Documente Academic
Documente Profesional
Documente Cultură
Diagram
For more information on tracks, also see the permanent way FAQ page.
Shown below is a diagram (not to scale) of a typical track formation. Dimensions
shown are indicative for a typical BG single line track. This is adapted from a
diagram published by IR. Also see the page on dimensional diagrams of tracks.
Note: This site is not officially affiliated with Indian Railways! The official web site of Indian
Railways is: http://www.indianrailways.gov.in
Permanent Way - Dimensional
Diagrams
For more information on tracks, also see the permanent way FAQ page.
Shown below are diagrams (not to scale) of typical track layouts on embankments
and in cuttings. Dimensions shown are for both BG (1676mm) and MG (1000mm),
except for the centre-to-centre distances for double lines and the track formation
widths which are shown for BG and MG (the latter marked with 'MG' in parentheses).
These are adapted from diagrams published by IR. Also see the page on a detailed
diagram of a track formation.
Correction Slips Issued after the publication of the last
issue of the Journal
INDIAN RAILWAYS PERMANENT WAY MANUAL
1986 (EDITION)
The fixing of guard rail on concrete sleepers shall be done as shown in drawing No.RDSO/T-
4088 to 4097 by proper tightening of rail screws. Provision of MS flats/ tie bars for tying PRC
sleepers together at ends is not required.
The para 901 of chapter IX of IRPWM - 1986 modified vide correction slip No.35 dated 19.08.99
be re-modified to read as under: -
901 General Location: As far as possible, new Level Crossings may not be located in busy
station yards where heavy detention to the road traffic and other operational problems are likely
to be encountered. If provision of Level Crossing is inescapable it may be located outside the
outermost facing points. For Level Crossings already located within busy station yards affecting
Railway operations and causing heavy detention to the road traffic, efforts should be made to
replace them by Road Over/ Under Bridges as per extant rules or shift them outside the outer
most facing points, especially during planning of gauge conversions, yard re-modelling and
doublings and its operation from the cabin should be possible.
INDIAN RAILWAYS PERMANENT WAY MANUAL
1986 - (EDITION)
The existing para 309 of Indian Railways Permanent Way Manual be renumbered as 309
(B).
309 (A) Project report for track renewal works : Systematic and meticulous planning for
various items of execution of track works is essential for achieving quality, economy and
timely completion of works. For every sanctioned track work e.g. CTR, TSR, TRR, deep
screening, bridge timber renewal, etc. a detailed project report should be prepared. The
report should, inter alia, cover the following aspects:
i) Details of work - Pink book detail, scope of work, locational details, cost and
estimate particulars etc.
ii)
Existing track structure - Inventory of existing track structure including the rails, sleepers,
fittings, ballast quantity/deficiency in track, type, width of formation and other details
should be taken as prescribed in P.Way diagram, details of level crossings, bridges,
electrical fittings, curves, height of bank/cuttings, yards, sidings, etc.
iii)
Classification of track materials - During inventory of the existing track structure by foot
by foot survey, identification, classification and colour marking of existing track
materials as second hand and scrap would be done as provided in para 320 of the
IRPWM. The classification should be approved by the competent authority. Action plan
for stacking/storage and disposal of the released materials should be clearly indicated.
Inventory of existing track material would normally be prepared jointly by the PWI of the
section and the PWI(Spl) for the renewal.
iv)
Proposed track structure - The proposed P.Way diagram of the affected length should be
prepared in the same format as done for the existing track structure and incorporated in
the project report.
v)
Existing/proposed gradient profile - The levels of existing track should be taken at every
20 metres and a gradient diagram prepared. Introduction of vertical curves should be
critically examined and the proposed profile of track shown in red line indicating the
proposed grades. Lowering of track should be avoided. Precise lift of track at girder
bridges should be worked out and a separate scheme developed for lifting of girders on
each of the affected bridges. Similarly, the magnitude of lifting at level crossing should
be worked out and indicated in the report. Care should be exercised to keep the road
surface in one level on level crossings spanning to across multiple tracks. This may
require regrading of adjacent lines too.
vi)
Realignment of curves - All curves should be measured afresh and slews worked out for
realignment wherever necessary, keeping in the obligatory points in view.
vii)
Method of execution -The work should be executed "bottom upwards" i.e. sequence of
execution of works will be in the following order-
viii) Formation:
a)
Repair and widening of cess: The project report should indicate the requirement of and
plan for widening of formation in both banks and cuttings wherever necessary. Provision
of proper drains in cuttings should also be planned.
b)
Formation treatment: Areas needing formation rehabilitation should be identified and a
study for possible solutions and method of execution of the rehabilitation scheme should
form part of the project report.
ix)
Ballast - The requirement indicating bifurcation of cess supply and depot supply and the
source and means of each should be spelt out clearly. Mode of providing ballast cushion
i.e. deep screening or raising should be identified along with sketches of cross sections
present and proposed. Sleeper renewal would normally not be started unless adequate
arrangements for supply of ballast have been made.
x)
Transportation of P.Way materials - The mode of transportation for various track
components and unloading of rails and sleepers in particular, at the work sites should be
indicated in the project report.
xi)
Welding - The complete details of welding requirements, the arrangements need to be
made for its execution whether departmentally or through contract should be clearly
indicated in the report.
xii)
Renewal of turnouts, bridge timbers, etc. - The project report should cover the complete
details of turnouts, bridge timbers, level crossings, etc. where renewal is to be carried out.
