Sunteți pe pagina 1din 45

ZHENGDA CORPORATION

SUMMARY OF OUTSTANDINGS (PRIME STRUCTURES)


Updated: 10/23/2019

Ref: item no
Prime Structures
Item Description Location On-site Progress from RTO
(comments/target date) Report

Painting & matching colors


1 between Archi fin supports and adjacent "Painting done." ref: no.4/7
colors of Arch.

Painting & matching colors


2 Level 2 to 7 "Done." ref: no.52
platform and adjacent matt grey color

Cleaning & painting/matching colors


3 level 7 "Done." ref: no 15/16
hollow sections and adjacent paint

Cleaning & painting/matching colors ref: no


4 Level 2 "Done."
hollow sections and adjacent paint 17/18/19

5 Cleaning & painting/matching colors Level 3 "Done." ref: no 25/27


hollow sections and adjacent paint

Cleaning & painting/matching colors


6 Level 4 "Done." ref: no 28
hollow sections and adjacent paint

Cleaning & painting/matching colors


7 Level 5 "Done." ref: no 30
hollow sections and adjacent paint

Cleaning & painting/matching colors


8 Level 6 "Done." ref: no 32
hollow sections and adjacent paint

Cleaning & painting/matching colors


9 Level 7 "Done." ref: no 34/35
hollow sections and adjacent paint

Gaps
10 "We will seal with sealant 2/7/2019." ref: no 6
between Aluminium Fins

Gaps
between Aluminium Box up and glass "Water proofing membrane done, termination
11 ref: no 21
railing to make good, to sealed off, no panel expected to complete by 04/07/19."
water ingress in the future.

"We will insert with Aluminium U channel to glass


Gaps
12 and to seal with sealant in between wall and U ref: no 41
on glass wall and concrete precast wall channel. Expect to be complete by 02/07/19."
ZHENGDA CORPORATION
SUMMARY OF OUTSTANDINGS (PRIME STRUCTURES)
Updated: 10/23/2019

Ref: item no
Prime Structures
Item Description Location On-site Progress from RTO
(comments/target date) Report

Level 4, Level 4 sky level "We had engage New Art to seal the gap between
Gaps ref: no 42/45
13 glass and sofit and expect to complete by
on ceiling and glass wall terrace 46/49
07/07/19."

Gaps "We had adjusted these bracket and seal with


14 ref: no 48
on ceiling and door sealant."

Gaps "Materials on site, start install by 22/6/2019 expect


15 ref: no 51
on floor and aluminium cladding to complete by 30/06/19."

Gaps
on glass railing and concrete, "Materials on site, start install by 22/6/2019 expect
16 ref: no 53
on glass facade and aluminium cladding to complete by 02/07/19."
box up

Gaps level 7 and all other


17 "Done." ref: no 38/43
to complete sealants. areas.

Broken Glass
18 Level 6 "Ordered, ETA mid July 2019." ref: no 9
to replace

Broken Glass ref: no 10/11


19 Level 1 & 2 "Ordered, ETA mid July 2019."
to replace 12

Brown spots ref: no 20/23


20 on Aluminium cladding at Architectural Level 2,3,4,5,6,7 "Done." 24/26/29/31
fins and at base of fins 33/36

Glass installed. Sealant Completed. Capping


21 Canopy glass installation. Canopy ref: no.1
installation target to complete 02/Jul/2019.
Firestop in between slab level and mail toilet and shower
22 ref: no.2/3
Façade wall to complete. room (L7)
"We cant push our ceiling up further due to M&E
23 Ceiling Level 4 ref: no 5
issues."
Red Triangular Sticker
24 Level 2 to 7 "Done and inspected." ref: no 8
to be placed in latches

Aluminium Box Alignment "Rectify works in progress expect to complete


25 ref: no 13
1 pc sticking out from the rest 07/07/19."

Vertical fins and Aluminium cladding


26 "Done." ref: no 14
to complete interfacing
ZHENGDA CORPORATION
SUMMARY OF OUTSTANDINGS (PRIME STRUCTURES)
Updated: 10/23/2019

Ref: item no
Prime Structures
Item Description Location On-site Progress from RTO
(comments/target date) Report

Fire Access Panel ref: no 20/23


27 to install properly, to complete water "PSB TUV water test on 21/06/19." 24/26/29/31
tightness test, to clean thoroughly 33/36

End Capping
28 Level 7 "Done." ref: no 37/39
to complete capping on cladding

Silver Tapes "Aluminium sheet materials ordered will deliver to


29 ref: no 40
to put in place properly site 27/06/19 expect to complete by 07/07/19."

Access Panel "The Inspection Hatch cover panel was push up and
30 to complete Level 4 left it inside ceiling. Hatch panel to stiffen with angle ref: no 44
before fix it back 01/07/2019."

Doors Installation
31 to complete Level 4, Terrace Door Installed. ref: no 47

Exposed Structural Support


structural support of aluminium cladding "We will cover it with panel, expect complete by
32 ref: no 50
need to make good 29/06/19."

Open End and Finisher


33 open end at canopy canopy ref AD: 133
Prepared By: Alfredo Claro -Archi. RTO
ZDC: Khin Khin Han Archi. Coordinator UPDATED ZDC ARCHITECTURAL OUTSTANDING WORKS AS AT 22 October 2019 244÷ 285 = 85.610% Accomplished

S/N Zhengda Before Photos Description After Rectification Photo - comments Ref AD Inspection Date Status Mr. Alfredo Mr. David
No. (acknowledgement) (acknowledgement)

TOILETS - change of the layout of the 5th, 6th


1 1 Toilet layout at L5, L6 and L7 and 7th storey toilets due to clash with the 47 C&S all completed C&S all completed
precast post tension strucutral elements (RFI-
ST-019)

2 1 AD no. 48 to 61 - C&S AD no. 48 to 61 - C&S 48-61 C&S all completed C&S all completed

Headroom shall not be less than 2.0. inspection completed:


3 1 Headrooms at Level 1 62 9/17/2019 17/09/2019

A handrail shall be provided on at least one inspection completed:


4 1 Handrail at Level 1 side of the flight of staircase. 62 8/6/2019 06/08/2019

All steps shall be fitted with non-slip nosing inspection completed:


5 1 steps at staircase 2 strip between 50mm and 65mm in width with 62 8/6/2019 06/08/2019: furhter
permant contrasting comment: paint to touch
up

Accessible individual washrooms shall be


equipped with two coat hooks mounted on a
side wall at two different heights of about
6 1 HDCP Toilet hooks 150mm and 1100mm from the floor. The 62 8/19/2019 inspection completed:
hooks shall not project more than 40mm from 19/08/2019
the wall.

7 1 HDCP Toilet Signs Signage at Handicapped toilets. 62 8/19/2019 inspection completed:


19/08/2019

8 1 coordination with New Arts coordination with New Arts


Prepared By: Alfredo Claro -Archi. RTO
ZDC: Khin Khin Han Archi. Coordinator UPDATED ZDC ARCHITECTURAL OUTSTANDING WORKS AS AT 22 October 2019 244÷ 285 = 85.610% Accomplished

S/N Zhengda Before Photos Description After Rectification Photo - comments Ref AD Inspection Date Status Mr. Alfredo Mr. David
No. (acknowledgement) (acknowledgement)

9 1 Ironmongery - door lock IRONMONGERY - M&E Riser besides Driveway 115 8/30/2019 inspection completed:
Door Lock damaged 30/08/2019

IRONMONGERY - M&E Riser Elect. inspection completed:


10 1 Ironmongery - door lock Riser besides driveway door lock damaged to 115 8/30/2019 30/08/2019
immediately be replaced.

IRONMONGERY - M&E Riser TEL. inspection completed:


11 1 Ironmongery - door lock Riser besides driveway door lock damaged to 115 8/30/2019 30/08/2019
immediately be replaced.

12 numbers of Tiles at Apron Slab just in fornt


12 1 Level 1 Apron Slab Tiles of Main Entrance Glass Wall, 12 numbers 115 9/23/2019 inspection completed:
oftiles chipped off Need to be replaced and 23/09/2019
make good.

inspection completed:
13 1 Level 1 Apron Slab Tiles Tile defect at Apron Slab need to be replaced. 115 9/23/2019 23/09/2019

Tiles at Apron Slab just in front of Main inspection completed:


14 1 Level 1 Apron Slab Tiles Entrance Glass Wall, CORNER of tiles chipped 115 9/23/2019
off need to be replaced and make good. 23/09/2019

Tiles at Apron Slab just in front of Main inspection completed:


15 1 Level 1 Apron Slab Tiles Entrance Glass Wall, CORNER of tiles chipped 115 9/23/2019
off need to be replaced and make good. 23/09/2019

Tiles at Apron Slab just in front of Main inspection completed:


16 1 Level 1 Apron Slab Tiles Entrance Glass Wall, CORNER of tiles chipped 115 9/23/2019
23/09/2019
off. Need to be replaced and make good.
Prepared By: Alfredo Claro -Archi. RTO
ZDC: Khin Khin Han Archi. Coordinator UPDATED ZDC ARCHITECTURAL OUTSTANDING WORKS AS AT 22 October 2019 244÷ 285 = 85.610% Accomplished

