Sunteți pe pagina 1din 14

THIRD DIVISION back to Manila.

back to Manila.[8] Notwithstanding this instruction, all FSI and LICOMCEN then proceeded to draft the Engineer and Contractor.
the ordered steel bars arrived in Legaspi City on January Terms of Reference.[21]
14, 1998.[9] Such decision shall be final and binding upon the parties
G.R. No. 167022, April 04, 2011 On February 4, 2003, LICOMCEN, through a and the Contractor shall proceed with the execution of
On January 15, 1998, LICOMCEN instructed FSI to collaborating counsel, filed its Ex Abundati Ad Cautela the Works with due diligence notwithstanding any
"hold all construction activities on the project,"[10] in Omnibus Motion, insisting that FSI's petition before the Contractor's objection to the decision of the Engineer.
LICOMCEN INCORPORATED, PETITIONER,
view of a pending administrative case against the CIAC should be dismissed for lack of jurisdiction; thus, If within a period of thirty (30) days from receipt of the
VS. FOUNDATION SPECIALISTS, INC.,
officials of the City Government of Legaspi and it prayed for the suspension of the arbitration LICOMCEN, INCORPORATED's decision on the
RESPONDENT.
LICOMCEN filed before the Ombudsman (OMB- proceedings until the issue of jurisdiction was finally dispute, either party does not officially give notice to
ADM-1-97-0622).[11] On January 19, 1998, ESCA settled. The CIAC denied LICOMCEN's motion in its contest such decision through arbitration, the said
[G.R. NO. 169678]
formalized the suspension of construction activities and February 20, 2003 order,[22] finding that the question of decision shall remain final and binding. However,
ordered the construction's demobilization until the case jurisdiction depends on certain factual conditions that should any party, within thirty (30) days from receipt of
FOUNDATION SPECIALISTS, INC.,
was resolved.[12] In response, FSI sent ESCA a letter, have yet to be established by ample evidence. As the the LICOMCEN, INCORPORATED's decision,
PETITIONER, VS. LICOMCEN
dated February 3, 1998, requesting payment of costs CIAC's February 20, 2003 order stood uncontested, the contest said decision, the dispute shall be submitted for
INCORPORATED, RESPONDENT.
incurred on account of the suspension which totaled arbitration proceedings continued, with both parties arbitration under the Construction Industry Arbitration
P22,667,026.97.[13] FSI repeated its demand for actively participating. Law, Executive Order 1008. The arbitrators appointed
DECISION
payment on March 3, 1998.[14] under said rules and regulations shall have full power to
The CIAC issued its decision on July 7, 2003,[23] ruling open up, revise and review any decision, opinion,
BRION, J.: ESCA replied to FSI's demands for payment on in favor of FSI and awarding the following amounts: direction, certificate or valuation of the LICOMCEN,
March 24, 1998, objecting to some of the INCORPORATED. Neither party shall be limited to
claims.[15] It denied the claim for the cost of the steel the evidence or arguments put before the LICOMCEN,
a. Unpaid accomplished work P
THE FACTS bars that were delivered, since the delivery was done in INCORPORATED for the purpose of obtaining his
billings................ 1,264,404.12
complete disregard of its instructions. It further said decision. No decision given by the LICOMCEN,
The petitioner, LICOMCEN Incorporated disclaimed liability for the other FSI claims based on the b. Material costs at INCORPORATED shall disqualify him from being
14,643,638.51
(LICOMCEN), is a domestic corporation engaged in suspension, as its cause was not due to LICOMCEN's site................................. called as a witness and giving evidence in the arbitration.
the business of operating shopping malls in the country. fault. FSI rejected ESCA's evaluation of its claims c. Equipment and labor standby It is understood that the obligations of the
in its April 15, 1998 letter.[16] 2,957,989.94 LICOMCEN, INCORPORATED, the Engineer and
costs...............
In March 1997, the City Government of Legaspi the Contractor shall not be altered by reason of the
awarded to LICOMCEN, after a public bidding, a lease On March 14, 2001, FSI sent a final demand letter d. Unrealized gross arbitration being conducted during the progress of the
5,120,000.00
contract over a lot located in the central business district to LICOMCEN for payment of profit.............................. Works.[26]
of the city. Under the contract, LICOMCEN was P29,232,672.83.[17] Since LICOMCEN took no
obliged to finance the construction of a commercial positive action on FSI's demand for payment, [18] FSI LICOMCEN was also required to bear the costs of LICOMCEN posits that only disputes "in connection
complex/mall to be known as the LCC Citimall filed a petition for arbitration with the Construction arbitration in the total amount of P474,407.95. with or arising out of the execution of the Works" are
(Citimall). It was also granted the right to operate and Industry Arbitration Commission (CIAC) on October subject to arbitration. LICOMCEN construes the
manage Citimall for 50 years, and was, thereafter, 2, 2002, docketed as CIAC Case No. 37-2002.[19] In the LICOMCEN appealed the CIAC's decision before the phrase "execution of the Works" as referring to the
required to turn over the ownership and operation to arbitration petition, FSI demanded payment of the Court of Appeals (CA). On November 23, 2004, the physical construction activities, since "Works" under the
the City Government.[1] following amounts: CA upheld the CIAC's decision, modifying only the GCC specifically refer to the "structures and facilities"
amounts awarded by (a) reducing LICOMCEN's required to be constructed and completed for the
For the Citimall project, LICOMCEN hired E.S. de liability for material costs at site to P5,694,939.87, and Citimall project.[27] It considers FSI's claims as mere
Castro and Associates (ESCA) to act as its engineering (b) deleting its liability for equipment and labor standby contractual monetary claims that should be litigated
a. Unpaid accomplished work costs and unrealized gross profit; all the other awards before the courts of Legaspi City, as provided in GC-05
consultant. Since the Citimall was envisioned to be a P 1,264,404.12
billings................
high-rise structure, LICOMCEN contracted respondent were affirmed.[24] Both parties moved for the of the GCC:
Foundation Specialists, Inc. (FSI) to do initial b. Material costs at reconsideration of the CA's Decision; LICOMCEN's
15,143,638.51
construction works, specifically, the construction and site................................... motion was denied in the CA's February 4, 2005
installation of bored piles foundation. [2] LICOMCEN c. Equipment and labor standby Resolution, while FSI's motion was denied in the CA's GC-05. JURISDICTION
and FSI signed the Construction Agreement,[3] and the 3,058,984.34 September 13, 2005 Resolution. Hence, the parties filed
costs.................
accompanying Bid Documents[4] and General their own petition for review on certiorari before the Any question between the contracting parties that
Conditions of Contract[5] (GCC) on September 1, 1997. d. Unrealized gross Court.[25] may arise out of or in connection with the Contract,
9,023,575.29
Immediately thereafter, FSI purchased the materials profit................................ or breach thereof, shall be litigated in the courts of
needed for the Citimall[6] project and began working in e. Attorney's LICOMCEN's Arguments Legaspi City except where otherwise specifically stated
300,000.00 or except when such question is submitted for
order to meet the 90-day deadline set by LICOMCEN. fees.........................................
LICOMCEM principally raises the question of the settlement thru arbitration as provided herein.[28]
f. Interest expenses equivalent to 15% of
On December 16, 1997, LICOMCEN sent word to FSI CIAC's jurisdiction, insisting that FSI's claims are non-
................................. the total claim
that it was considering major design revisions and the arbitrable. In support of its position, LICOMCEN cites LICOMCEN also contends that FSI failed to comply
suspension of work on the Citimall project. FSI replied GC-61 of the GCC: with the condition precedent for arbitration laid down
on December 18, 1997, expressing concern over the LICOMCEN again denied liability for the amounts in GC-61 of the GCC. An arbitrable dispute under GC-
revisions and the suspension, as it had fully mobilized claimed by FSI. It justified its decision to indefinitely 61 must first be referred to and settled by LICOMCEN,
its manpower and equipment, and had ordered the suspend the Citimall project due to the cases filed GC-61. DISPUTES AND ARBITRATION which has 30 days to resolve it. If within a period of 30
delivery of steel bars. FSI also asked for the payment of against it involving its Lease Contract with the City days from receipt of LICOMCEN's decision on the
accomplished work amounting to P3,627,818.00.[7] A Government of Legaspi. LICOMCEN also assailed the Should any dispute of any kind arise between the dispute, either party does not officially give notice to
series of correspondence between LICOMCEN and CIAC's jurisdiction, contending that FSI's claims were LICOMCEN INCORPORATED and the Contractor contest such decision through arbitration, the said
FSI then followed. matters not subject to arbitration under GC-61 of the [referring to FSI] or the Engineer [referring to ESCA] decision shall remain final and binding. However,
GCC, but one that should have been filed before the and the Contractor in connection with, or arising out should any party, within 30 days from receipt of
ESCA wrote FSI on January 6, 1998, stating that the regular courts of Legaspi City pursuant to GC-05.[20] of the execution of the Works, such dispute shall first LICOMCEN's decision, contest said decision, the
revised design necessitated a change in the bored piles be referred to and settled by the LICOMCEN, dispute shall be submitted for arbitration under the
requirement and a substantial reduction in the number During the preliminary conference of January 28, 2003, INCORPORATED who shall within a period of thirty Construction Industry Arbitration Law.
of piles. Thus, ESCA proposed to FSI that only 50% of LICOMCEN reiterated its objections to the CIAC's (30) days after being formally requested by either party
the steel bars be delivered to the jobsite and the rest be shipped jurisdiction, which the arbitrators simply noted. Both to resolve the dispute, issue a written decision to the LICOMCEN considers its March 24, 1998 letter as its
final decision on FSI's claims, but declares that FSI's suspension of the works, FSI sold 125,000 kg of steel standby costs on the ground that FSI's documentary
reply letter of April 15, 1998 is not the "notice to bars for P500,000.00 to a third person (a certain Ramon evidence was inadequate. FSI finds the ruling Excluded from the coverage of this law are disputes
contest" required by GC-61 that authorizes resort to Quinquileria). LICOMCEN alleges that FSI sold the erroneous, since LICOMCEN never questioned the list arising from employer-employee relationships which
arbitration before the CIAC. It posits that nothing in steel bars for a ridiculously low price of P 4.00/kilo, of employees and equipments employed and rented by shall continue to be covered by the Labor Code of the
FSI's April 15, 1998 letter states that FSI will avail of when the prevailing rate was P20.00/kilo. The sale FSI for the duration of the suspension.[39] Philippines.
arbitration as a mode to settle its dispute with could have garnered a higher price that would offset
LICOMCEN. While FSI's final demand letter of March LICOMCEN's liability. LICOMCEN also wants FSI to FSI also alleges that LICOMCEN maliciously and The jurisdiction of courts and quasi-judicial bodies is
14, 2001 mentioned its intention to refer the matter to account for and deliver to it the remaining 744 metric unlawfully suspended the Citimall project. While determined by the Constitution and the law.[44] It
arbitration, LICOMCEN declares that the letter was tons of steel bars not sold. Otherwise, FSI would be LICOMCEN cited several other cases in its petition for cannot be fixed by the will of the parties to a dispute; [45]
made three years after its March 24, 1998 letter, hence, unjustly enriched at LICOMCEN's expense, receiving review on certiorari as grounds for suspending the works, the parties can neither expand nor diminish a tribunal's
long after the 30-day period provided in GC- payment for materials not delivered to LICOMCEN.[33] its letters/notices of suspension only referred to one jurisdiction by stipulation or agreement. The text of
61. Indeed, FSI filed the petition for arbitration with case, OMB-ADM-1-97-0622, an administrative case Section 4 of E.O. 1008 is broad enough to cover any
the CIAC only on October 2, 2002.[29] Considering LICOMCEN also disagrees with the CA ruling that before the Ombudsman that was dismissed as early as dispute arising from, or connected with construction contracts,
FSI's delays in asserting its claims, LICOMCEN also declared it solely liable to pay the costs of October 12, 1998. LICOMCEN never notified FSI of whether these involve mere contractual money claims or
contends that FSI's action is barred by laches. arbitration. The ruling was apparently based on the the dismissal of this case. More importantly, no execution of the works.[46] Considering the intent
finding that LICOMCEN's "failure or refusal to meet its restraining order or injunction was issued in any of behind the law and the broad language adopted,
With respect to the monetary claims of FSI, obligations, legal, financial, and moral, caused FSI to these cases to justify the suspension of the Citimall LICOMCEN erred in insisting on its restrictive
LICOMCEM alleges that the CA erred in upholding its bring the dispute to arbitration."[34] LICOMCEN project.[40] FSI posits that LICOMCEN's true intent was interpretation of GC-61. The CIAC's jurisdiction cannot
liability for material costs at site for the reinforcing steel asserts that it was FSI's decision to proceed with the to terminate its contract with it, but, to avoid paying be limited by the parties' stipulation that only disputes in
bars in the amount of P5,694,939.87, computed as delivery of the steel bars that actually caused the damages for breach of contract, simply declared it as connection with or arising out of the physical
follows[30]: dispute; it insists that it is not the party at fault which "indefinitely suspended." That LICOMCEN conducted construction activities (execution of the works) are
should bear the arbitration costs.[35] another public bidding for the "new designs" is a telling arbitrable before it.
indication of LICOMCEN's intent to ease out FSI.[41]
2nd initial rebar requirements purchased FSI's Arguments Thus, FSI states that LICOMCEN's bad faith in In fact, all that is required for the CIAC to acquire
from Pag-Asa Steel Works, indefinitely suspending the Citimall project entitles it to jurisdiction is for the parties to a construction
P
Inc...................................... FSI takes exception to the CA ruling that modified the claim unrealized profit. The restriction under GC-41 contract to agree to submit their dispute to
799,506.83
amount for material costs at site, and deleted the awards that "[t]he contractor shall have no claim for anticipated arbitration. Section 1, Article III of the 1988 CIAC
Reinforcing steel bars purchased from for equipment and labor standby costs and unrealized profits on the work thus terminated,"[42] will not apply Rules of Procedure (as amended by CIAC Resolution
ARCA Industrial Sales (total net weight of profits. because the stipulation refers to a contract lawfully and Nos. 2-91 and 3-93) states:
744,197.66 kilograms) - 50% of net 5,395,433.0 properly terminated. FSI seeks to recover unrealized
amount due................... 4 Proof of damage to FSI is not required for profits under Articles 1170 and 2201 of the Civil Code
Subtotal.................................................. 6,194,939.8 LICOMCEN to be liable for the material costs of the Section 1. Submission to CIAC Jurisdiction. - An
.. 7 steel bars. Under GC-42, it is enough that the materials arbitration clause in a construction contract or a
were delivered to the contractor, although not used. FSI THE COURT'S RULING submission to arbitration of a construction dispute shall
Less said that the 744 metric tons of steel bars were ordered be deemed an agreement to submit an existing or
and paid for by it for the Citimall project as early as future controversy to CIAC jurisdiction,
Purchase cost of steel bars by Ramon November 1997. If LICOMCEN contends that these The jurisdiction of the CIAC notwithstanding the reference to a different
Quinquileria............................................ were procured for other projects FSI also had in arbitration institution or arbitral body in such
(500,000.00)
Legaspi City, it should have presented proof of this The CIAC was created through Executive Order No. contract or submission. When a contract contains a
TOTAL LIABILITY OF LICOMCEN
5,694,939.8 claim, but it failed to do so.[36] 1008 (E.O. 1008), in recognition of the need to establish clause for the submission of a future controversy to
TO FSI FOR MATERIAL COSTS AT
7 an arbitral machinery that would expeditiously settle arbitration, it is not necessary for the parties to enter
SITE..................
ESCA's January 6, 1998 letter simply suggested that only construction industry disputes. The prompt resolution into a submission agreement before the claimant may
50% of the steel bars be shipped to Legaspi City; it was of problems arising from or connected with the invoke the jurisdiction of CIAC.
