Documente Academic
Documente Profesional
Documente Cultură
Energy
journal homepage: www.elsevier.com/locate/energy
a r t i c l e i n f o a b s t r a c t
Article history: The use of a low pressure economizer (LPE) is an effective way to recover waste heat from the exhaust
Received 11 September 2018 flue gas in thermal power plants. In this paper, an improved bypass staged economizer scheme is pre-
Received in revised form sented for China's 600-MW ultra-supercritical power units. The simulation models of the bypass staged
28 November 2018
economizer and traditional LPE were established based on a 600-MW unit. The simulation results
Accepted 19 December 2018
showed that when the presented economizer system was adopted, the temperature of the exhaust flue
Available online 19 December 2018
gas was reduced to near the flue gas acid dew point, thereby greatly improving the energy-saving effects.
Compared with the traditional LPE system, the improved economizer system can reduce standard coal
Keywords:
Bypass staged economizer system
consumption rate by an additional 1.1 g/kWh. The bypass ratio under different loads could be adjusted to
Waste heat recovery achieve the best energy-saving effect. The optimum bypass ratio was analyzed under different loads. The
Off-design condition results showed that the improved economizer system had a better energy-saving effect by actively
Coal-fired power plant controlling the exhaust flue gas temperature.
© 2018 Elsevier Ltd. All rights reserved.
https://doi.org/10.1016/j.energy.2018.12.147
0360-5442/© 2018 Elsevier Ltd. All rights reserved.
186 P. Xiao et al. / Energy 170 (2019) 185e198
to perform work in the steam turbine. In terms of thermodynamics, and case study 2 should be higher than the low temperature acid
the first law and the second law were used to evaluate the effi- dew point to prevent corrosion of the heat transfer surfaces.
ciencies of the LPE installed in a CFPP. The thermal equilibrium The baseline case is the original design system for comparison,
efficiencies and the second law efficiencies increased, whereas the as shown in Fig. 2. The schematic thermal system of Case study 1 is
first law efficiency decreased after applying the LPE [16]. Different shown in Fig. 3. The extracted steam for heating the feedwater in
connections of the LPE with the steam turbine recovery heat system FWH No. 6 is replaced by the heat recovered by the LPE. The LPE
have been discussed [17e19]. Analysis results show that very little inlet of the feedwater is connected with the outlet of FWH NO.7 and
increase in the back pressure of the steam turbine occurs when a the LPE outlet of feedwater is connected with the inlet of FWH
proper LPE is installed, i.e., there are few negative impacts on the NO.5. The LPE is installed between the air preheater and the ESP.
operation of the boiler thermal system. Moreover, the recovered The schematic thermal system of Case study 2 is shown in Fig. 4.
heat from heating the high temperature feedwater has a better The flue separation system is built at the downstream of the high
energy saving effect than heating the low temperature feedwater. pressure economizer. The flue is divided into a main flue and a
There are many in-service units that have been retrofitted with the bypass flue by adding separate flue baffles and a control valve. A
traditional LPE in China, such as the Yudong power plant [20] and part of the high temperature flue gas from the outlet of the high
the Shangdu power plant [21]. However, the traditional LPE has a temperature economizer is bypassed. First, the bypassed flue gas is
defect in terms of the larger heat transfer temperature difference, used to heat the feedwater from the outlet of the feedwater pump
which leads to not making full use of waste heat. Therefore, it is in the first-stage bypass economizer. The heated feedwater is led to
shown that greater benefits resulted from installing the two stages the outlet of FWH NO. 2. The cooled flue gas is led to the second-
air preheater system proposed in Ref. [22]. A lignite-fired power stage bypass economizer to heat the condensate from the outlet
plant was transformed by adding an additional high pressure of FWH NO. 6. The heated condensate is led to the outlet of FWH
economizer to increase the unit gross efficiency [23]. A bypass flue NO. 5. The main flue gas is cooled by the air preheater and then
scheme that can effectively recover waste heat was constructively mixed with the bypassed flue gas. A new device named pre-air
proposed in the 1000-MWe lignite-fired power plant Nieder- preheater is set up in the position after the flue gas mixture to
aussem Unit K [24]. The exhaust flue gas is cooled from approxi- heat the air and cool the flue gas to ensure the exhaust flue gas
mately 160 Ce100 C. Based on this scheme, different plant temperature and air temperature are appropriate. The mixed flue
configurations and the relevant cost analyses were simulated by gas passes through the pre-air preheater and finally leads to the
Aspen Plus under low temperature exhaust flue gas [25,26]. ESP. The air passes through the pre-air preheater to the main air
However, most relevant studies have focused on the energy- preheater and eventually to the boiler furnace. This approach can
saving effects through structural improvement and the analysis of not only make full use of boiler exhaust heat to reduce exhaust flue
thermodynamics. Only a few studies have shown the operational gas temperature but also reduce the heat rate of the steam turbine
strategy of a reliable scheme. For example, when the heat transfer system.