S/N Zhengda Before Photos Description After Rectification Photo - comments Ref AD Inspection Date Status Mr. Alfredo Mr. David
No. (acknowledgement) (acknowledgement)

17 1 Kung Chong Road - drainage gaps Big Gaps on drainage Grating at Kung Chong 115 9/18/2019 inspection completed :
Road 18/09/2019

inspection completed:
18 1 Level 1 - building perimeter drainage At Building perimeter drainage not properly 115 8/26/2019 26/08/2019
cleaned must have proper flow Furhter Comment: main
driveway need to clean

19 1 Draw Pit Cover - In front of DRAW PIT COVER RUSTY AT DRIVEWAY NEAR 115 9/10/2019 inspection completed:
Substation ELECTRICAL SUBSTATION. 10/09/2019

DRAINAGE GRILL COVER WELDING POINT inspection completed :


20 1 Drainage Grill Cover RUSTY, CEMENT TO MAKE GOOD 115 8/13/2019 13/08/2019

21 L1 - Driveway Tiles Oil stains on driveway tiles, need make good 115 preparing for inspection

22 1 L1 - Driveway Tiles CRACKED ON BLACK COLOR DRIVEWAY TILES 115 9/23/2019 inspection completed:
23/09/2019
Prepared By: Alfredo Claro -Archi. RTO
ZDC: Khin Khin Han Archi. Coordinator UPDATED ZDC ARCHITECTURAL OUTSTANDING WORKS AS AT 22 October 2019 244÷ 285 = 85.610% Accomplished

S/N Zhengda Before Photos Description After Rectification Photo - comments Ref AD Inspection Date Status Mr. Alfredo Mr. David
No. (acknowledgement) (acknowledgement)

23 1 L1 - Driveway Tiles CRACKED ON BLACK COLOR DRIVEWAY TILES 115 9/23/2019 inspection completed:
23/09/2019

DEEP SPOTS ON FLOOR SLAB, TROWEL


MARKS, PAINT AND OIL STAINS ON FLOOR inspection completed:
24 1 Floor Slab SLAB 115 10/21/2019 21/10/2019

25 1 Plaster cracks near hand rail base PLASTER CRACKS NEAR HAND RAIL BASE 115 9/10/2019 inspection completed:
NEAR SECURITY ROOM 10/09/2019

26 1 Level 1, Fire Fighiting Lobby 2 AT 1ST Floor Level FireFighting Lobby 2 Tile on 115 9/23/2019 inspection completed:
Wall need to make good 23/09/2019

27 1 Basement CRACKS ON PLASTERED WALL, WALL PAINT 115 8/30/2019 inspection completed:
TO MAKE GOOD 30/08/2019
Prepared By: Alfredo Claro -Archi. RTO
ZDC: Khin Khin Han Archi. Coordinator UPDATED ZDC ARCHITECTURAL OUTSTANDING WORKS AS AT 22 October 2019 244÷ 285 = 85.610% Accomplished

S/N Zhengda Before Photos Description After Rectification Photo - comments Ref AD Inspection Date Status Mr. Alfredo Mr. David
No. (acknowledgement) (acknowledgement)

Fire Exit Door at Basement level, door jamb inspection completed:


28 1 Basement, Fire Fighting Lobby 2 need to rectify make good, joints start to get 115 10/16/2019 16/10/2019
loose

At Fire Fighting Lobby 2 Basement Level, door inspection completed:


29 1 Basement, Fire Fighting Lobby 2 jamb need to rectify make good 115 10/16/2019 16/10/2019

At 3rd floor fire fighting lobby 1, Fire Exit door inspection completed:
30 1 Level 3, Fire Fighting Lobby 1 jamb need to rectify. 115 10/9/2019 09/10/2019

31 1 Level 4, Fire Fighting Lobby 1 At 4th floor fire fighting lobby 1, Fire Exit door 115 10/9/2019 inspection completed:
jamb need to rectify. 09/10/2019

32 1 Level 5, Fire Fighting Lobby 1 At 5th floor fire fighting lobby 1, Fire Exit door 115 10/9/2019 inspection completed:
jamb need to rectify. 09/10/2019

33 1 Level 6, Fire Fighting Lobby 1 At 6th floor fire fighting lobby 1, Fire Exit door 115 10/9/2019 inspection completed:
jamb need to rectify. 09/10/2019
Prepared By: Alfredo Claro -Archi. RTO
ZDC: Khin Khin Han Archi. Coordinator UPDATED ZDC ARCHITECTURAL OUTSTANDING WORKS AS AT 22 October 2019 244÷ 285 = 85.610% Accomplished

S/N Zhengda Before Photos Description After Rectification Photo - comments Ref AD Inspection Date Status Mr. Alfredo Mr. David
No. (acknowledgement) (acknowledgement)

34 1 Level 7, Fire Fighting Lobby 1 At 7th floor fire fighting lobby 1, Fire Exit door 115 10/9/2019 inspection completed:
jamb need to rectify. 09/10/2019

35 1 Level 4 - Lobby 1 door AT 4TH FLOOR FIRE EXIT DOOR LESS THAN 1 115 7/25/2019 inspection completed :
METER ALLOWABLE CLEARANCE 25/07/2019

AT 6TH FLOOR FIRE EXIT DOOR LESS THAN 1 inspection completed :


36 1 Level 6 - Lobby 1 door METER ALLOWABLE CLEARANCE 115 7/25/2019 25/07/2019

ARCHITECTURAL FINS HAVE BROWN inspection completed:


37 1 Architectural Fins at all floors COLOURED RUST ON ALL FLOOR LEVEL 115 9/3/2019 03/09/2019

FAÇADE GLASS FROM 2ND FLOOR TO UPPER inspection completed:


38 1 Façade Glasses at All floors ROOF LEVEL WALLS AND FRAMES NEED 115 10/12/2019
THOROUGH CLEANING 12/10/2019

inspection completed :
1 pc of Damaged decking at 4th floor sky 13/08/2019
39 1 Level 4 - landscape area terrace, Decking not properly cleaned all the 115 8/13/2019 Further comment: to
way.
clean decks and the whole
walkway.
Prepared By: Alfredo Claro -Archi. RTO
ZDC: Khin Khin Han Archi. Coordinator UPDATED ZDC ARCHITECTURAL OUTSTANDING WORKS AS AT 22 October 2019 244÷ 285 = 85.610% Accomplished

S/N Zhengda Before Photos Description After Rectification Photo - comments Ref AD Inspection Date Status Mr. Alfredo Mr. David
No. (acknowledgement) (acknowledgement)

4th FLOOR SKY TERRACE, INSECTS MILLIPEDES


CRAWLING AT SKY TERRACE AND CRAWL UP inspection completed:
40 1 Level 4 - landscape area TO 6TH FLOOR AND MILLIPEDES DOWN TO 115 9/23/2019 23/09/2019
3RD FLOOR

Prime structues works at 4th floor level inspection completed :


41 1 Level 4 - Prime Structure Works corner have big gaps. 115 7/25/2019 25/07/2019

42 1 Level 4 - Prime Structure Works Gap on glass wall and precast wall need to 115 7/25/2019 inspection completed :
make good 25/07/2019

43 1 Level 2 & 3 - silver tapes Aluminium Tape on Façade wall to make good 115 8/30/2019 inspection completed:
30/08/2019

inspection completed:
30/08/2019
44 1 Broken Glass at Level 1 (Hoy Fatt Broken façade glass on 1st floor high level 115 8/30/2019 further comment:
Road) need to be replaced (Hoy Fatt Road) Installed glass deviates
from previously approved
color of Façade.
Prepared By: Alfredo Claro -Archi. RTO
ZDC: Khin Khin Han Archi. Coordinator UPDATED ZDC ARCHITECTURAL OUTSTANDING WORKS AS AT 22 October 2019 244÷ 285 = 85.610% Accomplished

S/N Zhengda Before Photos Description After Rectification Photo - comments Ref AD Inspection Date Status Mr. Alfredo Mr. David
No. (acknowledgement) (acknowledgement)

inspection completed:
30/08/2019
45 1 Broken Glass at Level 1 (Kung Chong Broken façade glass on 1st floor high level 115 8/30/2019 further comment:
Road) need to be replaced (Kung Chong Road) Installed glass deviates
from previously approved
color of Façade.

