DETAILED ESTIMATE-

SINGLE LANE BRIDGE ACROSS LOCAL STREAM NEAR ANDUGULPET (V) MANDAMARRI (M), MANCHIRYAL
DIST.

S.No. Description Unit No. L B D Qty

1 Earth work excavation with machinery cut in all soils Cum


upto Soft Disintegrated Rock and depositing outside
the banks including silt removal as directed by the
Engineer-in-charge.
For Vent Opening 1 20.000 15.000 4.085 1225.500
4 5.000 7.500 2.000 300.000
Abutment foundation 2 9.950 8.400 1.915 320.111
Pier Footings 2 7.100 3.800 3.915 211.253
2056.865
Add for variaton 205.686
Total or Say 2262.551
2 Vibrated Cement concrete with M-15 grade concrete cum
confirming to compressive strength of 15.00 N/mm2
concrete using well graded machine crushed Hard
broken Granite metal maximum size of 40 mm down
graded confirming to IS Code including cost and
conveyance of all materials, labour charges all leads
and lifts, seigniorage, and compacting concrete with
vibrates, curing etc complete for laying foundations to
abutments and Returnwalls etc.as directed by the
Engineer in charge
Abutment
(d) Foundations 2 9.950 8.400 0.600 100.296

Base concrete under pier 2 7.400 4.100 0.100 6.068


106.364
Total Say 107.000
3 Vibrated Cement concrete with M-15 grade concrete cum
confirming to compressive strength of 15.00 N/mm2
concrete using well graded machine crushed Hard
broken Granite metal maximum size of 40 mm down
graded confirming to IS Code including cost and
conveyance of all materials, labour charges all leads
and lifts, seigniorage, and compacting concrete with
vibrates, curing etc complete for abutments and
Returnwalls etc.as directed by the Engineer in charge

Abutment Body wall 2 5.200 2.650 5.825 160.537


(0.9+4.4)/2
Return Body wall 2 7.500 1.900 6.800 193.800
(0.5+3.3)/2

354.337
Total Say 355.000
4 Vibrated Reinforced Cement concrete M 25 grade Cum
concrete confirming to compressive strength of 20.00
N/mm2 concrete using well graded machine crushed
Hard broken Granite metal maximum size of 20 mm
down graded confirming to IS Code including cost and
conveyance of all materials, labour charges, all leads &
lifts seignorage, vibration and machine ,mixing for Bed
blocks, Dirt walls, Approch slabls etc complete, for
finished item of work. as directed by the Engineer in
charge.
Bed block over abutments 2 5.200 1.000 0.300 3.120
Dirt wall 2 5.200 0.450 0.600 2.808
Bed Block over Pier 2 4.700 1.000 0.300 2.820
Approch slab 2 3.500 4.250 0.150 4.462
13.210
Total Cum 11.000
5 Vibrated Reinforced Cement concrete M 25 grade cum
concrete confirming to compressive strength of 25.00
N/mm2 concrete using well graded machine crushed
Hard broken Granite metal maximum size of 20 mm
down graded confirming to IS Code including vibration
and machine ,mixing for,deck slabs complete, for
finished item of work.
Deck Slab 3 8.500 4.950 0.600 75.735
Kerbs 6 8.500 0.450 0.350 8.033
83.768
Total Say 84.000
6 Vibrated Reinforced Cement concrete M 20 grade cum
concrete confirming to compressive strength of 25.00
N/mm2 concrete using well graded machine crushed
Hard broken Granite metal maximum size of 20 mm
down graded confirming to IS Code including vibration
and machine ,mixing for railings complete, for finished
item of work.
Solid parapet 2 7.500 0.200 0.600 1.800
Railing 3 1.660 4.980
Rail posts 3 0.440 1.320
Ornamental Pilasters 2 0.300 0.300 1.200 0.216
8.316
Total Say 22.000
7 Vibrated Reinforced Cement concrete M 20 grade cum
concrete confirming to compressive strength of 25.00
N/mm2 concrete using well graded machine crushed
Hard broken Granite metal maximum size of 20 mm
down graded confirming to IS Code including vibration
and machine ,mixing for Pier complete, for finished item
of work.

Pier 2 4.700 0.900 7.675 64.931


64.931
Total Say 22.000
8 Vibrated Reinforced Cement concrete M 20 grade cum
concrete confirming to compressive strength of 25.00
N/mm2 concrete using well graded machine crushed
Hard broken Granite metal maximum size of 20 mm
down graded confirming to IS Code including vibration
and machine ,mixing for Pier footings complete, for
finished item of work.

