Sunteți pe pagina 1din 154

NKC PROJECTS PVT. LTD.

Project: Four Laning of TAKOLI to KULLU section of NH-21 (Km 242+00 to 272+00) under NHDP-IV B on EPC mode in the State of Himachal Pradesh.

Weightage in % to the Contract Price BOQ Planned for This Month Achived Up to Date Balance
S.No Description Amount (Crores) Remarks
Current
Sub-division Proposed Unit QTY Unit Rate Quantity Amount (Rs) Quantity Amount (Rs) Quantity Amount (Rs)
Schedule-H

The Contract Price for this Agreement is Rs. 3,288,310,336 Crores

1 Widening Subgrade Top 10.12% 332,777,006 Km 19.245 17,291,609 - - - -


2 Widening WMM Top 7.59% 249,582,755 Km 19.245 12,968,706 - - - -
3 Widening DBM Top 13.80% 65% 8.97% 294,961,437 Km 19.245 15,326,653 - - - -
4 Widening BC Top 35% 4.83% 158,825,389 Km 19.245 8,252,813 - - - -
5 Widening Box Culvert/Pipe Culverts 0.97% 31,896,610 Nos 26.000 1,226,793 - - - -
6 New- Subgrade Top 6.76% 222,289,779 Km 8.316 26,730,373 - - - -
7 New WMM Top 3.59% 118,050,341 Km 8.316 14,195,568 - - - -
8 New DBM Top 5.11% 65% 3.32% 109,221,228 Km 8.316 13,133,866 - - - -
9 New BC Top 35% 1.79% 58,811,430 Km 8.316 7,072,082 - - - -
10 New Box Culvert 1.42% 20% 46,670,236 Nos 38.000 1,228,164 - - - -
11 New- Pipe Culvert 1.68% 35% 55,267,385 Nos 45.000 1,228,164 - - - -
12 MNB 1.11% 36,500,245 Nos 3.000 12,166,748 - - - -
13 VUP 0.74% 24,333,496 Nos 2.000 12,166,748 - - - -
14 VOP 0.44% 14,468,565 Nos 1.000 14,468,565 - - - -
15 MJB- Well Foundations (6 No.) 2.09% 68,725,686 RM 110.000 624,779 - - - -
16 MJB- Substructure 2.78% 91,415,027 Nos 19.000 4,811,317 - - - -
17 MJB- Superstructure 9.05% 297,592,085 Metres 524.000 567,924 - - - -
18 Toll Plaza 2.19% 72,013,996 Nos 1.000 72,013,996 - - - -
19 Road side drains 1.42% 46,694,007 Km 28.690 1,627,536 - - - -
20 Road signs etc.. 1.38% 45,378,683 Km 28.690 1,581,690 - - - -
21 Bus Bay 0.01% 328,831 Nos 2.000 164,416 - - - -
22 Rest Areas 0.03% 986,493 Nos 1.000 986,493 - - - -
23 Providing wearing coat Bridges 0.02% 657,662 Nos 3.000 219,221 - - - -
24 Replacement of bearings, joints 0.03% 986,493 Nos 3.000 328,831 - - - -
25 Providing crash barriers 0.01% 328,831 Nos 3.000 109,610 - - - -
26 Protection works 27.28% 897,051,060 Km 27.561 32,547,842 - - - -
27 Safety, Traffic Management, Maintenance 0.24% 7,891,945 Months 30.000 263,065 - - - -
28 (x) Miscellaneous 0.14% 4,603,634 Km 28.690 160,461 - - - -
Grand Total Amount (Rs) 3,288,310,336 - - - As per Schedule-H
Actual Cumulative Completed as per DPR - Err:504
Certified upto IPC-01 -
Daily Progress Report Jun'18 16-Jun-18
Earthwork Progress on 16-Jun-18
Cutting Machinery Used Amount of Work Done Jun'18
S.No Sub-Contractor Name Total Soil Rock Excavator Breaker Dumper JCB Grader Tanker Loader Total Today Total Soil Rock
Cum Cum MT No. No. No. No. No. No. No. Lakhs Lakhs ₹ 95.00 ₹ 147.00
1 Ajay Pathania 423.59 344.00 127.35 3 1 4 - - - - ₹ 51,400 ₹ 805,541 4,600 2,507
2 Bhupender Singh - - - - - - - - - - ₹ - ₹ 153,520 1,616 -
3 Jham Jham 31.75 - 50.80 3 1 1 - - - - ₹ 7,468 ₹ 152,442 176 923
4 NKC 785.59 720.00 104.95 5 1 14 - - - - ₹ 83,828 ₹ 951,545 6,834 2,057
5 KG 43.22 - 69.15 1 - 1 - - - - ₹ 10,165 ₹ 116,214 8 785
Total 1,284.16 1064.00 352.25 12 3 20 - - - - 152,861 ₹ 2,179,262 13,234 6,272

Sub Grade on 16-Jun-18 Sub Grade


Sub Grade Machinery Used Amount of Work Done Jun'18
S.No Sub-Contractor Name Total Laying Dumping Excavator Breaker Dumper JCB Grader Tanker Loader Roller Laying Dumping Subgrade Layers (W&SER)
Cum Cum Cum No. No. No. No. No. No. No. No. - -
1 NKC - - - - - - - 2 2 - 2 - 125 ###

Total - 0.00 0.00 - - - - 2 2 - 2 - 125 125

GSB on 16-Jun-18 GSB


GSB Machinery Used Amount of Work Done Jun'18
S.No Sub-Contractor Name Total Laying Dumping Excavator Breaker Dumper JCB Grader Tanker Loader Roller Laying Dumping Total (MT)
MT MT MT No. No. No. No. No. No. No. No. - -
1 NKC - - - - - - - - - - - 213 2,960 ###

Total - 0.00 0.00 - - - - - - - - 213 2,960 3,173

WMM on 16-Jun-18 WMM


WMM Machinery Used Amount of Work Done Jun'18
S.No Sub-Contractor Name Total Laying Dumping Excavator Breaker Dumper JCB Grader Tanker Loader Roller Laying Dumping Total (MT)
MT MT MT No. No. No. No. No. No. No. No. - -
1 NKC 197.10 - 197.10 - - - - - - - - 1,055 1,822 ###

Total 197.10 0.00 197.10 - - - - - - - - 1,055 1,822 2,877

Protection Work Progress on 16-Jun-18


Gabion Retaining Wall Retaining Amount of Work DonAmount of Work Done TOTAL Quantity May'18 Total Amount May'18 Patch Work
Wall PCC
S.No Sub-Contractor Name
Quantity Labour Quantity Total Retaining R/W PCC Retaining R/W PCC Retaining R/W PCC
Name Quantity DBM Quantity BC
Cum No. Cum Lakhs ₹ 450 ₹ 120 Cum Cum ₹ 450 ₹ 120
1 Ashok Kumar Contractor 57.00 15 - ₹ 0.257 ₹ 25,650 ₹ - 288.00 - ₹ 129,600 ₹ - Ram Dev 113.07
2 Bhawan Kumar 15.00 10 - ₹ 0.068 ₹ 6,750 ₹ - 45.00 - ₹ 20,250 ₹ -
3 Chandan Premi 18.00 10 - ₹ 0.081 ₹ 8,100 ₹ - 228.00 - ₹ 102,600 ₹ -
4 Devi Singh - - - ₹ - ₹ - ₹ - 87.00 - ₹ 39,150 ₹ -
5 Kamal Kant - - - ₹ - ₹ - ₹ - - - ₹ - ₹ -
6 Kamlesh Thakur 12.00 5 - ₹ 0.054 ₹ 5,400 ₹ - 152.00 51.00 ₹ 68,400 ₹ 6,120
7 Kul Bahadur 6.00 3 - ₹ 0.027 ₹ 2,700 ₹ - 6.00 - ₹ 2,700 ₹ -
8 Suresh Kumar 10.00 4 - ₹ 0.045 ₹ 4,500 ₹ - 53.50 46.50 ₹ 24,075 ₹ 5,580
9 Madan Singh Chauhan - - - ₹ - ₹ - ₹ - 135.00 - ₹ 60,750 ₹ -
10 Jyoti Savroop Singh - - - ₹ - ₹ - ₹ - 45.00 - ₹ 20,250 ₹ -
11 Veneet Kumar 45.00 5 - ₹ 0.203 ₹ 20,250 ₹ - 45.00 76.00 ₹ 20,250 ₹ 9,120
12 Raj Kumar 5.00 4 10.00 ₹ 0.035 ₹ 2,250 ₹ 1,200 20.00 15.00 ₹ 9,000 ₹ 1,800
13 Surender mahant - - - ₹ - ₹ - ₹ - 39.00 - ₹ 17,550 ₹ -
Total 168.00 56 10.00 ₹ 0.768 ₹ 75,600 ₹ 1,200 1,144 189 ₹ 514,575 ₹ 22,620 - 113

