Sunteți pe pagina 1din 3

SPEC.

DOC February 27, 2019


Technical Specifications Page 1 of 3

Project : PROPOSED CONSTRUCTION OF POWER HOUSE


Project Owner : DSWD FO IV A
Location : BRGY BUROL II, DASMARINAS , CAVITE
Date : FEBRUARY 27, 2019

TECHNICAL SPECIFICATIONS

SECTION 0001

INTRODUCTION

The Drawings and the Technical Specifications are complementary to each other. Drawings are graphic means of
showing work to be done. They are particularly suited to showing where materials are located. Thus, drawings exist
essentially to show dimension, location and placement. Not all works however, can be presented in the drawings.
Generalized works are usually in statement form, and hence the Contractor is required to read the specifications
carefully.

Specifications, on the other hand, are used to describe the materials, construction techniques, samples, shop
drawings, guarantees, and other contract requirements. Together, the drawings and the specifications are used to
inform the Contractor. In cases where the specified brand carries with it the manufacturer's specifications, the
manufacturer's specifications shall hold precedence over these specifications.

The specification herein is presented in the form of Summary of Materials and Finishes which indicates in a concise
form the scope of work and materials for the project, as well as mentioning in a general way the location or
placement of construction elements within the project. As a general guide and in the spirit for which the working
specifications are prepared, works and materials necessary for the project, and which may, or may not be, included
herein are expected to conform with sound construction procedures, and especially as per the minimum requirement
of traditional and established institutes, societies, or associations for specific materials and work trades, and as per
the procedures proposed by pertinent governmental construction bodies whenever applicable.

THE LANGUAGE OF THE SPECIFICATIONS

The Technical Specifications are of the abbreviated type and include incomplete sentences.

The selection of sentence structure depends on the underlying principles of Specifications:

a. That the Technical Specifications are only one part of the Contract Documents;

b. That the Contract is between the Owner and the General Contractor; and,

c. That the General Contractor is the only party responsible for completing the work in accordance with the
Contract Documents.
SPEC.DOC February 27, 2019
Technical Specifications Page 2 of 3

SECTION 0002

SUMMARY OF MATERIALS & FINISHES

PART 1 GENERAL

1.01 All applicable provisions of the different divisions of the Specifications for each work trade shall apply for all
items cited in this Summary.

1.02 Materials specifically mentioned in this Summary shall be installed following efficient and sound
Engineering and Construction practice, and ESPECIALLY AS PER MANUFACTURER'S INSTRUCTIONS AND
SPECIFICATIONS FOR INSTALLATION, WHICH SHALL GOVERN ALL WORKS ALLUDED TO IN THESE
SPECIFICATIONS.

1.03 Materials and finishes for on-site improvement and facilities as listed below are part of the scope of work
and shall be supplied and installed by the Contractor without extra cost to the Owner.

a. Clearing and demolition works in preparation for construction

b. Topsoil stripping and stockpiling prior to excavation and filling, for re-use on planting areas

c. Demobilization, including hauling of debris, obstructions and other unusable materials from
construction area to designated disposal sites

d. Exterior utility lines, raceway system, fixtures, switches, buzzers of controls at their terminals, and
including fittings and accessories as required by the specialty trades under plumbing and electrical works

1.04 Off-site improvements shall generally be under the responsibility of the Contractor, the following shall be
part of the Contractor's work:

a. Concreting of driveway and transitional elements between existing and new walks and
driveways. This work shall make connections neatly with the existing roads or curbs and shall incorporate necessary
utility ways under such as required.

b. Permanent connections to the local utility lines for electrical, water, drainage, and telephone lines
including equipment, facilities, material, and/or work which utility companies or authorities may require
of the applicant owner, such as electrical transformers, meters, etc.
SPEC.DOC February 27, 2019
Technical Specifications Page 3 of 3

PART 2 DIVISION OF WORK

2.01 ELECTRICAL WORKS

The electrical installation shall be done in accordance with the approved plans and under the direct
supervision and control of a Professional Electrical Engineer and or Registered Electrical Engineer.
All electrical works and materials shall conform to the provisions of the latest edition of the Philippine National Electrical
Code.
The electrical wiring shall be installed through PVC electrical conduit, fittings and appurtenances that conform to ISO
dimensions.
The type of electrical services to be supplied to the building shall be 240W, AC single phase or three phase.
There shall only one service to be dropped from the nearest or local electrical company pole for the proposed building.
Electrical lightings shall be fluorescent lamp with mirrorized diffuser, lamp post at the roofdeck and
downlights/covelights at hallways. Electric wires for light and power shall not be smaller than 3.5sqmm (No.12), 600V
insulation.
Electrical materials to be used for the electrical installation shall be as follows:
Automation Circuit Breaker Flush
Wall Switches, Convenience - GE Brand or Approved Equal
Wires and Conductors - Columbia brand or Approved Equal

NOTE: All additional activities which is not indicated or specified on the plan but related to the
Scope of Works to complete the projects shall be done by the Contractor without any additional
cost to the DSWD FO IV A.

Prepared by:

Engr. EDGARDO H. LIGAS


Electrical Engineer
PRC No. 1936
PTR NO. 7323774 C
Date Issued: January 1, 2019
Place Issued: Quezon City
TIN: 190-533-271