load response and carrying ratio of piles in the non-con-
smaller thickness would decrease the raft settlement [9, 11, nected piled rafts in comparison with the connected forms.
12]. Azizkandi et al. [13] used 1 g shaking table tests and
numerical modeling to show the efficiency of non-connected
and connected piled raft foundations under seismic loading. 2 Methodology of Analysis
It was noted that the lateral stiffness of the connected piled
raft was higher than those of the non-connected forms; fur- 2.1 Finite Element Modeling
thermore, piles in the connected piled rafts behaved more
efficiently against lateral loads. Structural elements including raft and piles were modeled as
Load sharing between connected piles and a raft is a com- elastic materials, while geotechnical elements consisting of
plex phenomenon due to interactions between the piles, the subsoil and cushion layer were modeled by an elastic ideal
subsoil, and the raft. However, load sharing in a non-con- plastic constitutive model, following the Mohr–Coulomb
nected piled raft is even more complex due to placement of yield criterion. Although the assumption of linear elastic-
a deformable layer between the piles and the raft. In the con- ity for the subsoil is not very accurate in comparison with
nected piled raft, the maximum axial load mobilized within other superior soil models, this model was implemented in
pile length is at the connection of piles and the raft. The the numerical modeling to simplify the complex behavior
concentrated loads at the connection of piles to the raft is between piles and soil as well as raft and soil; however, some
decreased by introducing a cushion layer between the piles over-prediction of the interaction might have been observed
and raft [6, 14]. The applied load to the raft in a connected [20, 21]. Due to the symmetry of the numerical model, only
piled raft is diffused to greater and deeper volumes of soil. In one-quarter of piled raft foundations were modeled. Piled
contrast, due to presence of the interposed layer, the applied raft structure and soil mass including subsoil and cushion
load on the raft in a non-connected piled raft is distributed layers were modeled using a six-node linear triangular prism
indirectly by the pile head and the negative skin friction element (C3D6). To improve the accuracy of the results and
at the upper part of the piles [6, 15, 16]. Nakaia et al. [17] decrease the calculation time, a relatively fine mesh was
used dynamic centrifuge tests and numerical modeling to used in the vicinity of the pile-raft structure; the mesh size
show that even when piles are non-connected structurally did, however, increase as the distance from the pile structure
to the raft, they have a significant effect on the structural was increased. Figure 4 shows a typical non-connected piled
response under dynamic loading. Tradigo et al. [18] showed raft foundation with nine piles.
that the results of numerical modeling of a non-connected The ultimate shaft friction capacity of piles depends
piled raft (i.e. raft settlement and pile force distribution with on installation conditions and relative pile roughness (i.e.
1D embedded piles) were in good agreement when the piles Rn = Rt ∕D50 , where Rt = maximum pile surface roughness).
were modeled using the fully solid element method. According to Fioravante and Giretti [15], the minimum rela-
Russo and Viggiani [19] grouped piled raft foundations tive roughness of piles in the corresponding study was Rn
into two broad categories of small (raft breadth to the pile = 0.67. This value was higher than the proposed amount in
length ratio, Br ∕Lp < 1 ) and large piled rafts (i.e. Br ∕Lp > 1 ). the literature (i.e. Rn > 0.1) and ensures that no slip occurs
When the bearing capacity of a raft is insufficient, the small between the piles and surrounding soil [22, 23]. Therefore,
piled rafts are usually introduced to increase bearing capac- the perfectly rough interface between piles and the soil pre-
ity against failure. However, large piled rafts are defined vented the occurrence of failure in the soil–pile interface.
when the bearing capacity of a raft is adequate with an
acceptable safety factor, and the only reason for adding piles 2.2 Verification of Finite Element Model
is to reduce the maximum or differential settlements below
the allowable values. In order to verify the numerical modeling procedure using
In the present study, 125 different types of foundations ABAQUS, three different models were analyzed and cali-
including raft, non-connected, and connected piled rafts brated from a series of experimental tests in sandy soil. A
have been modeled by employing the 3D finite element simple raft, a non-connected, and a connected piled raft
method (ABAQUS) to investigate the behavior of small and foundation with nine piles were chosen from centrifuge tests
large non-connected piled raft foundations in comparison reported by Fioravante and Giretti [15]. The properties of

13
International Journal of Civil Engineering

materials and dimensions of different models used in the 7.5m 7.5m


validation (in the prototype scale) are summarized in Table 1
and Fig. 1, respectively [24–26].
Figure 2 compares the load–settlement behavior and total
load carried by piles from the experimental tests and FE

7.5m

7.5m
analysis results. It is clear that the obtained results from FE
analyses are in good agreement with the experiments regard-
ing load–settlement curve and total load carried by piles. S p =2.5m

3 Effect of Different Parameters on Piled UR NC09


Raft Axial Stiffness

1.65m

1.65m
In the present study, FE analysis was performed by executing
the ABAQUS (standard) software to investigate the differ-
ences between small and large connected and non-connected

19m
piled rafts. Various types of foundations including raft, con-
nected piled raft (PR), and non-connected piled raft (NC) Dp =0.5m
were considered to study the effects of several parameters
including subsoil and cushion stiffness (i.e. Young’s modu-
lus), length, spacing, and number of piles on the behavior
of raft settlement, load sharing coefficient, and stress along PR09
the pile length. According to the existing literature, these
parameters are of great importance in the vertical bearing
behavior of connected piled foundations [4, 27–29].
The piled raft model consists of a square raft with 12 m

19m
breadth (Br), piles with a diameter of 0.5 m (dp), various pile
lengths (Lp) ranging from 7 to 20 m and a 1-m-thick cush- Dp =0.5m
ion layer in the non-connected piled rafts under a constant
applied load of 500 kPa, which is shown in Fig. 3. The char-
acteristics of subsoil and cushion layer used in the present
study are summarized in Table 1. Figure 4 and Table 2 show Fig. 1  Geometry of different foundations used in validation [15]
one-quarter of a typical non-connected piled raft foundation
and a summary of the studied models, respectively. raft, namely PR and NC, and the number after that denote
the number of piles and normalized pile spacing; e.g. NC09-
3.1 Piled Raft Axial Stiffness and Load–Settlement S/d = 5 means non-connected piled raft with nine piles and
Behavior of Different Foundations normalized pile spacing of 5. However, the effect of structural
and geotechnical properties of piled raft foundations on the
Small and large piled rafts were considered in the selection settlement performance of PR/NC can be investigated using
of the various types of foundations in order to investigate the settlement efficiency ratio [6, 15] as follows:
the load–settlement behavior of the connected piled rafts in
wr ur − wr
comparison with the non-connected piled rafts. In the pre- 𝜂= , (1)
wr ur
sent study, the connected piled raft and non-connected piled