RRM on 16-Jun-18
PCC For RRM RRM Masonary Amount of Work Done TOTAL Quantity Total Amount Kerb Laying
S.No Sub-Contractor Name Quantity Labour Quantity Labour Total PCC Masonary PCC Masonary PCC Masonary Name Today Total Cum
Cum No. Cum No. Lakhs ₹ 200 ₹ 2,200 Cum Cum ₹ 200 ₹ 2,200
1 Ajay Pathania - - - - ₹ - ₹ - ₹ - - - ₹ - ₹ - NKC - -
2 Bhagwan Singh - - - - ₹ - ₹ - ₹ - - - ₹ - ₹ -
3 Milap Chand - - - - ₹ - ₹ - ₹ - - - ₹ - ₹ -
Total - - - - ₹ - ₹ - ₹ - - - ₹ - ₹ - - -
Completed
Structure Work Progress on 16-Jun-18
Details/Comments of Work Done
S.No Name Type Chainage Name Labour Concrete LHS RHS today Excavator Dumper Crane
well sinking in progress done upto 10.2M+
1 Bajora Bridge LP2 249+435 Mohd Forman 5 0.00 0 0 0
0.200= 10.4m
2 Bajora Bridge RP2 249+435 Mohd Forman 0 0.00 0 0 0 0
3 Bajora Bridge LP3 249+435 Mohd Forman 5 0.00 9.8m+0.300= 10.1 Completed 0 0 0
4 Bajora Bridge RP3 249+435 Mohd Forman 5+8 0.00 0 0 0 0

5 Jia Bridge P4 255+230 Mohd Forman 4 0.00 Overall down=4m 0 0 1

6 Jia Bridge P5 255+230 Sohan Lal 6 0.00 Overall down=9.7m 0 0 0

7 Jia Bridge P2 255+230 Sohan Lal 0 0.00 0 0 0 0

8 Jia Bridge P3 241+040 Mohd Farman 0 0.00 0 0 0 0


9 Minor Bridge MNB 258+800 S.K Contractor 0 0.00 0 0 0 0
10 Minor Bridge MNB 245+710 Vijay Kumar 0 0.00 0 0 0 0
11 Minor Bridge MNB 241+041 0 0 0.00 0 0 0 0
12 Culvert BC 236+753 0 0 - 0.00 0.00 0 0 0 0
13 Culvert BC (Wid) 236+803 0 0 - 0.00 0.00 0 0 0 0
14 Culvert BC (Wid) 237+995 Shubham Shharma 0 - 0.00 0.00 0 0 0 0
15 Culvert BC (Re-Con.) 238+286 Vijay Kumar 0 - Completed 0.00 0 0 0 0
16 Culvert BC (Re-Con.) 238+429 0 0 - 0.00 0.00 0 0 0 0
17 Culvert BC (Re-Con.) 238+516 0 0 - 0.00 0.00 0 0 0 0
18 Culvert PC (Re-Con) 238+805 Vijay Kumar 0 - Completed 0.00 0 0 0 0
19 Culvert BC (Re-Con.) 238+937 0 0 - 0.00 0.00 0 0 0 0
20 Culvert BC (Re-Con.) 239+956 0 0 - 0.00 0.00 0 0 0 0
21 Culvert BC (Wid) 240+080 0 0 - Completed 0.00 0 0 0 0
22 Culvert BC (Re-Con.) 240+580 0 0 - 0.00 0.00 0 0 0 0
23 Culvert PC (Re-Con) 240+973 0 3 6.50 0.00 0.00 RHS PC PCC Complete 1 2 0
24 Culvert PC (Re-Con) 241+494 0 0 - 0.00 0.00 0 0 0 0
25 Culvert BC (Re-Con.) 243+349 0 0 - 0.00 0.00 0 0 0 0
26 Culvert BC (Wid) 243+617 0 0 - 0.00 0.00 0 0 0 0
27 Culvert BC (Re-Con.) 243+867 0 3 3.50 0.00 0.00 LHS BC PCC completed 0 0 0
28 Culvert PC (Re-Con) 244+309 0 0 - 0.00 0.00 0 0 0 0
29 Culvert PC (Re-Con) 247+300 0 0 - 0.00 0.00 0 0 0 0
30 Culvert PC (Re-Con) 247+690 0 0 - 0.00 0.00 0 0 0 0
31 Culvert PC (Re-Con.) 248+024 0 0 - Completed Completed 0 0 0 0
32 Culvert PC (Re-Con.) 248+214 0 0 - Completed Completed 0 0 0 0
33 Culvert PC (Re-Con.) 248+580 0 0 - Completed Completed 0 0 0 0
34 Culvert BC (Re-Con.) 250+492 Sanjay Kumar 5 - 0.00 0.00 RHS BC wall final Lift and Top Slab 0 0 0
Deshuttering Completed
35 Culvert PC (Re-Con.) 251+032 0 0 - 0.00 Completed 0 0 0 0
36 Culvert BC (Re-Con.) 251+955 Expedite 0 - 0.00 0.00 0 0 0 0
Infraconstructors
37 Culvert BC (Re-Con.) 252+400 NKC 0 - 0.00 0.00 0 0 0 0
38 Culvert BC (Wid) 258+512 0 0 - 0.00 0.00 0 0 0 0
39 Culvert BC (Wid) 258+962 Suresh Kumar 5 - 0.00 0.00 LHS BC Haunch shuttering work completed 0 0 0
LHS Top Slab Dismantling of inner side
40 Culvert BC (Wid) 259+090 Suresh Kumar 0 - Completed 0.00 Shuttering Completed 0 0 0
41 Culvert BC (Re-Con.) 259+437 Suresh Kumar 0 - Completed 0.00 0 0 0 0
42 Culvert BC (Re-Con.) 260+087 0 0 - 0.00 Completed 0 0 0 0
43 Culvert BC (Wid) 260+272 0 0 4.50 0.00 0.00 0 0 0 0
44 Culvert BC (Wid) 260+346 0 0 - 0.00 Completed 0 0 0 0
45 Culvert PC (Re-Con.) 261+148 0 0 - 0.00 0.00 0 0 0 0
46 Culvert BC (Wid) 261+207 0 0 - 0.00 0.00 0 0 0 0
47 Culvert BC (Re-Con.) 261+646 0 0 - 0.00 Completed 0 0 0 0
48 Culvert PC (Re-Con) 262+618 Suresh Kumar 4 5.50 0.00 0.00 Pipe Encasing Concrete completed 0 0 0
49 Culvert BC (Wid) 262+775 0 5 - 0.00 0.00 RHS Paraphet 1st Lift Shuttering 0 0 0
Completed
RHS Paraphet 1st Lift Shuttering
50 Culvert BC (Wid) 264+275 0 0 - 0.00 0.00 0 0 0
Completed
51 Culvert PC (Re-Con) 264+412 Milap Chand 0 - 0.00 Completed 0 0 0 0
52 Culvert BC (Re-Con.) 264+912 0 0 - Completed 0.00 0 0 0 0
53 Culvert PC (Re-Con) 264+539 Milap Chand 0 - Completed Completed 0 0 0 0
54 Culvert PC (Wid) 264+680 Milap Chand 0 - Completed Completed 0 0 0 0
Total 45 20.00 0.00 0.00 0.00 0.00 1.00 2.00 1.00
NKC PROJECTS PVT. LTD.
Project: Four Laning of TAKOLI to KULLU section of NH-21 (Km 242+00 to 272+00) under NHDP-IV B on EPC mode in the State of Himachal Pradesh.
Cumulative Completed Upto This Cerified upto previous
Weightage in % to the Contract Price BOQ To Be Certified this Month
Month month
S.No Description Amount (Crores) Remarks
Current
Sub-division Proposed Unit QTY Unit Rate Quantity Amount (Rs) Quantity Amount (Rs) Quantity Amount (Rs)
Schedule-H

