Exxon Baytown Project

FOSTER WHEELER MEXICANA Job Schedule


Client: AMECFW
Id Modo de Nombre de tarea Duración Comienzo Fin oct '19 nov '19 dic '19 ene '20 feb '20 mar '20
tarea 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 01 08
1 100 días 18/10/19 05/03/20
Exxon Baytown WHB project
2 Commercial Stage 0 días 18/10/19 18/10/19 18/10

3 Purchase Order receipt from Client 0 días 18/10/19 18/10/19 18/10


4 Supply materials stage 66 días 18/10/19 17/01/20
5 Emmision of PO for Tubing 10 días 18/10/19 31/10/19
6 Emmision of PO for Plate 10 días 25/10/19 07/11/19
7 Emmision of PO for Insulation items 15 días 01/11/19 21/11/19
8 Receipt of bare tubing at shop 28 días 01/11/19 10/12/19
9 Receipt of finned tubing at shop 28 días 11/12/19 17/01/20
10 Receipt of plate materials at shop 10 días 08/11/19 21/11/19
11 Receipt of insulation and miscellaneous materials at shop 20 días 15/11/19 12/12/19
12 Manufacturing Stage 68 días 22/11/19 25/02/20
13 Superheater Module 58 días 22/11/19 11/02/20
14 Pressure parts manufacturing 26 días 07/01/20 11/02/20
15 Header Drilling 5 días 07/01/20 13/01/20
16 fitup tubing 2 días 20/01/20 21/01/20
17 Welding 12 días 22/01/20 06/02/20
18 NDT's 2 días 07/02/20 10/02/20
19 Release for hydrotest 1 día 11/02/20 11/02/20
20 Casing manufacturing 14 días 22/11/19 11/12/19
21 Layout and cut plates 2 días 22/11/19 25/11/19
22 Assembly plates for walls 2 días 26/11/19 27/11/19
23 Welding 4 días 28/11/19 03/12/19
24 Release for insulation 1 día 04/12/19 04/12/19
25 Insulation installation 4 días 05/12/19 10/12/19
26 Release for assembly 1 día 11/12/19 11/12/19
27 Boiler Module 56 días 26/11/19 11/02/20
28 Pressure parts manufacturing 21 días 14/01/20 11/02/20
29 Header Drilling 5 días 14/01/20 20/01/20
30 fitup tubing 3 días 21/01/20 23/01/20
31 Welding 10 días 24/01/20 06/02/20
32 NDT's 2 días 07/02/20 10/02/20
33 Release for hydrotest 1 día 11/02/20 11/02/20
34 Casing manufacturing 14 días 26/11/19 13/12/19
35 Layout and cut plates 2 días 26/11/19 27/11/19
36 Assembly plates for walls 2 días 28/11/19 29/11/19
37 Welding 4 días 02/12/19 05/12/19
38 Release for insulation 1 día 06/12/19 06/12/19
39 Insulation installation 4 días 09/12/19 12/12/19
40 Release for assembly 1 día 13/12/19 13/12/19
41 Interconnecting ducting 16 días 28/11/19 19/12/19
42 Casing manufacturing 16 días 28/11/19 19/12/19
43 Layout and cut plates 2 días 28/11/19 29/11/19
44 Assembly plates for walls 4 días 02/12/19 05/12/19
45 Welding 4 días 06/12/19 11/12/19
46 Release for insulation 1 día 12/12/19 12/12/19
47 Insulation installation 4 días 13/12/19 18/12/19
48 Release for assembly 1 día 19/12/19 19/12/19
49 Economizer module 62 días 02/12/19 25/02/20
50 Pressure parts manufacturing 26 días 21/01/20 25/02/20
51 Header Drilling 6 días 21/01/20 28/01/20
52 fitup tubing 4 días 29/01/20 03/02/20
53 Welding 11 días 04/02/20 18/02/20
54 NDT's 3 días 19/02/20 21/02/20
55 Release for hydrotest 2 días 24/02/20 25/02/20
56 Casing manufacturing 14 días 02/12/19 19/12/19
57 Layout and cut plates 2 días 02/12/19 03/12/19
58 Assembly plates for walls 3 días 04/12/19 06/12/19
59 Welding 3 días 09/12/19 11/12/19
60 Release for insulation 1 día 12/12/19 12/12/19
61 Insulation installation 4 días 13/12/19 18/12/19
62 Release for assembly 1 día 19/12/19 19/12/19
63 Hydrotesting stage 13 días 12/02/20 28/02/20
64 Hydrotest for superheater module 3 días 12/02/20 14/02/20
65 Hydrotest for Boiler Module 3 días 12/02/20 14/02/20
66 Hydrotest for Economizer module 3 días 26/02/20 28/02/20
67 Assembly stage 13 días 17/02/20 04/03/20
68 Assembly of superheater module 3 días 17/02/20 19/02/20
69 Assembly of Boiler module 3 días 17/02/20 19/02/20
70 Assembly of Economize module 3 días 02/03/20 04/03/20
71 Assembly of interconnecting ducting 3 días 20/02/20 24/02/20
72 Shipment at site stage 11 días 20/02/20 05/03/20
73 Superheater Module 1 día 20/02/20 20/02/20
74 Boiler Module 1 día 20/02/20 20/02/20
75 Economizer module 1 día 05/03/20 05/03/20

Tarea Tarea inactiva Informe de resumen manual Hito externo

División Hito inactivo Resumen manual Fecha límite


Proyecto: Exxon Project
Hito Resumen inactivo solo el comienzo Progreso
Fecha: 15/10/19
Resumen Tarea manual solo fin Progreso manual

Resumen del proyecto solo duración Tareas externas

Page 1 Rev. A
Made by: M.P
Revised by. D.M