Table 1  Material properties Material E (MPa) 𝜈 𝛾 (kN/m3) c (kPa) 𝜙o 𝜓o


used in validation [15]
Venice Lagoon Sand (Subsoil) 18.5 0.25 15.3 0 35 5
Ticino Sand (Cushion) 35 0.25 15.3 0 35 5
Pile 25,000 0.15 24 – – –
Raft 30,000 0.15 24 – – –

E Young’s modulus, 𝜈 Poisson’s ratio, 𝛾 unit weight, c cohesion, 𝜙o internal friction angle, 𝜓 o dilation angle

13
International Journal of Civil Engineering

0 0.0

Raft Relative Settlement, W r /Br (%)


Relative Raft Settlement, W r/Br (%)
0.5
1
1.0

2 1.5

UR-FEM in this study 2.0


UR-Centrifugal tests PR09-Centrifugal test
3 NC09-FEM in this study PR09-FEM in this study
NC09-Centrifugal tests 2.5
NC09-FEM in this study
PR09-Centrifugal tests
NC09-Centrifugal test
PR09-FEM in this study
3.0
4
0 10 20 30 40
0 100 200 300 400 500 600
Total Applied Load on Raft, Qpr (kPa) Total Load Carried by Piles, Qp (MN)
(a) ( b)

Fig. 2  Relation between the raft relative settlement and a total load imposed on the raft and b total load carried by piles

12m 12m 12m 12m 12m


12m

12m

12m

12m

12m
S p =Var. S p =Var. Sp =5d p

UR NC04 NC09 NC16 NC25


1m

1m

1m

1m
L p =Var.

L p =Var.

L p =Var.

L p =Var.
Dp =0.5m Dp =0.5m Dp =0.5m Dp =0.5m

PR04 PR09 PR16 PR25


L p =Var.

L p =Var.

L p =Var.

L p =Var.

Dp =0.5m Dp =0.5m Dp =0.5m Dp =0.5m

Fig. 3  Schematic illustrations of different types of foundations used respectively), NC04, NC09, NC16, and NC25 (non-connected piled
in the present study, UR (foundation without piles), PR04, PR09, raft foundation with 4, 9, 16, and 25 piles, respectively)
PR16, and PR25 (piled raft foundation with 4, 9, 16, and 25 piles,

where wr ur and wr are the settlements of the unpiled raft and of wr are always smaller than wr ur (i.e. 0 ≤ 𝜂 ≤ 1 ). Therefore,
connected/non-connected piled raft, respectively. Adding larger values for the settlement efficiency ratio means more
piles improves load–settlement behavior so that the values efficient in reducing raft settlement.

13
International Journal of Civil Engineering

raft foundations for np = 0, 4, and 9, Lp = 20 m and Br =


12 m. It can be observed that for a particular settlement,
the piled raft axial stiffness increases with increasing pile
spacing in both connected and non-connected systems.
That happens because increasing pile spacing increases the
area of the raft supported by piles; furthermore, increas-
ing pile spacing decreases the pile–soil–pile interaction
[10, 30, 31]. The effect of pile spacing on connected piled
rafts is significant because the applied loads are directly
transferred through the piles without any intermediate ele-
ment. As shown in Fig. 5, the load–settlement behavior of
connected piled rafts was more affected by increasing pile
spacing rather than using the non-connected piled rafts
[6, 14]. In addition, increasing the number of piles from 4
to 9 increased the effect of pile spacing in increasing the
raft axial stiffness. For instance, in the case of NC and PR
Fig. 4  One-quarter of finite element mesh of non-connected piled raft with 4 piles, by increasing the pile spacing from 3dp to
with 1 m cushion 9dp for a certain settlement (Wr/Br = 1%), the load carried
by the foundation increased by about 4 and 10%, respec-
tively, while the corresponding values for a piled raft with
3.1.1 Effect of Pile Spacing nine piles were 11 and 28%. The settlement behavior of
foundations indicated that the settlement efficiency ratio
Figure 5 shows the effect of pile spacing on the load–set- η improved up to 20 and 40% for connected piled rafts
tlement behavior of connected and non-connected piled with 4 and 9 piles, respectively, while the corresponding

Table 2  Summary of studied Parametric study Raft Subsoil Cushion Pile group Number of
models models
Br × Lr × tr (m) 𝜑 E (MPa) tc (m) 𝜑 E (MPa) np Lp Sp
Dp

Cushion stiffness 12 × 12 × 1.5 35 26 1 35 26 4 20 5 20


30
52 9
78 16
104 25
Subsoil stiffness 12 × 12 × 1.5 35 18.5 1 35 30 4 20 5 9
9
22
16
26
30
Pile spacing 12 × 12 × 1.5 35 18.5 1 35 30 4 20 3 6
5
7
9
9
Number of piles 12 × 12 × 1.5 35 18.5 1 35 30 0 20 5 2
4
9
16
25
Pile length 12 × 12 × 1.5 35 18.5 1 35 30 4 7 5 88
22 52 9 14
26
78 16
30 20

T thickness, E Young’s modulus, np number of piles, L length, B breadth, SP pile spacing, dp pile diameter

13
International Journal of Civil Engineering

0.0 0.0
Lp=20 m Lp=20 m

Raft Relative Settlement, W r/Br (%)


Raft Relative Settlement, W r/Br (%)

Esubsoil=18.5 MPa Esubsoil=18.5 MPa


0.5 0.5
Ecushion=26 MPa

1.0 1.0

1.5 1.5

2.0 UR 2.0 UR
PR04-s/d=3 NC04-s/d=3
PR04-s/d=5 NC04-s/d=5
2.5 2.5
PR04-s/d=7 NC04-s/d=7
PR04-s/d=9 NC04-s/d=9
3.0 3.0
0 100 200 300 400 500 0 100 200 300 400 500
Total Applied Load, Qpr (kPa) Total Applied Load, Qpr (kPa)
(a) (b)
0.0 0.0
Lp=20 m Lp=20 m
Relative Raft Settlement, W r/Br (%)

