Sunteți pe pagina 1din 1

Out-of-Phase High-Voltage Switching

AN AIEE C O M M I T T E E REPORT

T H E I N I T I A L O B J E C T I V E of this A I E E Joint Sub­


committee was to collect information on the frequency
and severity of out-of-phase high-voltage switching
receives not only a piece of equipment but guaranteed
performance. Generally it is recognized that there is
some margin of safety in performance; different for
operations and then to decide if further action was justified. different circuit breakers and for different conditions. If
It was felt that the Committeemembers, through their it is necessary to utilize some or all of this margin it would
business and committee affiliations, would be in a position obviously be the user's privilege and responsibility to d o so.
to give a reasonably representative picture o f high-voltage Because of the wide variety of circuit breakers and operat­
out-of-phase switching troubles; therefore, as a first step ing conditions, the manufacturers could not b e expected
a questionnaire was sent out to the Committee members to furnish generally applicable information but may be
on June 15, 1948. It was hoped that sufficient material consulted in each individual case. Attention is called to
could be obtained this way and that the industry in general the present trend to use circuit breakers with lower basic
could be spared another questionnaire. impulse insulation levels on effectively grounded systems,
T h e replies indicated relatively few difficulties. G e n ­ and the possibility that this method of reducing circuit-
eral conditions considered were: out-of-phase closing, breaker costs may in some cases conflict with the desire to
out-of-phase opening, and out-of-phase reclosing. obtain a margin for out-of-phase switching.
T h e total number of cases of out-of-phase switching Another promising method o f attack is the judicious
actually reported are eight, four of them from one c o m ­ application of high-speed relaying, preferably in con­
pany, although it is known that more cases have occurred. junction with 3- or 5-cycle circuit breakers. This means
In every case reported the circuit breaker cleared the a complete investigation of each individual case and is
fault even if it was damaged. Damage has been reported very likely to give the desired results, but such investigations
to interrupting-element parts and to a contact-bridging are outside the scope of this Committee.
resistor. In most cases the damage has not been serious Cases reporting the closing of a circuit breaker with the
enough to prevent return to service. two sides out-of-phase indicate that more vigilance in
T h e information received from the Committee members operation and a closer check of synchronizing equipment
includes not only the experience within their own c o m ­ would eliminate some of the problems.
panies but also the knowledge gained from discussions with System design and operating setup may be arranged
others and review of pertinent papers, such as ' T o w e r to minimize the probability and effect of out-of-phase
System Stability Requirements Determined by A-C Cal­ troubles. One system is built in such a manner that it
culating Board Study, and Operating Performance Proved can be automatically or manually separated at one point
b y Staged Fault Tests." 1
Therefore, it is felt that the by a predetermined group of switching operations. A plug
survey represents a large proportion of the industry. board is constantly arranged to trip any desired group of
There is no doubt that high-voltage out-of-phase switch­ circuit breakers in the event of instability. By constantly
ing presents a definite problem, but the indications are supervising this board the load dispatcher can be sure that
that in many cases a solution has been found. when a separation is made he will have as nearly as possible
T h e only generally applicable remedy would be to use an equitable distribution of load and generation. T h e
circuit breakers adequate and guaranteed to perform at general trend in system growth and interconnections is
twice normal voltage under all conditions. This would gradually increasing system stability and reducing the
obviously increase circuit-breaker size and cost. causes of out-of-phase switching trouble.
T h e impression gained from the survey is that the cost A generally applicable solution cannot be justified
o f the damage on the surveyed systems is much less than economically on the basis of the information obtained by
the cost of using circuit breakers adequate for twice normal this Committee. Each individual case requires a thorough
voltage. It does not appear appropriate to have general and special investigation to find the most satisfactory
circuit-breaker applications bear the burden of increased economical solution. This is beyond the scope of this
circuit-breaker size and cost, but there may be cases where Committee, but in addition to the general suggestions in
the use of a higher voltage circuit breaker would be justified. this report the circuit-breaker manufacturers are urged
A n investigation of the type made by this Committee is to continue their efforts to find economically applicable
obliged to consider the over-all picture, and there would means of increasing the chances of circuit breakers per­
be cases in disagreement with the general conclusion. forming satisfactorily under abnormal system conditions.
W h e n the manufacturer sells a circuit breaker, the user
REFERENCE
Essentially full text of the final report of the AIEE Joint Subcommittee on "Out-of- 1. Power System Stability Requirements Determined by A-C Calculating Board Study,
Phase High-Voltage Switching." Members of the committee were: K. J. Falck, and Operating Performance Proved by Staged Fault Tests, W. A. Morgan, Byron
Ckaimam; R. M . Fenill, G. D. Floyd, I. W. Gross, E. L. Harder, M. H. Hobbs, C. B. Evans. Internadonai Conference on I>arge Electric High-Tcnsion Systems (Paris,
Kelley, Cart Loweriaon, H. V. Nye, and B. W. Wyman. France), July 1948.

60 Out-of-Phase High-Voltage Switching ELECTRICAL ENGINEERING

S-ar putea să vă placă și