46 1 Level 6, Fire Fighting Lobby 1 At 6th Floor Level painting at walls, ceiling 115 10/2/2019 inspection completd:
works to make good 02/10/2019

At 5th floor level fire exist door, painting to


make good, seethru panel to be properly
47 1 Level 5, Fire Fighting Lobby 2 cleaned, door handle paint to be cleaned, 115 10/16/2019 inspection completed:
16/10/2019
door jamb to be properly fixed, need to make
good

At 5th floor level fire fighting lobby 2 and at


48 1 Level 5, Fire Fighting Lobby 2 other floors, floor and wall tiles to be cleaned 115 10/16/2019 inspection completed:
of dirt, ceiling to make good, ceiling access 16/10/2019
panel to be cleaned of dirt.
Prepared By: Alfredo Claro -Archi. RTO
ZDC: Khin Khin Han Archi. Coordinator UPDATED ZDC ARCHITECTURAL OUTSTANDING WORKS AS AT 22 October 2019 244÷ 285 = 85.610% Accomplished

S/N Zhengda Before Photos Description After Rectification Photo - comments Ref AD Inspection Date Status Mr. Alfredo Mr. David
No. (acknowledgement) (acknowledgement)

At 5th floor level fire fighting lobby 2, stains


49 1 Level 5, Fire Fighting Lobby 2 on floor to be cleaned, door jamb to be fixed 115 10/16/2019 inspection completed:
properly. 16/10/2019

50 1 Level 5, Fire Fighting Lobby 2 At 5th floor level, fire fighting lobby 2, door 115 10/16/2019 inspection completed:
hinges paint stains to make good 16/10/2019

51 1 Level 5, Fire Fighting Lobby 2 At 5th floor level fire fighting lobby 2, door 115 10/16/2019 inspection completed:
jamb to make good 16/10/2019

At 5th floor level fire fighting lobby 2, door


52 1 Level 5, Fire Fighting Lobby 2 jamb rusty color coming out at the base of 115 10/16/2019 inspection completed:
door jamb and at sides 16/10/2019
Prepared By: Alfredo Claro -Archi. RTO
ZDC: Khin Khin Han Archi. Coordinator UPDATED ZDC ARCHITECTURAL OUTSTANDING WORKS AS AT 22 October 2019 244÷ 285 = 85.610% Accomplished

S/N Zhengda Before Photos Description After Rectification Photo - comments Ref AD Inspection Date Status Mr. Alfredo Mr. David
No. (acknowledgement) (acknowledgement)

At 5th floor level and at other floors, Fire


53 1 Level 5, Fire Fighting Lobby 2 Hose Reel and M&E door jamb to make good 115 10/16/2019 inspection completed:
gaps on dry wall and timber door jamb to be 16/10/2019
fixed properly.

54 1 Level 7 - Water Tank Room At 7th floor roof rusty color on pump room 115 10/21/2019 inspection completed:
gates/pump need to paint blue. 21/10/2019

At 6th floor level and at other floors fire


fighting lobby 1, gaps start to occur in dry wall inspection completed:
55 1 Level 6 - Lobby 1 door and door jambs, door to be fixed properly and 115 10/9/2019 09/10/2019
make good

At 6th floor level and at other floors fire


56 1 Level 6 - Lobby 1 door fighting lobby 1, gaps start to occur in dry wall 115 10/9/2019 inspection completed:
and door jambs, door to be fixed properly and 09/10/2019
make good

At 4th floor level and at other floors fire


fighting lobby 1, gaps start to occur in dry wall inspection completed:
57 1 Level 4 - Lobby 1 door and door jambs, doors to be fixed properly 115 10/9/2019
and make good.. 09/10/2019
Prepared By: Alfredo Claro -Archi. RTO
ZDC: Khin Khin Han Archi. Coordinator UPDATED ZDC ARCHITECTURAL OUTSTANDING WORKS AS AT 22 October 2019 244÷ 285 = 85.610% Accomplished

S/N Zhengda Before Photos Description After Rectification Photo - comments Ref AD Inspection Date Status Mr. Alfredo Mr. David
No. (acknowledgement) (acknowledgement)

58 Level 1 - Ceiling At 1st floor high ceiling need to make good 115

At FIRE FIGHTING LOBBY 1 and at other floors,


Ceilings M&E alignment - Fire ceiling to make good, dirt on ceiling,
59 1 alignment to make good, metal screws to 115 Under M&E inspections
Fighting Lobbies 1 match color of ceiling, to make good

60 1 Roof Foundation Plinths - plaster At roof level, plaster on foundation plinths 115 10/2/2019 inspection completed:
spalling spalling 02/10/2019

2nd to upper roof fin support cement mortars


61 1 Fin Support Cement Mortars - All to be cleaned, color to match color of 115 9/3/2019 inspection completed:
floors 03/09/2016
adjacent paint

62 1 Façade Glasses at All floors Façade glass needs thorough cleaning, 115 10/12/2019 inspection completed:
markings on frames need to clean on all floors 12/10/2019
Prepared By: Alfredo Claro -Archi. RTO
ZDC: Khin Khin Han Archi. Coordinator UPDATED ZDC ARCHITECTURAL OUTSTANDING WORKS AS AT 22 October 2019 244÷ 285 = 85.610% Accomplished

S/N Zhengda Before Photos Description After Rectification Photo - comments Ref AD Inspection Date Status Mr. Alfredo Mr. David
No. (acknowledgement) (acknowledgement)

At roof level, gaps on cladding support need inspection completed:


63 1 Roof - Prime Structure Works to do proper sealant. 115 9/17/2019 17/09/2019

Lift Motor Room - cement plaster At external wall of lift motor room, visible inspection completed:
64 1 cement plaster cracks facing west direction 115 10/2/2019
cracks 02/10/2019

At Fire Fighting Lobby 1 door, door jamb to be inspection completed:


65 1 Basement, Fire Fighting Lobby 1 rectified almost all floors 115 10/9/2019
09/10/2019

Survey marking lineson, the floor need to inspection completed:


66 1 Floor to make good - Level 1, 2, 3 clean, paint splashed on floors need to clean 115 10/21/2019
21/10/2019
prior to hand over to owner

Platform and Railing constructed by prime


Prime Structures Platforms - Kung structures, color to match on façade frame 1st inspection on Furhter comment: 80%
67 1 115 painting done. To remove
Chong Road color, safety latch on fins to put red triangular 06/08/2019 other paint color
sticker
Prepared By: Alfredo Claro -Archi. RTO
ZDC: Khin Khin Han Archi. Coordinator UPDATED ZDC ARCHITECTURAL OUTSTANDING WORKS AS AT 22 October 2019 244÷ 285 = 85.610% Accomplished

S/N Zhengda Before Photos Description After Rectification Photo - comments Ref AD Inspection Date Status Mr. Alfredo Mr. David
No. (acknowledgement) (acknowledgement)

At 3rd floor level wash bay area, floor screed


68 Washing Bay - Level 3 have many visible cracks might cause leak on 115 preparing for inspection
lower floor

Joints on driveway tiles and concrete ramp to


69 Concrete Ramp - driveway area make good. 115 preparing for inspection

Metal on Drawpit rusty inspection completed:


70 1 Draw Pit Metal 115 9/10/2019 10/09/2019

Cracks on apron slab, west side of the


71 1 Apron Slab building 115 10/21/2019 inspection completed:
21/10/2019

At 2nd floor level and at other floors, FIRE


72 1 Fire Fighting Lobbies 1 FIGHTING LOBBY 1, gaps start to occur in dry 115 10/9/2019 inspection completed:
wall and door jambs, doors to be fixed 09/10/2019
properly and make good

73 1 Level 4,5,6 - PVC pipes installation At Level 4,5,6 Elect PVC pipes installed higher 115 8/5/2019 inspection completed:
than required slab level 05/08/2019
Prepared By: Alfredo Claro -Archi. RTO
ZDC: Khin Khin Han Archi. Coordinator UPDATED ZDC ARCHITECTURAL OUTSTANDING WORKS AS AT 22 October 2019 244÷ 285 = 85.610% Accomplished

S/N Zhengda Before Photos Description After Rectification Photo - comments Ref AD Inspection Date Status Mr. Alfredo Mr. David
No. (acknowledgement) (acknowledgement)

At 2nd floor level and at other floors, FIRE


74 1 Fire Fighting Lobbies 1 FIGHTING LOBBY 1, gaps start to occur in dry 115 10/9/2019 inspection completed:
wall and door jambs, doors to be fixed 09/10/2019
properly and make good

Besides driveway area brickwall to concrete


75 1 Level 1 - Driveway Area column joint crack lines visible need to make 115 9/18/2019 inspection completed:
good. 18/09/2019

76 Canopy Glass Prime structures to complete canopy glass 116


installation

77 1 Architectural Fins at all floors Painting of Architectural Fin Supports should 116 8/30/2019 inspection completed:
match adjacent color of Arch. Fins 30/08/2019

78 1 Architectural Fins at all floors Painting of Architectural fin supports to match 116 8/30/2019 inspection completed:
adjacent material colour 30/08/2019

Red Triangular sticker pointing arrow down to


79 1 FMAP windows be in placed at latch so that fireman knows 116 8/5/2019 inspection completed:
where to open the screen in case of 5/08/2019
emergency (2nd to 7th floor level)

80 1 Level 6 - Prime Structures Glass At 6th floor level, broken glass need to be 116 9/3/2019 inspection completed:
replaced at near gate 2 at Kung Chong Road 03/09/2019
Prepared By: Alfredo Claro -Archi. RTO
ZDC: Khin Khin Han Archi. Coordinator UPDATED ZDC ARCHITECTURAL OUTSTANDING WORKS AS AT 22 October 2019 244÷ 285 = 85.610% Accomplished

S/N Zhengda Before Photos Description After Rectification Photo - comments Ref AD Inspection Date Status Mr. Alfredo Mr. David
No. (acknowledgement) (acknowledgement)

inspection completed:
At 1st floor high level broken glass need to be 30/08/2019
replaced location near gate 2 at Kung Chong further comment:
81 1 Level 1 - Prime Strcutres Glass Road ` 116 8/30/2019 Installed glass deviates
from previously approved
color of Façade.

inspection completed:
Broken glass to be replaced at 1st floor high 30/08/2019
82 1 Level 1 - Prime Strcutres Glass level near gate 1 Hoy Fatt Road 116 8/30/2019 further comment:
Installed glass deviates
from previously approved
color of Façade.

