January 18, 2019

FOR : ENGR. C’ZAR M. SULAIK


DEPUTY ADMINISTRATOR
FOR ENGINEERING & OPERATIONS
This Agency

FROM : PRECIOUS LEIRAE E. PALACOL


HERSON FELIX C. HULIGANGA
Systems Management Division – Operations Department
Same Agency

SUBJECT : BACK TO OFFICE REPORT OF NIA – REGION 3

Submitted herewith is the back to office report with the field / ocular inspection conducted in connection with
the implementation of ongoing projects conducted on December 3-7, 2018.

BACKGROUND

The field visit and validation was conducted to monitor the progress of works of the ongoing projects at NIA –
Region III in the provinces of Pampanga, Bataan, Bulacan, Nueva Ecija, and Tarlac respectively, which
contributes to the performance of the Agency.

As per Online Inventory of November 2018, Region III has an Operations monitored projects physical
accomplishment of 99.67%, 88.37%, and 60.54% for CY 2016, 2017 and 2018, respectively.

SMD – staffs arrived at NIA – Region III, Tambubong, San Rafael, Bulacan on December 3, 2018 and
proceeded to the Engineering and Operations Manager, Engr. Virgilio J. Ilao.

As per the Operations & Maintenance aspect of NIA – Region III, the following were the findings and
observations of this Office which were addressed to the Regional Office and IMOs.

NAME OF SYSTEM FINDINGS/OBSERVATIONS REMARKS


1. TASMORIS/TARRIS, Tarlac FUSA – 14,879 hectares while Accordingly, it was programmed
City, Tarlac Irrigated area Dry – 4,007.33; more than 14,000 hectares for dry &
Wet – 4,372.22. wet seasons but during Mount
Pinatubo volcanic eruption of past
year of 1991 discharged ash flows
caused by lahars that silted in
1
irrigation canals, the programmed
area was 0 hectare then gradually
restored the operational area of
TASMORIS/TARRIS area to
maintain its FUSA. And by using
pump motor to irrigate the land, the
areas for wet & dry seasons
remained the same while waiting for
the completion of BBMP to benefit
the area with the said gap of more
than 10,000 hectares.
2. PDRIS, Arayat, Pampanga FUSA – 9,978 hectares while As per FUSA of PDRIS areas, the
Irrigated Area Wet – 3,623.95 municipalities of San Luis and
Candaba, Pampanga utilized
irrigation water for fishponds and
also the inundation of PDRIS service
areas caused by the convergence of
volume of river flows coming from
Rio Chico, Peñaranda and Abacan
rivers that were decline in the
irrigated area during wet season
compared to dry season.

Herewith are the projects validated / inspected:

TABLE 1
PROJECTS SELECTED FOR FIELD INSPECTION/VALIDATION
FUND CY
NAME OF PROJECT LOCATION ALLOCATION
SOURCE BUDGET
1. AMRIS, Lateral J Bulacan RRENIS 2016 10,000,000
2. AMRIS, After Bay Bulacan RRENIS 2017 30,000,000
3. Maronquillo PIS Bulacan RRECIS 2017 7,000,000
4. Pampanga Delta RIS San Luis # 2 Pampanga RRENIS 2017 5,000,000
5. Pugo PIS/Casongsong PIS Nueva Ecija RGPIS 2017 7,000,000

Please refer to attach documents for details.

ACTION TAKEN

As per exit conference, the Central Office personnel had emphasized to the Regional Office the commitment
to complete the carry over projects on or before December 2018. The Central Office personnel reminded the
Office to monitor / check previous submitted accomplishment report for counter checking of latest report.
Monthly accomplishment report submitted to the Regional Office by the IMO should tally with the actual
accomplishment of said projects and online inventory. The Regional Office was also reminded that the Online
Physical Accomplishment will prevail even the Office submits a hard copy report through the SMD – OD Office.
It was advised that all agreements, meetings between NIA, contractors, Irrigators Associations should all be
documented for perusal and references. It was also reminded by the Central Office personnel that Regional
Office monitor and check the encoding of physical accomplishment against the financial accomplishment
inputted by the IMO staffs.
2
REMARKS