Citing GC-42(2) of the GCC, LICOMCEN says it shall not a clear and specific directive. Even if it was, the construction industry was considered of necessary and
be liable to pay FSI "[t]he cost of materials or goods steel bars were ordered and paid for long before the vital for the fulfillment of national development goals, An arbitration agreement or a submission to arbitration
reasonably ordered for the Permanent or notice to suspend was given; by then, it was too late to as the construction industry provides employment to a shall be in writing, but it need not be signed by the
Temporary Works which have been delivered to the stop the delivery. FSI also claims that since it believed large segment of the national labor force and is a leading parties, as long as the intent is clear that the parties
Contractor but not yet used, and which delivery has in good faith that the Citimall project was simply contributor to the gross national product.[43] Section 4 agree to submit a present or future controversy arising
been certified by the Engineer."[31] None of these suspended, it expected work to resume soon after and of E.O. 1008 states: from a construction contract to arbitration.
requisites were allegedly complied with. It contends decided to proceed with the shipment.[37]
that FSI failed to establish that the steel bars delivered In HUTAMA-RSEA Joint Operations, Inc. v. Citra Metro
in Legaspi City, on January 14, 1998, were for the Contrary to LICOMCEN's arguments, GC-42 of the Sec. 4. Jurisdiction. The CIAC shall have original and Manila Tollways Corporation,[47] the Court declared that
Citimall project. In fact, the steel bars were delivered GCC does not require delivery of the materials at the site exclusive jurisdiction over disputes arising from, or "the bare fact that the parties x x x incorporated an
not at the site of the Citimall project, but at FSI's of the Citimall project; it only requires delivery to the connected with, contracts entered into by parties arbitration clause in [their contract] is sufficient to vest
batching plant called Tuanzon compound, a few contractor, which is FSI. Moreover, the Tuanzon involved in construction in the Philippines, whether the CIAC with jurisdiction over any construction
hundred meters from the site. Even if delivery to compound, where the steel bars were actually delivered, the dispute arises before or after the completion of controversy or claim between the parties. The
Tuanzon was allowed, the delivery was done in violation is very close to the Citimall project site. FSI contends the contract, or after the abandonment or breach arbitration clause in the construction contract ipso
of ESCA's instruction to ship only 50% of the that it is a normal construction practice for contractors thereof. These disputes may involve government or facto vested the CIAC with jurisdiction."
materials. Advised as early as December 1997 to to set up a "staging site," to prepare the materials and private contracts. For the Board to acquire jurisdiction,
suspend the works, FSI proceeded with the delivery of equipment to be used, rather than stock them in the the parties to a dispute must agree to submit the same Under GC-61 and GC-05 of the GCC, read singly and
the steel bars in January 1998. LICOMCEN declared crowded job/project site. FSI also asserts that it was to voluntary arbitration. in relation with one another, the Court sees no intent to
that it should not be made to pay for costs that FSI useless to have the delivery certified by ESCA because limit resort to arbitration only to disputes relating to the
willingly incurred for itself.[32] by then the Citimall project had been suspended. It The jurisdiction of the CIAC may include but is not physical construction activities.
would be unfair to demand FSI to perform an act that limited to violation of specifications for materials and
Assuming that LICOMCEN is liable for the costs of the ESCA and LICOMCEN themselves had prevented workmanship; violation of the terms of agreement; First, consistent with the intent of the law, an arbitration
steel bars, it argues that its liability should be minimized from happening.[38] interpretation and/or application of contractual time clause pursuant to E.O. 1008 should be interpreted at
by the fact that FSI incurred no actual damage from the and delays; maintenance and defects; payment, default its widest signification. Under GC-61, the voluntary
purchase and delivery of the steel bars. During the The CA deleted the awards for equipment and labor of employer or contractor and changes in contract cost. arbitration clause covers any dispute of any kind, not only
arising of out the execution of the works but also in with, contracts entered into by parties involved in INCORPORATED to complete the work, the qualified bidder, if true, to be extremely
connection therewith. The payments, demand and disputed construction in the Philippines.[49] This jurisdiction LICOMCEN, INCORPORATED at any time, by irresponsible and highly unprofessional. It might
issues in this case - namely, work billings, material costs, cannot be altered by stipulations restricting the nature written notice to the Contractor, may discontinue even be branded as fraudulent x x x [since] the invited
equipment and labor standby costs, unrealized profits - of construction disputes, appointing another arbitral the work and terminate the Contract in whole or in bidders [were required] to pay P2,000.00 each for a set
all arose because of the construction activities and/or body, or making that body's decision final and binding. part. Upon the issuance of such notice of termination, of the new plans, which amount was non-
are connected or related to these activities. In other the Contractor shall discontinue to work in such refundable. The presence of x x x deceit makes the
words, they are there because of the construction The jurisdiction of the CIAC to resolve the dispute manner, sequence and at such time as the LICOMCEN, whole story repugnant and unacceptable.[55]
activities. Attorney's fees and interests payment, on the between LICOMCEN and FSI is, therefore, affirmed. INCORPORATED/Engineer may direct, continuing
other hand, are costs directly incidental to the and doing after said notice only such work and only LICOMCEN's omissions and the imprudent
dispute. Hence, the scope of the arbitration clause, as The validity of the indefinite until such time or times as the LICOMCEN, rebidding of the Citimall project are telling
worded, covers all the disputed items. suspension of the works on the INCORPORATED/Engineer may direct.[51] indications of LICOMCEN's intent to ease out FSI
Citimall project and terminate their contract. As with GC-31, GC-
Second and more importantly, in insisting that contractual Under these stipulations, we consider LICOMCEN's 42(2) grants LICOMCEN ample discretion to
money claims can be resolved only through court Before the Court rules on each of FSI's contractual initial suspension of the works valid. GC-38 determine what reasons render it against its interest to
action, LICOMCEN deliberately ignores one of the monetary claims, we deem it important to discuss the authorizes the suspension of the works for factors or complete the work - in this case, the pendency of the
exceptions to the general rule stated in GC-05: validity of LICOMCEN's indefinite suspension of the causes which ESCA deems necessary in the interests of other cases and the revised designs for the Citimall
works on the Citimall project. We quote below two the works and LICOMCEN. The factors or causes of project. Given this authority, the Court fails to the see
contractual stipulations relevant to this issue: suspension may pertain to a change or revision of the logic why LICOMCEN had to resort to an
GC-05. JURISDICTION works, as cited in the December 16, 1997 and January 6, "indefinite suspension" of the works, instead of
1998 letters of ESCA, or to the pendency of a case outrightly terminating the contract in exercise of its
Any question between the contracting parties that may GC-38. SUSPENSION OF WORKS before the Ombudsman (OMB-ADM-1-97-0622), as rights under GC-42(2).
arise out of or in connection with the Contract, or cited in LICOMCEN's January 15, 1998 letter and
breach thereof, shall be litigated in the courts of Legaspi The Engineer [ESCA] through the LICOMCEN, ESCA's January 19, 1998 and February 17, 1998 We now proceed to discuss the effects of these findings
City except where otherwise specifically stated or INCORPORATED shall have the authority to letters. It was not necessary for ESCA/LICOMCEN to with regard to FSI's monetary claims against
except when such question is submitted for suspend the Works wholly or partly by written order wait for a restraining or injunctive order to be issued in LICOMCEN.
settlement thru arbitration as provided herein. for such period as may be deemed necessary, due any of the cases filed against LICOMCEN before it can
to unfavorable weather or other conditions considered suspend the works. The language of GC-38 gives The claim for material costs at site
The second exception clause authorizes the submission unfavorable for the prosecution of the Works, or for ESCA/LICOMCEN sufficient discretion to determine
to arbitration of any dispute between LICOMCEM and failure on the part of the Contractor to correct work whether the existence of a particular situation or GC-42 of the GCC states:
FSI, even if the dispute does not directly involve the conditions which are unsafe for workers or the general condition necessitates the suspension of the works and
execution of physical construction works. This was public, or failure or refusal to carry out valid orders, or serves the interests of LICOMCEN.
precisely the avenue taken by FSI when it filed its due to change of plans to suit field conditions as found GC-42 PAYMENT FOR TERMINATED
petition for arbitration with the CIAC. necessary during construction, or to other factors or Although we consider the initial suspension of the CONTRACT
causes which, in the opinion of the Engineer, is works as valid, we find that LICOMCEN
If the CIAC's jurisdiction can neither be enlarged nor necessary in the interest of the Works and to the wrongfully prolonged the suspension of the works If the Contract is terminated as aforesaid, the
diminished by the parties, it also cannot be subjected to LICOMCEN, INCORPORATED. The Contractor (or "indefinite suspension" as LICOMCEN calls Contractor will be paid for all items of work executed,
a condition precedent. GC-61 requires a party [FSI] shall immediately comply with such order to it). GC-38 requires ESCA/LICOMCEN to "issue an satisfactorily completed and accepted by the
disagreeing with LICOMCEN's decision to "officially suspend the work wholly or partly directed. order lifting the suspension of work when conditions to LICOMCEN, INCORPORATED up to the date of
give notice to contest such decision through resume work shall have become favorable or the termination, at the rates and prices provided for in the
arbitration" within 30 days from receipt of the In case of total suspension or suspension of activities reasons for the suspension have been duly Contract and in addition:
decision. However, FSI's April 15, 1998 letter is not the along the critical path of the approved PERT/CPM corrected." The Ombudsman case (OMB-ADM-1-97-
notice contemplated by GC-61; it never mentioned network and the cause of which is not due to any fault 0622), which ESCA and LICOMCEN cited in their
FSI's plan to submit the dispute to arbitration and of the Contractor, the elapsed time between the letters to FSI as a ground for the suspension, was 1. The cost of partially accomplished items
instead requested LICOMCEN to reevaluate its effective order for suspending work and the order dismissed as early as October 12, 1998, but neither of additional or extra work agreed upon by
claims. Notwithstanding FSI's failure to make a proper to resume work shall be allowed the Contractor by ESCA nor LICOMCEN informed FSI of this the LICOMCEN, INCORPORATED and
and timely notice, LICOMCEN's decision (embodied in adjusting the time allowed for his execution of the development. The pendency of the other cases[52] may the Contractor.
its March 24, 1998 letter) cannot become "final and Contract Works. justify the continued suspension of the works, but 2. The cost of materials or goods
binding" so as to preclude resort to the CIAC LICOMCEN never bothered to inform FSI of the reasonably ordered for the Permanent
arbitration. To reiterate, all that is required for the CIAC The Engineer through LICOMCEN, existence of these cases until the arbitration proceedings or Temporary Works which have been
to acquire jurisdiction is for the parties to agree to INCORPORATED shall issue the order lifting the commenced. By May 28, 2002, the City Government of delivered to the Contractor but not yet
submit their dispute to voluntary arbitration: suspension of work when conditions to resume work Legaspi sent LICOMCEN a notice instructing it to used and which delivery has been
shall have become favorable or the reasons for the proceed with the Citimall project;[53] again, certified by the Engineer.
suspension have been duly corrected.[50] LICOMCEN failed to relay this information to 3. The reasonable cost of demobilization
[T]he mere existence of an arbitration clause in the FSI. Instead, LICOMCEN conducted a rebidding of
construction contract is considered by law as an GC-41 LICOMCEN, INCORPORATED's RIGHT the Citimall project based on the new
agreement by the parties to submit existing or TO SUSPEND WORK OR TERMINATE THE design.[54] LICOMCEN's claim that the rebidding was
future controversies between them to CIAC CONTRACT conducted merely to get cost estimates for the new For any payment due the Contractor under the above
jurisdiction, without any qualification or condition design goes against the established practice in the conditions, the LICOMCEN, INCORPORATED,
precedent. To affirm a condition precedent in the xxxx construction industry. We find the CIAC's discussion however, shall deduct any outstanding balance due from
construction contract, which would effectively suspend on this matter relevant: the Contractor for advances in respect to mobilization
the jurisdiction of the CIAC until compliance therewith, 2. For Convenience of LICOMCEN, and materials, and any other sum the LICOMCEN,
would be in conflict with the recognized intention of INCORPORATED INCORPORATED is entitled to be credited.[56]
the law and rules to automatically vest CIAC with But what is more appalling and disgusting is the
jurisdiction over a dispute should the construction If any time before completion of work under the allegation x x x that the x x x invitation to bid was For LICOMCEN to be liable for the cost of materials
contract contain an arbitration clause.[48] Contract it shall be found by the LICOMCEN, issued x x x solely to gather cost estimates on the or goods, item two of GC-42 requires that
INCORPORATED that reasons beyond the redesigned [Citimall project] x x x. This Arbitral
The CIAC is given the original and exclusive control of the parties render it impossible or against Tribunal finds said act of asking for bids, without any
jurisdiction over disputes arising from, or connected the interest of the LICOMCEN, intention of awarding the project to the lowest and
a. the materials or goods were reasonably evidence, We deny the claim for equipment and the CIAC, the costs of arbitration shall be equally
ordered for the Permanent or Temporary Records, however, disclose that these claims are not labor standby costs.[65] divided between them, subject to the CIAC's
Works; entirely accurate. The memorandum of agreement and determination of which of the parties shall eventually
b. the materials or goods were delivered to sale covering the steel bars specifically stated that these The claim for unrealized profit shoulder the amount.[70] The CIAC eventually ruled
the Contractor but not yet used; and would be withdrawn from the Cagayan de Oro depot, that since LICOMCEN was the party at fault, it should
c. the delivery was certified by the Engineer. not Manila[61]; indeed, the bill of lading stated that the FSI contends that it is not barred from recovering bear the costs. As the CA did, we agree with this
steel bars were loaded in Cagayan de Oro on January 11, unrealized profit under GC-41(2), which states: finding. Ultimately, it was LICOMCEN's imprudent
1998, and arrived in Legaspi City within three days, on declaration of indefinitely suspending the works that
January 14, 1998.[62] The loading and delivery of the caused the dispute between it and FSI. LICOMCEN
Both the CIAC and the CA agreed that these requisites steel bar thus happened after FSI received ESCA's GC-41. LICOMCEN, INCORPORATED's RIGHT should bear the costs of arbitration.
were met by FSI to make LICOMCEN liable for the December 16, 1997 and January 6, 1998 letters - days TO SUSPEND WORK OR TERMINATE THE
cost of the steel bars ordered for the Citimall project; after the instruction to suspend the works. Also, the CONTRACT WHEREFORE, premises considered, the petition for
the two tribunals differed only to the extent of same stipulation that authorizes LICOMCEN to review on certiorari of LICOMCEN
LICOMCEN's liability because the CA opined that it suspend the works allows the extension of the period to INCORPORATED, docketed as G.R. No. 167022, and
should be limited only to 50% of the cost of the steel complete the works. The relevant portion of xxxx the petition for review on certiorari of FOUNDATION
bars. A review of the records compels us to uphold the GC-38 states: SPECIALISTS, INC., docketed as G.R. No. 169678, are
CA's finding. 2. For Convenience of the LICOMCEN, DENIED. The November 23, 2004 Decision of the
INCORPORATED Court of Appeals in CA-G.R. SP No. 78218 is
Prior to the delivery of the steel bars, ESCA informed In case of total suspension x x x and the cause of which MODIFIED to include the award of nominal
FSI of the suspension of the works; ESCA's January 6, is not due to any fault of the Contractor [FSI], the x x x. The Contractor [FSI] shall not claim damages in favor of FOUNDATION SPECIALISTS,
1998 letter reads: elapsed time between the effective order for damages for such discontinuance or termination of INC. Thus, LICOMCEN INCORPORATED is
suspending work and the order to resume work the Contract, but the Contractor shall receive ordered to pay FOUNDATION SPECIALISTS, INC.
