Details of the site to which vacant access and right of way to the contractor is not available.

Chainage

Length as on
S No. Side Details land status and site obstructions
01.08.2019
From To

Land not handed over as out of 9.73 Ha of land, 3G


award has been done for only 2.925 Ha (30%). 3D
pening for balance 6.805 Ha land.
1 82+500 84+300 BHS 1800 Out of sanctioned 3G estimates amounting to Rs.22.5
crores 2.925 Ha only Rs. 13.25 Crores has been
disbursed. (58%)

1) Approval of estimates of buildings is pending at


NHAI at Plot no. 2677, 2676, 2679 at Kulharia.
2) Disbursemet of land pendig for plot no. 2677,
2676 at Kulharia village
2 98+400 100+400 BHS 2000 3) 4 Nos tree affected due to withdrawal of tree
felling permission by DFO letter no. 251, Dt-
04.06.2019
4) Encroachment

1) Missing plots 1227, 1228, 928, 939, 1066, 944 for


which 3A yet to be done.
2) Award for land not done due to mismatch of
nature of land in 3D between Hindi and English-
1088/3704, 1088, 927.
3) Mazar and Graveyard 40+900 for which valuation
yet to be approved.
4) Land payment pending-1093, 1094, 1092, 1090 ,
1072, 1071, 1070, 1069 of Sakaddi
5) Structure payment pending- 1081, 1080, 1074,
3 106+500 111+620 BHS 5120 1073, 1072 1221, 1093, 1094, 1091, 1092 of
Sakaddi
6) Balance land for which partially disbursement
done due to proposed realignment is yet to be
disbursed.
7) Total disbursement is 46.40% of total awards
8) 10 Nos tree affected due to withdrawal of tree
felling permission by DFO letter no. 251, Dt-
04.06.2019

Page 1 of 2
Details of the site to which vacant access and right of way to the contractor is not available.

Chainage

Length as on
S No. Side Details land status and site obstructions
01.08.2019
From To

1) Missing plots 2635 and additional 0.158 Ha land


to be acquired for plot no. 2639for which 3A yet to
be done.
2) Award for land not done due to mismatch of
nature of land in 3D between Hindi and English-
1805, 1800, 1791, 1783, 1782, 1781, 1780, 1763,
1673, 2638, 2156, 2149, 1815, 1814, 1813, 125, 140,
155, 156, 157, 1576, 2893, 1594, 2319, 2323, 2324,
2325, 2327 at Gidha
3) 6 nos religious structures for which estimates yet
to be approved at Gidha
4) Structure no. 128, 129, 132, 144, 162, 182, 189,
190, 191, 192, 193, 195, 196 yet to be approved due
4 112+020 112+400 BHS 380 to mismatch o plot number with 3D at Gidha
5) Approval of building valuation penidng for plot
no. 1768, 1769, 1777, 1780, 1675, 1819 of Gidha
6) Out of 79 structures, compensation of only 5 nos
structures has been disbursed.
7) Total disbursement is 31.69% of total approved
awards
8) Trees are affected through out the stretch due to
withdrawal of tree felling permission by DFO letter
no. 251, Dt-04.06.2019
9) Electrical utility can not be shifted due to non
payment of Structures and land also.

1) Missing plots 1158, 1173, 1175, 1176, 1177, 1178,


1181, 1182, 1184, 1592, 1604, 1606, 1613, 1633,
1637, 1655, 1674, 1681, 1687, 1688, 1689, 1692,
1693 (Shobhi Dumra) and 1228, 1230, 1371/1720,
6 116+280 117+350 BHS 1070 1374, 1386, 1402, 1419, 1423, 1464, 1467, 1485,
1532, 1537, 1542, 1546, 1547, 1706 (Sarangpur) for
which 3G yet to be done.
2) Disbursement of Shobhi Dumra is 70.86% and
Sarangpur is 78.22%.

As per 3(D) notification dated 16.05.2019 the area


118+280 119+900 BHS 1620 notified 5.4 decimal instead of 35 decimal for khasra
number 225 of Ratandularpur in Ara Bypass

1) Missing plots 479, 480 (Bishunpura) for which 3G


yet to be done.
2) Missing plots . 40, 37, 36 of Bampali for which 3A
yet to be published
3) Award for land not done due to mismatch of
nature of land in 3D between Hindi and English-485,
7 122+600 129+950 BHS 7350 490, 493, 430, 401, 336, 486 of Bisunpura
4) Out of 40 nos structures 4 nos structures yet to be
approved due to mismatch o plot number with 3D at
Bisunpura.
5) Disbursement of Structures done for only 4 nos
structures (Bisunpura)
6) Disbursement of Bisunpura mouza is 32.47%

Total Land (m) 19340

Page 2 of 2