Based on the status report as of November 30, 2018 for project implementation of Region 3 under GAA Local
Funds CY 2017 (see “Annex”), the overall physical accomplishment for Operations Department – SMD
monitored project was 88.37% comprising of different funding sources. Percentages (%) of areas for physical
accomplishment were as follows: 133.64% for new area in terms of hectares; 83.26% for restored area;
136.57% & 146.68% for canals and canal lining in terms of kilometers and 156.60% for structures in terms of
number per unit. The remaining 11.63% for physical accomplishment of project implementation were all
targeted to be completed by the end of 4 th quarter of CY 2018 based on the catch-up plan commitment by
Regional Office 3.

With regards to O & M activities, Region 3 Irrigation Management Offices (IMOs) have complied on a monthly
basis the submission of reports for the operation and maintenance of irrigation/drainage facilities of National
Irrigation Systems (NIS) as per MC No. 55 series of 2014.

RECOMMENDATIONS

It is recommended to strengthen the regular feedback / communication between the Central Office and
Regional Office / Field Office in the monitoring and evaluation of projects in order to be properly updated of
project issues and concerns and come up with immediate actions to address such.

PREPARED BY:

PRECIOUS LEIRAE E. PALACOL HERSON FELIX C. HULIGANGA


Senior Engineer A Senior Materials Inspector

NOTED BY:

ELISA C. RAGUDO DELSY J. REVELLAME


Acting Manager Acting Manager
Systems Management Division Operations Department

C’ZAR M. SULAIK
Deputy Administrator for
Engineering and Operations

3
AMRIS, Lateral J, Pulilan, Bulacan

Project Cost: P 10,000,000.00


Fund Source: CY 2016 RRENIS
Physical Accomplishment (November 2018) – Online Accomplishment
Actual: 75 %

Findings / Observations:
1. It was observed during field visit / validation that remaining activities of work is 200 meters vertical
canal lining @ Station 6 + 400 – 6 + 600.
2. It was committed to be completed on or before December 31, 2018.

AMRIS, Slope Protection (Baywalk), San Rafael, Bulacan

Project Cost: P 30,000,000.00


Fund Source: CY 2017 RRENIS
Physical Accomplishment (November 2018)
Actual: 75 %

Findings / Observations:
1. For slope protection works (upstream San Rafael side), on-going concreting @ Sta. 1 + 300 – 1 +
500 of about 200 meters in length.
2. For remaining activities to wit: supply and installation of gabion boxes and mattresses; laying-in of
steel sheet pile and installation of railings.
3. The target date of completion of said project is on the 1st quarter of January 2019.

MARONQUILLO PIS, San Rafael, Bulacan

Project Cost: P 7,000,000.00


Fund Source: CY 2017 RRECIS
Physical Accomplishment (November 2018)
Actual: 40 %

FINDINGS/OBSERVATIONS:
1. For engine and pump house facilities, construction works was already completed.
2. For canal lining, concreting of cut & cover canal @ Sta. 0 + 000 – 585 of about 585 meters in
length was also completed.
3. Remaining activities, laying-in of 36 inches diameter RCP of about 150 meters in length.
4. The said project was committed to be completed on or before 4th week of January 2019.

PAMPANGA DELTA RIS, SAN LUIS # 2, San Luis, Pampanga

Project Cost: P 5,000,000.00


Fund Source: CY 2017
Physical Accomplishment (November 2018)
Actual: 85 %
4
FINDINGS/OBSERVATIONS:
1. For canal lining, construction of Class “B’ vertical canal lining @ Sta. 0 + 000 – 0 + 600 of about
600 meters in length was already completed.
2. Remaining activities, canal lining of about 100 meters in length.
3. It was observed that the canal lining has no backfill which may cause weakening on the sides of
the canal.
4. The said project was committed to be completed on or before January 2019.