1st insp:
Aluminium cladding interface with vertical 25/07/2019 inspection completed:
83 1 Vertical Fins fins at external metal staircase to complete 116 2nd insp: 01/08/2019
01/08/2019

Cleaning /painting of steel hollow section at inspection completed:


84 1 Level 7 - Steel Hollow Section 7th floor to match adjacent paint color matte 116
grey 02/10/2019

Cleaning /painting of steel hollow section at inspection completed:


85 1 Level 7 - Steel Hollow Section 7th floor to match adjacent paint color matte 116
02/10/2019
grey

Cleaning /painting of steel hollow section at inspection completed:


86 1 Level 2 - Steel Hollow Section 2nd floor to match adjacent paint color matte 116 9/3/2019
grey 03/09/2016
Prepared By: Alfredo Claro -Archi. RTO
ZDC: Khin Khin Han Archi. Coordinator UPDATED ZDC ARCHITECTURAL OUTSTANDING WORKS AS AT 22 October 2019 244÷ 285 = 85.610% Accomplished

S/N Zhengda Before Photos Description After Rectification Photo - comments Ref AD Inspection Date Status Mr. Alfredo Mr. David
No. (acknowledgement) (acknowledgement)

Cleaning /painting of steel hollow section at inspection completed:


87 1 Level 2 2nd floor to match adjacent paint color matte 116 9/3/2019
grey 03/09/2016

Cleaning /painting of steel hollow section at


88 1 Level 2 2nd floor to match adjacent paint color matte 116 9/3/2019 inspection completed:
grey 03/09/2016

Level 2 - cleaning of brown colored Cleaning of brown colored spots on inspection completed:
89 1 Aluminium cladding at Architectural Fins and 116 9/3/2019
spots at base of Fins at 2nd floor level 03/09/2016

Level 2 - cleaning of brown colored Cleaning of brown colored spots on inspection completed:
90 1 Aluminium cladding at Architectural Fins and 116 9/3/2019
spots 03/09/2016
at base of Fins at 2nd floor level

Level 2 - cleaning of brown colored Cleaning of brown colored spots on inspection completed:
91 1 Aluminium cladding at Architectural Fins and 116 9/3/2019
spots at base of Fins at 2nd floor level 03/09/2016

Cleaning /painting of steel hollow section at inspection completed:


92 1 Level 3 - hollow sections 3rd floor to match adjacent paint color matte 116 9/3/2019
grey 03/09/2016

Cleaning of brown colored spots on inspection completed:


93 1 Level 3 - Architectural Fins Aluminium cladding at Architectural Fins and 116 9/3/2019 03/09/2016
at base of Fins at 3rd floor level
Prepared By: Alfredo Claro -Archi. RTO
ZDC: Khin Khin Han Archi. Coordinator UPDATED ZDC ARCHITECTURAL OUTSTANDING WORKS AS AT 22 October 2019 244÷ 285 = 85.610% Accomplished

S/N Zhengda Before Photos Description After Rectification Photo - comments Ref AD Inspection Date Status Mr. Alfredo Mr. David
No. (acknowledgement) (acknowledgement)

Cleaning /painting of steel hollow section at inspection completed:


94 1 Level 3 - Hollow sections 3rd floor to match adjacent paint color matte 116 9/3/2019
grey 03/09/2016

Cleaning /painting of steel hollow section at inspection completed:


95 1 Level 4 - Hollow sections 4th floor to match adjacent paint color matte 116 9/3/2019 03/09/2016
grey

Cleaning of brown colored spots on inspection completed:


96 1 Level 4 - Architectural Fins Aluminium cladding at Architectural Fins and 116 9/3/2019
at base of Fins at 4th floor level 03/09/2016

Cleaning /painting of steel hollow section at inspection completed:


97 1 Level 5 - Steel Hollow section 5th floor to match adjacent paint color matte 116 9/3/2019
grey 03/09/2016

Cleaning of brown colored spots on inspection completed:


98 1 Level 5 - Architectural Fins Aluminium cladding at Architectural Fins and 116 9/3/2019
at base of Fins at 5th floor level 03/09/2016

Cleaning /painting of steel hollow section at inspection completed:


99 1 Level 6 - Hollow Sections 6th floor to match adjacent paint color matte 116 9/3/2019
grey 03/09/2016
Prepared By: Alfredo Claro -Archi. RTO
ZDC: Khin Khin Han Archi. Coordinator UPDATED ZDC ARCHITECTURAL OUTSTANDING WORKS AS AT 22 October 2019 244÷ 285 = 85.610% Accomplished

S/N Zhengda Before Photos Description After Rectification Photo - comments Ref AD Inspection Date Status Mr. Alfredo Mr. David
No. (acknowledgement) (acknowledgement)

Cleaning of brown colored spots on inspection completed:


100 1 Level 6 - Architectural Fins Aluminium cladding at Architectural Fins and 116 9/3/2019 03/09/2016
at base of Fins at 6th floor level

Cleaning /painting of steel hollow section at inspection completed:


101 1 Level 7 - Hollow Sections 7th floor to match adjacent paint color matte 116 9/3/2019 03/09/2016
grey

Cleaning of brown colored spots on


102 1 Level 7 - Architectural Fins Aluminium cladding at Architectural Fins and 116 9/3/2019 inspection completed:
at base of Fins at 7th floor level 03/09/2016

End capping on cladding at 7th floor roof inspection completed:


103 1 End capping at 7th floor, roof need to complete 116 9/17/2019 17/09/2019

104 1 Gaps at 7th floor Sealant on gaps need to complete at 7th floor 116 9/17/2019 inspection completed:
17/09/2019

105 1 End capping at 7th floor, roof End capping on cladding at 7th floor roof 116 9/17/2019 inspection completed:
need to complete 17/09/2019
Prepared By: Alfredo Claro -Archi. RTO
ZDC: Khin Khin Han Archi. Coordinator UPDATED ZDC ARCHITECTURAL OUTSTANDING WORKS AS AT 22 October 2019 244÷ 285 = 85.610% Accomplished

S/N Zhengda Before Photos Description After Rectification Photo - comments Ref AD Inspection Date Status Mr. Alfredo Mr. David
No. (acknowledgement) (acknowledgement)

Silver tape to be put in place properly inspection completed:


106 1 Silver Tapes at level 2 and level 3 116 8/30/2019 30/08/2019

107 1 Gap at Level 4 Gap on glass wall and concrete precast wall 116 7/25/2019 inspection completed :
need to complete 25/07/2019

Gap on ceiling and glass wall at 4th floor level inspection completed :
108 1 Gap at Level 4 sky terrace need to complete 116 7/25/2019 25/07/2019

109 1 Gap to have sealant Gap needs to have sealant 116 9/17/2019 inspection completed:
17/09/2019

At 4th floor level, ceiling access panel need to inspection completed :


110 1 Level 4 - Ceiling Access Panel be completed 116 7/25/2019
25/07/2019

gap on ceiling and glass wall at 4th floor level


111 1 Level 4 - gap at sky terrace sky terrace need to complete 116 7/25/2019 inspection completed :
25/07/2019

Gap on ceiling and glass wall/door not


112 1 Level 4 - gap at sky terrace installed at 4th floor level sky terrace need to 116 7/25/2019 inspection completed :
complete 25/07/2019
Prepared By: Alfredo Claro -Archi. RTO
ZDC: Khin Khin Han Archi. Coordinator UPDATED ZDC ARCHITECTURAL OUTSTANDING WORKS AS AT 22 October 2019 244÷ 285 = 85.610% Accomplished

S/N Zhengda Before Photos Description After Rectification Photo - comments Ref AD Inspection Date Status Mr. Alfredo Mr. David
No. (acknowledgement) (acknowledgement)

Doors at 4th floor sky terrace needs to be inspection completed :


113 1 Level 4 - Doors at landscaping area completed 116 7/25/2019 25/07/2019

114 1 Level 4 - gap at sky terrace Gap on ceiling and door need to be completed 116 inspection completed:
02/10/2019

gap on ceiling and glass wall need to be inspection completed :


115 1 Level 4 - gap completed at 4th floor 116 7/25/2019 25/07/2019

Exposed Structural Support


116 1 Level 4 - exposed structural support structural support of aluminium cladding need 116 8/5/2019 inspection completed :
to make good 05/08/2019

117 1 Level 4 - gap Gap on floor and aluminium cladding need to 116 7/25/2019 inspection completed :
make good 25/07/2019

Prime Structures Platforms - Kung Platform paint color not matched adjacent 1st inspection on 80% painting done. To
118 1 matte grey colour, 2nd floor level to 7th floor 116
Chong Road roof level 06/08/2019 remove other paint color

Gap on glass railing and concrete need to


119 1 Gap at Level 4 make good, gap on glass façade and 116 7/25/2019 inspection completed :
aluminium cladding box up need to make 25/07/2019
good
Prepared By: Alfredo Claro -Archi. RTO
ZDC: Khin Khin Han Archi. Coordinator UPDATED ZDC ARCHITECTURAL OUTSTANDING WORKS AS AT 22 October 2019 244÷ 285 = 85.610% Accomplished

S/N Zhengda Before Photos Description After Rectification Photo - comments Ref AD Inspection Date Status Mr. Alfredo Mr. David
No. (acknowledgement) (acknowledgement)

All aluminium and glazing works defects to be


Prime Structures Platforms - Kung rectified by 27 March 2019, including missing
120 1 links/items to complete the job between the 117 completed. completed.
Chong Road structrual wall and the aluminium structures.

