S/N JOB/ITEM DESCRIPTION ITEM QTY UNIT


1.00 M1 - PRELIMINARIES

1.10 Mobilise plant and equipment and materials tosite and including site prepration 1.1.1 1.00 per job
tocarry out works incuding cashes

1.20 18.1 1.00 per job


Carry out Pre & Post construction surveys and submit relevant documentation
Provide for carrying out relevant laboratory testing of works as directed and
1.30 submit test results. 18.2 1.00 per job

M1 - PRELIMINARIES TO SUMMARY
2.00 M2 - CONSTRUCTION OF Master Meter Foundation

2.10 Strip topsoil to an average depth of 150mm for construction of concrete m2


platform. = 2m* 2m 4

2.20 Excavate in all material except rock to a depth not exceeding 1.0 m and cart away 3.70 1.21 cu.m
materials from excavation for construction of drain and meter footing.= Drain
foundation (0.2m W * 0.3m D * 11m L) + meter foundation (1m x 1m x 0.55m).
Backfill with the exvacated sharp sand after work completion

2.30 Provide, mix, place and compact grade 15 concrete for blinding= platform 7.1 0.26 cu.m
((2*2*0.05)+ adjoining drain (0.3*3*0.05))*1.05

Provide, cut to size, bend to shape and fix Y16 high yield steel reinforcement @
2.40 150mm c/c for the foundation base, T16 rebars for the pedestal with T12 as 8.1 98.87 kg
stirrups @ 200mm c/c. = (base ((0.975/0.15+1)*1.3*4*1.58*1.05) + pedestal
(1.8*8*1.58*1.05) + stirrups ((0.5+0.5+0.5+0.5+0.2)*5*0.89*1.05)

Provide, cut and fix high yield steel fabric reinforcement No. A252 in
2.50 concrete for drain and platform= platform ((2*2) - (0.675*0.675)) + drain 12.34438 m2
((0.8*11)

2.60 Provide and fix treated wrought woodwork shuttering with fair finish to concrete 7.9 14.33 sq.m
= meter (0.975*0.2*4)+(0.95*0.65*4) + platform (2*0.2*4) + drain (0.2*11*4)

Provide, mix, place and compact grade 30 concrete =


2.70 ((0.975*0.975*0.2)+(0.675*0.675*0.95))*1.05 + platform ((2*2)- 7.4 4.98 cu.m
(0.675*0.675)*0.2) + drain (0.7*0.1*3)

Provide and fix 0.8'' (20mm) diameter bolt and studs and all accessories in
2.80 concrete structure to receive meter. Bolts shall be 3Nos spaced at 120 degrees 13.12 3.00 Nos.
which shall be aligned with meter on site. Bolts shall have a depth of 600mm
embedded in concrete.
M2 - CONSTRUCTION OF Master Meter Foundation TO SUMMARY
3.0 M3 -CONSTRUCTION OF SHELTER

3.1 Excavate for footing stanchion foundation commencing from existing strip level. = 3.70 6.75 m2
Footing (1.5m L * 1.5m W * 0.75m D) * 4 Nos

Supply and place plain in-situ concrete of grade 15N/mm2 as blinding bed under
3.2 foundation to a depth of 50mm. = Footing (1.5m L * 1.5m W * 0.05m D) * 4 Nos 7.1 0.4725 m3
*waste 1.05
3.3 Make provision for round bar Hot rolled high yield steel deformed bars to B.S 8.1 556.374 Kg
4449 and B.S 4461. 16mm diameter bars as specified, this shall be in line with the
bar bending schedule. Base = ((1.35/0.15+1)*1.7*4*4)*1.58 + pedestal
(1.6*8*4)*1.58 +Links (0.6/0.15*1.8)*4*0.89

Supply and place reinforced vibrated in-situ concrete of grade 30N/mm2 as


3.4 specified. = Footing base=(1.35*1.35*0.2)*4)+ pedestal column 7.9 1.944 m3
(0.45*0.45*0.6*4)