The Contract Price for this Agreement is Rs. 3,288,310,336.00 Crores

1 Widening Subgrade Top 10.12% 332,777,006.00 Km 19.245 17,291,609 3.440 59,483,133 1.124 19,435,768 2.32 40,047,365
2 Widening WMM Top 7.59% 249,582,754.50 Km 19.245 12,968,706 0 5,965,605 - 0.46 5,965,605
3 Widening DBM Top 13.80% 65% 8.97% 294,961,437.14 Km 19.245 15,326,653 - - - -
4 Widening BC Top 35% 4.83% 158,825,389.23 Km 19.245 8,252,813 - - - -
5 Widening Box Culvert/Pipe Culverts 0.97% 31,896,610.26 Nos 26.000 1,226,793 - - - -
6 New- Subgrade Top 6.76% 222,289,778.71 Km 8.316 26,730,373 2.019 53,968,622 0.84 22,453,513 1.18 31,515,109
7 New WMM Top 3.59% 118,050,341.06 Km 8.316 14,195,568 - - - -
8 New DBM Top 5.11% 65% 3.32% 109,221,227.81 Km 8.316 13,133,866 - - - -
9 New BC Top 35% 1.79% 58,811,430.36 Km 8.316 7,072,082 - - - -
10 New Box Culvert 1.42% 20% 46,670,235.85 Nos 38.000 1,228,164 Err:504 Err:504 - Err:504 Err:504
11 New- Pipe Culvert 1.68% 35% 55,267,384.56 Nos 45.000 1,228,164 Err:504 Err:504 - Err:504 Err:504
12 MNB 1.11% 36,500,244.73 Nos 3.000 12,166,748 - - - -
13 VUP 0.74% 24,333,496.49 Nos 2.000 12,166,748 - - - -
14 VOP 0.44% 14,468,565.48 Nos 1.000 14,468,565 - - - -
15 MJB- Well Foundations (6 No.) 2.09% 68,725,686.02 RM 110.000 624,779 - - - -
16 MJB- Substructure 2.78% 91,415,027.34 Nos 19.000 4,811,317 - - - -
17 MJB- Superstructure 9.05% 297,592,085.41 Metres 524.000 567,924 - - - -
18 Toll Plaza 2.19% 72,013,996.36 Nos 1.000 72,013,996 - - - -
19 Road side drains 1.42% 46,694,006.77 Km 28.690 1,627,536 - - - -
20 Road signs etc.. 1.38% 45,378,682.64 Km 28.690 1,581,690 - - - -
21 Bus Bay 0.01% 328,831.03 Nos 2.000 164,416 - - - -
22 Rest Areas 0.03% 986,493.10 Nos 1.000 986,493 - - - -
23 Providing wearing coat Bridges 0.02% 657,662.07 Nos 3.000 219,221 - - - -
24 Replacement of bearings, joints 0.03% 986,493.10 Nos 3.000 328,831 - - - -
25 Providing crash barriers 0.01% 328,831.03 Nos 3.000 109,610 - - - -
26 Protection works 27.28% 897,051,059.66 Km 27.561 32,547,842 5.459 177,678,667 1.31 42,767,864 4.15 134,910,803
27 Safety, Traffic Management, Maintenance 0.24% 7,891,944.81 Months 30.000 263,065 - - - -
28 (x) Miscellaneous 0.14% 4,603,634.47 Km 28.690 160,461 - - - -
As per
Grand Total Amount (Rs) 3,288,310,336 Err:504 84,657,145 Err:504
Schedule-H
Actual Cumulative Completed as per DPR - Err:504
Certified upto IPC-02 201,428,259
NKC PROJECT PVT LTD
Daily Progress Report for month of Jan'2018
Date: 3-Jun-18
Project Cost in Rupees: ₹ 3,288,310,336.00

Unit rate Achieved Achieved


S.No BOQ Item Description Unit
Scope of Work in Lakhs Achieved up For the For the Cumulative Achived %
to Mar-18
day Month

Bridges, Underpasses, Overpasses, Approaches to ROB/RUB/Major


A
Bridges/Structures ( but excluding service roads)

Road Work (Widening and Strengthening of Existing Road ) (W&SER)