area of the LPE is fixed, the exhaust gas temperature cannot be
controlled because of the fluctuations in the flue gas temperature 3. Model approach
caused by long-term operation, which may cause low temperature
corrosion. 3.1. Model of the prototype unit
In this paper, an efficient flue gas waste heat recovery system is
proposed. The simulation model was built to analyze the perfor- To study the thermal economic performance of the bypass
mance of the presented heat recovery system and the traditional staged economizer system, a simulation model of a 600-MW pro-
LPE system. The optimum bypass ratio was analyzed under totype unit is established by MATLAB/Simulink (version 7.0.1) in
different loads. The results showed that the improved economizer this paper. The thermal system model of the CFPP is constructed
system had a better energy-saving effect by actively controlling the according to the structure shown in Fig. 1. The whole plant model
exhaust flue gas temperature. consists of three main modules, namely, the boiler, the steam tur-
bine and the regenerative system. First, the parameters of the main
2. Design of improved economizer system steam and reheat steam are simulated from the boiler and input to
the steam turbine model. The steam turbine model simulates the
The boiler discussed in this paper is China's most widely used pressure and enthalpy of each extraction port and input to the
600-MW supercritical once-through boiler, which produces regenerative system, and the boiler simulation results are corrected
531.4 kg/s of superheated steam at 25.4 MPa and 571 C and 440 kg/ by calculating the exhaust parameters of the high pressure cylinder.
s of reheated steam at 3.83 MPa and 569 C in BMCR working The regenerative system simulates the extraction steam flow to
condition. The coal used is bituminous with 62.83% carbon, 3.62% feedback to the steam turbine model and the feedwater parameters
hydrogen, 9.94% oxygen, 0.70% nitrogen, and 0.41% sulfur, and the to feedback to the boiler model. The main working parameters of
lower heating value (LHV) is 22760 kJ/kg. The boiler efficiency is the whole unit can be simulated by inputting the wind, coal
estimated as 93.55% (LHV basis). Fig. 1 shows a diagram of the parameter and steam flow from the boiler side. The prototype unit
power plant system structure. There are three high pressure FWHs, simulation model is shown in Fig. 5.
one deaerator and four low pressure FWHs. The overall perfor- The simulation model of the supercritical once-through p type
mances of the unit are included in Table 1, and the details of the boiler is divided into spiral water wall, vertical water wall, partition
steam parameters are showed in Table 2. screen superheater, high temperature reheater, the finishing su-
In this study, an improved bypass staged economizer system is perheater, low temperature reheater hot forging, coated tube, low
proposed to recover the waste heat of the exhaust flue gas. To temperature reheater cold section, economizer, and air preheater,
facilitate the comparison and analysis, the calculation and analysis as shown in Fig. 6. The model building methods in these sub-
of the original design system and the traditional LPE system are modules are similar. According to the structure of the boiler and
conducted at the same time. Table 3 shows the descriptions of the the thermodynamic process, the boiler is divided into several
three case studies. The minimum exhaust flue gas temperature is coupling horizontal layers, and the simultaneous equations are
restricted by the dew point of SOx to prevent low temperature acid used to represent the inner horizontal layer of the thermodynamic
corrosion. The exhaust flue gas temperature design of case study 1 process. Parameter changes exist in the vertical direction, and
P. Xiao et al. / Energy 170 (2019) 185e198 187
Prh
P0
HP IP P5 LP LP
Pc
Boiler
P2 P1 P3 P4
P6 P7
P8
Condenser
Tc
DEA
Table 2
Details of the steam performance.