shall be allowed the Contractor by adjusting the compensation for reasonable expenses incurred in good the following amounts:
As per our information to you on December 16, time allowed for his execution of the Contract faith for the performance of the Contract and for
1997, a major revision in the design of the Legaspi Works.[63] reasonable expenses associated with termination of the
Citimall necessitated a change in the bored piles Contract. The LICOMCEN, INCORPORATED will a. P1,264,404.12 for unpaid balance on
requirement of the project. The change involved a The above stipulation, coupled with the short determine the reasonableness of such expenses. The FOUNDATION SPECIALISTS, INC.
substantial reduction in the number and length of period it took to ship the steel bars from Contractor [FSI] shall have no claim for anticipated billings;
piles. Cagayan de Oro to Legaspi City, thus negates both profits on the work thus terminated, nor any other b. P5,694,939.87 for material costs at site;
FSI's claim, except for the work actually performed at the and
We expected that you would have suspended the time of complete discontinuance, including any c. P100,000.00 for nominal damages.
deliveries of the steel bars until the new design has argument and the CIAC's ruling[64] that there was no variations authorized by the LICOMCEN,
been approved. necessity to stop the shipment so as to meet the 90-day INCORPORATED/Engineer to be done.
deadline. These circumstances prove that FSI acted
According to you[,] the steel bars had already been imprudently in proceeding with the delivery, contrary to The prohibition, FSI posits, applies only where the LICOMCEN INCORPORATED is also ordered to pay
paid and loaded and out of Manila on said date. LICOMCEN's instructions. The CA was correct in contract was properly and lawfully terminated, which the costs of arbitration. No costs.
holding LICOMCEN liable for only 50% of the costs was not the case at bar. FSI also took pains in
In order to avoid double handling, storage, security of the steel bars delivered. differentiating its claim for "unrealized profit" from the SO ORDERED.
problems, we suggest that only 50% of the total prohibited claim for "anticipated profits"; supposedly,
requirement of steel bars be delivered at The claim for equipment and unrealized profit is "one that is built-in in the contract
jobsite. The balance should be returned to Manila labor standby costs price, while anticipated profit is not." We fail to see the
where storage and security is better. distinction, considering that the contract itself neither
The Court upholds the CA's ruling deleting the award defined nor differentiated the two terms. [A] contract FIRST DIVISION
In order for us to consider additional cost due for equipment and labor standby costs. We quote in must be interpreted from the language of the contract
to the shipping of the excess steel bars, we need to agreement pertinent portions of the CA decision: itself, according to its plain and ordinary meaning." [66] If
know the actual dates of purchase, payments and the terms of a contract are clear and leave no doubt G.R. Nos. 159561-62, October 03, 2012
loading of the steel bars. Obviously, we cannot consider upon the intention of the contracting parties, the literal
the additional cost if you have had the chance to delay The CIAC relied solely on the list of 37 pieces of meaning of the stipulations shall control.[67]
the shipping of the steel bars.[57] R.V. SANTOS COMPANY, INC., PETITIONER,
equipment respondent allegedly rented and maintained
VS. BELLE CORPORATION, RESPONDENT.
at the construction site during the suspension of the Nonetheless, on account of our earlier discussion of
From the above, it appears that FSI was informed of project with the prorated rentals incurred x x x. To the LICOMCEN's failure to observe the proper procedure
the necessity of suspending the works as early as DECISION
mind of this Court, these lists are not sufficient to in terminating the contract by declaring that it was
December 16, 1997. Pursuant to GC-38 of the GCC, establish the fact that indeed [FSI] incurred the merely indefinitely suspended, we deem that FSI is
FSI was expected to immediately comply with the order to said expenses. Reliance on said lists is purely entitled to the payment of nominal damages. Nominal LEONARDO-DE CASTRO, J.:
suspend the work.[58] Though ESCA's December 16, speculative x x x the list of equipments is a mere damages may be awarded to a plaintiff whose right has
1997 notice may not have been categorical in ordering index or catalog of the equipments, which may be been violated or invaded by the defendant, for the
the suspension of the works, FSI's reply letter of utilized at the construction site. It is not the best purpose of vindicating or recognizing that right, and not For disposition of the Court is a Petition for Review on
December 18, 1997 indicated that it actually complied evidence to prove that said equipment were in fact for indemnifying the plaintiff for any loss suffered by Certiorari, assailing the Court of Appeals’ Decision [1]
with the notice to suspend, as it said, "We hope for the rented and maintained at the construction site during him.[68] Its award is, thus, not for the purpose of dated March 7, 2003 and Resolution[2] dated August 20,
early resolution of the new foundation plan and the the suspension of the work. x x x [FSI] should have indemnification for a loss but for the recognition and 2003 in the consolidated cases docketed as CA-G.R. SP
resumption of work."[59] Despite the suspension, FSI presented the lease contracts or any similar vindication of a right. A violation of the plaintiff's right, Nos. 60217 and 60224. In its Decision dated March 7,
claimed that it could not stop the delivery of the steel documents such as receipts of payments x x x. even if only technical, is sufficient to support an award 2003, the Court of Appeals affirmed the July 28, 2000
bars (nor found the need to do so) because (a) the steel Likewise, the list of employees does not in anyway of nominal damages.[69] FSI is entitled to recover the Decision[3] in CIAC Case No. 45-99 of the Construction
bars were ordered as early as November 1997 and were prove that those employees in the list were indeed at amount of P100,000.00 as nominal damages. Industry Arbitration Commission (CIAC), which,
already loaded in Manila and expected to arrive in the construction site or were required to be on call among others, (a) ordered RV Santos Company, Inc.
Legaspi City by December 23, 1997, and (b) it expected should their services be needed and were being paid The liability for costs of arbitration (RVSCI) to refund the amount of P4,940,108.58 to
immediate resumption of work to meet the 90-day their salaries during the suspension of the Belle Corporation (Belle), and (b) denied Belle’s claim
deadline.[60] project. Thus, in the absence of sufficient Under the parties' Terms of Reference, executed before for liquidated damages and RVSCI’s counterclaims for
unpaid billings and attorney’s fees. In the assailed Additional Order Nos. 1 and 2 but the former allegedly #01) 1998) P 4,554,540.95
August 20, 2003 Resolution, the Court of Appeals did not approve the cost estimate for Additional Order 476,503.33
denied the parties’ respective motions for No. 3 which Belle estimated should only cost Total P
reconsideration of its March 7, 2003 Decision. P22,442.47. Nonetheless, RVSCI proceeded to ------------------------ 15,312,170.95
implement Additional Order Nos. 1 and 3 while Belle Less: Advance Payment P
The present controversy arose from a Request for itself accomplished Additional Order No. 2. P11,598,994.44 11,000,000.00
Adjudication[4] filed by Belle with the CIAC on Net Due to
November 3, 1999. According to the Complaint[5] On August 10, 1998, RVSCI submitted its Progress LESS: [RVSCI] P 4,312,170.9
attached to said Request, Belle and RVSCI entered into Billing[12] to Belle, claiming 53.3% accomplishment of 5[20]
a Construction Contract on July 14, 1997. As stipulated the project, including the work done for Additional
therein, RVSCI undertook to construct a detailed Order No. 1, as set forth above. RVSCI claimed that Actual Value of Work RVSCI prayed for the dismissal of the Complaint and
underground electrical network for Belle’s Tagaytay the value of the work accomplished under the August Accomplished 4,868,443.59 for the CIAC to order Belle to pay the following
Woodlands Condominium Project located in Tagaytay 10, 1998 Progress Billing was P7,159,216.63 on the Approved Change of Specifications and amounts: (a) P4,312,170.95 as balance of RVSCI’s
City[6] with a project cost that shall not be more than main project and P1,768,000.00 on the additional work Additional Work progress billing(s), (b) P500,000.00 as moral damages,
Twenty-Two Million Pesos (P22,000,000.00), inclusive order. After deducting 50% of the Progress Billing on Orders 1,790,44 and (c) P500,000.00 as attorney’s fees and costs of
of all taxes, government fees and the service fee under the main project, the total amount billed by RVSCI was 2.70 suit.[21]
the Contract.[7] Likewise under said contract, Belle P5,347,608.03. Purportedly relying on RVSCI’s
advanced to RVSCI fifty percent (50%) of the contract representations, Belle’s project engineer recommended ------------------------- At the preliminary conference, the parties agreed on the
price in the amount of Eleven Million Pesos approval of the Progress Billing. NET DUE TO Terms of Reference for the arbitration of their
(P11,000,000.00)[8] for which RVSCI issued to Belle an [BELLE] P respective claims. According to the Terms of
official receipt[9] dated August 8, 1997. Subsequently, however, Belle reputedly made its own 4,940,108.15[18] Reference, the admitted facts and the issues to be
assessment of the work accomplished by RVSCI and resolved by the arbitration panel were as follows:
Some time thereafter, RVSCI commenced work on the determined that it was only worth P4,676,724.64. Belle RVSCI allegedly refused to return the excess payment
project. Under Article VII(A) of the Construction supposedly relayed its findings to RVSCI.[13] despite repeated demands. Thus, relying on the
Contract, the project was supposed to be completed and arbitration clause in the Construction Contract, Belle II. ADMITTED FACTS
ready for operation within 180 calendar days from On September 30, 1998, while negotiations were brought the matter before the CIAC and prayed that
receipt by RVSCI of the notice to commence from allegedly on-going between the parties regarding the RVSCI be directed to (a) reimburse Belle the amount of The parties admit the following:
Belle, provided that all civil related works necessary for payment of the Progress Billing, Belle claimed that P4,940,108.15, and (b) pay Belle the amount of
the execution of the project works were in place. RVSCI unceremoniously abandoned the project without P2,200,000.00 as liquidated damages.[19] 1. Their respective identity/juridical existence
However, the project was allegedly not completed prior notice and forced Belle to take over the and circumstances.
within the stipulated time frame. construction work therein. Belle purportedly sent a By way of defense, RVSCI claimed that its August 10, 2. The genuineness and due execution of the
Memorandum[14] dated December 15, 1998 to RVSCI to 1998 Progress Billing was a result of a “bilateral Contract (attached as Annex A of the
On March 17, 1998, Belle’s Woodlands General convey its “extreme disappointment” over the latter’s assessment” by the representatives of both parties and Complaint) for the construction of a
Committee supposedly set April 21, 1998 as the target abandonment of the project. was, in fact, approved/recommended for payment by detailed underground electrical network
date for completion of the Log Home Units in Belle’s representatives. RVSCI complained that Belle for the Tagaytay Woodlands
Woodlands. In a Memorandum[10] dated April 14, 1998, On January 11, 1999, the parties’ representatives met segregated the project into two phases (Phase 1 and Condominium Project in Tagaytay City
Belle purportedly informed RVSCI of the target date and during that meeting RVSCI allegedly advised Belle Phase 2) with Phase 1 comprising the area already entered into by the parties on 14 July 1997
and urged the latter to complete the project on or that it will not return to the site until the outstanding worked on by RVSCI and Phase 2 comprising the for a contract price of P22,000,000.00.
before said deadline. Still the project was not balance due to it is paid.[15] “unworked” area. It was Belle which advised RVSCI in 3. Article IV, Section 4.2 of the Construction
completed on April 21, 1998. a meeting on January 11, 1999 that the former was Contract which provide (sic) that the
Meanwhile, on January 22, 1999, Belle made an suspending Phase 2 of the project due to economic “Contractor [RVSCI] guarantees and
Subsequently, in June 1998, Belle placed additional work additional payment for electrical works to RVSCI in the difficulties. RVSCI allegedly made several demands for warrants that the total project cost shall
orders with RVSCI, who in turn made the following amount of P476,503.30. This payment was evidenced payment of its Progress Billing but Belle ignored said not be more than P22,000,000.00,
cost estimates for the additional work: by an official receipt[16] issued by RVSCI. Belle likewise demands. Thus, in view of Belle’s suspension of the inclusive of all taxes and government fees
remitted the amount of P122,491.14 to the Bureau of work and the nonpayment of the progress billing, and the service fee under the Contract.”
Internal Revenue representing the withholding tax due RVSCI was purportedly forced to stop work on the 4. Sec. 6.2(a), Art. VI of the Construction
Additional Order No. from RVSCI. project, despite being fully prepared to comply with its Contract which provides that: “Owner
1 P3,854,400 obligations under the contract. RVSCI further asserted [Belle] shall advance to Contractor an
.00 In February 1999, Belle engaged the services of an that it was not notified of, nor made privy to, the audit amount equivalent to 50% of the Contract
Installation of 7 units of Load break assessor, R.A. Mojica and Partners (R.A. Mojica), to work conducted by R.A. Mojica and therefore RVSCI Price or the amount of P11,000,000.00, as
switch, 102 units of kw-hrs. meters determine the value of the work done by RVSCI. After was not bound by such audit. Insisting on the accuracy down payment for the construction, upon
and fabrication of 21 sets of Bus ducts it conducted an electrical works audit, R.A. Mojica of its Progress Billing, RVSCI interposed a counterclaim execution of the Contract, receipt of which
reported to Belle that the work accomplished by RVSCI against Belle for the payment of the amount of is hereby acknowledged by Contractor.
Additional Order No. on the main project only amounted to P4,868,443.59 P4,312,170.95, computed thus: Progress payments to be made by Owner
2 541,528. and not P7,159,216.05 as billed by RVSCI.[17] to Contractor, proportionate to the
54 percentage of accomplishment of the
Supply and installation of one (1) unit In Belle’s view, it had overpaid RVSCI, based on the Progress Project, shall be deducted from the
MDP-DTIA following computation: Billing P 7,159,216 balance of the Contract Price. The same
.05 proportion of the down payment shall also
Additional Order No. be deducted from billing progress
3 158,612 Downpayment Remaining MDPs for delivery payments.”
.00 P11,000,000.00 Under original contract (11 sets @ 5. The payment made by Claimant to
Various work orders issued to Withholding Tax P327,128.54) P 3, Respondent in the amount of
[RVSCI] -------------------- Payable 122,491 598,413.94 P11,000,000.00 as acknowledged to have
.14 Approved Change of been received under Official Receipt No.
P4,554,540.54[11] Additional Payment for electrical works Specifications and Additional 0706 issued by the latter on 8 August 1997
(Billing Work Order/s (dated August 10, 1998 (attached as Annex B of the Complaint).
Belle admittedly approved RVSCI’s cost estimates for and September 30,
6. The following proposed cost estimate of 2. Is Claimant entitled to its claim for and executory and the total amount found to be due approval of RVSCI’s Progress Billing, contrary to the
the Respondent on Claimant’s additional liquidated damages? If so, how much by remains unpaid.[26] rulings of both the CIAC and the Court of
work orders in June 1998: way of liquidated damages should be Appeals. Assuming without conceding that Article
AdditionalInstallation of 7 units of awarded to it? Both Belle and RVSCI filed petitions for review under XIII, Section 13.4 of the Contract applies in this
Order Load break switch, 102 units Rule 43 of the Rules of Court to assail the foregoing instance, RVSCI believes that the final determination of
No. 1 of kw-hrs. meters and 2.1 Was Respondent justified in CIAC Decision with the Court of Appeals, which were the value of the works should be made by (a) both
fabrication of 21 sets of Bus suspending its work? docketed as CA-G.R. SP No. 60217 and CA-G.R. SP parties or (b) an independent third party mutually
ducts. P3,854,400.00 No. 60224, respectively. Upon motion by the parties, commissioned by them.