a Earthwork up to top of the Sub-grade
1 Excavation Ordinary Soil (W&SER) Km 0.00 0.00 0.00 0%
2 Excavation Hard Rock (W&SER) Km 0.00 0.00 0.00 0%
3 Embankment Layers (W&SER) 0.00 0.00 0%
4 Embankment top (W&SER) Km 19.245 51.87 3.250 0.00 0.00 3.25 0%
5 Subgrade Layers (W&SER) Km 3.250 0.00 0.03 3.28 0%
6 Subgrade top (W&SER) Km 19.245 121.04 3.395 0.00 0.05 3.44 0%
b Granular work (Sub-base, Base, Shoulders) 0.00 0%
5 Shoulder up to WMM TOP (W&SER) Km 0.00 0.00 0.00 0.00 0%
6 Shoulder from WMM-BC TOP (W&SER) Km 0.00 0.00 0.00 0.00 0%
7 GSB (W&SER) Km 19.245 77.81 0.81 0.00 0.05 0.86 0%
8 WMM 1st layer (W&SER) Km 0.39 0.00 0.00 0.39 0%
9 WMM Top (W&SER) Km 19.245 51.87 0.00 0.00 0.46 0.46 0%
10 Kerb (W&SER) Km 0.00 0.00 0.00 0.00 0%
c Bituminous Work 0.00 0%
11 DBM Top (W&SER) Km 19.245 141.48 0.00 0.00 0.00 0.00 0%
12 BC (W&SER) Km 19.245 94.32 0.00 0.00 0.00 0.00 0%
13 Median Filling (W&SER) Km 0.00 0.00 0.00 0.00 0%
Road Work (New 2-Lane Realignment / Bypass) 0.00 0.00 0%
a Earthwork up to top of the Sub-grade 0.00 0%
1 Excavation Ordinary Soil (Bypass) Km 0.00 0.00 0%
2 Excavation Hard Rock (Bypass) Km 0.00 0.00 0%
Embankment Layers (Bypass) 0.00 0.00 0%
3 Embankment top (Bypass) Km 8.316 160.38 1.969 0.00 0.00 1.97 0%
Subgrade Layers (Bypass) 0.00 0.00 0%
4 Subgrade top (Bypass) Km 8.316 106.92 2.019 0.00 0.00 2.02 0%
c Granular work (Sub-base, Base, Shoulders) 0.00 0.00 0%
5 Shoulder up to WMM TOP (Bypass) Km 0.00 0.00 0.00 0.00 0%
6 Shoulder from WMM-BC TOP (Bypass) Km 0.00 0.00 0.00 0.00 0%
7 GSB (Bypass) Km 8.316 85.17 0.79 0.00 0.00 0.79 0%
8 WMM 1st layer (Bypass) Km 0.13 0.00 0.00 0.13 0%
9 WMM Top (Bypass) Km 8.316 56.78 0.00 0.00 0.00 0.00 0%
10 Kerb (Bypass) Km 0.00 0.00 0.00 0.00 0%
d Bituminous Work 0.00 0.00 0%
11 DBM Top (Bypass) Km 8.316 121.24 0.00 0.00 0.00 0.00 0%
12 BC (Bypass) Km 8.316 80.82 0.00 0.00 0.00 0.00 0%
13 Median Filling (Bypass) Km 0.00 0.00 0.00 0.00 0%
Highways Total 1241.12 0.00 33.20 1274.32 Err:504
Widening and Repair of Culverts
Pipe Culverts (Widening)
1 HPC-Excavation (Widening) Nos 3 1.23 1.00 Err:504 Err:504 Err:504 0%
2 HPC-PCC M15 Head wall (Widening) Nos 3 1.23 1.00 Err:504 Err:504 Err:504 0%
3 HPC-Pipe Bottom (Widening) Nos 3 1.23 0.50 Err:504 Err:504 Err:504 0%
4 HPC-PCC M-20 (Head wall 1st lift) (Widening) Nos 3 1.23 0.50 Err:504 Err:504 Err:504 0%
5 HPC-Pipe laying (Widening) Nos 3 1.23 0.50 Err:504 Err:504 Err:504 0%
6 HPC-2nd lift (Widening) Nos 3 1.23 0.50 Err:504 Err:504 Err:504 0%
7 HPC-Cradle concrete (Widening) Nos 3 1.23 0.50 Err:504 Err:504 Err:504 0%
8 HPC-Final lift (Widening) Nos 3 1.23 0.50 Err:504 Err:504 Err:504 0%
10 HPC-Protection works (Widening) Nos 3 1.23 0.00 Err:504 Err:504 Err:504 0%
BOX Culvert (Widening) Err:504 Err:504 0%
1 BC-Excavation (Widening) Nos 23 1.23 8.00 Err:504 Err:504 Err:504 0%
2 BC-PCC (Widening) Nos 23 0.61 7.50 Err:504 Err:504 Err:504 0%
3 BC-Raft (Widening) Nos 23 1.23 6.00 Err:504 Err:504 Err:504 0%
4 BC-1st lift (Widening) Nos 23 0.61 5.50 Err:504 Err:504 Err:504 0%
5 BC-2nd Lift (Widening) Nos 23 0.61 2.50 Err:504 Err:504 Err:504 0%
6 BC-3rd lift (Widening) Nos 23 1.23 2.50 Err:504 Err:504 Err:504 0%
7 BC-Slab (Widening) Nos 23 2.45 2.50 Err:504 Err:504 Err:504 0%
8 BCRW-PCC (Widening) Nos 23 0.61 Err:504 Err:504 Err:504 0%
9 BCRW-Raft/Footing (Widening) Nos 23 0.61 Err:504 Err:504 Err:504 0%
10 BCRW-1st lift (Widening) Nos 23 0.61 Err:504 Err:504 Err:504 0%
11 BCRW-2nd lift (Widening) Nos 23 0.61 Err:504 Err:504 Err:504 0%
12 BCRW-Final lift (Widening) Nos 23 1.23 Err:504 Err:504 Err:504 0%
13 BC-Protection works (Widening) Nos 23 0.61 0.00 Err:504 Err:504 Err:504 0%
New Culverts Err:504 Err:504 0%
Pipe Culverts (Re-con) Err:504 Err:504 0%
1 HPC-Excavation (Re-con) Nos 45 1.23 8.00 Err:504 Err:504 Err:504 0%
2 HPC-PCC M15 Head wall (Re-con) Nos 45 1.23 7.00 Err:504 Err:504 Err:504 0%
3 HPC-Pipe Bottom (Re-con) Nos 45 1.23 7.00 Err:504 Err:504 Err:504 0%
4 HPC-PCC M-20 (Head wall 1st lift) (Re-con) Nos 45 1.23 7.00 Err:504 Err:504 Err:504 0%
5 HPC-Pipe laying (Re-con) Nos 45 1.23 5.00 Err:504 Err:504 Err:504 0%
6 HPC-2nd lift (Re-con) Nos 45 1.23 5.00 Err:504 Err:504 Err:504 0%
7 HPC-Cradle concrete (Re-con) Nos 45 1.23 4.50 Err:504 Err:504 Err:504 0%
8 HPC-Final lift (Re-con) Nos 45 1.23 4.50 Err:504 Err:504 Err:504 0%
10 HPC-Protection works (Re-con) Nos 45 1.23 0.00 Err:504 Err:504 Err:504 0%
BOX Culvert (Re-con) Err:504 Err:504 0%
1 BC-Excavation (Re-con) Nos 38 1.23 5.50 Err:504 Err:504 Err:504 0%
2 BC-PCC (Re-con) Nos 38 0.61 4.00 Err:504 Err:504 Err:504 0%
3 BC-Raft (Re-con) Nos 38 1.23 3.00 Err:504 Err:504 Err:504 0%
4 BC-1st lift (Re-con) Nos 38 0.61 3.00 Err:504 Err:504 Err:504 0%
5 BC-2nd Lift (Re-con) Nos 38 0.61 2.00 Err:504 Err:504 Err:504 0%
7 BC-Slab (Re-con) Nos 38 3.68 1.50 Err:504 Err:504 Err:504 0%
2 BCRW-PCC (Re-con) Nos 38 0.61 Err:504 Err:504 Err:504 0%
3 BCRW-Raft/Footing (Re-con) Nos 38 0.61 Err:504 Err:504 Err:504 0%
4 BCRW-1st lift (Re-con) Nos 38 0.61 Err:504 Err:504 Err:504 0%
5 BCRW-2nd lift (Re-con) Nos 38 0.61 Err:504 Err:504 Err:504 0%
6 BCRW-Final lift (Re-con) Nos 38 1.23 Err:504 Err:504 Err:504 0%
8 BC-Protection works (Re-con) Nos 38 0.61 0.50 Err:504 Err:504 Err:504 0%
Major Bridge Err:504 Err:504 0%

