Documente Academic
Documente Profesional
Documente Cultură
Abstract- Gas Insulated Switchgear Substation (GIS Substation) easy installation, maintenance and commissioning. GIS
has high reliability, easy maintenance, less area requirement etc. requires approximately 10% of the area of the conventional
Due to this, it has found wide range of application in power AIS.
system sector over last few decades. But the unique problem with
GIS substation is generation and propagation of very fast Despite these advantages, the GIS has its own unique
transient overvoltage (VFTO) due to switching operation of problems. These problems include generation of very fast
circuit breaker, disconnector switches or due to earth faults. The transient overvoltage (VFTO). VFTO’s are generated during
generated VFTO causes stress on the insulation of equipment’s switching operations of circuit breaker and disconnetor switch
like power transformer, bushings, spacers etc. connected to the within GIS. These VFTO generated have a very short rise time
GIS. The origin of VFTO, its propagation and impacts on GIS
and followed by oscillations having high frequencies. The
have been discussed in this paper. In this paper the components
of 132 kV GIS substation is modelled more accurately and
range of short rise time is of 4-100ns [1]. According to IEC
considered for simulation. Electromagnetic Transient Program standard VFTO belongs to the category of highest range of
(EMTP-RV) software is used for the simulation for various frequencies (30kHz to 100MHz).
switching condition. The variation in VFTO magnitude along the
VFTO has detrimental impacts on equipment connected in
GIS bus nodes for different magnitudes of trapped charge has
been studied. The VFTO peak along the GIS bus nodes during
substation and causes undesired effect on high voltage
circuit breaker operation and disconnector operation is equipment such as power transformer, which is the most
compared. The results show that VFTO magnitudes are higher important asset in substation. As dominant frequencies of
along the GIS bus nodes in case of circuit breaker operation as VFTO are in the range of few megahertz, they may coincide
compared to disconnector switch operation. The results also show with the natural frequency of power transformer connected to
that the increase of trapped charge on the line increases the a GIS and may cause internal resonance within the power
VFTO levels. transformer winding resulting in possible catastrophic damage
Keywords- EMTP-RV, VFTO, GIS Substation, Trapped Charge. to the power transformer.
In this paper, the VFTO at various locations in Gas Insulated
Substation for various switching operations is estimated. Also
I. INTRODUCTION the VFTO magnitude for circuit breaker operations in
In past few decades there has been a growing demand comparison with disconnector switching operation is
for installing gas insulated substation (GIS), due to several investigated. The effect of different magnitude of trapped
advantages over conventional air insulated substation(AIS). charge on the VFTO magnitude is studied.
Some advantages are higher personal and operational safety,
(E/P)0= breakdown field strength In aboce equations, ‘a’is the HV bus diameter and ‘b’ is the
inner diameter of the GIS enclosure, C is Capacitance and L is
p= gas pressure. Inductance. According to IEC 62271-4, velocity ‘v’has
value0.95times that of speed of light.
kt=Toepler spark constant
B. Modelling of Power Transformer
Capacitance of
Circuit breaker In Open Position theswitching
contactstowards
the ground
isconsidered.
In Closed Position
Transmission line
withdistributed
parameters.
Capacitance of
In Open Position (a)
theswitching
Disconnector switch contactstowards
the ground is
considered.
Lumped
Capacitance
towards the
Potential transformer
ground.
Lumped
Capacitance (b)
Spacer towards the
ground.
REFRENCES