AdditionalSupply and installation of 2.2 Is Respondent justified in declining to the cases were consolidated and after due proceedings,
Order one (1) unit MDP-DTIA return to work? the Court of Appeals issued a Decision dated March 7, As for the last ground, RVSCI asserts that the CIAC
No. 2 541,528.54 3. Is Respondent entitled to its counterclaim 2003, dismissing the petitions and affirming the CIAC and the Court of Appeals erred in denying RVSCI’s
AdditionalVarious work orders issued for attorney’s fees? If so, how much is Decision. The separate motions for reconsideration of claim for damages in view of Belle’s breach of the
Order to [RVSCI] Claimant liable to Respondent for such the parties were likewise denied by the Court of Appeals Contract by its unjustified refusal or failure to pay the
No. 3 158,612.00 claim?[22] in a Resolution dated August 20, 2003. Progress Billing.
--------------------
P4,554,540.54 RVSCI elevated the matter to this Court and questioned On the other hand, Belle claims that the Petition should
the Court of Appeals’ March 7, 2003 Decision and be dismissed for raising questions of fact, which are
The Terms of Reference further indicated the parties’ August 20, 2003 Resolution through the present improper in a petition under Rule 45 of the Rules of
7. Claimant approved Respondent’s agreement that the presentation of their testimonial petition for review on certiorari under Rule 45. The Court, without showing that this case fell under the
proposed estimates on Additional Orders evidence shall be by way of affidavits of grounds relied upon by RVSCI were: recognized exceptions under jurisprudence. On the
Nos. 1 and 2, but disputed the cost witnesses. Hearings were held on March 24 and 28, merits of the Petition, Belle argued that it had the right
estimate of Additional Order No. 3. 2000. Thereafter, the parties submitted their draft to determine the true value of work done and nothing
Thereafter, Respondent proceeded to Decisions to the arbitral tribunal. I. THE APPELLATE COURT GRAVELY in the Contract limited that right. According to Belle,
implement additional Orders Nos. 1 and 3. ERRED IN RULING THAT THE the CIAC and the Court of Appeals properly relied on
8. Progress Billing No. 1 (attached as Annex In a Decision dated July 28, 2000, the CIAC found that, SURVEYOR’S ELECTRICAL WORK Article VI, Section 6.2(c) and Article XIII, 13.4 of the
D of the Complaint) which Claimant under the Construction Contract[23] and industry AUDIT WAS COMPETENT AND Contract and on industry practice in upholding Belle’s
received on 10 August 1998. practice, Belle had the right to the true value of the MUST BE GIVEN WEIGHT. right for a re-evaluation of RVSCI’s actual work
9. On 11 January 1999, the parties’ work performed by RVSCI upon termination. Further, II. THE APPELLATE COURT GRAVELY accomplishment. Thus, the CIAC and the appellate
representatives met to discuss the reasons the CIAC ruled that according to the Uniform General ERRED IN RULING THAT BELLE court allegedly were correct in giving weight to the
for Respondent’s failure/refusal to return Conditions of Contract for Private Construction (CIAP MAY WITHDRAW ITS APPROVAL OF electrical audit report made by R.A. Mojica. Belle
to the Site. These representatives were Document 102), approval of a progress billing is THE PROGRESS BILLING further propounds that the lower tribunals correctly did
Fernando R. Santico, Edgardo F. Villarino provisional[24] and is subject to final review and approval PURSUANT TO ARTICLES VI(2)(C) not grant RVSCI any award for damages considering
& Rudy P. Aninipot, for the Claimant, and before acceptance of the completed work and prior to AND XIII(4) OF THE CONTRACT. that RVSCI did not prove such damages as it had, in
Renato V. Santos & Joey C. Caldeo, for final payment.[25] Hence, Belle was within its rights to III. THE APPELLATE COURT GRAVELY fact, been overpaid. As for RVSCI’s claim for the value
the Respondent. make a reevaluation of the work accomplishment of ERRED IN RULING THAT [RVSCI] IS of materials and equipment purportedly left at the site,
10. Claimant made additional payment to RVSCI. Finding that Engr. Raladin A. Mojica qualified NOT ENTITLED TO AN AWARD the same was not included in the Terms of Reference
Respondent for electrical works on 22 as an expert witness, the CIAC gave weight to the FOR DAMAGES.[27] and RVSCI was not allowed by the CIAC to present
January 1999 amounting to P476,503.30 as results of the re-survey done by R.A. Mojica and held evidence on the same. Thus, this matter cannot be
per Official Receipt No. 0717 issued by that Belle indeed made an overpayment to raised for the first time on appeal.
Respondent (attached as Annex G of the RVSCI. Since the date when RVSCI commenced work
Complaint).Existence of Respondent’s on the Project and the supposed completion date Anent the first ground, RVSCI argued that R.A. After a thorough review of the issues raised by the
letter to Claimant dated 4 May 1999 re: cannot be determined, the CIAC found no basis to Mojica’s electrical work audit that was unilaterally parties, the Court finds no merit in the Petition.
Underground Electrical Utilities (attached award liquidated damages in favor of Belle. The arbitral commissioned by Belle was not binding on the former
as Annex A of the Reply). tribunal likewise denied RVSCI’s counterclaims. Thus, since (a) it was not authorized by the Contract and was On the procedural issue:
the dispositive portion of the CIAC Decision reads: done without the consent or participation of RVSCI; (b)
xxxx assuming that the Contract allowed Belle to commission It must be stressed that in petitions for review under
such audit, it was incomplete as it failed to cover the Rule 45 only questions of law may be raised, unless the
WHEREFORE, award is hereby made as follows: entire work performed by RVSCI as shown by its petitioner shows that the case falls under the recognized
Progress Billing and Bill of Quantities, allegedly exceptions. In Makati Sports Club, Inc. v. Cheng,[28] we
IV. ISSUES TO BE DETERMINED 1. Claimant’s [Belle’s] claim for refund of P4,940,108.58, approved by Belle; and (c) the audit was tainted by explained, thus:
representing overpayment to the Respondent is hereby obvious partiality since R.A. Mojica was a regular
granted. Respondent is, therefore, ordered to pay this contractor of Belle and a competitor of RVSCI.
amount to Claimant with interest at the rate of 6% per At the outset, we note that this recourse is a petition for
1. Is Claimant entitled to its claims for annum from the date of this Award. With respect to the second ground, it is RVSCI’s review on certiorari under Rule 45 of the Rules of Court.
overpayment? If so, how much should be contention that Article VI, Section 6.2(c) of the Under Section 1 of the Rule, such a petition shall
returned to the Claimant? 2. Claimant’s claim for liquidated damages and Construction Contract merely differentiate acceptance raise only questions of law which must be distinctly
Respondent’s counterclaims for an alleged balance due by Belle of RVSCI’s work accomplishment from time to alleged in the appropriate pleading. In a case involving a
1.1How much was the work accomplished by and unpaid on progress billings and for attorney’s fees time from Belle’s final acceptance of work upon question of law, the resolution of the issue must rest
Respondent in the project? are denied. completion of the entire project. Also RVSCI claims solely on what the law provides for a given set of facts
1.2Whether or not Respondent has that Article XIII, Section 13.4 only allows Belle to drawn from the evidence presented. Stated differently,
manufactured/produced and/or installed 11 sets of 3. Arbitration fees and expenses shall be shared by the determine the true value of the works in cases of there should be nothing in dispute as to the state of
Main Distribution Panels? If so, is Claimant liable parties pro rata on the basis of the amount of their termination of the Contract upon occurrence of any of facts; the issue to be resolved is merely the correctness
and for how much should it be liable to pay claims and counterclaims. the events of default enumerated under Article XIII, of the conclusion drawn from the said facts. Once it is
Respondent for their cost/value? Section 13.1 and said provision has no application in clear that the issue invites a review of the probative
1.3Whether or not Respondent is entitled to its claim 4. The amount of P4,940,108.58 found in paragraph 1 instances of justified suspension of works due to Belle’s value of the evidence presented, the question posed is
for unpaid billings? of this Award to be due the Claimant plus interest at 6% breach of the Contract. In any event, it is RVSCI’s view one of fact. If the query requires a reevaluation of
per annum shall further earn interest at the rate of 12% that neither Article VI, Section 6.2(c) nor Article XIII, the credibility of witnesses, or the existence or
per annum from the time this decision becomes final Section 13.4 allows Belle to withdraw its previous relevance of surrounding circumstances and their
relation to each other, then the issue is necessarily likewise no provision prohibiting the same. Certainly, the suspicion that the same was bloated and
factual.[29] (Emphases supplied, citation omitted.) This rule, however, admits of certain exceptions. In RVSCI failed to point to any contractual stipulation inaccurate. Thus, Belle had a third party conduct an
Uniwide Sales Realty and Resources Corporation v. Titan-Ikeda preventing RVSCI to seek expert opinion regarding the audit of RVSCI’s actual work accomplishment. As the
In cases decided by the CIAC, the above rule finds even Construction and Development Corporation, we said: value of RVSCI’s accomplishment or the accuracy of CIAC noted, there was nothing to prevent RVSCI to
more stringent application. As we previously observed the Progress Billing, whether prior or subsequent to the secure the services of its own expert witness to contest
in one case: approval of such billing. the findings of R.A. Mojica and buttress the accuracy of
In David v. Construction Industry and Arbitration Commission, its Progress Billing with supporting documents other
we ruled that, as exceptions, factual findings of Second, the mere fact that the audit was unilateral, or than such billing but RVSCI did not.
Executive Order No. 1008, as amended, provides, in its construction arbitrators may be reviewed by this Court was not participated in by petitioner, did not render the
Section 19, as follows: when the petitioner proves affirmatively that: (1) the same objectionable. There is nothing in the Hence, we find no error on the part of the CIAC and
“Sec. 19. Finality of Awards. — The arbitral award shall award was procured by corruption, fraud or other Construction Contract which obligates Belle to inform the Court of Appeals in relying on the third party audit
be binding upon the parties. It shall be final and undue means; (2) there was evident partiality or RVSCI or to secure the latter’s participation should the report and giving it due weight in the resolution of the
inappealable except on questions of law which shall be corruption of the arbitrators or any of them; (3) the former decide to commission an audit of the work present case.
appealable to the Supreme Court.” arbitrators were guilty of misconduct in refusing to hear accomplished. On the contrary, in case of termination
Section 19 makes it crystal clear that questions of fact evidence pertinent and material to the controversy; (4) due to default of the contractor, Article XIII, Section Whether Belle’s approval of the Progress Billing is
cannot be raised in proceedings before the Supreme one or more of the arbitrators were disqualified to act as 13.4 of the Construction Contract explicitly allows Belle final and binding and may no longer be withdrawn
Court - which is not a trier of facts - in respect of an such under Section nine of Republic Act No. 876 and to unilaterally evaluate the value of the work and the
arbitral award rendered under the aegis of the CIAC. willfully refrained from disclosing such disqualifications only condition is that it be done in good faith. Even After careful consideration of the contentions of the
Consideration of the animating purpose of voluntary or of any other misbehavior by which the rights of any assuming arguendo we accept RVSCI’s contentions that it parties, we agree with the CIAC’s finding, as affirmed
arbitration in general, and arbitration under the aegis of party have been materially prejudiced; or (5) the justifiably suspended work and that Article XIII, by the Court of Appeals, that the owner’s approval of
the CIAC in particular, requires us to apply rigorously arbitrators exceeded their powers, or so imperfectly Section 13.4 merely covers instances of default and not progress billing is merely provisional. This much can be
the above principle embodied in Section 19 that the executed them, that a mutual, final and definite award situations of justified suspension of works, we see no gleaned from Article VI, Section 6.2(c) of the
Arbitral Tribunal’s findings of fact shall be final and upon the subject matter submitted to them was not reason why the procedure for cessation of work due to Construction Contract which states that “[t]he
[u]nappealable. made. default cannot be applied to other instances of cessation acceptance of work from time to time for the purpose
of work, particularly in the absence of a contractual of making progress payment shall not be considered as
xxxx Other recognized exceptions are as follows: (1) when provision governing termination or suspension of works final acceptance of the work under the
there is a very clear showing of grave abuse of in situations not involving a default. Contract.” There can be no other interpretation of the
Aware of the objective of voluntary arbitration in the discretion resulting in lack or loss of jurisdiction as said provision but that progress billings are but
labor field, in the construction industry, and in any when a party was deprived of a fair opportunity to Verily, the fact that the parties agreed to a unilateral preliminary estimates of the value of the periodic
other area for that matter, the Court will not assist one present its position before the Arbitral Tribunal or valuation of the work by the owner in the event of a accomplishments of the contractor. Otherwise, there
or the other or even both parties in any effort to subvert when an award is obtained through fraud or the termination of the contract due to default signifies that would be no need to include Article VI, Section 6.2(c)
or defeat that objective for their private purposes. The corruption of arbitrators, (2) when the findings of the the parties, including RVSCI, did not find anything in the Contract since final acceptance of the contractor’s
Court will not review the factual findings of an Court of Appeals are contrary to those of the CIAC, abhorrent in a one-sided valuation at the time of the work would come as a matter of course if progress
arbitral tribunal upon the artful allegation that such and (3) when a party is deprived of administrative due execution of the contract. If RVSCI believed that this billings were, as RVSCI contends, final and binding
body had “misapprehended the facts” and will not process.[31] (Citations omitted.) was unfair or that its participation should be required in upon the owner. On the contrary, progress billings and
pass upon issues which are, at bottom, issues of a review or audit of its work, then it should not have final acceptance of the work were clearly still subject to
fact, no matter how cleverly disguised they might In the case at bar, petitioner indeed raises factual acquiesced to such a provision in the first place and review by the owner.
be as “legal questions.” The parties here had recourse matters in the present controversy which this Court may instead insisted on a stipulation prohibiting a unilateral
to arbitration and chose the arbitrators themselves; they not look into under a petition for review on audit of its work. Moreover, we see no reason to disturb the CIAC ruling
must have had confidence in such arbitrators. The certiorari. We likewise find that this case is not among that the foregoing contractual provision is consistent
Court will not, therefore, permit the parties to relitigate the exceptions to this settled rule. Nevertheless, even if Third, bias on the part of a witness cannot be with industry practice, as can be deduced from Articles
before it the issues of facts previously presented and we were to excuse this procedural infirmity of the presumed. It is a basic rule that good faith is always 22.02, 22.04 and 22.09 of CIAP Document 102 which
argued before the Arbitral Tribunal, save only where a petition, we are still not inclined to reverse the lower presumed and bad faith must be proved.[32] In a pertinently state:
very clear showing is made that, in reaching its factual tribunals’ findings on the merits of the case. previous case, we have held that the witness’
conclusions, the Arbitral Tribunal committed an error employment relationship with, or financial dependence 22.02 REQUESTS FOR PAYMENT: The
so egregious and hurtful to one party as to constitute a On the substantive matters: on, the party presenting his testimony would not be Contractor may submit periodically but not
grave abuse of discretion resulting in lack or loss of sufficient reason to discredit said witness and label his more than once each month a Request for
jurisdiction. Prototypical examples would be factual Whether the third party audit report commissioned testimony as biased and unworthy of Payment for work done. The Contractor shall
conclusions of the Tribunal which resulted in by Belle is admissible and may be given weight credence.[33] Analogously, that Belle and R.A. Mojica furnish the Owner all reasonable facilities
deprivation of one or the other party of a fair had a long standing business relationship does not required for obtaining the necessary
opportunity to present its position before the Arbitral To recapitulate, petitioner assailed R.A. Mojica’s audit necessarily mean that the latter’s report was tainted with information relative to the progress and
Tribunal, and an award obtained through fraud or the report on the following grounds: (a) that there was no irregularity, especially in the absence of evidence that execution of the Work. x x x.
corruption of arbitrators. Any other, more relaxed, rule provision in the Construction Contract allowing Belle to the audit report was indeed inaccurate or erroneous. It xxxx
would result in setting at naught the basic objective of a unilaterally conduct an audit of petitioner’s work; (b) must be emphasized as well that RVSCI had ample 22.04 CONDITIONS RELATIVE TO
voluntary arbitration and would reduce arbitration to a assuming the Contract allows such an audit, it opportunity to cross-examine Engr. Mojica with respect PAYMENTS: The Owner shall estimate the
largely inutile institution.[30] (Emphasis supplied, nonetheless failed to include all the work done by to the particulars of his company’s audit report. value of work accomplished by the Contractor
citations omitted.) petitioner; and (c) it was tainted by bias and partiality using as basis the schedule stipulated in the
since R.A. Mojica was a regular, long time contractor of To be sure, RVSCI is not precluded from proffering Breakdown of Work and Corresponding Value.