Well Foundation Err:504 Err:504 0%


i) Foundation Err:504 Err:504 0%
1 MJB-Well Curb Casting RM 13.6 1.81 13.60 Err:504 Err:504 Err:504 0%
2 MJB-Well Curb Sinking RM 13.6 1.81 11.20 Err:504 Err:504 Err:504 0%
3 MJB-Well Steining Casting RM 75.6 7.23 30.00 Err:504 Err:504 Err:504 0%
4 MJB-Well Steining Sinking RM 75.6 10.85 16.15 Err:504 Err:504 Err:504 0%
5 MJB-Well Cap Nos 6 3.62 0.00 Err:504 Err:504 Err:504 0%
6 MJB-Open Foundation Excavation Nos 13 3.62 0.00 Err:504 Err:504 Err:504 0%
7 MJB-Open Foundation PCC Nos 13 3.62 0.00 Err:504 Err:504 Err:504 0%
8 MJB-Open Foundation Raft Nos 13 3.62 0.00 Err:504 Err:504 Err:504 0%
ii) Sub-Structure Err:504 Err:504 0%
1 MJB-Pier 1st lift RM 6 4.81 0.00 Err:504 Err:504 Err:504 0%
2 MJB-Pier 2nd lift Nos 6 4.81 Err:504 Err:504 0%
3 MJB-Pier 3rd lift Nos 6 4.81 Err:504 Err:504 0%
4 MJB-Pier 4Th lift Nos 6 4.81 Err:504 Err:504 0%
5 MJB-Pier 5th lift Nos 6 4.81 Err:504 Err:504 0%
6 MJB-Pier 6th lift Nos 6 4.81 Err:504 Err:504 0%
7 MJB-Pier Final lift/Cap Nos 6 4.81 Err:504 Err:504 0%
8 MJB-1st lift (Open Foundation) Nos 13 4.81 0.00 Err:504 Err:504 Err:504 0%
9 MJB-2nd lift (Open Foundation) Nos 13 4.81 0.00 Err:504 Err:504 Err:504 0%
10 MJB-Final lift/cap (Open Foundation) Nos 13 4.81 0.00 Err:504 Err:504 Err:504 0%
iii) Super Structure Err:504 Err:504 0%
Project Cost in Rupees: ₹ 3,288,310,336.00

Unit rate Achieved Achieved


S.No BOQ Item Description Unit
Scope of Work in Lakhs Achieved up For the For the Cumulative Achived %
to Mar-18
day Month

10 MJB-Pier Head Nos 6 Err:504 Err:504 0%


16 MJB-Slab RM 700 Err:504 Err:504 0%
17 MJB-Crash barrier RM 1400 Err:504 Err:504 0%
18 MJB-Approach Slab RM 700 Err:504 Err:504 0%
19 MJB-Mastic Asphalt Nos Err:504 Err:504 0%
20 MJB-Drainage Spout Nos Err:504 Err:504 0%
21 MJB-Protection Works Nos Err:504 Err:504 0%
8 MJB-Pedestal (Open Foundation) Nos Err:504 Err:504 0%
9 MJB- I Girders casting (Open Foundation) Nos Err:504 Err:504 0%
10 MJB- Deck Slab Casting (Open Foundation) Nos Err:504 Err:504 0%
11 MJB-Stressing & Grouting (Open Foundation) Nos Err:504 Err:504 0%
12 MJB-Crash barrier (Open Foundation) Nos Err:504 Err:504 0%
13 MJB-Approach Slab (Open Foundation) Nos Err:504 Err:504 0%
Minor Bridge Err:504 Err:504 0%
1 MIB-Excavation Nos 6 6.08 4.00 Err:504 Err:504 Err:504 0%
2 MIB-PCC Nos 6 6.08 4.00 Err:504 Err:504 Err:504 0%
3 MIB-Raft Nos 6 6.08 4.00 Err:504 Err:504 Err:504 0%
4 MIB-1st lift Nos 6 6.08 4.00 Err:504 Err:504 Err:504 0%
5 MIB-2nd lift Nos 6 6.08 4.00 Err:504 Err:504 Err:504 0%
6 MIB-Final lift Nos 6 6.08 4.00 Err:504 Err:504 Err:504 0%
7 MIB-Abutment Cap Nos 6 12.17 4.00 Err:504 Err:504 Err:504 0%
8 MIB-Pedestal Nos 6 6.08 Err:504 Err:504 0%
9 MIB- I Girders casting Nos 3 12.17 Err:504 Err:504 0%
10 MIB- Deck Slab Casting Nos 3 18.25 Err:504 Err:504 0%
11 MIB-Stressing & Grouting Nos 3 6.08 Err:504 Err:504 0%
12 MIB-Crash barrier Nos 18 6.08 0.00 Err:504 Err:504 Err:504 0%
13 MIB-Approach Slab Nos 18 6.08 0.00 Err:504 Err:504 Err:504 0%
14 MIB-Mastic Asphalt Nos 18 6.08 Err:504 Err:504 0%
15 MIB-Drainage Spout Nos 18 6.08 Err:504 Err:504 0%
16 MIB-Protection Works Nos 18 6.08 Err:504 Err:504 0%
VUP & Retaining wall Err:504 Err:504 0%
2 VUP-PCC Nos 2 0.00 Err:504 Err:504 Err:504 0%
3 VUP-Raft/Footing Nos 2 0.00 Err:504 Err:504 Err:504 0%
4 VUP-1st lift Nos 2 0.00 Err:504 Err:504 Err:504 0%
5 VUP-2nd lift Nos 2 0.00 Err:504 Err:504 Err:504 0%
6 VUP-Final lift Nos 2 0.00 Err:504 Err:504 Err:504 0%
6 VUP-Slab Nos 2 0.00 Err:504 Err:504 Err:504 0%
7 VUP-Crash Barrier Nos 2 0.00 Err:504 Err:504 Err:504 0%
7 VUP-Protection Works Nos 2 0.00 Err:504 Err:504 Err:504 0%
1 VUP-R/W Excavation Nos 2 0.00 Err:504 Err:504 Err:504 0%
2 VUP-R/W PCC Nos 2 0.00 Err:504 Err:504 Err:504 0%
3 VUP-R/W Raft/Footing Nos 2 0.00 Err:504 Err:504 Err:504 0%
4 VUP-R/W 1st lift Nos 2 0.00 Err:504 Err:504 Err:504 0%
5 VUP-R/W 2nd lift Nos 2 0.00 Err:504 Err:504 Err:504 0%
6 VUP-R/W Final lift Nos 2 0.00 Err:504 Err:504 Err:504 0%
7 VUP-R/W Crash Barrier Nos 2 0.00 Err:504 Err:504 Err:504 0%
VOP & Retaining wall Err:504 Err:504 0%
2 VOP-PCC Nos 1 0.00 Err:504 Err:504 Err:504 0%
3 VOP-Raft/Footing Nos 1 0.00 Err:504 Err:504 Err:504 0%
4 VOP-1st lift Nos 1 0.00 Err:504 Err:504 Err:504 0%
5 VOP-2nd lift Nos 1 0.00 Err:504 Err:504 Err:504 0%
6 VOP-Final lift Nos 1 0.00 Err:504 Err:504 Err:504 0%
6 VOP-Slab Nos 1 0.00 Err:504 Err:504 Err:504 0%
7 VOP-Crash Barrier Nos 1 0.00 Err:504 Err:504 Err:504 0%
7 VOP-Protection Works Nos 1 0.00 Err:504 Err:504 Err:504 0%
1 VOP-R/W Excavation Nos 1 0.00 Err:504 Err:504 Err:504 0%
2 VOP-R/W PCC Nos 1 0.00 Err:504 Err:504 Err:504 0%
3 VOP-R/W Raft/Footing Nos 1 0.00 Err:504 Err:504 Err:504 0%
4 VOP-R/W 1st lift Nos 1 0.00 Err:504 Err:504 Err:504 0%
5 VOP-R/W 2nd lift Nos 1 0.00 Err:504 Err:504 Err:504 0%
6 VOP-R/W Final lift Nos 1 0.00 Err:504 Err:504 Err:504 0%
7 VOP-R/W Crash Barrier Nos 1 0.00 Err:504 Err:504 Err:504 0%