Whether turnouts are to be laid manually or by mechanized means, should be clearly
brought out indicating the arrangements made. The report should also include the mode
and agency for overhauling and relaying and making up of road surface at the level
crossings.
xiii)
Use of machines -The requirement of machines for renewal (if mechanized renewal is
planned) deep screening (if mechanized deep screening is planned) and
tamping/stabilizing and the duration for which the machines are required should be
indicated. The machines that would be deployed should be identified and staff nominated.
The planning for repair of machines at the works site, supply of fuel and other
consumables should be planned. The requirement of additional lines in the existing yards
for making base depot and arrangements made for the same should be indicated in the
report
xiv)
Contracts - The contracts that are required to be entered into for various activities of
works and the activities, which are to be done departmentally, should be spelt out. The
planning for deployment of staff/supervisors for execution at various activities should be
indicated.
xv)
Material Planning - The material requirement should indicate the materials to be arranged
by the headquarters and by the Divisions. Against each material, the proper nomenclature
and drawing number should be indicated. Rails, nos. and sizes (including lead rails, check
rails etc.), sleepers (including specials), rail and sleeper fastenings, switches and
crossings, level crossing and bridge sleepers and fittings, etc. should be fully covered.
The consignee particulars and the destination, the mode of transport should also be
indicated.
xvi)
Manpower Planning - The requirement of manpower including the officers, supervisors,
artisan and other staff should be worked out with minute details. The arrangements made
for camping of these officials and mobilization should be reflected in the report.
xvii)
LWR/CWR plans - For welding of rails into LWR/CWR, the LWR plan should be got
approved by the competent authority well in advance. Such plan should form part of the
project reports.
xviii)
Requirement of speed restrictions, traffic blocks and other material train - Planning for
execution of track renewal works should be such that the time loss on account of speed
restriction is minimal and is within the permissible limits. The report should indicate
requirement of speed restrictions and traffic blocks together with durations. The corridor
for blocks is required to be planned in consultation with the Operating Department and
accordingly reflected in the report after obtaining the approval of DRM. Arrangements
made for various types of wagons for transportation of ballast, sleepers, etc. together with
requirement of locomotives should be indicated in the report in consultation with
Sr.DOM and with the approval of DRM.
xix)
Monitoring mechanism - The list of all activities involved and the time estimation for
each activity should be worked out. These activities should be sequenced and co-related
in logical manner and network diagram prepared using CPM method. The critical
activities should thus be identified. These should form part of the project report.
xx)
The detailed project report covering the various points as mentioned above should be
prepared as soon as the approval of Board to include the works in FWP is conveyed to the
railways. These reports should be submitted to headquarters for scrutiny and approval.
(a) Destressing must be done well in advance before summer season when rail temp
is as below:-
(i) differs beyond specified limits i.e.40mm for 52/60 Kg. and 60mm for others
position.
Destressing is required to be done after major repair work like deep screening, lifting
of track, realignment of track,Restoration of track,and laying of new track. It is also to
be done if no. of rail-fracture location exceed 3 per Km.
© Ballast profile should be maintained properly in good condition and kept fully
boxed.
(d) For regular maintenance rail-temperature should be as below :-
td +10 to td-30, and work should be completed well before onset of summer.
(e) Speed restriction is imposed if rail temperature after maintenance operation
exceeds td+20 during the period of consolidation. Speed restrictions are
for BG - 50 KMPH
for MG - 40 KMPH
(f) Not more than 30 sleepers spaces is to be opened at a time for through packing
or shallow screening.Remaining portion is to be tackled after passage of traffic for 24
hours in case of BG route carrying traffic greater than 10 GMT. For other route of
BG/MG, it is taken after passage of traffic for two days.
(i) Keyman should keep watch on the gap at SEj during daily inspection. it should be
maintained for requirement like aligning, greasing, fitting in position and packing
fortnightly. If buffer rail is used in lieu of SEJ it should be attended for lubrication
twice in a year. Gap in fish-plated joints should be 3mm -12mm.
(j) If mechanized maintenance if employed in LWR track requiring lifting, a general lift
should not exceed 50mm in PSC sleeper and 25mm in case of metal/wooden
sleeper. Lifting requiring more the above lift should be done in stages with adequate
consolidation period between the successive stages of lifting.
(l) During special work like major realignment of curve,through sleeper renewal,
rehabilitation of formation or bridge-work the effected length of LWR should be
separated from the main LWR by buffer-rail , and after work it should be continued
and distressed.