Relative Raft Settlement, W r/Br (%)


Esubsoil=18.5 MPa Esubsoil=18.5 MPa
0.5 0.5 Ecushion=26 MPa

1.0 1.0

1.5 1.5

2.0 UR 2.0 UR
PR09-s/d=3 NC09-s/d=3
PR09-s/d=5 NC09-s/d=5
2.5 2.5
PR09-s/d=7 NC09-s/d=7
PR09-s/d=9 NC09-s/d=9
3.0 3.0
0 100 200 300 400 500 0 100 200 300 400 500
Total Applied Load, Qpr (kPa) Total Applied Load, Qpr (kPa)
(c) (d)

Fig. 5  Effect of pile spacing on the load–settlement behavior of con- nected piled raft with four piles, c connected piled with nine piles, d
nected and non-connected piled rafts with the raft breadth of 12  m, non-connected piled with nine piles
20  m pile length: a connected piled raft with four piles, b non-con-

values for non-connected piled rafts were about 10 and subsoil stiffness reduces the foundation settlement. For
25%, respectively. instance, increasing the subsoil Young’s modulus from
18.5 to 30 MPa when Lp = 20 m decreased the settlement
3.1.2 Effect of Subsoil and Cushion Stiffness at the center of the raft for the connected and non-connected
piled raft by 38 and 34%, respectively. However, because
The underlying soil properties such as cushion and subsoil the applied loads on the connected piled raft can directly
stiffness somewhat affects the load bearing behavior of piled transfer to the deep layers with a higher stiffness, the effect
rafts [32, 33]. Figure 6 illustrates the effect of subsoil and of subsoil stiffness is more evident in the connected piled
cushion stiffness (i.e. Young’s modulus) on the load–settle- raft settlement than the non-connected piled rafts.
ment behavior of PR/NC with nine piles. Several Young’s In cases where the pile length is larger than the raft
moduli including 18.5, 22, 26, and 30 MPa for subsoil and breadth, the raft settlement of the connected piled raft is
30, 52, 78, and 104 MPa for cushion were considered. The even less than those of the non-connected piled rafts with
pile lengths were changed from 7 to 20 m, representing both high cushion stiffness (i.e. Young’s modulus of 104 Mpa).
small and large piled raft foundations. As shown in Fig. 6a, when the pile’s length is 20 m, the set-
As illustrated in Fig. 6, the efficiency of adding piles to tlement of a connected piled raft is always smaller than the
decrease raft settlement in both connected and non-con- corresponding case for non-connected piled rafts.
nected piled rafts is decreased significantly by decreasing In the case of shorter piles (i.e. Br ∕Lp > 1 in Fig. 6c),
the pile length. Moreover, Fig.  6 shows that increasing however, increasing the cushion stiffness without changing

13
International Journal of Civil Engineering

A UR A UR
B PR09,Lp=20m B PR09,Lp=14m
Raft Relative Settlement, Wr/Br (%)

3 C NC09,Lp=20m,Ec=30 MPa 3 C NC09,Lp=14m,Ec=30 MPa

Raft Relative Settlement, W r/Br (%)


A A
D NC09,Lp=20m,Ec=52 MPa D NC09,Lp=14m,Ec=52 MPa
A E NC09,Lp=20m,Ec=78 MPa C A E NC09,Lp=14m,Ec=78 MPa
B DE F
F NC09,Lp=20m,Ec=104 MPa F NC09,Lp=14m,Ec=104 MPa
C C
2 2 B DE F A
B D C A
EF A C A
B D B DE F
EF C C
B D C B DE F
E F B D
EF
1 1

0 0
18.5 22.0 26.0 30.0 18.5 22.0 26.0 30.0
Stiffness of Subsoil, E Subsoil (MPa) Stiffness of Subsoil, E Subsoil (MPa)
(a) (b)
A UR
B PR09,Lp=7m
Raft Relative Settlement, Wr/Br (%)

3 A C NC09,Lp=7m,Ec=30
BC D D NC09,Lp=7m,Ec=52 MPa
EF E NC09,Lp=7m,Ec=78 MPa
A
BC D F F NC09,Lp=7m,Ec=104 MPa
E
2 A
BC DE F
A BC
DE F

0
18.5 22.0 26.0 30.0
Stiffness of Subsoil, E Subsoil (MPa)
(c)

Fig. 6  a Relation between raft relative settlement and subsoil/cushion stiffness for pile length of a 20 m, b 14 m, and c 7 m, under Qpr = 500 kPa

other parameters decreases the settlement of non-connected reduction in the non-connected and connected piled rafts,
piled rafts even more than that of connected piled rafts. Fig- respectively). Therefore, in terms of displacement-based
ure 6c clearly shows that the settlement of non-connected designs and similar to the connected piled rafts reported by
piled rafts with 7 m piles are always smaller than the cor- other researchers [34], the number of piles to increase the
responding cases for a connected piled raft. axial stiffness of a non-connected piled raft is limited to a
specific number.
3.1.3 Effect of Number of Piles
3.2 Pile–Subsoil Displacement
The influence of number of piles on the raft settlement with
20 m length piles and pile spacing of Sp/dp = 5 is illus- Due to several interactions among piles, subsoil, cushion,
trated in Fig. 7. As predicted, the raft relative settlement and the raft, the load response and load carrying of piles in
was improved by increasing the number of piles for both a non-connected piled raft foundation are more complicated
connected and non-connected piled rafts [9]. A compari- than those of the connected piled raft [18]. In the non-con-
son of consecutive cases in Fig. 7a shows a decrease in the nected piled raft foundation, due to the separation of piles
rate of the raft settlement, which causes a slight difference from the raft, the raft settlement causes a relative raft–pile
in the settlement corresponding to the piled rafts with 16 (i.e. Wr > Wp) and pile–subsoil displacement (Ws > Wp). The
and 25 piles (referring to the Fig. 7b 4% and 8% settlement mechanism of load transferring in the non-connected piled