Structures Total 754.57 Err:504 Err:504 Err:504 Err:504

1 (ii) Toll Plaza Nos


2 (iii) Road side drains Km 0%
3 (iv) Road signs, markings, km stones, safety devices. Km 0%
4 (v) Project Facilities 0%
5 a) Bus Bay Nos 0%
6 (c) Rest areas Nos 0%
7 (vi) Repairs to bridges / Structures Nos 0%
8 (a) Providing wearing coat Nos 0%
9 (b) Replacement of bearings, joints Nos 0%
10 (c) Providing crash barriers Nos 0%
11 (viii) Protection works Km 0%
12 Gabion Retaining Wall Nos 27.561 162.74 5.41 0.00 0.00 5.41 0%
13 Gabion Breast Wall Nos 27.561 162.74 5.41 0.00 0.00 5.41 0%
14 Safety, Traffic Management and Maintenance during Construction Km 0%
15 (x) Miscellaneous Km 0%

Other.Works 1762.14 1762.14

Total Amnt (In Lakhs) 3757.83 Err:504 Err:504 Err:504 Err:504


Plant Reports
Section
Sl.No Cost code Description Month SHORTFALL REASONS
Unit Up to Dec'17 On Date
Cumulative

1 Boulders site to Camp MT 65,047 118 Err:509

Boulders Site to Gabion MT 10,926 - Err:509

Boulders camp to Gabion MT 4,689 - Err:509

Boulders camp to Other Works (STR & Camp Work) MT 232 - Err:509

Boulders camp to Crusher Plant MT 8,780 - Err:509

2 Crusher-1 Err:509

a GSB MT 7,382 - Err:509

b 40mm MT 547 - Err:509

20mm MT 126 - Err:509

10mm MT 200 - Err:509

c Dust MT 200 - Err:509

5 Batching Plant Cum Err:509 - Err:509

PCC M15 Cum 610 - Err:509

PCC M20 Cum 121 - Err:509

RCC M25 Cum 212 - Err:509

RCC M30 Cum 270 - Err:509

RCC M35 Cum 1,251 - Err:509

RCC M40 Cum -

6 WMM Plant MT - Err:509

7 Hot Mix Plant MT - Err:509


P
Description Unit May'18 Jun'18 1-Jun 2-Jun 3-Jun 4-Jun 5-Jun 6-Jun 7-Jun 8-Jun 9-Jun 10-Jun

Boulders site to Camp MT 6427.59 245.79 805.35 117.57 635.10 448.22 657.03 252.29 89.72 461.79 285.58

Boulders Site to Gabion MT 0.00

Boulders camp to Gabion MT 0.00

Boulders camp to Other Works


MT 0.00
(STR & Camp Work)

Boulders camp to Crusher Plant MT 9670.00 20.00 700.00 1280.00 420.00 1100.00 580.00 660.00 90.00

Crusher-1 0.00

GSB MT 3277.77 302.36 316.35 541.42 537.16 285.82

40mm MT 0.00

20mm MT 0.00

10mm MT 0.00

Dust MT 0.00

WMM MT 2836.93 336.10 363.01 304.67 430.92

Batching Plant 0.00

PCC M15 cum 540.00 30.00 42.50 30.50 50.00 24.00 7.00 10.00 77.00

PCC M20 cum 33.00 2.00 6.50

RCC M25 cum 0.00


RCC M30 cum 125.00 31.00 49.00

RCC M35 cum 272.50 75.00 67.50

RCC M40 cum 0.00

RCC M45 cum 0.00

WMM Plant MT 0.00

Hot Mix Plant(DBM) MT 66.56 215.27 92.28 122.99

Hot Mix Plant(BC) MT 1124.29 277.25 21.71 26.23 35.58 35.37 36.60 39.71
PLANTS DPR
11-Jun 12-Jun 13-Jun 14-Jun 15-Jun 16-Jun 17-Jun 18-Jun 19-Jun 20-Jun 21-Jun 22-Jun 23-Jun 24-Jun 25-Jun 26-Jun

278.38 744.31 478.27 292.25 283.69 352.25

800.00 1220.00 700.00 220.00 1080.00 800.00

282.92 552.48 81.77 321.52 55.97

182.91 254.75 47.67 365.89 411.13 139.88

38.50 60.50 67.00 15.00 88.00

6.00 6.00 7.00 5.50


45.00

130.00

82.05
27-Jun 28-Jun 29-Jun 30-Jun
S.No Description Unit May'18 Rate (Rs.) This Month 1-Jun

Road Work
Excavation Ordinary Soil (W&SER)
1 Ajay Pathania Cum 6700 95.00 4600.00 280.00
2 Bhupender Singh Cum 7968 95.00 1616.00 320.00
3 Jham Jham Cum 347 95.00 176.00 0.00
4 NKC Cum 10590 95.00 6834.00 496.00
5 KG Cum 0 95.00 8.00 0.00

Excavation Hard Rock (W&SER) 0 0.00


1 Ajay Pathania Cum 5305 147.00 2507.08 111.20
2 Bhupender Singh Cum 183 147.00 0.00 0.00
3 Jham Jham Cum 778 147.00 923.28 0.00
4 NKC Cum 7285 147.00 2056.56 45.16
5 KG Cum 960 147.00 785.40 89.43

Subgrade Layers (W&SER) 0 0.00


1 NKC Cum 1163 125.00 0.00

Gabion Retaining Wall


1 Ashok Kumar Contractor Cum 724 450.00 288.00 0.00
2 Bhagat Singh Cum 33 450.00 0.00 0.00
3 Chandan Premi Cum 306 450.00 228.00 3.00
4 Devi Singh Cum 159 450.00 87.00 9.00
5 Kamal Kant Cum 210 450.00 0.00 0.00
6 Kamlesh Thakur Cum 68 450.00 152.00 18.00
7 Kul Bahadur Cum 12 450.00 6.00 0.00
8 Madan Singh Chauhan Cum 276 450.00 135.00 0.00
9 Jyoti Savroop Singh Cum 450.00 45.00 6.00
10 Veneet Kumar Cum 450.00 45.00 0.00
11 Surender mahant Cum 120 450.00 39.00 3.00
0 450.00 0.00
PCC For RMM 0 0.00
1 Ajay Pathania Cum 28 200.00 0.00 0.00
2 Bhagwan Singh Cum 8 200.00 4.50 0.00
3 Milap Chand Cum 0 200.00 0.00 0.00
4 Kul Bahadur Cum 0 200.00 0.00 0.00

RRM Masonary 0 0.00


1 Ajay Pathania Cum 366 2200.00 0.00 0.00
2 Bhagwan Singh Cum 98 2200.00 0.00 0.00
3 Milap Chand Cum 20 2200.00 0.00 0.00
Total Amount in Lakhs 1.58
NKC PROJECT PV
Daily Progress Rep
2-Jun 3-Jun 4-Jun 5-Jun 6-Jun 7-Jun 8-Jun 9-Jun 10-Jun

0.00 328.00 216.00 448.00 352.00 328.00 200.00 272.00 360.00


256.00 176.00 144.00 120.00 144.00 0.00 120.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
256.00 0.00 280.00 592.00 640.00 312.00 648.00 456.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 8.00 0.00 0.00

106.94 94.83 169.14 40.12 110.78 158.34 66.56 160.83 214.64


0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
69.22 0.00 108.41 236.34 128.29 0.00 0.00 0.00 0.00
562.13 0.00 357.55 171.76 345.34 0.00 144.00 184.73 0.00
67.05 22.74 0.00 0.00 72.62 93.95 23.16 116.23 70.94

0.00 0.00 0.00 125.00 0.00 0.00 0.00 0.00 0.00

12.00 24.00 24.00 48.00 42.00 0.00 18.00 0.00 0.00


0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
24.00 9.00 18.00 24.00 12.00 0.00 18.00 0.00 24.00
0.00 0.00 0.00 0.00 0.00 0.00 12.00 0.00 12.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
12.00 9.00 9.00 9.00 12.00 0.00 6.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
12.00 0.00 12.00 6.00 18.00 0.00 36.00 0.00 12.00
9.00 9.00 12.00 9.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 9.00 0.00 9.00 0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00