In another case, we have also held that: Belle. evidence to rebut the findings of R.A. Such estimate of the Owner of the amount of
Mojica. However, RVSCI did not present or point to work performed shall be taken as the basis for
On this issue, we uphold the CIAC and the Court of documents, invoices, and receipts to show that the the compensation to be received by the
It is settled that findings of fact of quasi-judicial bodies, Appeals in their allowance of the third party audit amounts and quantities in the audit report were not Contractor. While such preliminary estimates of
which have acquired expertise because their jurisdiction report done by R.A. Mojica. correct, nor did RVSCI convincingly substantiate its amount and quantity shall not be required to be
is confined to specific matters, are generally accorded assertion that it had completed work in other areas of made by strict measurement or with exactness,
not only respect, but also finality, especially when First, while there was no provision in the Construction the project that was not included in said report. RVSCI they must be made as close as possible to the
affirmed by the Court of Appeals. In particular, factual Contract expressly authorizing Belle to secure the merely relied on its own Progress Billing as supposedly actual percentage of work accomplishment.
findings of construction arbitrators are final and services of a third party auditor to determine the value signed by Belle’s representatives. However, it is that xxxx
conclusive and not reviewable by this Court on appeal. of the work accomplished by petitioner RVSCI, there is Progress Billing which was later questioned by Belle on 22.09 ACCEPTANCE AND FINAL PAYMENT:
Whenever the Contractor notifies the Owner counterclaims for lack of merit. Manpower, Tools/Equipment, Consumables for the 8. Who between the parties shall bear the cost of
that the Work under the Contract has been Electrical Works-Power and Equipment Supply, Bus Arbitration?
completely performed by the Contractor, the WHEREFORE, the instant petition for review is Duct Installation" for the Phillip Morris Greenfield
Owner shall proceed to verify the work, shall DENIED. The Decision dated March 7, 2003 and the Project (hereafter Project) covered by Purchase Order The CIAC rendered the assailed decision after the
make the final estimates, certify to the Resolution dated August 20, 2003 of the Court of Nos. 4501200300-000274 and 4501200300-000275 presentation of the parties' evidence. [The dispositive
completion of the work, and accept the same. Appeals in CA-G.R. SP Nos. 60244 and 60217 are amounting to P15,724,000.00 and P9,276,000.00 portion of said decision reads as follows:
AFFIRMED. respectively, or a total amount of P25,000,000.00. The
From the above-quoted provisions, it is readily apparent parties also agreed that respondent will perform
that, whether in the case of progress billings or of turn- SO ORDERED. variation orders in the Project. In connection with the WHEREFORE, judgment is hereby rendered in favor
over of completed work, the owner has the right to Project, petitioner supplied manpower chargeable of the claimant and respondent is ordered to pay
verify the contractor’s actual work accomplishment against respondent. claimant its unpaid account in the sum of P3,728,960.54
prior to payment. plus legal interest of 6% reckoned from June 25, 2003
Respondent was not able to finish the entire works with up to the filing of the case on October 11, 2004 and
In all, we approve the CIAC’s pronouncement that petitioner due to financial difficulties. Petitioner paid 12% of P3,728,960.54 from the finality of the judgment
“[t]he owner is, therefore, not estopped [from respondent a total amount of P26,547,624.76. On June until fully paid and arbitration cost of P104,333.82
questioning] a prior evaluation of the percentage of SECOND DIVISION 25, 2005 [should read 2003], respondent, through its representing claimant's share of the arbitration cost
accomplishment of the contractor and to downgrade former counsel sent a letter to petitioner demanding for which respondent should reimburse.
such accomplishment after re-evaluation. It is the right the payment of its unpaid balance amounting to
of every owner to re-evaluate or re-measure the work of G.R. No. 172525, October 20, 2010 P5,275,184.17. Petitioner claimed material back SO ORDERED.]
its contractor during the progress of the work.”[34] charges in the amount of P4,063,633.43. On September
26, 2003, respondent only acknowledged P2,371,895.33 Petitioner accepts the ruling of the CIAC only in Issue
Whether Belle should be made SHINRYO (PHILIPPINES) COMPANY, INC., as material back charges. Thereafter, on October 16, No. 1 and Sub-Issue No. 1.1 and in Issue No. 2 in so
liable to RVSCI for damages PETITIONER, VS. RRN INCORPORATED,* 2003, respondent sent another letter to petitioner for far as the amount of P440,000.00 awarded as back
RESPONDENT. them to meet and settle their dispute. charges for the use of scaffoldings. x x x[3]
Anent the third issue, it is apropos to state here that the
rationale underlying the owner’s right to seek an DECISION On January 8, 2004, respondent sent another letter to
evaluation of the contractor’s work is the right to pay petitioner regarding the cost of equipment rental and On February 22, 2006, the CA promulgated the assailed
only the true value of the work as may be reasonably the use of scaffolding. Thereafter, on August 12, 2004, Decision affirming the decision of the CIAC. The CA
determined under the circumstances. PERALTA, J.: petitioner sent a letter to respondent denying any upheld the CIAC ruling that petitioner failed to adduce
unpaid account and the failure in their negotiations for sufficient proof that the parties had an agreement
This is consistent with the law against unjust amicable settlement. regarding charges for respondent's use of the
This resolves the Petition for Review on Certiorari under
enrichment under Article 22 of the Civil Code which manlift. As to the other charges for materials, the CA
Rule 45 of the Rules of Court, praying that the
states that “[e]very person who through an act of On September 3, 2004, respondent, through its new held that the evidence on record amply supports the
Decision[1] of the Court of Appeals (CA) dated February
performance by another, or any other means, acquires counsel, advised petitioner of their intention to submit CIAC findings. Petitioner moved for reconsideration of
22, 2006, affirming the Decision of the Construction
or comes into possession of something at the expense the matter to arbitration. Thereafter, their dispute was said ruling, but the same was denied per Resolution
Industry Arbitration Commission (CIAC), and the CA
of the latter without just or legal ground, shall return the submitted to arbitration. During the preliminary dated April 26, 2006.
Resolution[2] dated April 26, 2006, denying herein
same to him.” Expounding on this provision in a petitioner's motion for reconsideration, be reversed and conference, the parties agreed in their Terms of
recent case, we have held that “[t]he principle of unjust Reference to resolve eight issues, to wit: Hence, this petition where it is alleged that:
set aside.
enrichment essentially contemplates payment when
there is no duty to pay, and the person who receives the
The facts, as accurately narrated in the CA Decision, are I. THE HONORABLE COURT OF APPEALS
payment has no right to receive it.”[35] 1. What should be the basis in evaluating the variation
as follows. COMMITTED GRAVE REVERSIBLE ERROR
cost?
In the case at bar, we uphold the CIAC’s factual finding 1.1 How much is the variation cost? WHEN IT DENIED PETITIONER'S CLAIM FOR
that the value of the total work accomplished by RVSCI 2. Is the Respondent (petitioner in the instant case) MANLIFT EQUIPMENT RENTAL IN THE
Petitioner Shinryo (Philippines) Company, Inc.
on the main project was P4,868,443.59 while the cost of justified in charging claimant (herein respondent) the AMOUNT OF P511,000.00 DESPITE EVIDENCE
(hereinafter petitioner) is a domestic corporation
the additional work amounted to P1,768,000.00 plus equipment rental fee and for the use of the scaffoldings? ON RECORD THAT RESPONDENT RRN
organized under Philippine laws. Private respondent
P22,442.27, for a total of P6,658,885.86. On the other If so, how much should be charged to Claimant? ACTUALLY USED AND BENEFITED FROM THE
RRN Incorporated (hereinafter respondent) is likewise a
hand, Belle had made payments in the total amount of MANLIFT EQUIPMENT.
domestic corporation organized under Philippine laws.
P11,598,994.44.[36] It is thus undeniable that RVSCI 3. What should be the basis in evaluating the total cost
had received payments from Belle in excess of the value of materials supplied by Respondent to the Project II. IN RENDERING THE QUESTIONED
Respondent filed a claim for arbitration against
of its work accomplishment. In light of this which is chargeable to Claimant? DECISION AND QUESTIONED RESOLUTION,
petitioner before CIAC for recovery of unpaid account
overpayment, it seems specious for RVSCI to claim that THE HONORABLE COURT OF APPEALS HAS
which consists of unpaid portions of the sub-contract,
it has suffered damages from Belle’s refusal to pay its 3.1 How much is the total cost of materials supply DECIDED A QUESTION OF SUBSTANCE NOT
variations and unused materials in the total sum of
Progress Billing, which had been proven to be excessive chargeable to Claimant? IN ACCORD WITH LAW AND/OR WITH THE
P5,275,184.17 and legal interest in the amount of
and inaccurate. Bearing in mind the law and APPLICABLE DECISIONS OF THE HONORABLE
P442,014.73. Petitioner filed a counterclaim for
jurisprudence on unjust enrichment, we hold that 4. How much is the value of the remaining works left SUPREME COURT.
overpayment in the amount of P2,512,997.96.
RVSCI is indeed liable to return what it had received undone by the Claimant in the project?
beyond the actual value of the work it had done for III. THE COURT OF APPEALS COMMITTED A
The parties admitted several facts before the CIAC. It
Belle. 5. Is the Claimant's claim for inventory of excess GRAVE REVERSIBLE ERROR IN AFFIRMING
was shown that petitioner and respondent executed an
materials valid? If so, how much is the value thereof? THE CIAC AWARD FOR THE VALUE OF
Agreement and Conditions of Sub-contract (hereafter
On a related note, this Court cannot grant RVSCI’s INVENTORIED MATERIALS CONSIDERING
Agreement signed on June 11, 1996 and June 14, 1996,
claim for the value of materials and equipment allegedly 6. Is the Respondent entitled to its claim for an THAT:
respectively. Respondent signified its willingness to
left at the site. As observed by the CIAC, this particular accept and perform for petitioner in any of its projects, overpayment in the amount of P2,512,997.96?
claim was not included in the Terms of Reference and, a part or the whole of the works more particularly
hence, could not be litigated upon or proved during the 7. Is Claimant entitled to its claim for interest? If so, A. RESPONDENT RRN ADMITTED THE
described in Conditions of Sub-Contract and other Sub- VALIDITY OF THE DEDUCTIONS ON
CIAC proceedings. contract documents. how much?
ACCOUNT OF MATERIAL SUPPLY, WHICH
In conclusion, the CIAC rightly dismissed RVSCI’s INCLUDED THE INVENTORIED MATERIALS.
On June 11, 2002, the parties executed a "Supply of
their jurisdiction is confined to specific matters, are result or effect of failure to make remuneration of or for and Resources Corporation v. Titan-Ikeda Construction and
B. RESPONDENT RRN HAS NO BASIS TO generally accorded not only respect, but also property or benefits received under circumstances that Development Corporation,[11] that:
CLAIM BECAUSE ENGR. BONIFACIO finality, especially when affirmed by the Court of give rise to legal or equitable obligation to account for
ADMITTED THAT RESPONDENT RRN FAILED Appeals. In particular, factual findings of them; to be entitled to remuneration, one must confer
TO ESTABLISH WHETHER THE MATERIALS construction arbitrators are final and conclusive benefit by mistake, fraud, coercion, or request. Unjust x x x The Court will not review the factual findings of
CAME FROM RESPONDENT RRN OR FROM and not reviewable by this Court on appeal. enrichment is not itself a theory of reconvey. Rather, it an arbitral tribunal upon the artful allegation that such
PETITIONER AND THAT IT WAS PETITIONER is a prerequisite for the enforcement of the doctrine of body had "misapprehended facts" and will not pass
THAT ACTUALLY INSTALLED THE SAID This rule, however, admits of certain exceptions. In restitution. upon issues which are, at bottom, issues of fact, no
MATERIALS AS PART OF REMAINING WORKS Uniwide Sales Realty and Resources Corporation v. Titan-Ikeda matter how cleverly disguised they might be as "legal
THAT PETITIONER TOOK OVER FROM Construction and Development Corporation, we said: Article 22 of the New Civil Code reads: questions." The parties here had recourse to arbitration
RESPONDENT RRN. and chose the arbitrators themselves; they must have
had confidence in such arbitrators. The Court will not,
C. THE CLAIM FOR THE VALUE OF In David v. Construction Industry and Arbitration Commission, Every person who, through an act of performance by therefore, permit the parties to relitigate before it the
INVENTORIED MATERIALS IS A DOUBLE we ruled that, as exceptions, factual findings of another, or any other means, acquires or comes into issues of facts previously presented and argued before
CLAIM OR DOUBLE ENTRY BECAUSE IN THE construction arbitrators may be reviewed by this Court possession of something at the expense of the latter the Arbitral Tribunal, save only where a clear showing is
COMPUTATION OF THE FINAL ACCOUNT, when the petitioner proves affirmatively that: (1) the without just or legal ground, shall return the same to made that, in reaching its factual conclusions, the
RESPONDENT RRN WAS CREDITED THE FULL award was procured by corruption, fraud or other him. Arbitral Tribunal committed an error so egregious and
CONTRACT PRICE AND THE COST OF undue means; (2) there was evident partiality or hurtful to one party as to constitute a grave abuse of
VARIATIONS, WHICH INCLUDED THE corruption of the arbitrators or any of them; (3) the In order that accion in rem verso may prosper, the essential discretion resulting in lack or loss of jurisdiction.[12]
INVENTORIED MATERIALS. arbitrators were guilty of misconduct in refusing to hear elements must be present: (1) that the defendant has
evidence pertinent and material to the controversy; (4) been enriched, (2) that the plaintiff has suffered a loss, As discussed above, there is nothing in the records that
IV. IN RENDERING THE QUESTIONED one or more of the arbitrators were disqualified to act as (3) that the enrichment of the defendant is without just point to any grave abuse of discretion committed by the
DECISION AND QUESTIONED RESOLUTION, such under Section nine of Republic Act No. 876 and or legal ground, and (4) that the plaintiff has no other CIAC.
THE COURT OF APPEALS COMMITTED A willfully refrained from disclosing such disqualifications action based on contract, quasi-contract, crime or
GRAVE REVERSIBLE ERROR IN THAT IT or of any other misbehavior by which the rights of any quasi-delict. The awards for interests and arbitration costs are,
COMPLETELY DISREGARDED THE party have been materially prejudiced; or (5) the likewise, correct as they are in keeping with prevailing
PROVISION OF THE SUBCONTRACT, WHICH arbitrators exceeded their powers, or so imperfectly An accion in rem verso is considered merely an auxiliary jurisprudence.[13]
ALLOWED PAYMENT OF ACTUAL COST executed them, that a mutual, final and definite award action, available only when there is no other remedy on
INCURRED BY PETITIONER IN COMPLETING upon the subject matter submitted to them was not contract, quasi-contract, crime, and quasi-delict. If IN VIEW OF THE FOREGOING, the Petition is
THE REMAINING WORKS THAT PRIVATE made. there is an obtainable action under any other institution DENIED. The Decision of the Court of Appeals
RESPONDENT ADMITTEDLY FAILED TO of positive law, that action must be resorted to, and the dated February 22, 2006 and its Resolution dated April
COMPLETE. Other recognized exceptions are as follows: (1) when principle of accion in rem verso will not lie.[9] 26, 2006 are AFFIRMED.
there is a very clear showing of grave abuse of
V. THE COURT OF APPEALS COMMITTED A discretion resulting in lack or loss of jurisdiction as As found by both the CIAC and affirmed by the CA, SO ORDERED.