13
International Journal of Civil Engineering

3.5 0.7
sp/dp=5 PR PR-S/d=5
Lp=20 m
Raft Relative Settlement, Wr/Br (%)

UR NC-s/d=5
3.0

(
Esubsoil=18.5 MPa

Settlement Efficiency Ratio, (η


NC 0.6 sp/dp=5
Ecushion=26 MPa
2.5 Lp=20 m
Esubsoil=18.5 MPa
0.5 Ecushion=26 MPa
2.0

1.5
0.4

1.0
0.3
0.5

0.0 0.2
0 4 9 16 25 4 9 16 25
Pile Number, n p Pile Number, n p

(a) (b)

Fig. 7  Effect of number of piles on a raft relative settlement and b settlement efficiency ratio for piled rafts with pile length of 20 m, and pile
spacing of 5

raft is shown in Fig. 8a, in which the imposed load on the understanding the mechanical parameters of a non-con-
raft transfers through a relative displacement between piles nected piled raft foundation on the behavior of pile–subsoil
and subsoil (negative skin friction) and pile head [16]. In displacement can, therefore, lead to a better understand-
contrast, as indicated in Fig. 8b, the applied load on the raft ing of the load transferring mechanism of non-connected
in the connected piled raft is transferred directly to the piles, piles. In order to investigate the pile–subsoil displacement
and due to the structural connection between piles and the more quantitatively, a normalized ratio can be introduced
raft, relative displacement between piles and the raft does as follows:
not occur (i.e. Wr = Ws = Wp). Moreover, within all the Ws − Wp
length of piles, only positive skin frictions are mobilized 𝜁= × 100, (2)
[15, 16, 18]. Br
As the applied load on the non-connected piled raft is where Ws, Wp, and Br are the settlement of the subsoil sur-
partially transferred to the pile through the pile’s head and face, piles, and the raft breadth, respectively. Since the
partially through the negative skin friction at the upper part,

Neutral plane

Neutral plane

(a) (b)

Fig. 8  Schematic illustrations of load transferring mechanism in a non-connected piled raft in comparison with b connected piled raft

13
International Journal of Civil Engineering

values of Ws in the non-connected piled raft are always larger spacing on the pile–soil displacement was investigated
than Ws, bigger values of 𝜁 means bigger relative pile–soil using a non-connected piled raft with nine piles of 20 m
displacement and larger negative skin friction at the upper in length. The results showed that with increasing pile
parts of the piles. spacing from Sp/dp = 3 to Sp/dp = 9, the pile–subsoil dis-
Figure 9 shows the effects different parameters, such as placement increased gradually and was accompanied by
number, spacing, and pile length, and subsoil have on the the higher amount of negative skin friction on the upper
maximum settlement of piles and subsoil in non-connected part of the piles (from 𝜁 = 0.5 to 𝜁 = 0.7 ). The obtained
piled raft foundations. results also showed that by decreasing the piles length
Numerical modeling results showed that by increas- from 20 to 7 m, the values of pile–subsoil displacement
ing the number of piles in the non-connected piled raft decreased, and the displacement of subsoil surface became
from 4 to 25 at a constant pile length of 20 m and nor- smoother by decreasing the pile length. In addition, the
malized pile spacing of 5 decreased the value of 𝜁 from pile length has much more influence on decreasing 𝜁 than
0.75 to 0.25, which indicates that increasing the number the subsoil Young’s modulus and the number of piles. It
of piles decreases negative skin friction. The values 𝜁 were was seen that, by decreasing pile length from 20 to 7 m,
reduced from 0.6 to 0.35 as the subsoil Young’s modulus 𝜁 decreased by about 50% (from 0.5 to 0.25). In addition,
was increased from 18.5 to 30 MPa in a non-contact piled by increasing the cushion Young’s modulus, the values of
raft with nine piles of 20 m in length. The effect of pile 𝜁 remained approximately constant.

0.00
0.00 sp/dp=5 Maximum settlement of subsoil
Maximum settlement of subsoil np=9 piles Maximum settlement of piles
sp/dp=5 0.05
Maximum settlement (m)

Maximum settlement of piles Esubsoil=18.5 MPa


0.05
Maximum settlement (m)

Lp=20 m
Ecushion=26 MPa
Esubsoil=18.5 MPa 0.10
0.10 Ecushion=26 MPa

0.15
0.15

0.20
0.20

0.25
0.25

0.30
0.30
7 14 20
4 9 16 25
Pile length, Lp (m)
Pile Number, n p
(a) (b)

0.00 0.00
np=9 piles Maximum settlement of subsoil np=9 piles Maximum settlement of subsoil
Lp=20 m Maximum settlement of piles sp/dp=5 Maximum settlement of piles
0.05 0.05
Maximum settlement (m)

Maximum settlement (m)

Esubsoil=18.5 MPa Lp=20 m


Ecushion=26 MPa Ecushion=26 MPa
0.10 0.10

0.15 0.15

0.20 0.20

0.25 0.25

0.30 0.30
3 5 7 9 18.5 22.0 26.0 30.0
Pile spacing, s p/dp Subsoil Young's modulus, Esubsoil (MPa)

(c) (d)

Fig. 9  Variation of the maximum settlement of subsoil and piles by increasing a number of piles, b pile length, c pile spacing, and d subsoil
Young’s modulus

13
International Journal of Civil Engineering

4 Load Sharing and Carrying Mechanism 4.1.1 Effect of Pile Spacing


of Piles
As shown in Fig. 10a, increasing pile spacing in an NC/
4.1 Load Sharing Ratio PR with 4 and 9 piles of 20 m lengths also increases the
pile load sharing ratio [35]. However, as seen, pile spacing
The bearing capacity of piled raft foundations can be inves- has a little effect on the pile load ratio of non-connected
tigated by introducing the load-sharing ratio as follows: piled rafts compared with connected piled raft founda-
tions. After a specific value of pile spacing (Sp/dp = 5), the
QP QP
𝛼pr = = , (3) increasing rate of load sharing ratio becomes quite small
QPR QR + QP in most cases. Increasing the number of piles, especially
where QPR, QR, and QP represent the total load carrying by for connected piled rafts, can increase the pile loads and,
a piled raft, the load carrying by the raft and piles, respec- thus, make pile performance more efficient. For example,
tively. In this study, the effects of several parameters includ- at the pile spacing of Sp/dp = 9, an increase of piles from
ing spacing, number, length of piles, subsoil, and cushion 4 to 9 results in 1.2 times the pile loads, and the piles bear
stiffness were considered to analyze the variation of pile load about 90% of the applied load (Fig. 10a).
response and carrying behavior in non-connected piled rafts
in comparison with connected systems.