Skim-coating to the underside of Skim coating to the underside of slabs to be inspection completed :
121 1 slabs completed. 117 7/25/2019 25/07/2019

122 1 Floor uneveness Floor unevenness to be rectified. 117 7/25/2019 inspection completed :
25/07/2019

Removal of imported worms via soil at storey


4 planter areas and independent lab test of
123 1 L4 - landscaping area the soil supplier by ZDC/landscape 117 9/23/2019 inspection completed:
subcontractor. RTO to witness soil sample 23/09/2019
retrieval and subsequent removal from site by
the independent testing agency.

124 1 Installation of SOB boxes Installation of SOB boxes as per the M&E 117 7/25/2019 inspection completed :
consultant's approval. 25/07/2019

125 1 Level 7 - missing screed Level 7 missing screed for ZDC to check their 117 10/12/2019 inspection completed.
BQ to find out if they are to screed that area. 12/10/2019

Open channel on the floor for the SOB boxes inspection completed :
126 1 Open Channel on the floor to be concreted back. 117 7/25/2019
25/07/2019
Prepared By: Alfredo Claro -Archi. RTO
ZDC: Khin Khin Han Archi. Coordinator UPDATED ZDC ARCHITECTURAL OUTSTANDING WORKS AS AT 22 October 2019 244÷ 285 = 85.610% Accomplished

S/N Zhengda Before Photos Description After Rectification Photo - comments Ref AD Inspection Date Status Mr. Alfredo Mr. David
No. (acknowledgement) (acknowledgement)

To advise the possible utilization of one of the


127 1 M&E existing operational lifts to hoist ID materials 117 Under M&E Under M&E inspections
to the upper floor. Twice a week and each inspections
time 3 hours usage.

128 1 Baement - Water Seepage Some earth pits waterlogged at basement 118 8/1/2019 inspection completed
01/08/2019.

129 1 M&E Permanent power supply for ZDC basement 119 Under M&E Under M&E inspections
hacking work inspections

130 1 AD the same as AD no.62 AD the same as AD no.62 120 completed completed

Toilet
131 1 Level 7 - Male Toilet Urinal too narrow from edge of urinal to 121 9/20/2019 inspection completed:
cubicle partition wall. Unacceptable. 20/09/2019

Water Seepage at Level 7


132 1 Level 7 - Water Seepage Flooding due to clogged drain by scattered 122 8/1/2019 inspection completed:
Plastics, rain coming into a void besides the 01/08/2019
door.

133 1 Level 7 - Water Seepage Water Ingress on void in front of door. 122 10/12/2019 inspection completed:
12/10/2019

134 1 Level 7 - Unfinished floor outside the Unfinished floor outside the door. 122 10/12/2019 inspection completed:
door 12/10/2019
Prepared By: Alfredo Claro -Archi. RTO
ZDC: Khin Khin Han Archi. Coordinator UPDATED ZDC ARCHITECTURAL OUTSTANDING WORKS AS AT 22 October 2019 244÷ 285 = 85.610% Accomplished

S/N Zhengda Before Photos Description After Rectification Photo - comments Ref AD Inspection Date Status Mr. Alfredo Mr. David
No. (acknowledgement) (acknowledgement)

135 1 FMAP windows Many FMAP windows are open. 122 7/25/2019 inspection completed
25/07/2019.

136 1 M&E defects and works M&E defects and works 123 Under M&E Under M&E inspections
inspections

137 1 M&E fix alignment To ensure proper and centered alignment of 124 Under M&E Under M&E inspections
the M&E final fix at all the ceiling area. inspections

138 1 Attendance Attendance at weekly meeting by ZDC top 125


management

139 1 Attendance Attendance at sub-committee meeting in AAS 126


centre

140 1 Drainage Opening Drainage 127 7/10/2019 completed. (email dated:


to widen from 900mm to 1200mm. 10/07/2019)

M&E
141 1 M&E coordinator to engage for the M&E site 128 Under M&E Under M&E inspections
issues. inspections

Skim coating to the underside of slabs to be


142 1 Skim-coating to the underside of completed. 129 7/25/2019 inspection completed :
slabs 25/07/2019

Open channel on the floor for the SOB boxes inspection completed :
143 1 Open Channel on the floor to be concreted back. 129 7/25/2019 25/07/2019
Prepared By: Alfredo Claro -Archi. RTO
ZDC: Khin Khin Han Archi. Coordinator UPDATED ZDC ARCHITECTURAL OUTSTANDING WORKS AS AT 22 October 2019 244÷ 285 = 85.610% Accomplished

S/N Zhengda Before Photos Description After Rectification Photo - comments Ref AD Inspection Date Status Mr. Alfredo Mr. David
No. (acknowledgement) (acknowledgement)

Level 6 floor screed unable to use floor


144 1 Level 6 - Floor Screed conduits. To top up cement to those areas 129 7/25/2019 inspection completed :
affected. 25/07/2019

Prime Structures Works - Aluminium Aluminium works - boxed up to side window


145 Boxed up panels still outstanding. 129

146 1 Pest control - L4 landscape Pest control at level 4. 129 9/23/2019 inspection completed:
23/09/2019

147 1 Levelness of floor Levelness of floor to all level. 129 7/25/2019 inspection completed :
25/07/2019

148 1 Water Leaking - Level 6 to 5 Leaking 129 8/6/2019 inspection completed :


leaking from level 6 to level 5. 06/08/2019

149 1 Rainwater ingress - staircase 2 exit Rainwater Ingress 130 7/25/2019 inspection completed :
doors @level 2-7 rainwater entering from exit doors 25/07/2019

Door
150 1 Door Jamb - Staircase 2 Exit doors ` visible brown spots and rusty color @staricase 130 10/16/2019 inspection completed:
2 exit door jambs 16/10/2019
Prepared By: Alfredo Claro -Archi. RTO
ZDC: Khin Khin Han Archi. Coordinator UPDATED ZDC ARCHITECTURAL OUTSTANDING WORKS AS AT 22 October 2019 244÷ 285 = 85.610% Accomplished

S/N Zhengda Before Photos Description After Rectification Photo - comments Ref AD Inspection Date Status Mr. Alfredo Mr. David
No. (acknowledgement) (acknowledgement)

FMAP Windows
151 1 FMAP windows always open. Even rainy days. 130 7/25/2019 inspection completed :
25/07/2019

Water Clog
Clogged drainage at level 7 due to scattered inspection completed :
152 1 Water Clog at Level 7 cement paper bags, plastics and cigarrette 130 8/1/2019 01/08/2019
butts.

Water Seepage
at basement slab from CRACK on slab inspection completed :
153 1 Basement Water Seepage @ earthpit 1, @ earthpit near firehosereel, @ 130 8/1/2019
near Lift wall 01/08/2019

154 1 Meeting attendance Attendance at weekly site meeting by 131


zhengda top management

155 1 Basement Water Seepage Grid E-3 Near Fire Fighting lobby 1 door crack 132 8/1/2019 inspection completed :
on slab 01/08/2019

156 1 Basement Water Seepage Grid E-4 Outside firelift wall corner crack on 132 8/1/2019 inspection completed :
slab 01/08/2019
Prepared By: Alfredo Claro -Archi. RTO
ZDC: Khin Khin Han Archi. Coordinator UPDATED ZDC ARCHITECTURAL OUTSTANDING WORKS AS AT 22 October 2019 244÷ 285 = 85.610% Accomplished

S/N Zhengda Before Photos Description After Rectification Photo - comments Ref AD Inspection Date Status Mr. Alfredo Mr. David
No. (acknowledgement) (acknowledgement)

157 1 Basement Water Seepage Grid F-3 Earthpit near hosereel 132 8/1/2019 inspection completed :
01/08/2019

inspection completed :
158 1 Basement Water Seepage Grid F-2 Ramp location of I-Beam Support 132 8/1/2019 01/08/2019

inspection completed :
159 1 Basement Water Seepage Grid F-1 Earth Pit 132 8/1/2019 01/08/2019

160 1 Basement Water Seepage Grid G-0 location of I-Beam Support 132 8/1/2019 inspection completed :
01/08/2019
Prepared By: Alfredo Claro -Archi. RTO
ZDC: Khin Khin Han Archi. Coordinator UPDATED ZDC ARCHITECTURAL OUTSTANDING WORKS AS AT 22 October 2019 244÷ 285 = 85.610% Accomplished

S/N Zhengda Before Photos Description After Rectification Photo - comments Ref AD Inspection Date Status Mr. Alfredo Mr. David
No. (acknowledgement) (acknowledgement)