Items NO.1 FWH NO.2 FWH NO.3 FWH Deaerator NO.5 FWH NO.6 FWH NO.7 FWH NO.8 FWH
Extracted steam pressure (MPa) 5.977 4.047 1.829 0.951 0.392 0.119 0.059 0.019
Extracted steam enthalpy (kJ/kg) 3054.8 2970.1 3376.2 3189.1 2974.9 2733.8 2621.1 2493.7
Extracted steam flow rate (kg/s) 28.95 40.50 16.91 21.91 22.92 11.29 15.17 9.87
Outlet feedwater temperature ( C) 275 249.2 206.4 180.8 138.2 100.3 81.21 54.81
Drain temperature ( C) 254.8 211.9 186.4 0 105.9 86.87 60.19 42.52
Table 3
Descriptions of the case studies.
Cases Descriptions
Baseline The designed power plant system without waste heat recovery
Case study The power plant system with traditional LPE with one-stage LPE to heat the feedwater
1
Case study The power plant system with a bypass staged economizer system and with a control valve to divide the flue, the first-stage LPE to heat the feedwater, the
2 second-stage LPE to heat the condensate, and the pre-air preheater to preheat the air
188 P. Xiao et al. / Energy 170 (2019) 185e198
Flue gas
Economizer
Flue gas
Pump
Air preheater
$LU
Flue gas
ESP
Economizer
Flue gas
Pump
Air preheater
Flue gas
$LU
LPE
Flue gas
ESP
diagram of each subsystem of steam turbine system established in further calculate the operating characteristics of the bypass staged
MATLAB/Simulink is given in Fig. 5. economizer system and calculate the energy-saving effect, a suit-
The boiler system and the steam turbine system simulation able unit simulation computing platform is established.
model are coupled and connected to establish the simulation
model of the coal-fired unit; the model intuitively reflects the
3.2. Unit model with bypass staged LPE systems
operating characteristics of the coal-fired unit and accurately sim-
ulates the operating parameters of equipment. According to the
An economizer model is developed to investigate the perfor-
design data of a 600-MW supercritical unit, the calculation results
mance of different LPE systems under all conditions by the water-
of the model are verified. The model calculation results have high
wall heat exchange surface mathematical method [27]. Case
accuracy compared with the design data. Among the data points
studies 1 and 2 can be modeled based on the prototype unit model
used to verify the calculation, the data points with error less than
built above. The bypass staged economizer system simulation
3% accounted for 97% of all data points, as shown in Table 4. To
model of case study 2 is introduced in Fig. 7. The import parameters
P. Xiao et al. / Energy 170 (2019) 185e198 189
Flue gas
Economizer
FWH FWH FWH FWH FWH FWH FWH
NO. 1 NO. 2 NO. 3 Deaerator NO. 5 NO. 6 NO. 7 NO. 8
First-stage
economizer
Air preheater
Second-stage
economizer
$LU
Control
valve
Pre-air preheater
Flue gas
$LU
ESP
of the model are the flue gas temperature at the outlet of the high water vapor will condense on the wall, resulting in the low tem-
pressure economizer, the flue gas flow rate, the condensate inlet perature acid corrosion.
temperature and the feedwater inlet temperature. The heat transfer The following equations given by “Boiler Unit Thermal Calcu-
area under rated load can be calculated by assuming the heat lation Standard Method” of the former Soviet Union is widely used
transfer end difference. When the share of the bypass flue gas is to calculate the flue gas dew point:
given, the temperature increase in the condensate and feedwater,
the heat of the flue gas being cooled and the temperature of the flue pffiffiffiffiffi
b 3 Sn
gas before entering the pre-air preheater can be calculated. tsld ¼ tld þ (1)
1:05ah A
n
The simulation model of the baseline case is the prototype unit,
as shown in Fig. 5. The traditional LPE is connected with the pro-
totype unit model between the ESP and the air preheater in the tld ¼ 1:2102 þ 8:4064gh 0:4749g2h þ 0:01042g3h (2)
simulation model of case study 1. The detailed simulation model of
scheme 1 is omitted here. The unit simulation model of case study 2
is shown in Fig. 8; a part of exhaust flue gas is sent to the bypass Sn ¼ 4187Sar =Qnet (3)
economizers to heat the condensate and the feedwater. The heated
feedwater and condensate are returned to the regenerative system.