1.0 1.0
NC04
Load Sharing Ratio (Qp/Qpr), α pr
PR04
Load Sharing Ratio (Qp/Qpr), αpr

NC09
0.8
Lp=20 m 0.8
PR09
Esubsoil=18.5 MPa
Ecushion=26 MPa
0.6 0.6

0.4 0.4

sp/dp=5
0.2 0.2 Lp=20 m
NC Esubsoil=18.5 MPa
PR E
cushion=26 MPa
0.0 0.0
3 5 7 9 4 9 16 25
Pile Spacing, sp/dp Pile Number, np
(a) (b)
1.0
NC04 PR09 sp/dp=5 NC04 sp/dp=5
Load Sharing Ratio (Qp/Qpr), α pr

PR04 NC16 Esubsoil=18.5 MPa NC09 Lp=20 m


1.0
Load Sharing Ratio (Qp/Qpr), αpr

NC09 PR16 Ecushion=26 MPa NC16 Esubsoil=18.5 MPa


0.8
NC25
0.8
0.6
0.6

0.4
0.4

0.2 0.2

0.0
0.0
7 14 20
26 52 78 104
Pile length, Lp Ecushion (MPa)
(c) (d)

Fig. 10  Relation between load sharing ratio and a pile spacing, b number of piles, c pile length, d cushion Young’s modulus

13
International Journal of Civil Engineering

4.1.2 Effect of Number of Piles the cushion stiffness is not a solution to mobilize the pile
capacity; rather, the subsoil stiffness and its reinforcement
The connected piled raft with 4 piles of 20 m length takes are also essential factors.
about 3.3 times more loads than the non-connected piled
raft, as demonstrated in Fig. 10b. Nevertheless, increasing 4.2 Vertical Stress Along the Pile’s Depth
the number of piles from 4 to 25 reduces the ratio of load
carrying by connected piles to non-connected piles to 2. By From the design approach, pile location, spacing, and
increasing the number of piles from 16 to 25, the load shar- length significantly affect the designing criteria; therefore,
ing ratio of connected piled rafts increases by about 5% [34], understanding pile structural behavior could lead to better
while this value is more significant, nearly 25%, for non- economic designing [36]. Due to the structural connection
connected piled rafts. However, because the load sharing between the piles and the raft, the interposed load on the raft
ratio for non-connected piled rafts is much lower than that in a connected piled raft foundation is directly transferred
for connected piled rafts, it is not favorable to use a larger to the piles, and the amount of pile stress from pile head to
number of piles, and the limit of np = 16 is suitable for both pile tip gradually decreases [15, 16]. In the non-connected
forms. piled raft, however, the load is transferred to the piles due
to the interposed layer between the piles and the raft. As a
4.1.3 Effect of Pile Length result, the relative displacement between piles and subsoil
causes negative skin friction at the upper part of the piles.
The relation between the load sharing ratio and pile length Few researches have been conducted on the load transfer-
for NC/PR with np = 4, 9, 16, and Sp/dp = 5 is shown in ring behavior of non-connected piles in comparison with
Fig. 10c. According to this figure, the load sharing ratio connected piles [14, 16]. This section illustrates the effect of
increases with increasing the pile length, especially for the several parameters such as pile spacing, subsoil and cushion
connected piled raft. A similar trend was reported by Cao stiffness on the load–response behavior of connected and
et al. [6] and Liang et al. [12], which is because more capac- non-connected piles.
ity is mobilized along the piles at the deep layers of the
soils. Further, the efficiency of pile length in increasing the 4.2.1 Effect of Pile Spacing
load-sharing ratio of the connected piled raft is more sig-
nificant than that of the non-connected forms. For instance, The vertical stress behavior of piles along their lengths in
by increasing the pile length from 7 to 20 m when the num- PR/NC with 4 and 9 piles was investigated in pile spacing
ber of piles was 9, the load sharing ratio of non-connected of 3dp, 5dp, 7dp, and 9dp (Fig. 11). Figure 11a illustrates
and connected piled rafts increased by about 75 and 86%, that increasing pile spacing in a connected piled raft with
respectively. Furthermore, the effect of the number of piles four piles by up to 5dp increases the stress at the pile head
on the load-sharing ratio for both foundation options showed by about 30%; however, the results remain constant with
a similar trend. Increasing the number of piles from 9 to 16 further increase in the pile spacing. The effect of pile spac-
when the pile length was 20 m also increased the load shar- ing is more considerable in the connected piled raft with
ing ratio of the non-connected and connected piled rafts by nine piles, and by increasing the pile spacing, the maxi-
about 28 and 25%, respectively. Connected piled rafts with mum values of the pile head stress increase by up to 100%
high load sharing ratios are more favorable in design when (Fig. 11b–d).
piles are considered as load carrying members as well as However, in the non-connected piled raft, by increasing
settlement-reducers. the pile spacing, the vertical stress of the pile head slightly
increases while the maximum vertical stress along the pile
4.1.4 Effect of Cushion Stiffness length rises considerably. Further, Clancy and Randolph
[35] report that pile location significantly affects the verti-
Figure 10d shows the impact of cushion stiffness on the load cal stress along pile length in a non-connected piled raft.
sharing ratio for a non-connected piled raft with np = 4, 9, Generally, a pile located in the center of the raft experi-
16, 25, and Sp/dp = 5. As shown, a higher cushion stiffness ences a larger increase of negative skin friction (Fig. 11b–d).
indicates a higher portion of the load carried by piles [12]. Figure 11 shows that increasing pile spacing from 3dp to
Using a cushion layer with four times higher stiffness in a 9dp presents the highest increase in the amount of negative
non-connected piled raft with four piles increases the pile skin friction in the non-connected piled raft with 9 piles, P1,
load by about 80%. Figure 10b also shows that the efficiency located in the center of the raft(i.e. 65% increase in maxi-
of the cushion Young’s modulus for increasing pile load car- mum vertical stress along pile length). The P2 and P3 piles
rying decreases as the number of piles in the foundation show a 50 and 45% increase in the maximum vertical stress,
increases. It can be concluded that the mere act of increasing respectively (Fig. 11c, d).

