Documente Academic
Documente Profesional
Documente Cultură
Document No YGP-PL-HSE-0007
table of contents
1. INTRODUCTION........................................................................................... 3
1.1 Purpose and Scope ................................................................................................ 3
1.2 Objectives ................................................................................................................ 3
2. SITE DESCRIPTION ....................................................................................... 4
3. CONSTRUCTION ACTIVITIES ...................................................................... 7
3.1 Water Supply ............................................................................................................ 9
3.2 Power Generation, Fuels and Chemical Storage ............................................ 10
3.3 Waste ...................................................................................................................... 10
4. EXISTING ENVIRONMENT ......................................................................... 11
5. ENVIRONMENTAL MANAGEMENT ......................................................... 16
6. STAKEHOLDER CONSULTATION .............................................................. 20
7. REFERENCES .............................................................................................. 25
List of Figures
Figure 1: YGP route
List of Tables
Table 1: Pipeline coordinates
Table 2 YGP Activity Summary
Table 3:Water Requirements
Table 4: Distances to potentially sensitive features
Table 5:Biogeographic sub-regions traversed
Table 6: Key environmental hazards and control measures
Table 7: Summary of stakeholder interactions
1. Introduction
This Environment Plan (EP) Summary provides an overview of the environmental
management requirements for the construction of the Yamarna Gas Pipeline (YGP), which
will be located within pipeline licence area (PL114), GRJV Miscellaneous Licences L38/252,
L38/260; with short sections also within GRJV tenements M38/435, M38/437, M38/438,
M38/841, M38/1179, M38/1255 and M38/1267. The YGP includes the pipeline and
associated infrastructure to facilitate gas transport from the existing Eastern Goldfields
Pipeline (EGP) to the Gruyere gold mining and processing project, presently under
construction by the Gruyere Joint Venture (GRJV) on the Yamarna pastoral station. The
YGP will be operated by APA Operations Pty Ltd (APA).
The pipeline will be approximately 198km long; beginning approximately 25 km south-
south-west of Laverton, running north-north-east towards the town, bypassing the townsite
and several minesites, turning east-north-east to follow the public White Cliffs – Yamarna
Road for about 150 km, then departing from the road to continue north-east into the
Gruyere minesite, about 160 km north-east of Laverton (Figure 1).
1.2 Objectives
The overall environmental objectives of the CEP/MP are to:
Outline the measures to be taken to manage potential environmental impacts
associated with construction of the YGP.
Facilitate approvals under the Pipelines Petroleum Act 1969 (Pipelines Act) and Mining
Act 1978 (Mining Act).
Provide direction to project personnel in meeting APA’s environmental obligations and
commitments.
Ensure compliance with project approval, pipeline licence, minerals tenement, and
other conditions.
2. Site Description
The YGP will begin (YGP KP0) at a hot tap onto the existing EGP, at EGP KP42.5; an offtake
station will be installed at this point. The YGP will terminate at approximately KP197.5 on
the Gruyere minesite, adjacent to the proposed power station, where a metering and
delivery station will be installed. A mainline valve will be installed on the YGP at KP98.5,
near its midway point.
Selected pipeline coordinates and KPs are summarised in Table 1 below; as the pipeline
comprises many (mostly slight) bend points, it is not practicable to list them all. All pipeline
coordinates are provided in the spatial data that accompanies this submission.
3. Construction Activities
The YGP construction project has an estimated duration of 9 months and is estimated to
take place from December 2017 to July 2018, with first gas supplied to the Gruyere mine
site power station shortly after.
Works associated with the YGP construction are summarised in Table 2.:
Activity Description
Horizontal If open cut trench methods are not suitable for specific
Directional Drilling crossings, horizontal directional drilling (HDD) methods will be
the preferred means of trenchless construction.
Hot Tapping Safely drilling and welding a new fitting to allow connection of
the off-take into the operating EGP.
Pipe will be delivered to the construction ROW and laid out end-
to-end alongside the trench. Individual pipe segments will be
placed on raised timber skids or sandbags to protect them from
damage, and facilitate welding into continuous lengths (pipe
strings).
