Documente Academic
Documente Profesional
Documente Cultură
Blocks shall be stacked properly near the place of work (Do not stack too
large quantity near the work area thereby causing safety hazard).
Height of the stack should not be more than one and half meter.
Working space to be clear of rubbish waste mortar etc so that easy access
is ensured
CT props to be fixed in front of lift shaft to tie the safety belt.
Pre Construction
During Construction
Post Construction
Material Selection
Shop Drawings
Workmen Training
Preparation
Material Selection
Cement
Crush Sand
Water
AAC Blocks
Block Adhesive
CEMENT
No Presence of Lumps
Grade 43 / 43-S
IS 4031:1988
Part 4
LABORATORY TESTS Consistency 29 – 30%
No Cracks and
Size Of the damages
Blocks
Dimensional Tolerance
For Length Max +/- 5mm
For Width & Height +/- 3mm
Ready to use.
Self cured.
Less wastage.
Shop Drawings
Workmen Training
Preparation
Shop Drawings
D X B D : Specific Details
C
X - SHOP DRAWING AAC BLOCKWORK
Shop Drawings
Workmen Training
Preparation
Material Management
Quantity Estimation
Shifting Arrangements
Mortar Mixing Equipment's
Scaffolding Arrangements
Accessories, Tools & Tackles
Estimate quantity required floor wise, flat wise
Consider wastage factor for
• Material handling
• Cutting wastages
Shifting Arrangements
Horizontal Shifting
Vertical Shifting
BOBCAT
WHEEL BARROW
MATERIAL LIFT
MATERIAL HOIST
MORTAR Mixing Equipment's
Wire Brush
Ghamela / Tray
Material Selection
Shop Drawings
Workmen Training
Preparation
WORKMEN TRAINING
Conduct training session for workmen, to prevent the bad quality works.
WORKMEN TRAINING
Conduct training session for workmen, to prevent the bad quality works.
Material Selection
Shop Drawings
Workmen Training
Preparation
PREPARATION
Clean the floor where blockwork to be done
RCC surface hacked
All binding wires, nails, masking tapes and stuck shuttering material is removed.
Patching of honeycomb if any completed and curing of it monitored
All binding wires, nails, masking tapes and stuck shuttering material is removed.
Patching of honeycomb if any completed and curing of it monitored
Mark the wall lines on floor to get proper layout of blockwork, check the clear height
between the floor top and the beam bottom / slab bottom.
h
y
D
Measurement of Height
Marking on Floor
Check all Embedded MEP cutouts are correct, if not then correct it before blockwork
Decide on the thickness of leveling course mortar to avoid wastage / cutting of blocks
at top course and to maintain the gap of 10 to 15mm at top of block work. The
thickness of leveling course mortar should not be more than 25mm.
Blocks should be cut only with cutting machine by trained mason.
Light Weight Block
Masonry Stages
Pre Construction
During Construction
Post Construction
Base Course
Mix quantity of mortar, which will be consumed in next 1 hour only. Mixing shall be done with
proper measurements of ingredients in proportion of 1:6 with pharma.
Add water to the dry mix of cement crush sand in required quantity.
Fix one block at the ends of walls in level as per layout.
Blocks should be wet before placing to avoid absorption of water from mortar.
Carry out leveling course of Blockwork with ‘‘dry bond’’ (i.e. without mortar in the vertical joints,
lay the blocks in position) by fixing line thread on end blocks. Use piece of plywood to have
uniform vertical joints.
Lay mortar for full bed width and for a length of 3 blocks at a time.
Lay one block at a time & gently pressing it in the mortar bed. Use 12mm thick plywood piece to
ensure uniform vertical joints.
Excess mortar coming out on the edge (while pressing block in position in bed mortar) to be
taken by trowel and reused.
Use straight edge / sprit levels on top of the blocks laid & check the top level. Make sure that the
spirit level is in working condition & read the bubble carefully.
Lay the last closure block in the course, to close the bond and locate it to be near the center of
the wall normally.
Floor
Check the layout of leveling course Blockwork and then fill all vertical joints of blocks with cement mortar.
As soon as mortars in the joints have initially set, use a proper tool and strike the vertical joints to the
depth of 12mm.
Curing to the base course should be done for next 7days.
Floor
Curing
In hot & dry weather the mortar is likely to dry up before it has attained its final set in the block
work. This leads to crumbling of mortar and resulting in weak block masonry. This shall be
prevented, by keeping the base Blockwork layer constantly wet, for at least seven days.
Blockwork done with adhesive doesn’t required curing.
Blockwork with Adhesive
After completion of the base course Blockwork should be done with approved block adhesive.
Block adhesive should be applied with adhesive application trowel only to ensure the uniform
application.
Before starting the block fixing work above base course, the positions of full and cut (required size) blocks
should be finalized to ensure the staggered vertical joints at least by 6” and to minimize the wastage of
blocks. This can be done by making elevation sketch/drawing for walls and pass on the same to Workers for
execution.
Adhesive should be applied on both faces where block to RCC joint comes and on one face where block to
block joints come.
Clean the surface of block and apply adhesive on it from end of the wall. Fix the block on
adhesive by pressing it within 3 minutes.
For fixing next block apply the adhesive on two sides (i.e.- face of the block fixed earlier and at
the top of below block) and fix the block in position with the help of wooden mallet.
Each fixed block should be checked for its line, level and plumb by mason.
The thickness of adhesive is 3 to 4mm if not checked at the time of fixing will result in unleveled
blockwork with the cavities in joints.
While fixing the block between two laid blocks, adhesive should be applied on all three sides of blocks.
Floor Beam
Adhesive to be applied on
all three sides of block
Column
Floor
Repeat the above points for building more courses.
All joints should be sealed from all sides while fixing blocks.
Floor Beam
to build more
all of
Check line and level three faces of
courses.
installed block
each block immediately
Apply Adhesive
after on
installation
RCC + Apply
block Adhesive
face and on two
on below
facesblock top block
of installed
face
Floor
Clear gap of minimum 10mm should be left between top most layer and RCC bottom.
This gap should be filled with very lean mortar and 10mm aggregates should fixed on the surface.
This is to prevent the cracks afterwards in the wall plastering (due to presence of different
materials like block and RCC).
If the gap is bigger than 20mm the mortar with aggregate should be made to fill it.
In walls where, the gap between Blockwork and RCC bottom is 100 to 150 mm flyash
bricks should be fixed at the top instead of cutting blocks.
In double wall area, opening for water drainage and circulation of air should be made in chajja.
After doing three layers of blockwork, ghotai to the chajja should be done with slope towards
opening. Ghotai should be done on all sides of box up to 300mm height.
Light Weight Block
Masonry Stages
Pre Construction
During Construction
Post Construction
Post Construction
2. Verticality
3. Line
4. Right Angle
5. Hollow Joints
6. Opening Dimensions
Check For Horizontal Level
Check For Verticality
Check For Line
Check for Right Angle
Check For Hollow Joints
Check For Opening Sizes
Post Construction
Completed work should be duly certified and recorded.
Record Checklist
Sample Checklist Format
Do’s & Don’t
Do stack the blocks on a proper platform & clean surface in direction it is going to fit in wall.
Do not raise any part of wall during construction by more than one and a half meter above the
general construction level.
Do’s & Don’t