13
International Journal of Civil Engineering

0.0 0.0
np=4 piles P3
Lp=20 m P1 P2
Depth Relative to Pile Length, Z/L

Depth Relative to Pile Length, Z/L


0.2 Esubsoil=18.5 MPa 0.2
Ecushion=26 MPa

0.4 0.4
Pile's number: P1
NC04-s/d=3 NC09-s/d=3
0.6 NC04-s/d=5 0.6 NC09-s/d=5
NC04-s/d=7 NC09-s/d=7
NC04-s/d=9 NC09-s/d=9
PR04-s/d=3 np=9 piles PR09-s/d=3
0.8 PR04-s/d=5
0.8 PR09-s/d=5
Lp=20 m
PR04-s/d=7 Esubsoil=18.5 MPa PR09-s/d=7
PR04-s/d=9 Ecushion=26 MPa PR09-s/d=9
1.0 1.0
0 10 20 30 40 50 0 10 20 30 40 50
Vertical Stress (MPa) Vertical Stress (MPa)

(a) (b)
0.0 0.0
P3 P3
np=9 piles np=9 piles
Depth Relative to Pile Length, Z/L

Depth Relative to Pile Length, Z/L


0.2 Lp=20 m P1 P2 0.2 Lp=20 m P1 P2
Esubsoil=18.5 MPa Esubsoil=18.5 MPa
Ecushion=26 MPa Ecushion=26 MPa
0.4 0.4
Pile's number: P2 Pile's number: P3
NC09-s/d=3 NC09-s/d=3
0.6 NC09-s/d=5 0.6 NC09-s/d=5
NC09-s/d=7 NC09-s/d=7
NC09-s/d=9 NC09-s/d=9
PR09-s/d=3 PR09-s/d=3
0.8 PR09-s/d=5
0.8 PR09-s/d=5
PR09-s/d=7 PR09-s/d=7
PR09-s/d=9 PR09-s/d=9
1.0 1.0
0 10 20 30 40 50 0 10 20 30 40 50
Vertical Stress (MPa) Vertical Stress (MPa)

(c) (d)

Fig. 11  Effect of pile spacing on vertical stress along the pile length for connected and non-connected piled raft with constant 12 m raft breadth,
pile length of 20 m, and a 4 piles, b 9 piles-P1, c 9 piles-P2, d 9 piles-P3

4.2.2 Effect of Pile Length However, increasing pile length from 7 to 14 m causes more
pile stress in piles than increasing the pile length from 14
Piled raft foundations with 9 piles and Sp/dp = 5, having to 20 m, which indicates more pile contribution in carrying
three different pile lengths (7, 14, and 20 m), were chosen loads.
to investigate the effect of pile length on the behavior of pile
stress along the depth. According to Fig. 12, increasing the
pile length from 7 to 20 m increases the pile stress values 4.2.3 Effect of Subsoil Stiffness
in both NC/PR foundations [6]. Increasing pile length in
NC increases the pile head stress by about 50%, while the The effect of increasing the subsoil Young’s modulus on the
maximum pile stress along the depth experiences a larger vertical stress along the pile length is negligible for the con-
increase of 95%. The reason for the smaller pile head is the nected piles, although, as shown in Fig. 13a, it does cause a
load shared by the cushion. Further, it seems that pile length slight increase in the vertical pile stress of a non-connected
has a slight effect on the reduction of pile head stress by piled raft. As a result, the effect of other parameters on the
disconnecting piles from the raft, and the reduction values pile stress should be thoroughly considered for both con-
in the pile head stress are increased between 60 and 70%. nected and non-connected systems.

13
International Journal of Civil Engineering

0.0 0.0
np=9 piles P3
sp/dp=5

Depth Relative to Pile Length, Z/L


P1 P2
Depth Relative to Pile Length, Z/L

Esubsoil=18.5 MPa 0.2


0.2 P3
Ecushion=26 MPa
P1 P2
0.4 0.4

Pile's number: P1 Pile's number: P2


0.6 0.6
NC09-Lp=20 m NC, Lp=20 m
NC09-Lp=14m NC09-Lp=14 m
NC09-Lp=7 m np=9 piles NC09-Lp=7 m
0.8 PR09-Lp=20 m 0.8 sp/dp=5 PR09-Lp=20 m
PR09-Lp=14 m Esubsoil=18.5 MPa PR09-Lp=14 m
PR09-Lp=7 m PR09-Lp=7 m
Ecushion=26 MPa
1.0 1.0
0 10 20 30 40 50 0 10 20 30 40 50
Vertical Stress (MPa) Vertical Stress (MPa)

(a) (b)
0.0
P3
Depth Relative to Pile Length, Z/L

P1 P2
0.2

0.4

Pile's number: P3
0.6
NC09-Lp=20 m
NC09-Lp=14 m
np=9 piles NC09-Lp=7 m
0.8 sp/dp=5 PR09-Lp=20 m
Esubsoil=18.5 MPa PR09-Lp=14 m
Ecushion=26 MPa PR09-Lp=7 m
1.0
0 10 20 30 40 50
Vertical Stress (MPa)
(c)

Fig. 12  Effect of pile length on vertical stress along piles depth for connected and non-connected piled raft with 9 piles with Sp/dp = 5 a P1, b
P2, c P3