GRAVE REVERSIBLE ERROR WHEN IT when a party was deprived of a fair opportunity to petitioner failed to prove that respondent's free use of
COMPLETELY DISREGARDED THE EVIDENCE present its position before the Arbitral Tribunal or the manlift was without legal ground based on the
ON ACTUAL COST INCURRED BY PETITIONER when an award is obtained through fraud or the provisions of their contract. Thus, the third requisite,
IN COMPLETING THE REMAINING WORKS. corruption of arbitrators, (2) when the findings of the i.e., that the enrichment of respondent is without just or
Court of Appeals are contrary to those of the CIAC, legal ground, is missing. In addition, petitioner's claim
VI. THE COURT OF APPEALS COMMITTED and (3) when a party is deprived of administrative due is based on contract, hence, the fourth requisite − that
GRAVE REVERSIBLE ERROR WHEN IT process.[6] the plaintiff has no other action based on contract,
AFFIRMED THE CIAC AWARD FOR INTERESTS quasi-contract, crime or quasi-delict − is also SECOND DIVISION
AND ARBITRATION COSTS IN FAVOR OF A perusal of the records would reveal that none of the absent. Clearly, the principle of unjust enrichment is
RESPONDENT RRN.[4] aforementioned circumstances, which would justify not applicable in this case.
exemption of this case from the general rule, are present G.R. No. 179628, January 16, 2013
The petition is bereft of merit. here. Such being the case, the Court, not being a trier The other issues raised by petitioner all boil down to
of facts, is not duty-bound to examine, appraise and whether the CIAC or the CA erred in rejecting its
Despite petitioner's attempts to make it appear that it is analyze anew the evidence presented before the claims for costs of some materials. THE MANILA INSURANCE COMPANY, INC.,
advancing questions of law, it is quite clear that what arbitration body.[7] PETITIONER. VS. SPOUSES ROBERTO AND
petitioner seeks is for this Court to recalibrate the Again, these issues are purely factual and cannot be AIDA AMURAO, RESPONDENTS.
evidence it has presented before the CIAC. It insists Petitioner's reliance on the principle of unjust properly addressed in this petition for review on
that its evidence sufficiently proves that it is entitled to enrichment is likewise misplaced. The ruling of the certiorari. In Hanjin Heavy Industries and Construction Co., DECISION
payment for respondent's use of its manlift equipment, Court in University of the Philippines v. Philab Industries, Ltd. v. Dynamic Planners and Construction Corp.,[10] it was
and even absent proof of the supposed agreement on Inc.[8] is highly instructive, thus: emphasized that mathematical computations, the
propriety of arbitral awards, claims for "other costs" and DEL CASTILLO, J.:
the charges petitioner may impose on respondent for
the use of said equipment, respondent should be made "abandonment" are factual questions. Since the
to pay based on the principle of unjust Unjust enrichment claims do not lie simply because one discussions of the CIAC and the CA in their respective The jurisdiction of the Construction Industry
enrichment. Petitioner also questions the amounts party benefits from the efforts or obligations of others, Decisions show that its factual findings are supported Arbitration Commission (CIAC) is conferred by law.
awarded by the CIAC for inventoried materials, and but instead it must be shown that a party was unjustly by substantial evidence, there is no reason why this Section 4[1] of Executive Order (E.O.) No. I 008,
costs incurred by petitioner for completing the work left enriched in the sense that the term unjustly could mean Court should not accord finality to said findings. Verily, otherwise known as the Construction Industry
unfinished by respondent. illegally or unlawfully. to accede to petitioner's request for a recalibration of its Arbitration Law, "is broad enough to cover any dispute
evidence, which had been thoroughly studied by both arising from, or connected with construction contracts,
As reiterated by the Court in IBEX International, Inc. v. Moreover, to substantiate a claim for unjust enrichment, the CIAC and the CA would result in negating the whether these involve mere contractual money claims or
Government Service Insurance System,[5] to wit: the claimant must unequivocally prove that another objective of Executive Order No. 1008, which created execution of the works."[2]
party knowingly received something of value to which an arbitration body to ensure the prompt and efficient
he was not entitled and that the state of affairs are such settlement of disputes in the construction This Petition for Review on Certiorari[3] under Rule 45 of
It is settled that findings of fact of quasi-judicial that it would be unjust for the person to keep the industry. Thus, the Court held in Uniwide Sales Realty the Rules of Court assails the Decision[4] dated June 7,
bodies, which have acquired expertise because benefit. Unjust enrichment is a term used to depict
2007 and the Resolution[5] dated September 7, 2007 of
the Court of Appeals (CA) in CA-G.R. SP No. 96815. disregarded the fact that the CCA was not yet signed at Petitioner likewise imputes error on the part of the CA lack of cause of action and lack of jurisdiction.
the time petitioner issued the performance bond on in treating petitioner as a solidary debtor instead of a
Factual Antecedents February 29, 2000.[28] The CA explained that the solidary guarantor.[37] Petitioner argues that while a The respondent-spouses have cause of action
performance bond was intended to be coterminous with surety is bound solidarily with the obligor, this does not against the petitioner; the performance bond
On March 7, 2000, respondent-spouses Roberto and the construction of the building.[29] It pointed out that make the surety a solidary co-debtor.[38] A surety or is coterminous with the CCA
Aida Amurao entered into a Construction Contract “if the delivery of the original contract is guarantor is liable only if the debtor is himself liable. [39]
Agreement (CCA)[6] with Aegean Construction and contemporaneous with the delivery of the surety’s In this case, since respondent-spouses and Aegean Petitioner claims that respondent-spouses have no cause
Development Corporation (Aegean) for the obligation, each contract becomes completed at the agreed to submit any dispute for arbitration before the of action against it because at the time it issued the
construction of a six-storey commercial building in same time, and the consideration which supports the CIAC, it is imperative that the dispute between performance bond, the CCA was not yet signed by
Tomas Morato corner E. Rodriguez Avenue, Quezon principal contract likewise supports the subsidiary respondent- spouses and Aegean must first be referred respondent-spouses and Aegean.
City.[7] To guarantee its full and faithful compliance with one.”[30] The CA likewise said that, although the to arbitration in order to establish the liability of
the terms and conditions of the CCA, Aegean posted contract of surety is only an accessory to the principal Aegean.[40] In other words, unless the liability of Aegean We do not agree.
performance bonds secured by petitioner The Manila contract, the surety’s liability is direct, primary and is determined, the filing of the instant case is
Insurance Company, Inc.[8] (petitioner) and Intra Strata absolute.[31] Thus: premature.[41] A careful reading of the Performance Bond reveals that
Assurance Corporation (Intra Strata).[9] the “bond is coterminous with the final acceptance of
Finally, petitioner puts in issue the fact that the the project.”[53] Thus, the fact that it was issued prior to
On November 15, 2001, due to the failure of Aegean to WHEREFORE, we resolve to DISMISS the petition as performance bond was issued prior to the execution of the execution of the CCA does not affect its validity or
complete the project, respondent spouses filed with the we find that no grave abuse of discretion attended the the CCA.[42] Petitioner claims that since there was no effectivity.
Regional Trial Court (RTC) of Quezon City, Branch issuance of the order of the public respondent denying existing contract at the time the performance bond was
217, a Complaint,[10] docketed as Civil Case No. Q-01- the petitioner’s motion to dismiss. executed, respondent- spouses have no cause of action But while there is a cause of action against petitioner,
45573, against petitioner and Intra Strata to collect on against petitioner.[43] Thus, the complaint should be the complaint must still be dismissed for lack of
the performance bonds they issued in the amounts of IT IS SO ORDERED.[32] dismissed.[44] jurisdiction.
P2,760,000.00 and P4,440,000.00, respectively.[11]
Petitioner moved for reconsideration but the CA denied Respondent spouses’ Arguments The CIAC has jurisdiction over the case
Intra Strata, for its part, filed an Answer[12] and later, a the same in a Resolution[33] dated September 7, 2007.
Motion to Admit Third Party Complaint,[13] with Respondent-spouses, on the other hand, maintain that Section 4 of E.O. No. 1008 provides that:
attached Third Party Complaint[14] against Aegean, the CIAC has no jurisdiction over the case because
Ronald D. Nicdao, and Arnel A. Mariano. Issues there is no ambiguity in the provisions of the CCA. [45]
Besides, petitioner is not a party to the CCA.[46] Hence, SEC. 4. Jurisdiction. – The CIAC shall have original and
Petitioner, on the other hand, filed a Motion to Hence, this petition raising the following issues: it cannot invoke Article XVII of the CCA, which exclusive jurisdiction over disputes arising from, or
Dismiss[15] on the grounds that the Complaint states no provides for arbitration proceedings.[47] connected with, contracts entered into by parties
cause of action[16] and that the filing of the Complaint is involved in construction in the Philippines, whether the
premature due to the failure of respondent-spouses to Respondent-spouses also insist that petitioner as a dispute arises before or after the completion of the
implead the principal contractor, Aegean.[17] The RTC, A. surety is directly and equally bound with the principal. [48] contract, or after the abandonment or breach thereof.
however, denied the motion in an Order [18] dated May 8, The fact that the performance bond was issued prior to These disputes may involve government or private
2002. Thus, petitioner filed an Answer with THE HONORABLE [CA] ERRED WHEN IT HELD the execution of the CCA also does not affect the contracts. For the Board to acquire jurisdiction, the
Counterclaim and Cross-claim,[19] followed by a Third THAT IT IS ONLY WHEN THERE ARE latter’s validity because the performance bond is parties to a dispute must agree to submit the same to
Party Complaint[20] against Aegean and spouses Ronald DIFFERENCES IN THE INTERPRETATION OF coterminous with the construction of the building. [49] voluntary arbitration.
and Susana Nicdao. ARTICLE I OF THE CONSTRUCTION
AGREEMENT THAT THE PARTIES MAY The jurisdiction of the CIAC may include but is not
During the pre-trial, petitioner and Intra Strata RESORT TO ARBITRATION BY THE CIAC. Our Ruling limited to violation of specifications for materials and
discovered that the CCA entered into by respondent- workmanship, violation of the terms of agreement,
spouses and Aegean contained an arbitration The petition has merit. interpretation and/or application of contractual time
clause.[21] Hence, they filed separate Motions to B. and delays, maintenance and defects, payment, default
Dismiss[22] on the grounds of lack of cause of action and Nature of the liability of the surety of employer or contractor, and changes in contract cost.
lack of jurisdiction. THE HONORABLE [CA] ERRED IN TREATING
[PETITIONER] AS A SOLIDARY DEBTOR A contract of suretyship is defined as “an agreement Excluded from the coverage of the law are disputes
Ruling of the Regional Trial Court INSTEAD OF A SOLIDARY GUARANTOR. whereby a party, called the surety, guarantees the arising from employer-employee relationships which
performance by another party, called the principal or shall continue to be covered by the Labor Code of the
On May 5, 2006, the RTC denied both motions.[23] obligor, of an obligation or undertaking in favor of a Philippines.
C. third party, called the obligee. It includes official
Petitioner and Intra Strata separately moved for
reconsideration but their motions were denied by the recognizances, stipulations, bonds or undertakings Based on the foregoing, in order for the CIAC to
THE HONORABLE [CA] OVERLOOKED AND issued by any company by virtue of and under the acquire jurisdiction two requisites must concur: “first,
RTC in its subsequent Order[24] dated September 11,
FAILED TO CONSIDER THE FACT THAT provisions of Act No. 536, as amended by Act No. the dispute must be somehow connected to a
2006.
THERE WAS NO ACTUAL AND EXISTING 2206.”[50] We have consistently held that a surety’s construction contract; and second, the parties must
CONSTRUCTION AGREEMENT AT THE TIME liability is joint and several, limited to the amount of the have agreed to submit the dispute to arbitration
Aggrieved, petitioner elevated the case to the CA by
THE MANILA INSURANCE BOND NO. G (13) bond, and determined strictly by the terms of contract proceedings.”[54]
way of special civil action for certiorari.[25]
2082 WAS ISSUED ON FEBRUARY 29, 2000.[34] of suretyship in relation to the principal contract
Ruling of the Court of Appeals between the obligor and the obligee.[51] It bears In this case, both requisites are present.
Petitioner’s Arguments stressing, however, that although the contract of
On June 7, 2007, the CA rendered a Decision[26] suretyship is secondary to the principal contract, the The parties agreed to submit to arbitration proceedings
Petitioner contends that the CA erred in ruling that the surety’s liability to the obligee is nevertheless direct, “[a]ny dispute arising in the course of the execution and
dismissing the petition. The CA ruled that the presence
parties may resort to arbitration only when there is primary, and absolute.[52] performance of [the CCA] by reason of difference in
of an arbitration clause in the CCA does not merit a
difference in the interpretation of the contract interpretation of the Contract Documents x x x which
dismissal of the case because under the CCA, it is only
documents stated in Article I of the CCA.[35] Petitioner In this case, respondent-spouses (obligee) filed with the [the parties] are unable to resolve amicably between
when there are differences in the interpretation of
insists that under Section 4 of E.O. No. 1008, it is the RTC a Complaint against petitioner (surety) to collect themselves.”[55] Article XVII of the CCA reads:
Article I of the construction agreement that the parties
CIAC that has original and exclusive jurisdiction over on the performance bond it issued. Petitioner, however,
can resort to arbitration.[27] The CA also found no grave
construction disputes, such as the instant case.[36] seeks the dismissal of the Complaint on the grounds of
abuse of discretion on the part of the RTC when it
ARTICLE XVII – ARBITRATION CA-G.R. SP No. 96815 are hereby ANNULLED and work areas. Resultantly, the contract period of 450 days the rate of 12% per annum shall be paid on the total of
SET ASIDE. The Presiding Judge of the Regional Trial was extended to 693 days. PEA also failed to turn over these 3 awards amounting to P27,930,018.11 until full
17.1 Any dispute arising in the course of the execution Court of Quezon City, Branch 217 ts DIRECTED to the entire 105-hectare work area due to the presence of payment of the awarded amount shall have been made,
and performance of this Agreement by reason of dismiss Civil Case No. Q-01-45573 for lack of squatters. Thus, on March 15, 1999, the PEA Project "this interim period being deemed to be at that time already a
difference in interpretation of the Contract Documents jurisdiction. Management Office (PEA-PMO) issued Change Order forbearance of credit" (Eastern Shipping Lines, Inc. v. Court of
set forth in Article I which the OWNER and the No. 2-LC,[6] excluding from the contract the 45-square- Appeals, et al., 243 SCRA 78 [1994]; Keng Hua Paper
CONTRACTOR are unable to resolve amicably SO ORDERED. meter portion of the park occupied by squatters. Products Co., Inc. v. Court of Appeals, 286 SCRA 257
between themselves shall be submitted by either party [1998]; Crismina Garments, Inc. v. Court of Appeals, G.R.
to a board of arbitrators composed of Three (3) In view of the delay in the delivery of work area, EDC No. 128721, March 9, 1999).
members chosen as follows: One (1) member shall be claimed additional cost from the PEA-PMO amounting
chosen by the CONTRACTOR AND One (1) member to P181,338,056.30. Specifically, Uy alleged that he SO ORDERED.[11]
shall be chosen by the OWNER. The said Two (2) incurred additional rental costs for the equipment, Uy received the CIAC decision on June 7, 2000. On
members, in turn, shall select a third member acceptable THIRD DIVISION which were kept on standby, and labor costs for the idle June 16, 2000, Uy filed a motion for correction of
to both of them. The decision of the Board of manpower. He added that the delay by PEA caused the computation,[12] followed by an amended motion for
Arbitrators shall be rendered within Ten (10) days from topsoil at the original supplier to be depleted; thus, he correction of computation,[13] on July 21, 2000. The
the first meeting of the board, which decision when G.R. NOS. 147925-26, June 08, 2009 was compelled to obtain the topsoil from a farther CIAC, however, failed to resolve Uy's motion and
reached through the affirmative vote of at least Two (2) source, thereby incurring extra costs. He also claims that amended motion within the 30-day period as provided
members of the board shall be final and binding upon he had to mobilize water trucks for the plants and trees in its rules, and Uy considered it as denial of the motion.
the OWNER and CONTRACTOR. ELPIDIO S. UY, DOING BUSINESS UNDER which had already been delivered to the site.