161 1 Basement Water Seepage Grid E-1 Earthpit 132 8/1/2019 inspection completed :
01/08/2019

162 1 Basement Water Seepage Grid D-1 Earthpit 132 8/1/2019 inspection completed :
01/08/2019

163 1 Basement Water Seepage Grid B-1 Location of previous I-Beam Support 132 8/1/2019 inspection completed :
01/08/2019

inspection completed :
164 1 Basement Water Seepage Grid A-0 Crack on Slab 132 8/1/2019 01/08/2019

165 1 Gap at Level 4 Landscaping 133 7/25/2019 inspection completed :


gap at L4 Terrace to complete. 25/07/2019
Prepared By: Alfredo Claro -Archi. RTO
ZDC: Khin Khin Han Archi. Coordinator UPDATED ZDC ARCHITECTURAL OUTSTANDING WORKS AS AT 22 October 2019 244÷ 285 = 85.610% Accomplished

S/N Zhengda Before Photos Description After Rectification Photo - comments Ref AD Inspection Date Status Mr. Alfredo Mr. David
No. (acknowledgement) (acknowledgement)

166 1 Gap at Level 4 Gaps 133 7/25/2019 inspection completed :


on ceiling and glass wall 25/07/2019

167 1 Gap at Level 4 L4 - lasndscapping area 133 7/25/2019 inspection completed :


25/07/2019

inspection completed :
Landscaping 13/08/2019
168 1 Damaged deck/ Uncleaned Walkway Damaged deck. (no x 1pc) 133 8/13/2019 Further comment: to
at Landscaping area Unclean deck. clean decks and the whole
walkway.

169 1 Glass Canopy Fire Protection 133 8/1/2019 inspection completed :


Sprinkler pipe to match glass canopy frame. 01/08/2019

Open End and Finisher 1st insp:


170 1 Open End Finisher open end at canopy 133 25/08/2019 inspection completed :
2nd insp: 01/08/2019
01/08/2019

171 1 Drainage Drainage 133 8/13/2019 inspection completed :


cut of drain. 13/08/2019

Newly cast basement slab have visible crack


172 1 Basement Water Seepage on slab in front of consumer switch room at 134 8/1/2019 inspection completed :
basement have water seepage ( at earthpit 01/08/2019
and at location of previous I-Beam Support)
Prepared By: Alfredo Claro -Archi. RTO
ZDC: Khin Khin Han Archi. Coordinator UPDATED ZDC ARCHITECTURAL OUTSTANDING WORKS AS AT 22 October 2019 244÷ 285 = 85.610% Accomplished

S/N Zhengda Before Photos Description After Rectification Photo - comments Ref AD Inspection Date Status Mr. Alfredo Mr. David
No. (acknowledgement) (acknowledgement)

Rectified door at 4th floor fire fighting lobby 2 inspection completed :


173 1 Level 4 - Fire Fighting lobby 2 totally cannot close 134 8/1/2019 01/08/2019

Rectified door at 6th floor fire fighting lobby 1 inspection completed.


174 1 Level 6 - Fire Fighting lobby 1 totally cannot close 134 8/19/2019 19/08/2019

FMAP Windows
175 1 FMAP windows always open. Even rainy days. 134 7/25/2019 inspection completed :
25/07/2019

176 1 Level 1 - handicapped toilet Door handle missing at level 1 - handicapped 134 inspection completed:
toilet 02/10/2019

177 1 Fire-stop at level 3 Firestop damaged at fire hose reel 134 9/24/2019 inspection completed :
compartment 24/09/2019
Prepared By: Alfredo Claro -Archi. RTO
ZDC: Khin Khin Han Archi. Coordinator UPDATED ZDC ARCHITECTURAL OUTSTANDING WORKS AS AT 22 October 2019 244÷ 285 = 85.610% Accomplished

S/N Zhengda Before Photos Description After Rectification Photo - comments Ref AD Inspection Date Status Mr. Alfredo Mr. David
No. (acknowledgement) (acknowledgement)

At handicap toilets from 2nd floor to 7th floor


178 1 Handicapped Toilets - hooks not installed yet (@1.1/ 1,5 meters from floor 135 8/19/2019 inspection completed:
installation finish) 19/08/2019

179 1 Drainage Orifice Discharge drain rectified orifice not done yet 135 7/10/2019 completed. (email dated:
10/07/2019)

At 7th floor male toilet WC Cubicle wall and inspection completed :


180 1 Level 7 - Male Toilet urinal, space E5 not acceptable too narrow 135 9/20/2019 20/09/2019

181 1 Security Room - door/ floor / Celing Door Jamb at security door not installed 135 inspection completed:
properly floor and ceiling not done 19/08/2019

182 1 Architectural Fins at all floors Painting of Architectural Fin Supports should 135 8/30/2019 inspection completed:
match adjacent color of Arch. Fins 30/08/2019

183 Ceiling at Level 4 - landscaping area At 4th floor level, ceiling to make good 135
Prepared By: Alfredo Claro -Archi. RTO
ZDC: Khin Khin Han Archi. Coordinator UPDATED ZDC ARCHITECTURAL OUTSTANDING WORKS AS AT 22 October 2019 244÷ 285 = 85.610% Accomplished

S/N Zhengda Before Photos Description After Rectification Photo - comments Ref AD Inspection Date Status Mr. Alfredo Mr. David
No. (acknowledgement) (acknowledgement)

inspection completed:
At 1st floor high level broken glass need to be 30/08/2019
184 1 Broken Glass at Level 1 - Kung Chong replaced location near gate 2 at Kung Chong 135 8/30/2019 further comment:
Road Road Installed glass deviates
from previously approved
color of Façade.

inspection completed:
Broken glass to be replaced at 1st floor high 30/08/2019
185 1 Broken Glass at Level 1 - Hoy Fatt level near gate 1 Hoy Fatt Road 135 8/30/2019 further comment:
Road Installed glass deviates
from previously approved
color of Façade.

Broken Glass at Level 2 - Hoy Fatt Broken glass to be replaced at 2nd floor level
186 Road near gate 1 Hoy Fatt Road 135

187 Aluminium Box-up alignment Aluminium box up alignment 1pc sticking out 135
from the rest

188 1 Meter Room Level 1 - door / signage Respective finishing / signage/ at meter room 135 10/16/2019 inspection completed:
door not yet completed 16/10/2019

189 1 Gas Riser Room Level 1 - door / Respective finishing / signage/ at gas riser 135 8/1/2019 inspection completed :
signage / finishing door not yet completed 01/08/2019

190 Metal Staircase 2 - discrepancies in Metal Staircase #2 135


perforation
Prepared By: Alfredo Claro -Archi. RTO
ZDC: Khin Khin Han Archi. Coordinator UPDATED ZDC ARCHITECTURAL OUTSTANDING WORKS AS AT 22 October 2019 244÷ 285 = 85.610% Accomplished

S/N Zhengda Before Photos Description After Rectification Photo - comments Ref AD Inspection Date Status Mr. Alfredo Mr. David
No. (acknowledgement) (acknowledgement)

All fireman access panels need to install


properly, many damaged lock, water ingress
191 1 FMAP windows during water tightness test, take note that 135 completed.
glass façade haven't tested for water tightness
test glass façade need to be thoroughly
cleaned prior to handover to owner

Cleaning of brown colored spots on inspection completed:


192 1 Architectural Fins at all floors Aluminium cladding at Architectural Fins and 135 9/3/2019 03/09/2019
at base of Fins at level 2 to level 7

Cleaning /painting of steel hollow section at inspection completed:


193 1 Hollow sections at all floors level 2 to level 7 adjacent paint color matte 135 9/3/2019 03/09/2019
grey

194 1 Gaps on Aluminium fins at Staircase Gaps on Aluminium fins to make good/cover 135 8/22/2019 inspection completed:
2 22/08/2019

195 1 Architectural Fins at all floors Painting of Architectural fins supports to 135 8/22/2019 inspection completed:
match adjacent material color 22/08/2019

196 1 Broken Glass at Level 6 - Kung Chong At 6th floor level broken glass need to be 135 9/3/2019 inspection completed:
Road replaced near Gate 2 @ Kung Chong Road 03/09/2019
Prepared By: Alfredo Claro -Archi. RTO
ZDC: Khin Khin Han Archi. Coordinator UPDATED ZDC ARCHITECTURAL OUTSTANDING WORKS AS AT 22 October 2019 244÷ 285 = 85.610% Accomplished

S/N Zhengda Before Photos Description After Rectification Photo - comments Ref AD Inspection Date Status Mr. Alfredo Mr. David
No. (acknowledgement) (acknowledgement)

Water ingress on FMAP prime structures need


to have proper sealant to prevent water
197 1 FMAP windows ingress. Façade glass not yet totally done 135 completed.
TEST, Water leak test, damaged lock need to
make good, previous test failed at 2nd floor
FMAP.