3.5 Provide and fix treated wrought woodwork shuttering of fair finish to concrete. = 7.4 5.4 m3
Footing ((0.2m*1.35m*4*4)+(0.6*.0.45m*4*4)

3.6 Provide and install 10mm thick base plate (400mm x 400mm), 4 Nos. @ 12.56 kg 4 Nos
each

3.7 Provide and install 20mm diameter anchor bolts,450mm long at 4 Nos per base 16 Nos
plate and 0.86kg per piece for 4 Nos. stanchions
M3 -CONSTRUCTION OF SHELTER to SUMMARY

4.00 M4 CONSTRUCTION OF ROOF STEEL MEMEBERS , STANCHIONS AND ROOFING


COVERING
4.1 SHELTER ROOF STEEL MEMBERS AND STANCHIONS

Supply fabricate, weld and install vertical I-sections- 1PE150 -160x82 x 6mm
thick) as stanchions with height of 2.6m for (4nos) which are to be bolted to
existing foundation footing using 10mm steel plate and 20mm thick diameter
4.1.1 bolt. Stanchions shall also be bolted to angle bar to receive z purlins for roof. 2 lengths
Rates also should include for necessary bolts and nuts and all standard lifting
equipment to install stanchions which are to be screwed properly following
standard . I-sections -160x82 x 6mm is 6m per length .

Supply fabricate, weld and install I-sections 100x50x4mm as rafters beam with
length of 6m each for 2 Nos. This are to receive purlins using appropriate
bracing. Rates shall include bracing of rafters to stanchions using 10mm steel
4.1.2 2 lengths
plate and 20mm diameter bolt . Rates shall also include necessary bolts and nuts
and all standard lifting equipment to install rafters which are to be screwed
properly following standard . I-sections 100x50x4mm is 6m per length

Supply fabricate weld and install I-sections-100x 50 X 4mm as tie beam to brace
stanchions to stanchions using appropriate 10mm steel plate and 20mm
4.1.3 diameter steel bolts. Rates shall include necessary bolts and nuts and all 4 lengths
standard lifting equipment to installation tie in beam which are to be screwed
properly to standard. I-sections 100x50x4mm is 6m per length = (6*2+3.2*2)/6

Make provision for and install 75mm x 75mm angle bar iron 6mm to receive z-
purlins and aluminum cladding . Angle bar shall be bolted horizontally and
vertically @ every 450mm interval to steel stanchions using 20mm diameter
4.1.4 bolts. angle bar steel iron shall also be bolted diagonally like a cross at each 2 9 lengths
Nos stanchions. Rates shall include necessary bolts and nuts for rafter installation
srewd properly to standard . 75 x 75x 6mm thick angle bar is 6m per length =
(6.6m * 8)/6.

supply fabricate and install Z purlins (150x50x2mm) as roof purlins at 450mm


4.1.5 centres. = Roof = ((6/0.45+1)) @3m each = 8 lengths of 6m + cladding 16 lengths
((2/0.45+1))+ diagonals 2*5.2 @4.8m each = 8 lengths of 6m each

4.2 SHELTER ROOFING COVERING SHEET AND PAINTING


4.2.1 Make provision( supply and install) for aluminum roofing, and cladding gauge 29 m2
0.7mm. Rate to procure aluminum should include for the fabrication of site and
installation to trusses and for cladding .= Cladding (4.8*2) + Roofing sheet (6*3.2)

4.2.2 Allow for painting of entire stanchions using approved red oxide paint as 1st 1 LS
primer and standard corrosion paint dulux for 2nd and 3rd coating to prevent
erosion. To be checked by Seplat corrosion team prior to use .
SHELTER ROOF STEEEL MEMBERS AND STANCHIONS AND SHELTER ROOFING
COVERING SHEET AND PAINTING TO SUMMARY
5.00 M5- DEMOBILISATION
5.10 Demobilise personnel and equipment from site 1.4.1 1 per job
M5 - DEMOBILISATION TO SUMMARY
TOTAL