Pipe Assembly The pipeline will be bent in places to follow the pipeline route,
and/or conform to the terrain.
Pipe segments are welded into continuous lengths before being
laid in the trench. Welded joints will be x-ray tested and garnet-
blasted to remove surface scale and rust, and then coated with
a high build epoxy (HBE) to provide a continuous external
coating and prevent corrosion.
Once welded, the pipe strings will be placed into the trench by
side-boom pipe-layers (or equivalent). Fine bedding and
padding sand will be placed around the pipe to prevent any
Pipe Lowering sharp objects (such as rocks in the trench spoil) from damaging
the pipe coating. Bedding and padding material will be
sourced from the trench spoil itself by screening, wherever
possible.
Supporting services required for the activity include water supply, power generation and
chemical storage and waste management. These aspects of the project are summarised
in the sections below.
3.3 Waste
Project wastes are expected to principally comprise:
Inert waste, including packaging, wooden pallets, steel (e.g. pipe off-cuts), builder’s
rubble, formwork, welding rods etc., and minor quantities of waste concrete.
Putrescible waste, predominantly food scraps;
4. Existing environment
Distances to potentially sensitive environmental or social features in the region are
summarised in Table 4 below.
The YGP falls within the Murchison – Eastern (MUR1), Great Victorian Desert – Shield (GVD1)
and Great Victorian Desert – Central (GVD2) sub-regions as defined by the Biogeographic
Regionalisation for Australia version 7 (IBRA; DoEE 2012). The biogeographical
characteristics of these sub-regions are summarised in Table 5 below. The area has a
“desert” climate of hot summers and mild winters
The YGP traverses the “Leemans Sandplain (274)” and “Salinaland Plains (279)” zones of
the “Murchison (27)” province, and “North-western Great Victoria Desert (122)” zone of
the “Gunbarrel” province, as mapped by DAFWA (DAFWA 2014, cited in Botanica 2017).
These zones may be further subdivided into 14 soil-landscape systems crossed by the YGP.
The YGP route is principally dominated by two systems, namely the:
“Bullimore” system, characterised as “gently undulating sandplain with occasional
linear dunes and stripped surfaces supporting spinifex grasslands with mallees and
acacia shrubs”; and the
“My99” system, characterised as “plains with extensive gravel pavements and small
tracts of longitudinal dunes”.
A short section of the YGP crosses a mapped DAFWA soil-landscape system associated
with actual or potential acid sulphate soils (ASS/PASS), namely the “Carnegie” system,
described as “salt lakes with fringing saline alluvial plains, kopi dunes and sandy banks,
supporting halophytic shrublands and acacia tall shrublands” (Tille 2006).
MBS (2017) visited the location in July 2017 to assess the potential for ASS in line with
Identification and Investigation of Acid Sulfate Soils and Acidic Landscapes (DWER 2015a).
Soils were noted to comprise a shallow layer of alluvial material (to 1m), over a hardpan
of calcrete and ferricrete; no signs of ASS (such as sulfidic black material or jarosite
mottling) were observed. MBS took nine soil samples to refusal (hardpan) depth, for field
and laboratory testing of parameters indicative of ASS. No values consistent with PASS or
ASS were recorded in the surface samples, and while the pipeline trench may be
excavated somewhat below the depth of sampling, MBS noted that the hardpan would
be expected to comprise high-clay-content oxic material for many metres above the
5. Environmental Management
Environmental management will be implemented in compliance with the APA ISO14001
accredited Health, Safety and Environmental (HSE) Management System which provides
for:
communication of policies, objectives and roles and responsibilities
inductions, training and competency of personnel
monitoring, auditing, record keeping and reporting, including dedicated hazard and
incident reporting system
management of non-conformances and corrective actions
development, tracking and ongoing maintenance of documentation
emergency preparedness and response
toolbox talks
A risk based approach has been adopted to manage potential threats to the
environment. This process involved initial identification of environmental interactions
(aspects) resulting from project activities followed by an environmental risk assessment
(ERA) workshop attended by key personnel. The ERA process involved:
assessment of environmental risks in terms of likelihood and consequence
identification of mitigating factors and management measures to reduce
environmental risks to ALARP
risk ranking according to severity
A summary of the key environmental hazards, control measures and mitigating factors
identified for the YGP has been provided in Table 6. Table 6 only provides an indication
of major hazards and controls and is not a comprehensive summary of all commitments
associated with the YGP.