Therefore, the heat consumption of the steam turbine system and An ¼ 4187Aar =Qnet (4)
the standard coal consumption rate of the entire unit will be
reduced. The model of the steam turbine system also must increase where t sld is the flue gas acid dew point, tld is the water vapor dew
the input of heat at the corresponding location. point in the flue gas calculated by Eq. (2). b is a constant associated
with the excess air ratio aT , aT < 1.25, b ¼ 121; aT > 1.25,
and b ¼ 129. Sn is the converted share of the flue sulfur; Sar is the
4. Model of performance share of the sulfur in the as received flue. An is the converted share
of the flue ash. Aar is the share of the ash in the as received flue. Qnet
4.1. Acid dew point is the LHV of as received flue. ah is the fly ash content of the flue ash,
generally taken as 0.9 in China. gh is the share of water vapor in the
To avoid corrosion caused by a low temperature heating surface flue gas.
to ensure boiler operation safety and improve boiler efficiency, low Eq. (1) showed that the flue gas acid dew point t sld is mainly
temperature acid corrosion is one of the important factors that related to the water vapor dew point t ld . t ld varies with the share of
must be considered when reducing the exhaust gas temperature. water vapor in flue gas under different loads. The flue gas acid dew
When the temperature of the wall surface is lower than the acid point of the boiler discussed in this paper under different loads is
dew point, the sulfuric acid vapor produced by sulfur trioxide and calculated, as shown in Table 5.
190 P. Xiao et al. / Energy 170 (2019) 185e198
D_MS, P_MS, T_MS The flow, pressure and temp of the main steam T_DW The temp of the primary desuperheating water
P_RS, T_RS The pressure and temp of the reheated steam D_PA, T_PA The flow and temp of the primary air
D_FW, P_FW, T_FW The flow, pressure and temp of the feed water D_SA, T_SA The flow and temp of the secondary air
The flow of the primary and secondary The flow and temp of the outlet flue gas of
D_PDW, D_SDW D_FG_Eco T_FG_Eco
desuperheating water economizer
4.2. The heat rate and standard coal consumption rate 4.3. The bypass ratio
Because the accurate model of the whole unit mentioned above The bypass flue gas flow is controlled by the flue baffle. The
can be used, relevant accurate data can be extracted directly from bypass ratio is actually a mathematical description of the opening
the model when the economizer model is connected to the steam degree of the flue baffle. The bypass ratio is the proportion of the
turbine model and the regenerative system model. Coal, wind, and flue gas flow entering the bypass flue to the outlet flue gas flow of
water-related input parameters can be calculated when the load the high temperature economizer and can be calculated by Eq. (7):
and coal quality are entered. After the calculation of the boiler
model, the parameters of the pressure, temperature and flow of the Fby
R¼ (7)
main steam and reheated steam can be calculated. When the Ft
output parameters of the boiler are used as the input parameters of
the steam turbine system model, the power generation and the where R is the bypass ratio; Fby is the bypassed flue gas flow; Ft is
enthalpy of the inlet reheated steam can be calculated. the outlet flue gas flow of the high temperature economizer.
The heat rate and standard coal consumption rate can be
calculated by Eq. (5) and Eq. (6): 5. Results and discussion
Q0 .
5.1. Performance analysis of THA condition
q¼ ¼ D0 h0 hfw þ Drh ðhrh h1 Þ Pe (5)
Pe
The performance parameters of three cases are simulated at the
Bcp BQnet turbine heat-rate acceptance (THA) condition with electric power
bcp ¼ ¼ (6) output at 600 MW. The temperature parameters of the baseline
Pe 29270Pe
case can be extracted in the prototype unit model. In case study 1,
where q is the heat rate; Q0 is the heat consumption; Pe is the unit the outlet temperature of the high pressure economizer is 347.4 C.
power; D0 and Drh are the main steam flow and the reheat steam The air is heated from 25 to 313.3 C. The flue gas side temperature
flow, respectively; h0 and hfw represent the enthalpy of the main of the air preheater will drop to 135.8 C. The feedwater from the
steam and the enthalpy of the boiler feedwater, respectively. hrh outlet of the FWH NO. 7 is heated by the exhaust flue gas then sent
and h1 represent the enthalpy of the reheat steam and the enthalpy to the outlet of FWH NO. 6. The flue gas temperature will drop to
of the high pressure cylinder outlet, respectively. 95.4 C.