PUGO PIS/CASONGSONG PIS, Cuyapo, Nueva Ecija

Project Cost: P 7,000,000.00


Fund Source: CY 2017 RGPIS
Physical Accomplishment (November 2018)
Actual: 70 %

FINDINGS/OBSERVATIONS:
1. For the engine and pump house, on-going fabrication for steel frame of said pump house; for
canal lining, on-going construction @ Sta. 0 + 500 – 0 + 700 of about 200 meters length.
2. Remaining works, supply of engine and groundwater rotary pump.
3. The commitment of completion of said project is on or before 1st quarter of CY 2019.

SUMMARY/GENERAL RECOMMENDATIONS:
1. Fast-track implementation and completion of said projects to assure essential and sufficient
supply of water.
2. Close monitoring and supervision of the implementation of major activities as indicated in the
Program of Work (POW), plans, and lay-out by the In-Charge Project Engineer to assure the
quality and workmanship of accomplishments.
3. The RIO, IMO and the Contractor should be initiated a weekly regular meeting with regards to the
progress of said project in terms of physical and financial accomplishment.
4. The percentage slippages of project implementation for physical accomplishment were delayed
due to the schedule of water delivery for farming activities during wet season.
5. For additional item in the masterlist of activities, backfilling along both sides of canal lining should
be included for the protection of stability of canal structure.

CONG DADONG DAM

Arayat, Pampanga

As per attached memorandum dated September 3, 2018 form NIA Regional Office 3, RIM Josephine
B. Salazar, the final report for the conduct of geo-technical and structural assessment of PDRIS-Cong Dadong
Dam, the causes of crack at piers/gap of bridge girder due to heat of hydration. For the Alkali-Silica-Reaction
(ASR), there are no laboratory test and chemical analysis conducted to conclude the cause of cracks. For
shrinkage stresses due to heat hydration there are no cracks analysis.

In view of this, we also observed that the presence of gap of bridge girder (seismic joint) @ pier 4 as
shown in the photo. Therefore, we also recommended for the conduct of laboratory test and stress analysis.
5
PHOTOS:

CY 2016 Angat RIS (AMRIS), Lat. J, Pulilan, Bulacan

On-going construction of Class “B” concrete vertical canal lining @ Sta. 5 + 800 - 5 + 900 & Sta. 6 + 500 – 6 +
600

6
CY 2017 Angat RIS (AMRIS), Lat. D-1/D-1-D/D-1-A, Apalit, Pampanga

Completed on Class “B” concrete trapezoidal canal lining @ Sta. 0 + 500 – 0 + 600

7
CY 2017 Angat-Maasim RIS (Baywalk), San Rafael, Bulacan

On-going construction of slope protection wall in San Rafael Side (upstream portion) @ Sta. 1 + 300 – 1 + 400

8
CY 2017 Maronquillo PIS, San Rafael, Bulacan

Completed on construction of pump house & supply of vertical turbine pump & Right Angle Gear Drive
(RAGD); on-going installation of 36” diameter RC pipes @ Sta. 0 + 300 – 0 + 400

9
CY 2017 Pampanga Delta RIS San Luis #2, San Luis, Pampanga

On-going construction of Class “B” concrete vertical canal lining @ Sta. 0 + 500 – 0 + 600

10
CY 2018 Batol CIP, Samal, Bataan

On-going construction of Diversion Dam @ Sta. 0 + 000

11
CYs 2017 & 2018 Bernabe CIS, Balanga, Bataan

On-going construction of access road On-going fabrication of steel frame for concrete
canal lining

12
CY 2017 Pugo PIS/Casongsong PIS (GP – 85), Bantug, Cuyapo, Nueva Ecija

On-going construction of pump house On-going construction of Class “B” vertical


canal lining @ Sta. 0 + 200 – 0 + 300

13
TARRIS/TASMORIS Dam, Tarlac City, Tarlac

TARRIS Ogee type dam with two (2) sluice gate and intake opening right side

TASMORIS Ogee type dam with two (2) sluice gate

14
Cong Dadong Dam, Arayat, Pampanga

Pampanga Delta RIS general lay-out plan/map

Dam’s control room/automatic steel gates

15
Cong Dadong Dam, Arayat, Pampanga

Gap of bridge girder (seismic joint) @ Pier 3 was wider than of bridge girder @ Pier 4

Downstream portion of the river/left main canal of the dam