THE NAME AND STYLE EDISON Furthermore, it became necessary to construct a nursery Hence, on July 24, 2000, Uy filed a petition for review[14]
17.2 Matters not otherwise provided for in this Contract DEVELOPMENT & CONSTRUCTION, shade to protect and preserve the young plants and trees with the CA, docketed as CA-G.R. SP No. 59849. Uy's
or by Special Agreement of the parties shall be PETITIONER, VS. PUBLIC ESTATES prior to actual transplanting to the landscaped area. The petition was consolidated with CA-G.R. SP No. 59308,
governed by the provisions of the Arbitration Law, AUTHORITY AND THE HONORABLE PEA-PMO evaluated the EDC's claim and arrived at a the earlier petition filed by PEA, assailing the same
Executive Order No. 1008.[56] COURT OF APPEALS, RESPONDENTS. lesser amount of P146,484,910.[7] The evaluation of CIAC decision.
PEA-PMO was then referred to the Heritage Park
In William Golangco Construction Corporation v. Ray Burton DECISION Executive Committee (ExCom) for approval. On August 1, 2000, the CIAC issued an Order[15]
Development Corporation,[57] we declared that monetary denying Uy's motion for correction of computation.
claims under a construction contract are disputes arising NACHURA, J.: On November 12, 1999, the Performance Audit
from “differences in interpretation of the contract” Committee (PAC) reviewed the progress report On September 25, 2000, the CA rendered the now
because “the matter of ascertaining the duties and submitted by the works engineer and noted that the assailed Joint Decision dismissing both petitions on
obligations of the parties under their contract all involve Petitioner Elpidio S. Uy (Uy) appeals by certiorari the EDC's landscaping works were behind schedule by both technical and substantive grounds. PEA's petition
interpretation of the provisions of the contract.”[58] Joint Decision[1] dated September 25, 2000 and the Joint twenty percent (20%). The PAC considered this delay was dismissed because the verification thereof was
Following our reasoning in that case, we find that the Resolution[2] dated April 25, 2001 of the Court of unreasonable and intolerable, and immediately defective. Uy's petition, on the other hand, was
issue of whether respondent-spouses are entitled to Appeals (CA) in the consolidated cases CA-G.R. SP recommended to BCDA the termination of the dismissed upon a finding that it was belatedly filed.
collect on the performance bond issued by petitioner is Nos. 59308 and 59849. landscaping contract.[8] The BCDA adopted PAC's Further, the CA found no sufficient basis to warrant the
a “dispute arising in the course of the execution and recommendation and demanded from PEA the reversal of the CIAC ruling, which it held is based on
performance of [the CCA] by reason of difference in Respondent Public Estates Authority (PEA) was termination of the contract with EDC. In compliance, clear provisions of the contract, the evidence on record
the interpretation of the contract documents.” designated as project manager by the Bases Conversion PEA terminated the agreement on November 29, 1999. and relevant law and jurisprudence.
Development Authority (BCDA), primarily tasked to
The fact that petitioner is not a party to the CCA cannot develop its 105-hectare demilitarized lot in Fort PEA fully paid all the progress billings up to August 26, The CA disposed thus:
remove the dispute from the jurisdiction of the CIAC Bonifacio, Taguig City into a first-class memorial park 1999, but it did not heed EDC's additional claims. WHEREFORE, premises considered, the petitions in
because the issue of whether respondent- spouses are to be known as Heritage Park. PEA then engaged the Consequently, Uy filed a Complaint[9] with the CA-G.R. SP No. 59308, entitled "Public Estates
entitled to collect on the performance bond, as we have services of Makati Development Corporation (MDC) to Construction Industry Arbitration Commission (CIAC), Authority v. Elpidio S. Uy, doing business under
said, is a dispute arising from or connected to the CCA. undertake the horizontal works on the project; and Uy, docketed as CIAC Case No. 02-2000. the name and style of Edison [D]evelopment &
doing business under the name and style Edison Construction," and CA-G.R. SP No. 59849, "Elpidio
In fact, in Prudential Guarantee and Assurance, Inc. v. Anscor Development and Construction (EDC), to do the On May 16, 2000, the CIAC rendered a Decision,[10] the S. Uy, doing business under the name and style of
Land, lnc.,[59] we rejected the argument that the landscaping. dispositive portion of which reads: Edison [D]evelopment & Construction v. Public
jurisdiction of CIAC is limited to the construction WHEREFORE, Judgment is hereby rendered in favor Estates Authority," are both hereby DENIED DUE
industry, and thus, cannot extend to surety contracts. In For a contract price of Three Hundred Fifty-Five of the [Petitioner] Contractor ELPIDIO S. UY and COURSE and accordingly DISMISSED, for lack of
that case, we declared that "[a]lthough not the Million Eighty Thousand One Hundred Forty-One and Award is hereby made on its monetary claims as merit.
construction contract itself, the performance bond is 15/100 Pesos (P355,080,141.15), PEA and EDC signed follows:
deemed as an associate of the main construction the Landscaping and Construction Agreement[3] on Consequently, the Award/Decision issued by the
contract that it cannot be separated or severed fi·om its November 20, 1996. EDC undertook to complete the Respondent PUBLIC ESTATES AUTHORITY is Construction Industry Arbitration Commission on May
principal. The Performance Bond is significantly and landscaping works in four hundred fifty (450) days directed to pay the [petitioner] the following amounts: 16, 2000 in CIAC Case No. 02-2000, entitled "Elpidio
substantially connected to the construction contract that commencing on the date of receipt of the notice to P 19,604,132.06 --- for the cost of idle time of S. Uy, doing business under the name and style of
there can be no doubt it is the CIAC, under Section 4 of proceed. equipment. Edison [D]evelopment & Construction v. Public
E.O. No. 1008, which has jurisdiction over any dispute 2,275,721.00 --- for the cost of idled manpower. Estates Authority," is hereby AFFIRMED in toto.
arising from or connected with it."[60] EDC received the notice to proceed on December 3, 6,050,165.05 --- for the construction of the nursery
1996;[4] and three (3) days after, or on December 6, shade net area. No pronouncement as to costs.
In view of the foregoing, we agree with the petitioner 1996,[5] it commenced the mobilization of the 605,016.50 --- for attorney's fees.
that jurisdiction over the instant case lies with the equipment and manpower needed for the project. PEA, Interest on the amount of P6,050,165.05 as cost for the SO ORDERED.[16]
CIAC, and not with the RTC. Thus, the Complaint filed however, could not deliver any work area to EDC construction of the nursery shade net area shall be paid PEA and Uy filed motions for reconsideration.
by respondent-spouses with the RTC must be because the horizontal works of MDC were still at the rate of 6% per annum from the date the Subsequently, PEA filed with the CA an Urgent Motion
dismissed. ongoing. EDC commenced the landscaping works only Complaint was filed on 12 January 2000. Interest on the for Issuance of a Temporary Restraining Order and/or
on January 7, 1997 when PEA finally made an initial total amount of P21,879,853.06 for the cost of idled Writ of Preliminary Injunction,[17] seeking to enjoin the
WHEREFORE, the petition is hereby GRANTED. delivery of a work area. manpower and equipment shall be paid at the same rate CIAC from proceeding with CIAC Case No. 03-2001,
The Decision dated June 7, 2007 and the Resolution of 6% per annum from the date this Decision is which Uy had subsequently filed. PEA alleged that the
dated September 7, 2007 of the Court of Appeals in PEA continuously incurred delay in the turnover of promulgated. After finality of this Decision, interest at case involved claims arising from the same Landscaping
and Construction Agreement, subject of the cases IT ENJOINED THE PROCEEDINGS IN CIAC failed to discern any admission of liability on the part of that PEA is admitting its liability. The evaluation
pending with the CA. CASE NO. 03-2001 IN ITS JOINT RESOLUTION PEA. contained in the above memorandum is merely a
DATED 25 APRIL 2000, WHICH CASE IS verification of the accuracy of EDC's claims. As a
On April 25, 2001, the CA issued the assailed Joint TOTALLY DIFFERENT FROM THE CASE A The PEA-PMO evaluation dated January 6, 2000,[23] matter of fact, the evaluation is still subject for review
Resolution, thus: QUO[20] where PEA allegedly admitted its liability, reads in full: by the project manager, whose decision on the matter
WHEREFORE, the present Motion/s for We will deal first with the procedural issue. MEMORANDUM requires the approval of the Heritage Park ExCom.
Reconsideration in CA-G.R. SP No. 59308 and CA- Second, Messrs. Ignacio and Urcia had no legal authority
G.R. SP No. 59849 are hereby both DENIED, for lack Appeals from judgment of the CIAC shall be taken to For : Mr. Jaime R. Millan to make admissions on behalf of PEA. Thus, even
of merit. the CA by filing a petition for review within fifteen (15) Project Manager assuming that the evaluation contained in the
days from the receipt of the notice of award, judgment, Heritage Park Project memorandum was in the nature of an admission, the
Accordingly, let an injunction issue permanently final order or resolution, or from the date of its last Subject: EDC's Various Claim same cannot bind PEA. Third, Uy filed his complaint
enjoining the Construction Industry Arbitration publication if publication is required by law for its Landscape Development Works with the CIAC because PEA did not act on EDC's
Commission from proceeding with CIAC CASE NO. effectivity, or of the denial of petitioner's motion for Revision shall be made on our evaluation dated 28 various claims. This supports our conclusion that PEA
03-2001, entitled ELPIDIO S. UY, doing business new trial or reconsideration duly filed in accordance December 1999 concerning various claims of contractor never admitted, but on the contrary denied, whatever
under the name and style of EDISON with the governing law of the court or agency a quo.[21] EDC-Landscape Development Works (Package IV), additional liabilities were claimed by Uy under the
DEVELOPMENT & particularly on the claim on Project Equipment on landscaping contract.
Admittedly, Uy received the CIAC decision on June 7, Standby (item a of the earlier evaluation).
CONSTRUCTION v. PUBLIC ESTATES 2000; that instead of filing a verified petition for review Neither do we find any admission of liability on the part
AUTHORITY and/or HONORABLE CARLOS P. with the CA, Uy filed a motion for correction of Reference to item 4 of the Terms and Conditions of of PEA during the proceedings before the CIAC. What
DOBLE. computation on June 16, 2000, pursuant to Section 9, 1998 ACEL Rate Equipment Guidebook, the CMO was admitted by PEA was that PMO evaluated the claim at
Article XV of the Rules of Procedure Governing inadvertently did not consider are the wages and salaries the lesser amount of P146,484,910 (Exh. "S").[24] The
SO ORDERED.[18] Construction Arbitration: of standby operator/driver corresponding to the admission of the evaluation made by PEA cannot
PEA and Uy then came to us with their respective Section 9. Motion for Reconsideration. - As a matter of equipment standby being claimed. translate to an admission of liability. There is simply no
petitions for review assailing the CA ruling. PEA's policy, no motion for reconsideration shall be allowed. basis for Uy to claim that PEA had admitted its liability.
petition was docketed as G.R. Nos. 147933-34, while Any of the parties may, however, file a motion for Thus, the corresponding gross amount to be
that of Uy was docketed as G.R. Nos. 147925-26. The correction within fifteen (15) days from receipt of the incorporated shall be P4,925,600.00 computed based on This issue disposed of, we now resolve Uy's claims on
petitions, however, were not consolidated. award upon any of the following grounds: the total man-months of each standby equipment being the basis of the evidence presented.
claimed.
On December 12, 2001, this Court resolved G.R. Nos. Uy claims P95,740,834.30 as the standby equipment
147933-34 in this wise: A. An evident miscalculation of figures, a cost. CIAC, however, did not agree and granted only
A tabulation of the claims is shown hereinbelow:
WHEREFORE, in view of the foregoing, the petition typographical or arithmetical error; P19,604,132.06 as the cost of standby equipment using
for review is DENIED. The Motion to Consolidate this B. An evident mistake in the description of its so-called equitable method:
any party, person, date, amount, thing or Works
petition with G.R. No. 147925-26 is also DENIED. Nature of PMO [Uy] had mobilized manpower and equipment sufficient
property referred to in the award. EDC Claim Engineer
Claim Evaluation to do the landscaping works for the entire 105 hectares.
Evaluation
SO ORDERED.[19] The unilateral reduction in scope of work made by
a.Project P95,740,834. 67,422,840.4 81,851,396.08
Thus, what remains for us to resolve is Uy's petition, [PEA] thus laid idle the men and equipment of [Uy] in
The filing of the motion for correction shall interrupt Equipment 30 0
raising the following issues: direct proportion to said reduction. In effect, therefore,
the running of the period for appeal. on Standby
I Uy had on hand manpower and equipment amounting
With the filing of the motion for correction, the running Equipment 4,925,600.00
to 42.85% in excess of that necessary to perform the
of the period to appeal was effectively interrupted. Operator/Dri
WHETHER OR NOT RESPONDENT COURT OF landscaping works for the reduced scope of work. [Uy]
ver
APPEALS HAS DEPARTED FROM THE thus suffered costs in terms of excess manpower and
CIAC was supposed to resolve the motion for b Manpower on 28,165,022.00 2,275,721.00 2,275,721.00
ACCEPTED AND USUAL COURSE OF JUDICIAL equipment in proportion to the reduced scope of work.
correction of computation within 30 days from the time . Standby
PROCEEDINGS IN DISMISSING PETITIONER
the comment or opposition thereto was submitted. In c Topsoil Add'l 37,780,200.00 37,780,200.0 37,780,200.00
UY'S PETITION IN CA-G.R. SP NO. 59849 ON xxxx
Uy's case, no resolution was issued despite the lapse of . Hauling 0
THE ALLEGED GROUND OF NON-
the 30-day period, and Uy considered it as a denial of Distance
COMPLIANCE WITH THE REGLEMENTARY The total contract period - original extensions - to
his motion. Accordingly, he elevated his case to the CA d Water Truck 19,652,000.00 15,467,800.0 19,652,000.00
PERIOD IN FILING AN APPEAL complete the landscaping works for the entire 105
on July 24, 2000. But not long thereafter, or on August . Operating 0
hectares is 693 days. The reduction in scope of work
1, 2000, the CIAC issued an Order[22] denying the Cost
42.85% laid idle his equipment by the same percentage
II motion for correction of computation. ---------------------------------------------------------------------
of 42.85[%] or 296.95 days. Since [Uy] calculated his
---------------------------------------
claim for idled equipment on a per month basis, it is
WHETHER OR NOT THE RESPONDENT Obviously, when Uy filed his petition for review with Total P181,338,056 122,946,561. 146,484,917.[
necessary to convert this into months. 296.95 days is
COURT OF APPEALS, IN AFFIRMING THE the CA, the period to appeal had not yet lapsed; it was .30 40 08]
equivalent of 9.89 months. Multiplied by the rate of
DECISION OF THE CIAC ARBITRAL TRIBUNAL interrupted by the pendency of his motion for
P1,982,217.60 per month of delay, this would translate
INSOFAR AS IT DENIED CERTAIN CLAIMS OF computation. There is no basis, therefore, to conclude Further, it is being specified that the PMO maintains
to P19,604,132.06 as the cost of idle time for equipment
PETITIONER UY, HAS DECIDED A QUESTION that the petition was belatedly filed. the earlier notes of the CMO in its memo of 18 October
by reason of the [delay].[25]
OF SUBSTANCE NOT IN ACCORDANCE WITH 1999 and that legal interpretations on each item of
Upon review of the records before us, we find a need to
LAW AND THE APPLICABLE DECISIONS OF The foregoing notwithstanding, inasmuch as the CA claims is likewise enjoined.
