Sunteți pe pagina 1din 4

PROGRESS MONITORING C

Master Tiles Pvt. Ltd.

DATE: Tuesday, July 23, 2019 START DATE Wednesday, August 08, 201

Conveyor Belting Systems for Ba

S. NO. SCOPE WEIGHTAGE %AGE PROGRESS IN SCOPE

A ENGINEERING 10 100.00
B PROCUREMENT 25 98.00
C CONSTRUCTION 50 57.50
D COMMISSIONING 15 0.00

TOTAL WEIGHTAGE 100

A. ENGINEERING

WEIGHTAGE
S. NO. ACTIVITIES MONITORING UNIT
%AGE
1 Civil JOB 20
2 Electrical JOB 40
3 Mechanical JOB 40

TOTAL WEIGHTAGE 100


B. PROCUREMENT

WEIGHTAGE
S. NO. ACTIVITIES MONITORING UNIT
%AGE

1 Procurement of Drive Units/Gear Motor JOB 10


2 Procurement of Variable Frequency Drive JOB 10
3 Procurement of Conveyor Belt JOB 10
4 Procurement of Pulley Lagging JOB 5
5 Procurement of Mechanical accessories JOB 55
6 Procurement of Electrical accessories JOB 10

TOTAL WEIGHTAGE 100


C. CONSTRUCTION

WEIGHTAGE
S. NO. ACTIVITIES MONITORING UNIT
%AGE
WEIGHTAGE
S. NO. ACTIVITIES MONITORING UNIT
%AGE

1 Fabrication of Rollers JOB 5


2 Fabrication of Pulleys JOB 15
3 Fabrication of Frames and Troughing Sets JOB 10
4 Fabrication of Chutes JOB 5
5 Fabricartion of Conveyor Structure JOB 50
6 Fabrication of Vibrating Feeder Box JOB 5
7 Fabrication of Electric Panel JOB 10

TOTAL WEIGHTAGE 100


D. COMMISSIONING

WEIGHTAGE
S. NO. ACTIVITIES MONITORING UNIT
%AGE

1 Commissioning (Mechanical) JOB 20


2 Commissioning (Electrical) JOB 80

TOTAL WEIGHTAGE 100


ESS MONITORING CHART
Master Tiles Pvt. Ltd.

Wednesday, August 08, 2018 COMPLETION DATE

or Belting Systems for Ball Mill

WEIGHTED
%AGE PROGRESS IN SCOPE PROGRESS
%AGE

100.00 10.00
98.00 24.50
57.50 28.75
0.00 0.00

OVER ALL PROGRESS 63.25

% COMPLETION
REMARKS
ACTIVITY PROJECT
100.00 20.00 Completed
100.00 40.00 Completed
100.00 40.00 Completed

OVER ALL PROGRESS 100.000

% COMPLETION
REMARKS
ACTIVITY PROJECT
100.00 10.00 Completed
100.00 10.00 Completed
100.00 10.00 Completed
100.00 5.00 Completed
100.00 55.00 Completed
80.00 8.00 Procurement is in progress

OVER ALL PROGRESS 98.000

% COMPLETION
REMARKS
% COMPLETION
REMARKS
ACTIVITY PROJECT
100.00 5.00 Compeletd
100.00 15.00 Compeletd
100.00 10.00 Compeletd
0.00 0.00 Material is procured
35.00 17.50 In Progress
0.00 0.00 Not yet started
100.00 10.00 In Progress

OVER ALL PROGRESS 57.500

% COMPLETION
REMARKS
ACTIVITY PROJECT
0.00 0.00
0.00 0.00

OVER ALL PROGRESS 0.000