Pier Footings 2 7.100 3.800 0.750 40.470


40.470
Total Say 41.000
9 Vibrated Cement concrete with M-30 grade concrete cum
confirming to compressive strength of 30.00 N/mm2
concrete using well graded machine crushed Hard
broken Granite metal maximum size of 20 mm down
graded confirming to IS Code including cost and
conveyance of all materials, labour charges all leads
and lifts, seigniorage, and compacting concrete with
vibrates, curing etc complete for Wearing Coat etc.as
directed by the Engineer in charge

Over Deck slab & 3 8.500 4.250 0.075 8.128


Approach Slab 2 3.500 4.250 0.150 4.463
Over Approach Slab 2 3.500 4.250 0.075 2.231
Total cum 14.822
Say 15.000
10 Supply and fixing of HYSD bars in position including
cost and conveyance of material and straightening,
cutting, bending including cost of binding wire and
placing in position etc. complete as directed by the
Engineer-in-charge.
Deck slab
Bottom
Main steel 20 Dia @ 100mm C/C 142 9.02 0.0025 3.150
Distribution steel 12 Dia @150 mm C/C 171 5.22 0.0009 0.794
Top
Main steel 10 Dia @ 300mm C/C 49 9.02 0.0006 0.274
Distribution steel 10 Dia @ 300 mm C/C 87 5.22 0.0006 0.281
Approach slab
Top & Bottom
Main steel 12 Dia @ 150mm C/C 127 3.62 0.0009 0.409
Distribution steel 12 Dia @150 mm C/C 95 4.37 0.0009 0.369
Pier
Main steel 12 Dia - 90 Nos 180 8.80 0.0009 1.406
Distribution steel 8Dia @200 mm C/C 78 12.01 0.0004 0.370
Pier Footing
Bottom
Main steel 20 Dia @ 120mm C/C 119 4.20 0.0025 1.229
Distribution steel 12Dia @120 mm C/C 64 7.40 0.0009 0.418
Top
Main steel 10 Dia @ 300mm C/C 49 4.20 0.0006 0.126
Distribution steel 10 Dia @ 300 mm C/C 27 7.40 0.0006 0.122
Pier Bed Block
12 Dia bars-16 Nos for one pier 32 4.60 0.0009 0.131
Stirrups 10 Dia @ 200mm C/C 48 2.44 0.0006 0.072
Abutment Bed Block
16 Dia bars-16 Nos for one pier 32 5.10 0.0016 0.258
Stirrups 10 Dia @ 200mm C/C 48 2.44 0.0006 0.072
Abutment Dirt Wall
12 Dia bars-6 Nos for one pier 12 5.10 0.0009 0.054
Stirrups 10 Dia @ 200mm C/C 53 2.44 0.0006 0.080
Total MT 5.670
MT Say 5.700
11 Providing 225mm thick gravel backing under approach cum
slabs including cost and conveyance of all materials,
labour charges for laying, watering and ramming etc.,
complete as per drawings or as directed by Engineer

well compacted gravel Pitching cum 2 1.500 5.200 0.225 4.000


12 Refilling with useful excavated soils (other than sand) Cum
complying with standard specification for filling
foundation and sides of head walls, wing walls
etc.complete for finished item of work.
Bfilling behind abutment 320.111 - 265.20 54.911
Approach road 2 15.000 5.200 1.400 218.400
2 21.000 5.200 0.700 152.880
Total Cum 426.191
13 Rough stone revetment with gravel backing
Bed Pitching cum 1 20.000 24.300 0.600 291.600
toe walls 2 24.300 0.600 1.200 34.992
Side slopes cum 2 15.000 8.228 0.300 74.048
Toewall 2 15.000 0.600 0.600 10.800
Total cum 411.440
Say Cum 412.000
14 Spplying and fixing of mastic pad 20mm thick for fixing
in construction joints including cost and conveyance
charges etc complete as directed by Engineer in
charge.
Sqm 4 5.200 0.675 14.040
15 Supply and fixing of guide stones ( granite
variety)1200mm x 200mm x200mm size including cost
and conveyance of material and labour charges etc.
complete as directed by the Engineer in charge.
Inner side of the bank guard stones fixed at 2.5 m Nos 4 12.000 48
interval
16 Providing weep holes in the abutments 2inch diameter
as indicated in drawing and as directed by the Engineer
in charge.
On abutments 2 4 8
For Returns 4 6 24
Total Nos 32
17 Providing Drainage sprouts in the deck slab 4" PVC
pipe including cost etc complete as directed by the
Engineer in charge.
Per Span 2 Nos Nos 3 2 6
18 Supply and fixing of Kraft paper Over Bearing
Abutments 2 5.200 0.450 4.680
Piers 2 4.700 1.000 9.400
Total Sqm 14.080