1st insp:
198 1 Vertical Fins - near staircase 2 Aluminium cladding interface with vertical 135 25/08/2019 inspection completed :
(outside of building) fins at external metal staircase to complete 2nd insp: 01/08/2019
01/08/2019

199 1 135 8/1/2019 inspection completed :


01/08/2019

At level 4 and level 6, fire door was finally


rectified (more than the minimum 1 meter
Staircase 1 exit doors - Level 4 and clearance from the edge of the door leaf to
Level 6 edge of hand railing) BUT painting not yet
completed and PSB sticker on fire door not
yet done

200 1 135 8/1/2019 inspection completed :


01/08/2019

201 1 LED lights in the toilets LED on toilet mirror not yet installed 135 inspection completed:
Prepared By: Alfredo Claro -Archi. RTO
ZDC: Khin Khin Han Archi. Coordinator UPDATED ZDC ARCHITECTURAL OUTSTANDING WORKS AS AT 22 October 2019 244÷ 285 = 85.610% Accomplished

S/N Zhengda Before Photos Description After Rectification Photo - comments Ref AD Inspection Date Status Mr. Alfredo Mr. David
No. (acknowledgement) (acknowledgement)

Ingress of rainwater - ZDC to install aluminium


202 1 Water Ingress at Staircase 2 exit 75mm +300mm both sides to prevent any rain 135 7/25/2019 inspection completed :
doors water ingress goes inside the fire fighting 25/07/2019
lobby

Water seepage at Basement floor, earthpit


203 1 Water Seepage at Basement and kingpost, rectification not done yet, 135 8/1/2019 inspection completed :
method statement from ZDC needs approval 01/08/2019
prior to rectification

204 Water Tap Handle Missing Water tap missing handle at green buffer 135

At fire fighting lobby #2 missing LED lights,


205 1 Lobby 2 - LED lights supply power in there but LED not installed 135 inspection completed:
yet, ceiling finishing not the same as new art 02/10/2019
drawing

206 Signage Permanent signage of fire escape plan and 135


structural loading plan all floors

207 1 Fire Damper to be installed on duct Fire-damper to be installed on duct 137 Under M&E Under M&E inspections
penetration through fire-rated wall penetration through fire rated wall inspections

208 1 Earthpits basement completion of earthpits 138 completed completed

inspection completed :
209 1 Basement Moisture reading at basement 138 8/6/2019 06/08/2019

210 1 Basement Drying of basement 138 8/6/2019 inspection completed :


06/08/2019

211 1 Basement Marking of driveway and car parking lots 138 8/16/2019 inspection completed :
16/08/2019
Prepared By: Alfredo Claro -Archi. RTO
ZDC: Khin Khin Han Archi. Coordinator UPDATED ZDC ARCHITECTURAL OUTSTANDING WORKS AS AT 22 October 2019 244÷ 285 = 85.610% Accomplished

S/N Zhengda Before Photos Description After Rectification Photo - comments Ref AD Inspection Date Status Mr. Alfredo Mr. David
No. (acknowledgement) (acknowledgement)

212 1 Basement Final touch-up and handover 138 inspection completed:


03/10/2019

213 1 Security Room Installation of false ceiling 138 completed.

214 1 Level 1 - lift lobby wall Level 1 lift lobby 2- to remove marble wall 138 8/13/2019 inspection completed :
cladding to expose lift door jamb 13/08/2019

215 1 Lift lobby 2 Lights not install as per approved drawing. 138 inspection completed:
(lights to be fitted inside the cove) 02/10/2019

216 1 Lift lobby 2 Timber threshold to be removed and to 138 8/23/2019 inspection completed :
perform water test on the alum edge. 23/08/2019

217 Staircase 2 Steel staircase landing - inconsistence of 138


perforation

inspection completed:
30/08/2019
218 1 Level 1 Level 1 - external façade, cracked on curtain 138 8/30/2019 further comment:
wall glass. Installed glass deviates
from previously approved
color of Façade.

Ceiling at Basement
219 1 Ceiling at Basement Ceiling is inconsistent with 3rd floor Ceiling 139 9/18/2019 inspection completed:
Construction, Recessed Ceiling not 18/09/2019
constructed
Prepared By: Alfredo Claro -Archi. RTO
ZDC: Khin Khin Han Archi. Coordinator UPDATED ZDC ARCHITECTURAL OUTSTANDING WORKS AS AT 22 October 2019 244÷ 285 = 85.610% Accomplished

S/N Zhengda Before Photos Description After Rectification Photo - comments Ref AD Inspection Date Status Mr. Alfredo Mr. David
No. (acknowledgement) (acknowledgement)

Ceiling at 1st Floor


220 1 Ceiling at Level 1 Ceiling is inconsistent with 3rd floor Ceiling 139 9/18/2019 inspection completed:
Construction, Recessed Ceiling not 18/09/2019
constructed

Ceiling at 2nd Floor


221 1 Ceiling at Level 2 Ceiling is inconsistent with 3rd floor Ceiling 139 9/18/2019 inspection completed:
Construction, Recessed Ceiling not 18/09/2019
constructed

Ceiling at 3rd Floor


222 1 Ceiling at Level 3 Ceiling have recessed, down light not 139 9/18/2019 inspection completed:
installed, rows of light left side and right side 18/09/2019
of ceiling

Ceiling at 4th FLoor


Ceiling is inconsistent with 3rd floor Ceiling inspection completed:
223 1 Ceiling at Level 4 Construction, Recessed Ceiling not 139 9/18/2019 18/09/2019
constructed

Ceiling at 5th Floor


224 1 Ceiling at Level 5 Ceiling is inconsistent with 3rd floor Ceiling 139 9/18/2019 inspection completed:
Construction, Recessed Ceiling not 18/09/2019
constructed

Ceiling at 6th Floor


225 1 Ceiling at Level 6 Ceiling is inconsistent with 3rd floor Ceiling 139 9/18/2019 inspection completed:
Construction, Recessed Ceiling not 18/09/2019
constructed

Ceiling at 7th Floor


226 1 Ceiling at Level 7 Ceiling is inconsistent with 3rd floor Ceiling 139 9/18/2019 inspection completed:
Construction, Recessed Ceiling not 18/09/2019
constructed

Ceiling at Security Room


227 1 Ceiling at Security Room ZDC doing but must comply to fire code 139 completed.
requirements
Prepared By: Alfredo Claro -Archi. RTO
ZDC: Khin Khin Han Archi. Coordinator UPDATED ZDC ARCHITECTURAL OUTSTANDING WORKS AS AT 22 October 2019 244÷ 285 = 85.610% Accomplished

S/N Zhengda Before Photos Description After Rectification Photo - comments Ref AD Inspection Date Status Mr. Alfredo Mr. David
No. (acknowledgement) (acknowledgement)

228 1 Column Angle Guards at Basement Column Guard not installed yet, materials for 139 8/20/2019 inspection completed:
approval not submitted 20/08/2019

EPS systems at Rump going up and EPS not installed yet at RUMP GOING UP TO Under M&E
229 1 1ST FLOOR AND AT RUMP GOING DOWN TO 139 Under M&E inspections
going down BASEMENT FLOOR inspections

230 Cat Ladder at Upper Roof Cat Ladder not installed yet, Location at upper 139
roof near Car Lift Motor Room

At roof of Car Lift Motor Room, actual


231 Gondola Supports at Upper Roof gondola support installed different from 139
drawing

232 Gondola Supports at Upper Roof Actual Gondola support constructed not the 139
same as drawing

233 Platforms at Kung Chong Road Platform not same as drawing 139

234 Gondola Supports at Upper Roof Actual Gondola platform constructed not the 139
same as drawing

At 7th floor roof end cap not installed,


235 1 Prime Structure Works - End Capping possible water ingress going to below floor 139 9/17/2019 inspection completed:
at Level 7 level 17/09/2019

Building banner light timer not properly in


236 1 Building Banner Light Timer function or no timer. Last upper rows of lights 139 9/24/2019 inspection completed :
is always on, 24 hours a day. 2nd row with 24/09/2019
lights but not powered.
Prepared By: Alfredo Claro -Archi. RTO
ZDC: Khin Khin Han Archi. Coordinator UPDATED ZDC ARCHITECTURAL OUTSTANDING WORKS AS AT 22 October 2019 244÷ 285 = 85.610% Accomplished

S/N Zhengda Before Photos Description After Rectification Photo - comments Ref AD Inspection Date Status Mr. Alfredo Mr. David
No. (acknowledgement) (acknowledgement)

237 Metal Staircase 2 - discrepancies in Perforated staircase, perforation inconsistent 139


perforation with adjacent perforation.

238 1 Plaseter Cracks at Basement Wall Plaster cracks on wall of ramp going down to 139 inspection completed:
basement 03/10/2019

239 1 2.2m Clear Height in Basement Non-compliance to minimum 2.2m clear 140 Under M&E Under M&E inspections
height in basement car park area inspections

240 1 Basement Basement moisture reading test to conduct 141 8/6/2019 inspection completed:
06/08/2019

241 1 Status of sty 4 soil replacement ZDC to resolve the infestation 141 9/23/2019 inspection completed:
23/09/2019

Lift handover to AAS, ZDC to liaise with DC on Under M&E


242 1 Lift Handover to AAS the full contractural requirements for the lift 141 inspections Under M&E inspections
handing over.