6. Stakeholder Consultation
APA is committed to maintaining positive relations with all stakeholders throughout the
duration of its activities. A brief summary of engagement to date is provided in Table 7.
Consultation with government has involved meetings with agencies to generally advise
them of the project, and discuss approval requirements (including information
requirements), and timeframes. APA notes that no major issues of concern in regard to
potential project environmental impacts have been raised to date.
Liaison with affected land holders and managers has commenced with the affected
landholders and impacted tenement holders (through the GRJV Miscellaneous License
application process) since project conception, and is ongoing. A comprehensive line list
will be generated for affected landowners / occupiers that identify individual concerns
over access to properties as well as requirements regarding usage, impacts and
reinstatement. Where applicable or as required, property inspection reports will be
prepared to record agreed requirements of landowners / occupiers and to ensure such
requirements are complied with.
Affected stakeholders will be kept aware of scheduled activities and impacts as the
project progresses. Ongoing consultation will occur for this project via email/letters,
meetings and circulation of updates to relevant stakeholders.
Feedback from all interested parties will be encouraged and monitored during the entire
project. A register will be maintained that records actions taken to address any
issues/feedback received.
Landholders
Liaison has been ongoing since project conception as GJV is the only present 8/11/2016
customer.
Interactions have broadly revolved around commercial contracts and requirements,
GRJV /
land tenure and access agreements, environmental aspects and approvals, safety
Yamarna
planning, and heritage surveys to name a few.
Pastoral Station
Communication channels remain open with all key contacts as the approvals process
progresses towards practical kick-off. Reporting lines will be established for ongoing
works together throughout construction, and then into operational contracts.
Liaison with the Yilka Native Title Group has been channelled through the GRJV and 2/05/2017
will continue to do so throughout the construction of the pipeline. This is mainly due to 14/08/2017
the contractual agreement that is in place between GJV and Yilka. APA has submitted 3/10/2017
documentation for Yilka review prior to be formally submitted to government
Yilka Native
departments. This includes this CEP/MP.
Title Group /
Cosmo Yilka have been consulted with respect to the planned works that are progressing for
Newberry the pipeline and are providing monitors during ground disturbing works.
Yilka has been notified of the pipeline application under section 24 MD (6A) the Native
Title Act 1993. The Cosmo Newberry Aboriginal Corporation has been notified of the
application due to the capacity as occupier of Crown Reserve 22032.
Mt Weld station lease is held by Gold Fields Australia, which is also a tenement holder. 22/03/17
Communication has been ongoing as per below tenement holders, as well as in
relation to the station and additional agreements.
Mt Weld The Station is managed by Pat Hill. No major issues have been raised from the station
Station manager. He is aware of all planned works and will be regularly updated throughout
works.
Pat Hill has been notified prior to surveyors being on the Mt Weld Pastoral Station. There
has been no issues raised.
Laverton Downs station lease is held by Trevor Schutz. Communication has been 24/04/2017
ongoing with regards to the construction of the pipeline and the early survey works. 1/06/2017
Discussion have been mainly around the location of bores in the vicinity of the 27/06/2017
proposed pipeline.
Laverton
Downs Station No major issues have been raised, Laverton Downs are aware of all planned works and
will be regularly updated throughout works.
Trevor Schutz has been notified prior to surveyors being on the Mt Weld Pastoral Station.
There has been no issues raised.
White Cliffs station lease is held by Noel McKay. Communication has been ongoing 26/04/2017
with regards to the construction of the pipeline and the early survey works. Discussion 30/06/2017
have been mainly around the location of the pipeline where it traverses the station 4/07/2017
and bores in the vicinity of the proposed pipeline. 27/09/2017
White Cliffs No major issues have been raised, White Cliffs are aware of all planned works and will
Station be regularly updated throughout works. Noel has enquired about the flora and fauna
survey documentation for the pipeline route, APA and GRJV are working on providing
this information.