Buckling of Track
If the rails are slender elements and when subjected to compressive forces, the track
tends to buckle unless restrained by the weight of track and the lateral resistance
offered by ballast. If the track loses lateral resistance due to any of the reasons:
Improper destressing
Jammed Switch Expansion Joint (SEJ)
Stress Free temperature quite low as compared with the prevailing
temperature
Attention to track affecting lateral ballast resistance
Lifting of track for any reason
Buckling is a very serious occurrence for track and the safety is immediately
jeopardised if a train passes over buckled track or track which is about to buckle
(Incipient buckling condition). Hot weather patrolmen and p-way officials on track
have to vigilant to look out for signs of buckling.
A couple of photographs of buckled track in one foreign railway are shown below:
1)
Indian Railways Manual for Long Welded Rails
2)
IRICEN book on Long Welded Rails
C:/wamp/www/doku/data/pages/lwr.txt · Last modified: 2010/11/26 04:38 by iricen
================================Note====
==========
In the forging stage the two rail ends are forced together
suddenly with high pressure so that they become welded
together. Semi-liquid metal is forced out all around the
periphery forming 'flash' that will be removed almost
immediately by the Weld Trimmer
Moving the rail from the welder and trimming the rail takes
only about 10 seconds.
"Further Operations"
"Weld Trimmer"
As the weld came out of the welder, the trimmer tools closed
around the rail and when the weld contacted the tools the
heavy frame of the trimmer would be forced back against
powerful springs. The rail would be clamped and the trimming
action begun. It was important to start the trim with the tools
in contact with the weld so they only needed to move a short
distance. As soon as the cut finished, the tools and clamp were
released and the weld travelled to the next work station. Time
for trimming was 10 seconds only.
The buildings that housed the welding plant was sealed as far
as possible, and the air pressure inside the building was
slightly raised to stop the sand blowing in and small apertures
"Small tools"
Gauge
Skew
Cant (Superelevation)
Versines over a chord of 10 metres, measured for both
rails
High and low points for each rail.
The trolley could run in either direction; the chart always ran
the same way. Three scales of recording were available
depending on the job in hand. The PV6 could be fitted
with Ultrasonic Rail Flaw Detection Equipment to detect
cracks in the rail. These are not always visible from outside the
rail.
This coach, 77ft long, could be linked up to any train and was
capable of making geometric and dynamic records of track
parameters under realistic loads. It weighed 60 tons and could
record at speeds up to 75m.p.h In its day it was probably the
height of recording technology. Is it being beaten today?
Ballast Cleaner
RM 900-HD
The New South Wales railway network commenced ballast cleaning operations in the
1970’s with one RM 62 and four RM 76 ballast cleaning machines in 1978 and 1979.
Whilst these machines had performed well for many years, maintenance costs,
reliability and safety factors led to a reduced operating fleet of two RM 76 ballast
cleaning machines by the year 2000.
With the intention of introducing new technology, greater capacity, better reliability
and improved safety, the Rail Infrastructure Corporation (now known as RailCorp
NSW) invested in a newhigh performance ballast cleaning machine – the RM 900-HD
– to replace the old machines. The order was placed in June 2002, which was the
commencement of a two year project for the design, manufacture, testing and
commissioning of the largest single machine ever manufactured by Plasser Australia
at the Sydney workshops.
The RailCorp RM 900-HD has a number of unique features that distinguish it from
other RM 900 ballast cleaners:
Height 4,200 mm
Width 2,970 mm
Engines
two V12 - 710kW Caterpillar 3
- drive & work systems
412
- AC generator & star screens
one 310 kW Caterpillar C10
The ballast bed distributes the loads of the trains uniformly onto the
track substructure and assures a firm, unshifting position of the
sleepers. To withstand these dynamic impacts the ballast bed has to
be very elastic. The good function depends on the depth of the
ballast bed, the size of the ballast stones and the degree of fouling.
Fouling occurs under normal operational loads. This causes the
edges of the ballast stones to break off,settlement of the stones
and friction processes. Other causes of fouling are material rising
up from the subsoil and external environmental influences. Overall,
this causes an increase in the proportion of fines which reduces the
elasticity of the track, the water permeability and the durability of
the track geometry. As a consequence, there will be irregular
settlement of the track which tamping can compensate only for
short periods. From a certain point in time it will be more
economical to clean the entire ballast bed.
High output
ballast bed
cleaning
HRM 2004 CH -
Machine with two
screen units and a
supply of new ballast
RM 900 HD-100
‹›
High capacity ballast cleaning machine for plain track with one excavating
chain, two screening units and one stabilising unit
RM 95-800 W
‹›
High capacity ballast cleaning machine for plain track with one excavating
chain, two screening units, one stabilising unit, a finger screen, a metal
separator, a ballast sharpening plant, a high-pressure ballast washing plant
and a waste water clarification plant
RM 80 UHR-N
‹›
Ballast cleaning machine for plain track and turnouts with one excavating
chain, one screening unit and if required with supply of new ballast
RM 2002
‹›
High capacity ballast cleaning machine for plain track with one excavating
chain and two screening units
RM 74 BR-UHR
‹›
Ballast cleaning machine for plain track and turnouts with one excavating
chain, one screening unit and on request with additional axles to reduce
the maximum axle load. Machine especially suited for work on lines with
tight clearance gauge and for narrow gauge tracks