0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00


0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
1.98 0.88 1.92 2.19 2.46 0.98 1.68 1.37 0.98
KC PROJECT PVT LTD
Daily Progress Report
11-Jun 12-Jun 13-Jun 14-Jun 15-Jun 16-Jun 17-Jun 18-Jun 19-Jun

272.00 176.00 312.00 368.00 344.00 344.00 0.00 0.00 0.00


0.00 0.00 336.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 176.00 0.00 0.00 0.00 0.00 0.00 0.00
760.00 938.00 240.00 40.00 456.00 720.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

191.38 530.01 274.72 112.05 38.19 127.35 0.00 0.00 0.00


0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
18.30 0.00 0.00 180.20 131.72 50.80 0.00 0.00 0.00
0.00 0.00 27.22 0.00 113.72 104.95 0.00 0.00 0.00
68.70 91.43 0.00 0.00 0.00 69.15 0.00 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.00 0.00 12.00 18.00 33.00 57.00 0.00 0.00 0.00


0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15.00 15.00 18.00 18.00 12.00 18.00 0.00 0.00 0.00
12.00 15.00 15.00 12.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 26.00 15.00 12.00 12.00 12.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 6.00 0.00 0.00 0.00
9.00 0.00 0.00 21.00 9.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 45.00 0.00 0.00 0.00
6.00 6.00 6.00 0.00 0.00 0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00


0.00 0.00 0.00 0.00 4.50 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00


0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
1.58 2.25 1.75 1.18 1.48 2.15 0.00 0.00 0.00
20-Jun 21-Jun 22-Jun 23-Jun 24-Jun 25-Jun 26-Jun 27-Jun 28-Jun

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00


0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00


0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00


0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00


0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00


0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
29-Jun 30-Jun

0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00

0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00

0.00 0.00

0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00

0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00

0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
S.No Date Contractor Progress work Layer Misc works From To Side Unit Nos Length Breadth Depth Quantity Excavators Dumpers JCB Grader Roller Water Tanker Exca with
Loader Breaker Boulder screning Labour Dumping Lead (One Dumping at Remarks
dumper Chainage Side) KM