4.2.4 Effect of Cushion Stiffness 5 Conclusion


Referring to Fig. 13b, increasing cushion stiffness from This research thoroughly compares the load sharing and car-
26 to 104 MPa has a uniform effect on the pile response rying mechanism of piles and load–settlement behaviors of
and causes a considerable increase in the pile load through non-connected and connected piled rafts. The effect of geo-
both pile head and along the depth. The use of a cushion technical and structural parameters of a piled raft, including
layer with 4 times higher stiffness increases the pile head number, length, the spacing of piles, subsoil, and cushion
stress and maximum stress along the pile length by about 70 stiffness has been investigated. The following conclusions
and 15%, respectively. In other words, a cushion layer with can be drawn from this study:
higher stiffness can transfer a larger portion of the total load
to the piles without increasing too much stress along the pile (a) The effect of pile spacing in decreasing raft settlement
length (i.e. about 15%). Furthermore, the difference between was seen to be more significant for connected piled
the pile head stress and the maximum vertical stress along rafts than non-connected rafts.
the pile length decreases. Thus, using a cushion layer with (b) The effect of cushion stiffness was seen to be more
higher stiffness is a simple way to improve the load carrying significant for a non-connected piled raft with shorter
mechanism in piles. piles than one with longer piles. Further, similar to the

13
International Journal of Civil Engineering

0.0 0.0
np=9 piles np=9 piles
Lp=20 m Lp=20 m
Depth Relative to Pile Length, Z/L

Depth Relative to Pile Length, Z/L


Ecushion=26 MPa Esubsoil=18.5 MPa
0.2 0.2
P3
P3
Pile's number: P1 P1 P2
0.4 P1 P2 0.4
NC09-Es=18.5 MPa
NC09-Es=22.0 MPa
NC09-Es=26.0 MPa
0.6 0.6 Pile's number: P1
NC09-Es=30.0 MPa
PR09-Es=18.5 MPa NC09-Ec=26 MPa
0.8 PR09-Es=22.0 MPa 0.8 NC09-Ec=52 MPa
PR09-Es=26.0 MPa NC09-Ec=78 MPa
PR09-Es=30.0 MPa NC09-Ec=104 MPa
1.0 1.0
0 10 20 30 40 50 0 10 20 30 40 50
Vertical Stress (MPa) Vertical Stress (MPa)

0.0 0.0
np=9 piles np=9 piles
Lp=20 m Lp=20 m
Depth Relative to Pile Length, Z/L

Depth Relative to Pile Length, Z/L


Ecushion=26 MPa Esubsoil=18.5 MPa
0.2 0.2
P3 P3

P1 P2 Pile's number: P2 P1 P2
0.4 0.4
NC09-Es=18.5 MPa
NC09-Es=22.0 MPa
NC09-Es=26.0 MPa
0.6 0.6
NC09-Es=30.0 MPa Pile's number: P2
PR09-Es=18.5 MPa NC09-Ec=26 MPa
0.8 PR09-Es=22.0 MPa 0.8 NC09-Ec=52 MPa
PR09-Es=26.0 MPa NC09-Ec=78 MPa
PR09-Es=30.0 MPa NC09-Ec=104 MPa
1.0 1.0
0 10 20 30 40 50 0 10 20 30 40 50
Vertical Stress (MPa) Vertical Stress (MPa)
0.0 0.0
np=9 piles np=9 piles
Lp=20 m Lp=20 m
Depth Relative to Pile Length, Z/L

Depth Relative to Pile Length, Z/L

Ecushion=26 MPa Esubsoil=18.5 MPa


0.2 0.2
P3 P3
P1 P2
Pile's number: P3
P1 P2
0.4 0.4
NC09-Es=18.5 MPa
NC09-Es=22.0 MPa
NC09-Es=26.0 MPa
0.6 0.6
NC09-Es=30.0 MPa Pile's number: P3
PR09-Es=18.5 MPa NC09-Ec=26 MPa
0.8 PR09-Es=22.0 MPa 0.8 NC09-Ec=52 MPa
PR09-Es=26.0 MPa NC09-Es=78 MPa
PR09-Es=30.0 MPa NC09-Es=104 MPa
1.0 1.0
0 10 20 30 40 50 0 10 20 30 40 50

Vertical Stress (MPa) Vertical Stress (MPa)


(a) (b)

Fig. 13  Influences of a subsoil and b cushion Young’s modulus on vertical stress along the pile length for NC/PR with 9 piles, 12 m raft breadth,
and pile length of 20 m

connected piled raft, an upper limit for increasing the (c) In general, piles in a connected piled raft carry more
number of piles for the axial stiffness of non-connected load than a non-connected piled raft. However, by
piled raft was observed. increasing cushion stiffness, non-connected pile loads

13
International Journal of Civil Engineering

Table 3  Summary of results Parameters Variation Raft settlement reduc- Load sharing ratio (%)
tion (%)
CPR NCPR CPR foundation NCPR foundation
founda- founda-
tion tion

Pile spacing From 3dp to 9dp 35 13 38 20.9


Subsoil stiffness From 18.5 to 30 MPa 38 34 −4 − 27
Cushion stiffness From 30 to 104 MPa – 12 – 75.4
Pile length From 7 to 20 m 35 24 89.9 74.9
Number of piles From 4 to 25 51 37 239.6 106.5