P. Xiao et al. / Energy 170 (2019) 185e198 191
Low
temper-
Division High ature
Final
panel tenper- reheater Coated
super-
Flue gas parameters super- ature (high pipes
heater
(flow temperature heater reheater temperat
component) ure HP Cylinder Exhaust
section)
Low temper-
Vertical ature
water wall Steam parameters reheater
(flow temperature (low
model pressure)
Reheat temperature )
steam FWH NO. 1 Outlet
Super-
heated
steam
Spiral water
wall model
Economizer
Coal parameters
(consumption
Gas
ingredient content)
Air
preheater
Air parameters
(flow temperature)
Air Feedwater parameters
(flow temperature
pressure)
Table 4
Value of operating parameters.
Parameter (THA condition) Design value Simulation value Relative error (%)
Flue gas flow Flue gas flow Flue gas flow Air temperature
Air Temperature Air temperature Air temperature Exhaust flue gas temperature
Bypass ratio
Bypass flue gas flow Flue gas flow Flue gas flow
Low
Divisio High temper-
Final ature
n panel tenper- Coated
super- reheater
Flue gas parameters super- ature (high pipes
heater
(flow temperature heater reheater temperatur
HP Cylinder Exhaust
component) e section)
Low temper-
ature
Vertical water reheater
Steam parameters
wall model (low
(flow temperature
Reheat pressure) temperature )
FWH NO.1 Outlet
steam
Super-
heated
Spiral water steam
wall model
Economizer
Mixture
Gas Pre-air
preheater
Air
preheater
Fig. 8. The unit simulation model of the bypass staged economizer system.
P. Xiao et al. / Energy 170 (2019) 185e198 193
5.2. Performance analysis of the part load conditions In case study 2, the change in the bypass ratio will directly affect
the exhaust gas temperature. For example, the flow of bypassed
When the unit load changes, the outlet temperature of the air flue gas will change when the bypass ratio changes at the THA
preheater will also change significantly. In this situation, the energy working condition. To ensure that the economizer feedwater outlet
saving effect of these cases is a matter of concern. In Fig. 10, the temperature matches the temperature of the corresponding FWH
temperature of exhaust flue gas varies with the load. The design at the regenerative system, the flow of feedwater of two stage
temperatures of case study 1 and case study 2 are the same at the economizers should be correspondingly changed. The changes in
THA condition; thus, the exhaust temperature is similar between flow of two stage economizers in different bypass ratios are shown
case studies 1 and 2. However, in comparison to the baseline, the in Fig. 16. The second-stage feedwater flow is changed for main
exhaust temperature is greatly reduced by an average of 34.9 C. adjustment, while the first-stage feedwater flow is changed for
Notably, when the load is less than 600 MW, the exhaust temper- auxiliary adjustment.
ature is lower than the design temperature. The acid dew point is The exhaust flue gas temperatures of the unit under different
calculated according to Eq. (1) and Eq. (2) as 81.42 C with the load loads with different bypass ratios are shown in Fig. 17. Fig. 18 shows
changes. The exhaust temperature is 77.86 C at 450 MW, i.e., when the energy saving effects of case study 2 at different bypass ratios,
the load is lower than 450 MW, the heat recovery system faces the which are compared with the results of case study 1. The exhaust
risk of acid corrosion. Thus, the performance analyses only consider flue gas temperature is different when the load and bypass ratio
loads between 450 MW and 600 MW. change. The greater the bypass ratio is, the lower the exhaust
Table 6
Comparison of performance parameters in three cases.
Temperature( )
150 135.8 150
95.4 95.6
100 100
50 50
0 0
SCE consumption Exhaust flue gas temperature
Fig. 9. Comparison of the standard coal consumption rate and the exhaust flue gas temperature.