Gondola brackets to comply with the


243 Gondola Brackets approved ZDC shop-drawings 141

244 1 Operation of EPS barrier system To update the technicals of EPS barrier system 141 Under M&E Under M&E inspections
inspections

245 1 Basement Basement 2.2m clear basement height check 141 Under M&E Under M&E inspections
inspections

246 1 Lift Lobby Lift Lobby ceiling and wall tiling at lift door 141 9/18/2019 inspection completed:
18/09/2019

247 1 M&E fix alignment Metal M&E final fix at the fireman lift lobby 141 9/18/2019 inspection completed:
18/09/2019

248 1 To follow up on all observation All observation reports and ADs to follow up 141
reports and ADs issued

249 Level 3 - Washing Bay Washing Bay to rectify 141


Prepared By: Alfredo Claro -Archi. RTO
ZDC: Khin Khin Han Archi. Coordinator UPDATED ZDC ARCHITECTURAL OUTSTANDING WORKS AS AT 22 October 2019 244÷ 285 = 85.610% Accomplished

S/N Zhengda Before Photos Description After Rectification Photo - comments Ref AD Inspection Date Status Mr. Alfredo Mr. David
No. (acknowledgement) (acknowledgement)

250 All outstanding works to complete all outstanding works to complete 141

To fabricate one pair of outriggers of each


dimension as indicated on approved shop-
251 Outriggers and gondola brackets drawing. 142
To install gondola brackets as per the
approved shop-drawings.

4 nos of broken glass not rectified yet


Prime Structure Works - Broken 1 no at 6th floor
252 Glasses 2 nos at 2nd floor 143/144
1 no at 1t floor.

At 1st floor level, ZDC subcon opened up the


253 1 Ceiling at Level 1 - infront of meter ceiling. ZDC to reinstate the ceiling in good 143/144 10/16/2019 inspection completed:
room condition. Door of sub meter not installed 16/10/2019
yet.

254 1 Bin Centre at Level 1 At bin centre, ZDC subcon store their 143/144 9/24/2019 inspection completed :
materials inside the Bin Centre 24/09/2019

Damaged door locks at M&E risers, ZDC to


255 1 Damaged Ironmongeries replace damaged door locks and to complete 143/144 8/30/2019 inspection completed:
installation of missing door locks and handle 30/08/2019
doors at staircase 1 and at staircase 2.

7 nos of internal drain covers along the


256 1 Drain Covers without pins - along driveway are not properly installed, without 143/144 9/18/2019 inspection completed:
driveway area PIN, may cause hazard to vehicles doing 18/09/2019
loading or unloading.

wheel guards installed.


257 Bicycle Racks at Basement At basement level, wheel guards and bicycle 143/144 (inspection completed
rack not yet installed yet. 50%)

258 Exit Sign at Level 7 - outside of Lobby At 7th floor roof, Green coloured exit sign 143/144 preparing for inspection
2 turned into Blue color.
Prepared By: Alfredo Claro -Archi. RTO
ZDC: Khin Khin Han Archi. Coordinator UPDATED ZDC ARCHITECTURAL OUTSTANDING WORKS AS AT 22 October 2019 244÷ 285 = 85.610% Accomplished

S/N Zhengda Before Photos Description After Rectification Photo - comments Ref AD Inspection Date Status Mr. Alfredo Mr. David
No. (acknowledgement) (acknowledgement)

Earthpit covers at basement damaged, inspection completed:


259 1 Earthpit covers at Basement cracked and chipped-off. Earthpit covers not 143/144 8/30/2019 30/08/2019
replaced yet.

260 Level 3 - Washing Bay At 3rd floor, washing bay rectification not 143/144
done yet.

At M&E compartment, ZDC to clear all


261 1 M&E compartment - to clean prior to unwanted materials and clean all M&E 143/144 10/14/2019 inspection completed:
handing over compartment prior to handing over the 14/10/2019
building to the owner.

At 6th floor, fire rated door installed by ZDC.


Door at Level 6 - internal metal Until now, no psb stickers, wall installed inspection completed :
262 1 staircase adjacent to door jamb to rectify immediately 143/144 9/24/2019 24/09/2019
and make good.

Visible red stickers marked at staircase 1,


263 1 painting to make good. Painting at hand rail at 143/144 10/16/2019 inspection completed:
Staircase 1 - red stickers to remove staricase 1, ZDC to touch up painting from 16/10/2019
Straicase 1 & 2 - paint to make good level 7 till basement level.
Staricase 1 - handrail paints

264 1 RC Kerb at drive way area chipped off corners of RC wll. RC kerb to 143/144 8/30/2019 inspection completed:
make good. 30/08/2019

At level 7, fire extinguisher bracket or hook to


265 All fire-extinguishers - to place at make good. All fire extinguishers, ZDC subcon 143/144 preparing for inspection
proper location all fire extinguishers must be put back to its
proper location to all floor level.

At level 7 fire fighting lobby 1, visible holes


266 Lobby 1 at Level 7 - visible holes on on RC wall besides fire alarm bell need 143/144 preparing for inspection
RC wall besides fire alarm bell painting to make good
Prepared By: Alfredo Claro -Archi. RTO
ZDC: Khin Khin Han Archi. Coordinator UPDATED ZDC ARCHITECTURAL OUTSTANDING WORKS AS AT 22 October 2019 244÷ 285 = 85.610% Accomplished

S/N Zhengda Before Photos Description After Rectification Photo - comments Ref AD Inspection Date Status Mr. Alfredo Mr. David
No. (acknowledgement) (acknowledgement)

At 3rd floor level, slab surface to make good.


Level 3 Floor Slab - visible survey All visible survey marking, all depressed
267 markings, depressed areas, areas, protruding bars, floor surface to make 143/144
protruding bars, all to make good. good.

Level 2 Floor Slab - visible survey At 2nd floor level, slab surface to make good,
268 markings, depressed areas, all visible survey marking, all depressed areas, 143/144 preparing for inspection
protruding bars, all to make good. protruding bars, floor surface to make good.

Level 1 Floor Slab - visible survey At 1st floor level, slab surface to make good,
269 markings, depressed areas, all visible survey marking, all depressed areas, 143/144 preparing for inspection
protruding bars, all to make good. protruding bars, floor surface to make good.

2 wall tiles at bin center to install, neighbour's


Bin Centre - 2 wall tiles to install, Bin power cable already been shifted finishing to
270 containers to put back inside. make good inside and outside of Bin Centre, 2 143/144
Bin containers to put back inside

271 1 Doors at Lobby 1 and Lobby 2 - all Defects on all doors at fire fighting lobby 1 143/144 10/9/2019 inspection completed:
floors and at fire fighting lobby 2 not rectified yet 09/10/2019

Lobby 1 and Lobby 2 - fire break Gaps to make good to all fire break glass inspection completed:
272 1 glass panel and lift panels to make panel and lift panels at fire fighting lobby 1 143/144 10/16/2019
good. and at fire fighting lobby 2. 16/10/2019

273 1 Level 1 to 7 - gaps at door At level 7 to basement level, gaps on fire 143/144 10/16/2019 inspection completed:
doors needs to be rectified. 16/10/2019

Many places at basement floor level, have the


274 Basement Floor Surface same case. Need rectification of basement 143/144
floor surface and epoxy floor finishing works.
Prepared By: Alfredo Claro -Archi. RTO
ZDC: Khin Khin Han Archi. Coordinator UPDATED ZDC ARCHITECTURAL OUTSTANDING WORKS AS AT 22 October 2019 244÷ 285 = 85.610% Accomplished

S/N Zhengda Before Photos Description After Rectification Photo - comments Ref AD Inspection Date Status Mr. Alfredo Mr. David
No. (acknowledgement) (acknowledgement)

Lobby 1 - lift doors, plastic At fire fighting lobby 1, door of lifts, plastic inspection completed:
275 1 protection, door frames to be protection, door frames to be cleared of paint 143/144 8/30/2019
cleared of paint stains at all floors stains, from level 7 to basement level. 30/08/2019

276 Signage Temporary signage still in placed at fire 143/144


fighting lobby 1 and at fire fighting lobby 2

Fire Doors - paint stains, silicone Fire door, paint stains, silicone stains, ZDC to inspection completed :
277 1 stains ZDC to make good make good. 143/144 9/24/2019 24/09/2019

278 Level 4 - landscape area Installation of lights and LED lights at 145
landscape area

Green wall and other plants are turning


brown due to possible lack of watering.
279 Level 4 - landscape area Plants start to wither. 145
ZDC to ensure proper and regular
maintenance of the landscape works.

Water feature not yet complete.


280 Level 4 - landscape area Timer to water the plants malfunctioned. 145
ZDC to make good.

Under the conditions of contract,


281 1 M&E defects, works and T&C M&E defects works to proceed immediately 146 Under M&E Under M&E inspections
M&E outstandings to proceed immediately inspections
M&E T&C to proceed immediately

282 1 M&E defects, works and T&C M&E 147 Under M&E Under M&E inspections
inspections

283 Land Scape at Green buffer Poor landscaping at green buffer 148

All façade glasses must be the same as


284 Façade glasses deviation in color approved color 149

ZDC to immediately rectify water leaking at


285 1 Level 7 dog house dog house - Level 7, leaking to level 6 staff 150 10/15/2019 inspection completed:
area. Rectification procedures/MOS to 15/10/2019
submit.

S-ar putea să vă placă și