increased up to a certain value. Similar to the results 8. Wong I, Chang M, Cao X (2000) Raft foundations with discon-
reported by Mandolini et al. [34], by increasing the nected settlement reducing piles. Paper presented at the design
applications of raft foundations, London
ratio of (Sp/dp)/(Ag/A), the raft proportion of load carry- 9. Eslami A, Veiskarami M, Eslami M (2012) Study on optimized
ing increased up to the specific value and then remained piled–raft foundations (PRF) performance with connected
constant by increasing (Sp/dp)/(Ag/A) further. and non-connected piles-three case histories. Int J Civ Eng
(d) Increasing the pile length showed a similar increasing 10(2):100–111
10. Rasouli H, Azizkandi AS, Baziar M, Modarresi M, Shahnazari
trend for both NC and PR. However, while increasing H (2015) Centrifuge modeling of non-connected piled raft sys-
non-connected pile lengths showed a slight increase of tem. Int J Civ Eng 13(2):114–123
the pile head stress, the stress increase along the pile 11. Zheng J-J, Abusharar SW, Wang X-Z (2008) Three-dimensional
depth was seen to be more significant. As a result, more nonlinear finite element modeling of composite foundation
formed by CFG–lime piles. Comput Geotech 35(4):637–643
precaution is needed when choosing long piles for a 12. Liang F-Y, Chen L-Z, Shi X-G (2003) Numerical analysis of
non-connected piled raft. composite piled raft with cushion subjected to vertical load.
Comput Geotech 30(6):443–453
A quantitative summary from the present study is shown 13. Azizkandi AS, Baziar MH, Yeznabad AF (2017) 3D dynamic
finite element analyses and 1 g shaking table tests on seismic per-
in Table 3. In terms of the design approach, the number of formance of connected and nonconnected piled raft foundations.
piles and length have the most significant effect on designing KSCE J Civ Eng. https​://doi.org/10.1007/s1220​5-017-0379-2
both types of foundations. Furthermore, cushion stiffness 14. Tradigo F, Pisanò F, Di Prisco C, Mussi A (2015) Non-linear
in a non-connected piled raft is an important factor of the soil–structure interaction in disconnected piled raft foundations.
Comput Geotech 63:121–134
pile length. 15. Fioravante V, Giretti D (2010) Contact versus noncontact piled
raft foundations. Can Geotech J 47(11):1271–1287
16. Fioravante V (2011) Load transfer from a raft to a pile with an
interposed layer. Geotechnique 61(2):121
17. Nakaia S, Katoa H, Ishidaa R, Manob H, Nagatac M (2004)
References Load bearing mechanism of piled raft foundation during earth-
quake. In: Proceedings of 3rd UJNR workshop on soil-structure
1. Davis E, Poulos H (1972) The analysis of pile raft systems. J Aust interaction. Citeseer, pp 29–30
Geomech 62(1):21–27 18. Tradigo F, Pisanò F, di Prisco C (2016) On the use of embedded
2. Poulos HG, Davis EH (1980) Pile foundation analysis and design. pile elements for the numerical analysis of disconnected piled
Wiley, New Jersey rafts. Comput Geotech 72:89–99
3. Burland JB, Broms BB, de Mello VF (1978) Behaviour of foun- 19. Russo G, Viggiani C (1998) Factors controlling soil–struc-
dations and structures. In: 9th international conference of soil ture interaction for piled rafts. In: International conference on
mechanics and foundation engineering, pp 495–546 soil–structure interaction in urban civil. Darmstadt University,
4. Poulos H (2001) Piled raft foundations: design and applications. pp 297–322
Geotechnique 51(2):95–113 20. Poulos HG (1989) Pile behaviour—theory and application. Geo-
5. Ghalesari AT, Barari A, Amini PF, Ibsen LB (2015) Development technique 39(3):365–415
of optimum design from static response of pile–raft interaction. 21. Burland JB (2012) ICE manual of geotechnical engineering,
J Mar Sci Technol 20(2):331–343. https​://doi.org/10.1007/s0077​ volume 2—geotechnical design, construction and verification.
3-014-0286-x ICE Publishing, London
6. Cao XD, Wong IH, Chang M-F (2004) Behavior of model rafts 22. Garnier J, Konig D (1998) Scale effects in piles and nails load-
resting on pile-reinforced sand. J Geotech Geoenviron Eng ing tests in sand. In: Centrifuge, pp 205–210
130(2):129–138 23. Uesugi M, Kishida H (1986) Influential factors of friction
7. Wei X, Wang Q, Wang J (2008) Damage patterns and failure between steel and dry sands. Soils Found 26(2):33–46
mechanisms of bridge pile foundation under earthquake. In: The 24. Lo Presti DCF, Pallara O, Fioravante V, Jamiolkowski M (1998)
14th world conference on earthquake engineering Assessment of quasi-linear models for sands. In: Jardine R,

13
International Journal of Civil Engineering

Davies M, Hight D, Smith A, Stallebrass S (eds) Prefailure 32. Rasouli H, Ghalesari AT, Modarresi M, Hasanzadeh A (2017)
deformation behaviour of geomaterials. Thomas Telford, Lon- Numerical study of non-contact piled raft interaction under static
don, UK, pp 363–372 loads. In: Mebarki A (ed) Civil engineering and urban planning,
25. Saccenti A (2006) Sul comportamento meccanico dei terreni della pp 750–762. https​://doi.org/10.1142/97898​13225​237_0058
Laguna di Venezia. Ph.D. thesis, The University of Ferrara, Fer- 33. Ghalesari AT, Rasouli H (2014) The effect of gravel layer on the
rara, Italy (In Italian) behavior of piled raft foundations. In: Advances in soil dynam-
26. Giretti D (2010) Modelling of piled raft foundations in sand. PhD ics and foundation engineering, ASCE GSP 240, Proceed-
thesis, The University of Ferrara, Italy ings of GeoShanghai 2014, Shanghai, pp 373–382. https​://doi.
27. Taghavi Ghalesari A, Janalizadeh Choobbasti A (2016) Numerical org/10.1061/97807​84413​425.038
analysis of settlement and bearing behaviour of piled raft in Babol 34. Mandolini A, Russo G, Viggiani C (2005) Pile foundations: exper-
clay. Eur J Environ Civ Eng 22:1–26 imental investigations, analysis and design. In: XVI international
28. Barari A, Ibsen LB, Taghavi Ghalesari A, Larsen KA (2016) conference on soil mechanics and geotechnical engineering, vol
Embedment effects on vertical bearing capacity of offshore 1, pp 177–213
bucket foundations on cohesionless soil. Int J Geomech 35. Clancy P, Randolph M (1993) An approximate analysis procedure
17(4):04016110 for piled raft foundations. Int J Numer Anal Methods Geomech
29. de Sanctis L, Mandolini A (2006) Bearing capacity of piled rafts 17(12):849–869
on soft clay soils. J Geotech Geoenviron Eng 132(12):1600–1610 36. O’Brien AS, Burland JB, Chapman T (2012) Chapter 56 Rafts and
30. Azizkandi AS, Baziar M, Modarresi M, Salehzadeh H, Rasouli H piled rafts. In: ICE manual of geotechnical engineering, vol II, pp
(2014) Centrifuge modeling of pile–soil–pile interaction consider- 853-886. https​://doi.org/10.1680/moge.57098​.0853
ing relative density and toe condition. Sci Iran 4:1330–1339
31. Modarresi M, Rasouli H, Ghalesari AT, Baziar MH (2016) Exper-
imental and numerical study of pile-to-pile interaction factor in
sandy soil. Proced Eng 161:1030–1036

13

S-ar putea să vă placă și