modify, by increasing, the award for standby equipment
THE HONORABLE COURT resolved the petition on the merits, we now confront cost.
the substantive issue - the propriety of the CA's Attached are pertinent documents for your review and
affirmance of the CIAC decision. reference
CIAC found that PEA incurred delays in the turnover
III of work areas:
Uy cries foul on the award granted by CIAC, and (Sgd.) (Sgd.) The first delay was the turn-over of a portion of Area 1
WHETHER OR NOT THE RESPONDENT affirmed by the CA. He posits that PEA already ROGELIO H. IGNACIO FLORO C. URCIA A that was made on 17 April 1997. The start of work on
COURT OF APPEALS ACTED WITHOUT OR IN admitted its liability, pegged at P146,484,910.10, in its PMO-B Asst. Project Manager that area was scheduled for March, 1997. There was,
EXCESS OF ITS JURISDICTION OR WITH memorandum dated January 6, 2000. Thus, he faults the By no stretch of the imagination can we consider this therefore, a delay of about one month. The second delay
GRAVE ABUSE OF DISCRETION AMOUNTING CA for awarding a lesser amount. memorandum an admission of liability on the part of was the turn-over of a portion of Area 2 A that was
TO LACK OR EXCESS OF JURISDICTION WHEN PEA. First, nowhere in the memorandum does it say made on 20 October 1997. The start of work on that
We meticulously reviewed the records before us and
area was scheduled for May, 1997. There was, therefore, ART. 1724. The contractor who undertakes to build a In Powton Conglomerate, Inc. v. Agcolicol,[31] we emphasized: bigger additional costs to operate the water trucks. No
a delay of about five months. The third delay was the turn- structure or any other work for a stipulated price, in The written consent of the owner to the increased costs explanation was offered for such a mystifying
over of a portion of Area 2 B that was made on 05 conformity with plans and specifications agreed upon sought by the respondent is not a mere formal requisite, differential treatment. He cannot, therefore, pass on
March 1998. The start of work on that area was with the land-owner, can neither withdraw from the but a vital precondition to the validity of a subsequent without any contractual basis, such additional costs to
scheduled for mid-February 1997. There was, therefore, contract nor demand an increase in the price on account contract authorizing a higher or additional contract the [PEA].
a delay of more than one (1) year. Altogether, of the higher cost of labor or materials, save when there price. Moreover, the safeguards enshrined in the Neither can we hold PEA liable based on solutio indebiti,
has been a change in the plans and specifications, provisions of Article 1724 are not only intended to the legal maxim that no one should enrich itself at the
the several periods of delayed turn-over of work areas total one provided: obviate future misunderstandings but also to give the expense of another. As we explained in Powton
year and six months or 546 days.[26] parties a chance to decide whether to bind one's self to Conglomerate, Inc. v. Agcolicol,[35]
Surely, on the days that EDC was waiting for the turn (1) Such change has been authorized by the proprietor or withdraw from a contract. the principle of unjust enrichment cannot be validly
over of additional work areas, it was paying rentals for in writing; and By proceeding to obtain topsoil up to a 40-kilometer invoked by the respondent who, through his own act or
the equipment on standby. Yet, CIAC completely radius without written approval from the PEA general omission, took the risk of being denied payment for
ignored these delays in determining the cost of (2) The additional price to be paid to the contractor has manager, Uy cannot claim the additional cost he additional costs by not giving the petitioners prior
equipment on standby, reasoning that: been determined in writing by both parties. incurred. notice of such costs and/or by not securing their
It must be pointed out, however, that the division of the By this article, a written authorization from the owner is written consent thereto, as required by law and their
vast area to be landscaped into distinct work areas with required before the contractor can validly recover his Uy further claims P19,625,000.00 for cost of contract.
different start of work schedules under the PERT-CPM, claim. The evident purpose of the provision is to avoid mobilization of water trucks. He asserts that PEA Uy cannot, therefore, claim from PEA the costs of the
[Uy] could easily have shifted his equipment from an litigation for added costs incurred by reason of completely failed to provide the generator sets necessary additional hauling distance of topsoil, and of the
area where the delivery was delayed to the area where additions or changes in the original plan. Undoubtedly, to undertake the watering and/or irrigation works for mobilization of water trucks.
there was an advanced turn-over.[27] it was adopted to serve as a safeguard or a substantive the landscaping and construction activities.[32]
This is wrong. condition precedent to recovery.[28] Uy also assails the grant of attorney's fees equivalent to
Uy, however, admitted that MDC had already installed a 10% of the total amount due. Citing paragraph 24.4 of
Records establish that EDC promptly commenced the This provision is echoed in the Landscaping Contract, deep well in the project site, and EDC used it in its the Landscaping and Construction Agreement, Uy
landscaping work on every area that was turned over. viz.: landscaping and construction activities.[33] Under the asserts entitlement to attorney's fees of twenty percent
EDC, in fact, shifted its equipment where there was an ARTICLE IX contract, the operational costs of the deep well and its (20%) of the total amount claimed. He ascribes error to
advance delivery, if only to minimize the additional CHANGE OF WORK appurtenant accessories, including the generator sets, the CIAC and the CA for reducing the stipulated
expenses incurred by reason of the long delays in the shall be borne by EDC: attorney's fees from 20% to 10% of the total amount
turnover of the other work areas. Thus, in addition to xxxx The CONTRACTOR shall shoulder all cost of due.
the award of P19,604,132.06 for cost of idle time for electricity, maintenance, repairs, replacement of parts,
equipment by reason of the reduction of scope of work, 9.3. Under no circumstances shall PEA be held liable when needed, and all costs of operation of the Paragraph 24.4 of the agreement provides:
Uy is entitled to the cost of idle time for equipment by for the payment of change of work undertaken without deepwell/s, and its appurtenant accessories, i.e. Should the PEA be constrained to resort to judicial or
reason of the delay incurred in the delivery of work the written approval of the PEA General Manager x x x. generator sets, etc. (which are already existing at the quasi-judicial relief to enforce or safeguard its rights and
areas. project site, constructed by another Contractor) while interests under this Agreement, the CONTRACTOR if
such deepwell/s are being used by CONTRACTOR found by the court or [the] quasi-judicial body, as the
The period of owner-caused delay was 546 days or 18.2 ARTICLE X herein for its landscaping and construction activities. case [may be], to have been at fault, shall be liable to
months. The rate given by the Association of Carriers EXTRA WORK These [deepwells] shall be turned over to PEA by PEA for attorney's fees in an amount equivalent to
and Equipment Lessors (ACEL), Inc., and which was CONTRACTOR in good operating/usable condition as twenty percent (20%) of the total [amount] claimed in
also used as basis by CIAC in granting the costs for xxxx when it was first used by CONTRACTOR.[34] the complaint, exclusive of [any] damages and costs of
equipment on standby, was P1,982,271.60 per month of Thus, Uy cannot claim additional cost for providing suit.[36]
delay. Considering that PEA was in delay for 564 days 10.3. Under no circumstances shall PEA be held liable generator sets. Clearly, the cited provision cannot support Uy's
or 18.2 months, Uy is entitled to an additional award of for the payment of extra work undertaken without the insistence. Paragraph 24.4 on stipulated attorney's fees is
P36,076,360.32. Accordingly, he is entitled to an written approval of the PEA General Manager to Uy also attempts to justify his claim for cost of applicable only in complaints filed by PEA against the
aggregate amount of P55,680,492.38 for the equipment perform the said work.[29] mobilization of water trucks by alleging that the water contractor. The provision is silent on the amount of
rentals on standby. Admittedly, EDC did not secure the required written from the deep well provided by MDC and PEA was attorney's fees that can be recovered from PEA.
approval of PEA's general manager before obtaining the grossly insufficient to undertake the watering works for
As to the awards of P2,275,721.00, for the cost of idle topsoil from a farther source. As pointed out by the the project; hence, he was constrained to mobilize water Besides, even assuming that Paragraph 24.4 is
manpower, and P6,050,165.05, for the construction of CIAC: trucks to save the plants from dying. applicable, the amount of attorney's fees may be
the nursery shade net area, we find no reason to disturb There is no change order authorizing payment for the reduced if found to be iniquitous or unconscionable.
the same, as Uy never raised this issue in his petition. increased cost upon which this claim is based. There is, Indisputably, Uy mobilized water trucks for the Thus:
therefore, no legal right based upon contract (the landscaping projects and, certainly, incurred additional Articles 1229 and 2227 of the Civil Code empower the
Next, we resolve Uy's claims for costs for additional landscaping agreement or a change order) that would costs. But like his claim for additional cost of topsoil, courts to reduce the penalty if it is iniquitous or
hauling distance of topsoil and for mobilization of water impose such a liability upon [PEA]. In a lump sum such additional expenses were incurred without prior unconscionable. The determination of whether the
truck. contract, as that entered into by the parties, the matter written approval of PEA's general manager. Thus, he penalty is iniquitous or unconscionable is addressed to
of how the contractor had made [a] computation to cannot claim payment for such cost from PEA. the sound discretion of the court and depends on
The approved hauling cost of topsoil was only arrive at [a] bid that he submits is completely irrelevant. several factors such as the type, extent, and purpose of
P12.00/kilometer or P120.00 for the 10 kms original The contract amount of delivered topsoil is P780.00 per As aptly said by the CIAC: the penalty, the nature of the obligation, the mode of
source. Uy, however, claims that due to the delay in truckload of 5.5 cubic meters sourced from a distance Since [Uy] had presumably intended all along to charge breach and its consequences.[37]
delivery of work areas, the original source became of [10] km. or 100 [meters]. There is nothing in Exhibit [PEA] for the water truck operating costs, considering The Court finds Uy's claim for attorney's fees equivalent
depleted; hence, he was constrained to haul topsoil "L" or in the landscaping contract (Exhibit "A") that the very substantial amount of his claim, the prudence to 20% of whatever amount is due and payable to be
from another source located at a much farther distance would indicate an agreement of [PEA] to pay for the that he presumably has, as an experienced general exorbitant. The CIAC and the CA, therefore, correctly
of 40 kms. Uy insists that the exhaustion of topsoil at increase in hauling cost if the source of topsoil exceeds contractor of the highest triple A category, should have awarded 10% of the total amount due and payable as
the original source was solely attributable to the delay in 10 kilometers. Corollarily, there is also nothing therein dictated that he negotiate with the [PEA] for a change reasonable attorney's fees.
the turnover of the project site. Thus, he claims from to show that [PEA] would also be entitled to decrease order or an extra work order before continuing to spend
PEA the increased cost of topsoil amounting to said costs by paying less if the distance would have been the huge amounts that he claims to have spent. [Uy] did Finally, on the propriety of the writ of injunction.
P37,780,200.00. less than 10 kilometers. Had there been such a just that in relation to his much smaller claim for the
counterpart provision, there might have been more construction of the nursery shade x x x. He, however, Uy asserts that the CA acted without or in excess of
Article 1724 of the Civil Code provides: arguable claim for [Uy]. Unfortunately, no such made no effort to negotiate with the PEA for a similar jurisdiction when it enjoined the proceedings in CIAC
provision exists.[30] change order or extra work order to safeguard his even Case No. 03-2001, despite the fact that the said case is
totally different from the instant case. CIAC Case No. 02-2000. There is only one cause of
action running through Uy's litigious undertakings - his
By grave abuse of discretion is meant such capricious alleged right under the Landscaping and Construction
and whimsical exercise of judgment equivalent to lack Agreement. Therefore, the landscaping agreement is
of jurisdiction. Mere abuse of discretion is not enough. indispensable in prosecuting his claims in both CIAC
It must be grave, as when it is exercised arbitrarily or Cases Nos. 02-2000 and 03-2001.
despotically by reason of passion or personal hostility;
and such abuse must be so patent and so gross as to As we held in Villanueva v. Court of Appeals:[40]
amount to an evasion of a positive duty or to a virtual A party, by varying the form or action or by bringing
refusal to perform the duty enjoined or to act at all in forward in a second case additional parties or
contemplation of law.[38] arguments, cannot escape the effects of the principle of
res judicata when the facts remain the same at least where
The CA granted PEA's prayer for the injunctive writ such new parties or matter could have been impleaded
not without reason. We quote its Joint Resolution, viz.: or pleaded in the prior action.
[T]here is no question that Elpidio S. Uy's amended WHEREFORE, the petition is PARTIALLY
complaint is based on the same Landscaping and GRANTED. The assailed Joint Decision and Joint
Construction Agreement, as he himself admits. The claims Resolution of the Court of Appeals in CA-G.R. SP Nos.
pertinent thereto had already been arbitrated and passed 59308 and 59849 are AFFIRMED with
upon in CIAC CASE NO. 02-2000 and the decision MODIFICATIONS. Respondent Public Estates
therein was already elevated to Us for review and, in Authority is ordered to pay Elpidio S. Uy, doing
view of Our joint decision in the instant petitions, a business under the name and style Edison Development
reconsideration thereof. and Construction, P55,680,492.38 for equipment rentals
on standby; P2,275,721.00 for the cost of idle
Based on the foregoing, We are inclined to grant the manpower; and P6,050,165.05 for the construction of
prayer of PEA to enjoin the CIAC from further the nursery shade net area; plus interest at 6% per
proceeding with CIAC CASE NO. 03-2001, considering annum to be computed from the date of the filing of
that the allegations therein constrain Us to apply the the complaint until finality of this Decision and 12% per
doctrine of litis pendentia, which has for its requisites: (a) annum thereafter until full payment. Respondent PEA
identity of parties, or at least such parties who represent is further ordered to pay petitioner Uy 10% of the total
the same interests in both actions; (b) identity of rights award as attorney's fees.
asserted and relief prayed for, the relief being founded
on the same facts; and (c) the identity with respect to SO ORDERED.
the two preceding particulars in the two (2) cases is such
that any judgment that may be rendered in the pending
case, regardless of which party is successful, would
amount to res judicata in the other case. Forum shopping
exists where the elements of litis pendentia are present or
where a final judgment in one case will amount to res
judicata in the other. The principle of bar by prior
judgment raised by the PEA, i.e., res judicata, finds
application only upon a showing of a final judgment as
one of its requisites, which is not yet present under the
present circumstances.

At this juncture, it bears stressing that the essence of forum


shopping is the filing of multiple suits involving the same parties
for the same cause of action, either simultaneously or successively,
for the purpose of obtaining a favorable judgment. Accordingly,
based on Our holding that the final resolution of the
instant petitions takes precedence as it is the appropriate
vehicle for litigating the issues between the parties, now that the
instant petitions before Us have come full circle with
this joint resolution and, if the parties herein so choose,
may seek further relief to the High Tribunal afterwards.
We cannot allow CIAC CASE NO. 03-2001 to proceed
because to do so would render inutile the proscriptions
against forum shopping which is frowned upon in Our
jurisdiction. Hence, the grant of injunctive relief. This
must be done, or else a travesty of the efficient
administration of justice would lamentably result.[39]
Indeed, the assailed resolution shows no patent or gross
error amounting to grave abuse of discretion. Neither
does it show an arbitrary or despotic exercise of power
arising from passion or hostility.

At this point, it should be stated that the Court is not


convinced by Uy's argument that the claims under
CIAC Case No. 03-2001 are different from his claims in

S-ar putea să vă placă și