Noel McKay has been notified prior to surveyors being on the Mt Weld Pastoral Station.
There has been no issues raised.
As identified above, liaison and negotiation with all impacted tenement holders has 28/03/2017
been ongoing as a part of the tenure acquisition process. All access agreements have 24/04/2017
now been finalised, which include ongoing (if any) reporting requirements. 14/08/2017
Tenement 4/09/2017
There are ongoing discussions with a few tenement holders regarding vehicle crossings
Holders 5/10/2017
of the pipeline.
All tenement holders have been notified prior to surveyors being on their tenements.
There has been no issues raised.
Government
Ongoing meetings and phone calls have taken place with regards to licencing, safety 8/12/2016
and environment, with both the Petroleum and Mines divisions. 21/03/2017
DMIRS Reporting will be ongoing throughout the project and into operations. It is anticipated
that audits from multiple divisions will also take place throughout the project.
Liaison throughout CEP / MP and NVCP review, assessment and acceptance period.
The project has been formally referred (14-888438) (via GRJV) with the outcome being 11/05/2016
EPA
determined as not requiring assessment by the EPA.
Communication with DBCA has been through DMIRS regarding the NVCP. APA has 25/07/2017
DBCA
responded to the queries, mainly around the Mt Jumbo BIF area. 4/08/2017
DOW (now part Communication with DOW has not been a key requirement at the early stages of the
of DWER) project, however meetings will be held if abstraction licences are required.
Liaison with DWER has not been a key requirement at the early stages of the project,
DWER however from previous experience meetings / communications will be held regarding
any requirements for works approvals associated with a WWTP if required
The Department has been consulted (via GRJV) upon the findings of heritage surveys. 17/05/2017
DPLH There has been a Section 18 application submitted for partial impact. The project is 2/06/2017
awaiting a response from the Ministers office regarding the application.
The ALT has been notified of the pipeline licence application due to the capacity as 3/10/2017
Aboriginal the manager of the Crown Reserves 25050 and 22032 vested under Part III of the
Lands Trust Aboriginal Affairs Planning Authority Act 1972. Acknowledgement has been received
by APA.
Contact has been ongoing with the CEO and Shire President, including email 7/04/2017
communications and face to face meetings. The Shire will continue to be consulted 31/07/2017
Shire of and updated throughout the project. 17/08/2017
Laverton 13/10/2017
A site meeting was held to discuss the locations of shire borrow pits along White Cliffs
road.
DMIRS has confirmed that the pipeline licence application has now been considered 15/08/2017
a future act under the Commonwealth Native Title Act 1993. Under section 24MD(6A) 13/10/2017
Goldfields and (6B) notification to the representative body for the area was triggered and both
Land and Sea APA as the applicant and DMIRS have notified GLSC.
Council (GLSC GLSC has responded to the notification from DMIRS outlining concerns regarding the
heritage sites intersecting the project area. APA and GRJV are in the process of
responding to the GLSC letter (dated 28 September 2017)
7. References
Botanica 2017. Level 1 Flora & Fauna Survey Yamarna Gas Pipeline Project. Report
prepared by Botanica Consulting Pty Ltd for Gold Road Resources Limited.
DoEE 2012. Interim Biogeographic Regionalisation for Australia, Version 7. Department
of the Environment and Energy. Available at:
http://www.environment.gov.au/land/nrs/science/ibra; accessed 30 May 2017.
GRJV 2016. Gruyere Gas Pipeline Project EPA Referral Supporting Document. Report
by Gold Road Resources Limited.
Johnson, Commander & O’Boy (1999) Groundwater Resources of the Northern
Goldfields. Water and Rivers Commission. Available at: https://www.water.wa.gov.
au/__data/assets/pdf_file/0010/4330/10480.PDF; accessed 29 May 2017.
MBS 2017. Baseline Soil Assessment for the Yamarna Gas Pipeline and Gruyere Power
Station. Report by Martinick Bosch Sell Pty Ltd for APA Group.
Tille 2006. Soil-landscapes of Western Australia's Rangelands and Arid Interior.
Available at: http://researchlibrary.agric.wa.gov.au/rmtr/295/; accessed 29 May
2017.