140
130
120
Temperature ( )
110
100
90
Baseline
80
Case study 1
70
Case study 2
60
400 450 500 550 600 650
Load (MW)
Fig. 10. Temperature of the exhaust flue gas under different loads in the three case studies.
55
50
45
40
Flow (kg/s)
35
30
25
20 First-stage
15 Second-stage
10
400 450 500 550 600 650
Load (MW)
6000
Case study 1
5500
Case study 2
4500
4000
3500
3000
2500
2000
440 460 480 500 520 540 560 580 600 620
Load (MW)
7850
Baseline
Case study 2
Heat rate (kJ/kWh)
7650
7550
7450
7350
400 450 500 550 600 650
Load (MW)
290
Baseline
Standard coal consumption rate (g/kWh)
288
Case study 1
286 Case study 2
284
282
280
278
276
274
400 450 500 550 600 650
Load (MW)
45
44.5
43.5
43
Baseline
42.5 Case study 1
Case study 2
42
400 450 500 550 600 650
Load (MW)
90
First Stage
80
Second Stage
70
60
Flow (kg/s)
50
40
30
20
10
10 15 20 25 30 35 40 45
Bypass ratio (%)
Fig. 16. The flow of two stage economizers in different bypass ratios.
95
550MW
500MW
90
600MW
Temperature ( )
450MW
85
80
75
5 10 15 20 25 30 35 40 45
Bypass ratio (%)
Fig. 17. The exhaust flue gas temperature of case study 2 at different bypass ratios.
P. Xiao et al. / Energy 170 (2019) 185e198 197
2
(g/kWh)
1.5
1 600MW
550MW
0.5 500MW
450MW
0
5 10 15 20 25 30 35 40 45
Bypass ratio (%)
Fig. 18. The energy saving effects of case study 2 at different bypass ratios.
temperature. Therefore, flue gas temperature control can be ach- bypass ratio. This ratio can ensure not only that the temperature of
ieved by adjusting the bypass ratio. Taking into account the flue gas flue gas at inlet of the lower temperature ESP is 80 C but also that
acid dew point limit, the exhaust gas temperature must be operations are safe. The higher the unit load, the greater the pro-
controlled at above 80 C. The maximum bypass ratio can be read portion of flue gas that can be used to heat the feedwater and
from Figs. 17 and 18. The bypass ratio should be controlled below condensate and the lower the standard coal consumption rate.
42% when the load is 600 MW. The corresponding maximum en- Therefore, the performance of case study 2 is better than case study 1.
ergy saving effect is approximately 2.5 g/kWh. If the bypass ratio is
greater than 42%, then the temperature of the flue gas at the inlet of
the ESP will be below the acid dew point (80 C). When the load is 6. Conclusions
550 MW, the bypass ratio should be controlled below 31%. The
corresponding maximum energy saving effect is approximately An improved economizer system for China's typical 600-MW
2.3 g/kWh. When the load is 500 MW, the bypass ratio should be ultra-supercritical power units is proposed that can effectively
controlled below 19%. The corresponding maximum energy saving recover the waste heat and increase the unit efficiency. The scheme
effect is approximately 1.8 g/kWh. When the load is 450 MW, the can be used not only for the transformation of the economizer
bypass ratio should be controlled below 13%. The corresponding system of the existing unit in China but also for the design of the
maximum energy saving effect is approximately 1.4 g/kWh. new unit. The following conclusions are drawn from this study:
The optimal bypass flue gas ratio and the best coal saving effects
for different loads are shown in Fig. 19. The unit can adjust the (1) At the THA condition, in comparison with the baseline, the
separate flue baffles according to different loads to achieve the best bypass staged economizer can reduce the standard coal
consumption rate by 2.5 g/kWh at the optimal bypass ratio.
45 3
40
2.5
Standard coal consumption rate
35
reduction(g/KWh)
Bypass ratio (%)
30
2
25
20 1.5
15
Optimal bypass ratio 1
10
Optimal SCE consumption reduction
5 0.5
400 450 500 550 600 650
Load (MW)
Fig. 19. Optimal bypass ratio and best coal saving effects for different loads.
198 P. Xiao et al. / Energy 170 (2019) 185e198