1 1-Dec-17 Gaurav Const. Excavation Ordinary Soil (W&SER) Excavation upto SG Top 239+000 239+100 LHS Cum 24 192.00 6.00 1.00 2.00 237+940
May'18 1-May-18 Bhupender Singh Excavation Ordinary Soil (W&SER) Excavation upto SG Top 259+820 25+890 RHS Cum 70 560.00 2.00 2.00 1.00 259+750
May'18 1-May-18 Dinesh Kumar Saini Excavation Ordinary Soil (W&SER) Excavation upto SG Top 259+600 259+650 RHS Cum 60 480.00 1.00 2.00 259+750
May'18 1-May-18 KG Excavation Ordinary Soil (W&SER) Excavation upto SG Top 256+950 256+050 RHS Cum 2.00
May'18 1-May-18 Jham Jham Excavation Ordinary Soil (W&SER) Excavation upto SG Top 256+740 256+840 RHS Cum 1.00 1.00
May'18 1-May-18 DMC Excavation Hard Rock (W&SER) Excavation upto SG Top 243+600 243+700 LHS Cum 1.00 3.00
May'18 1-May-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 239+500 239+700 LHS Cum 40 320.00 2.00 7.00 1.00 241+000
May'18 1-May-18 Jham Jham Excavation Hard Rock (W&SER) Excavation upto SG Top 256+740 RHS Cum 2 27.81 248+700 B NKC Camp
May'18 1-May-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 236+900 237+600 LHS Cum 25 200.00 5.00
May'18 1-May-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 236+900 237+600 LHS Cum
May'18 2-May-18 DMC Excavation Hard Rock (W&SER) Excavation upto SG Top 243+600 243+700 LHS Cum 1.00 3.00
May'18 2-May-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 239+500 239+700 LHS Cum 40 320.00 2.00 7.00 1.00
May'18 2-May-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 236+900 237+600 LHS Cum 20 160.00 5.00
May'18 2-May-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 236+900 237+600 LHS Cum
May'18 2-May-18 Bhupender Singh Excavation Ordinary Soil (W&SER) Excavation upto SG Top 259+820 259+960 RHS Cum 43 344.00 2.00 2.00 1.00 259+750
May'18 2-May-18 Dinesh Kumar Saini Excavation Ordinary Soil (W&SER) Excavation upto SG Top 259+600 259+650 RHS Cum 1.00 2.00
May'18 2-May-18 KG Excavation Ordinary Soil (W&SER) Excavation upto SG Top 256+950 257+050 RHS Cum 2.00
May'18 2-May-18 Jham Jham Excavation Ordinary Soil (W&SER) Excavation upto SG Top 256+640 256+740 RHS Cum 1.00 2.00 1.00
May'18 2-May-18 NKC Subgrade Layers (W&SER) Bed Preperation 260+900 261+000 RHS Cum 1.00 1.00
May'18 2-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 260+800 260+830 RHS Cum 17 136.00 1.00 2.00 263+600
May'18 2-May-18 NKC Subgrade Layers (W&SER) Soil levelling 263+540 263+620 RHS Cum 1.00
May'18 2-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 246+700 246+800 LHS Cum 20 160.00 1.00 3.00 Radha Swami 7, 252400=11, 243+520=2
May'18 2-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+700 246+800 LHS Cum 10
May'18 2-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+700 246+800 LHS Cum 1.00
May'18 2-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+020 246+110 LHS Cum 1.00
May'18 2-May-18 NKC GSB (W&SER) GSB bed preperation 238+540 238+620 LHS Cum
May'18 2-May-18 NKC RRM Masonary WMM Bed Preperation 238+540 238+620 LHS Cum 1.00 1.00
May'18 2-May-18 NKC WMM Dumping WMM Unloading 238+540 238+620 LHS Cum 294.82
May'18 2-May-18 NKC GSB (W&SER) GSB Unloading 238+540 238+620 LHS Cum 56.26
May'18 2-May-18 NKC WMM Top (W&SER) WMM Unloading 243+180 243+230 LHS Cum
May'18 2-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 246+120 246+200 LHS Cum 34 272.00 1.00 6.00 Radha Swami 12, 252400=12, 243+520=10
May'18 2-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+120 246+200 LHS Cum 1.00
May'18 2-May-18 NKC WMM Dumping WMM Unloading 246+030 246+090 LHS Cum 56.20
May'18 2-May-18 NKC GSB (W&SER) GSB bed preperation 243+180 243+230 LHS Cum
May'18 2-May-18 Ashok Kumar Contractor Gabion Retaining Wall 3rd Gabion RW 3rd lift 251+525 258+534 LHS Cum 12 9.00 4 1 36.00 10
May'18 2-May-18 Jham Jham Excavation Hard Rock (W&SER) Excavation upto SG Top 256+650 256+660 RHS Cum 7 89.81 248+700 B NKC Camp
May'18 2-May-18 Bhupender Singh Excavation Hard Rock (W&SER) Excavation upto SG Top 259+820 RHS Cum 2 259+820 B Gabion
May'18 2-May-18 Dinesh Kumar Saini Excavation Hard Rock (W&SER) Excavation upto SG Top 259+650 RHS Cum 2 258+550 B Gabion
May'18 2-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+130 LHS Cum 6 91.41 248+700 B NKC Camp
May'18 2-May-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 237+500 LHS Cum 10 173.60 248+700 B NKC Camp
May'18 2-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+800 LHS Cum 6 91.41 248+700 B NKC Camp
May'18 2-May-18 DMC Excavation Hard Rock (W&SER) Excavation upto SG Top 243+700 Cum 14 155.14 248+700 B NKC Camp
May'18 3-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 240+000 240+050 LHS Cum 6 91.29 1.00 4.00 248+700 B NKC Camp
May'18 3-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 240+000 240+050 LHS Cum 10 152.16 2.00 248+700 B NKC Camp
May'18 3-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 240+000 240+055 LHS Cum 1.00 1.00
May'18 3-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 240+070 240+110 LHS Cum
May'18 3-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 240+070 240+100 LHS Cum 2 16.00 2.00 radha swami
May'18 3-May-18 NKC GSB (W&SER) GSB Top bed preperation 243+180 243+240 LHS Cum
May'18 3-May-18 NKC WMM Dumping WMM Unloading 243+180 243+240 LHS Cum
May'18 3-May-18 NKC WMM Dumping WMM Unloading 243+180 243+320 LHS Cum
May'18 3-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 246+720 246+800 LHS Cum 1.00 3.00
May'18 3-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+720 246+800 LHS Cum 3 45.65 248+700 B NKC Camp
May'18 3-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+720 246+800 LHS Cum 2.00
May'18 3-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+120 246+200 LHS Cum 12 182.59 2.00 3.00 248+700 B NKC Camp
May'18 3-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+120 246+200 LHS Cum 2.00
May'18 3-May-18 NKC GSB (W&SER) GSB Top bed preperation 248+050 248+140 BHS Cum 90.00 21 0.2 878.00 1.00 1.00
May'18 3-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 246+120 253+160 BHS Cum 11 77.00
May'18 3-May-18 DMC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 243+600 243+700 LHS Cum
May'18 3-May-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 239+500 239+700 LHS Cum 42 336.00 2.00
May'18 3-May-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 236+900 237+700 LHS Cum 25 200.00 5.00 7.00 1.00 241+000
May'18 3-May-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 237+500 LHS Cum 12 196.56 248+700 B NKC Camp
May'18 3-May-18 Ashok Kumar Contractor Gabion Retaining Wall 3rd Gabion RW 3rd lift 258+534 258+540 LHS Cum 8 6.00 4 1 24.00 9
May'18 3-May-18 Bhupender Singh Excavation Ordinary Soil (W&SER) Excavation upto SG Top 259+820 259+960 RHS Cum 28 224.00 2.00 2.00 1.00 259+750
May'18 3-May-18 Dinesh Kumar Saini Excavation Ordinary Soil (W&SER) Excavation upto SG Top 259+600 259+650 RHS Cum 22 176.00 1.00 1.00 259+750
May'18 3-May-18 KG Excavation Ordinary Soil (W&SER) Excavation upto SG Top 256+950 257+050 RHS Cum 2.00
May'18 3-May-18 KG Excavation Hard Rock (W&SER) Excavation upto SG Top 5 53.12 248+700 B NKC Camp
May'18 3-May-18 Jham Jham Excavation Ordinary Soil (W&SER) Excavation upto SG Top 256+640 256+740 RHS Cum 1.00 2.00 1.00
May'18 3-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 260+800 260+830 RHS Cum 10 80.00 1.00 1.00 263+600 8 trips 263600, 2 trips sevbag
May'18 3-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 260+100 260+200 RHS Cum 6 91.29 1.00 3.00 1.00 248+700 B NKC Camp
May'18 3-May-18 NKC Subgrade Layers (W&SER) Bed Preperation 263+550 263+600 LHS Cum
May'18 3-May-18 Revati Ram Excavation Hard Rock (W&SER) Excavation upto SG Top 6 98.53 248+700 B NKC Camp
May'18 4-May-18 NKC GSB (W&SER) GSB Top bed completed 251+840 251+900 LHS Cum 60.00 11.5 0.2 1.00 1.00 1.00
May'18 4-May-18 NKC WMM Dumping WMM Unloading Camp 248+000 BHS Cum 560.00 4.00 248+100
May'18 4-May-18 DMC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 243+600 243+700 LHS Cum 1.00 3.00
May'18 4-May-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 239+700 239+800 LHS Cum 24 192.00 2.00 241+000
May'18 4-May-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 237+600 237+700 LHS Cum 5 40.00 5.00 7.00 1.00
May'18 4-May-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 236+800 236+850 LHS Cum 14 247.13 248+700 B NKC Camp
May'18 4-May-18 Bhupender Singh Excavation Ordinary Soil (W&SER) Excavation upto SG Top 259+820 259+960 RHS Cum 42 336.00 3.00 2.00 1.00
May'18 4-May-18 KG Excavation Ordinary Soil (W&SER) Excavation upto SG Top 256+050 257+100 RHS Cum 2.00 1.00
May'18 4-May-18 Jham Jham Excavation Ordinary Soil (W&SER) Excavation upto SG Top 256+640 256+740 RHS Cum 2.00 2.00
May'18 4-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 260+800 260+830 RHS Cum 14 112.00 1.00 2.00 sevbag=6, 263+600= 8 trips
May'18 4-May-18 Revati Ram Excavation Hard Rock (W&SER) Excavation upto SG Top 260+100 260+200 RHS Cum 9 153.43 1.00 3.00 248+700 B NKC Camp Boulder trip by nkc
May'18 4-May-18 NKC Subgrade Layers (W&SER) Bed Preperation 263+500 263+600 RHS Cum 1.00 1.00
May'18 4-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 240+050 240+055 LHS Cum 2 16.00 1.00 1.00 radha swami 2 trips
May'18 4-May-18 NKC GSB (W&SER) GSB Unloading 240+070 240+110 LHS Cum 9 243.35
May'18 4-May-18 NKC WMM Dumping WMM Unloading 243+180 243+240 LHS Cum 4 114.55
May'18 4-May-18 NKC WMM Dumping WMM Unloading 243+340 243+380 LHS Cum 3 83.35
May'18 4-May-18 NKC GSB (W&SER) GSB Bed Preperation 240+070 240+110 LHS Cum
May'18 4-May-18 NKC Subgrade Layers (W&SER) Bed Preperation 240+000 240+050 LHS Cum 1.00 1.00
May'18 4-May-18 NKC WMM Top (W&SER) Bed Preperation completed 243+240 243+320 LHS Cum
May'18 4-May-18 NKC WMM Top (W&SER) Bed Preperation completed 243+340 243+380 LHS Cum
May'18 4-May-18 NKC Subgrade Layers (W&SER) Bed Preperation 239+000 239+050 LHS Cum 9 1.00 4.00
May'18 4-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 246+120 246+200 LHS Cum 27 216.00 2.00 4.00 24370=6,245+600=21
May'18 4-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+120 246+200 LHS Cum 14 221.67 248+700 B NKC Camp
May'18 4-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+120 246+200 LHS Cum 1.00
May'18 4-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 246+700 246+800 LHS Cum 1.00 1.00
May'18 4-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+700 246+800 LHS Cum 11 174.17 1.00 1.00 248+700 B NKC Camp
May'18 4-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+700 246+800 LHS Cum
May'18 4-May-18 NKC Excavation Ordinary Soil (W&SER) Bed Preperation 243+600 243+620 RHS Cum
May'18 4-May-18 KG Excavation Hard Rock (W&SER) Excavation upto SG Top 256+050 256+070 RHS Cum 6 76.48 248+700 B NKC Camp
May'18 5-May-18 NKC GSB (W&SER) GSB Unloading 251+840 ### RHS Cum 60.00 11.5 0.2 138.00 1.00 1.00
May'18 5-May-18 NKC WMM Dumping WMM Unloading Camp 248+000 BHS Cum 11 318.00 3.00
May'18 5-May-18 NKC WMM Top (W&SER) WMM Bed Preperation 254+550 254+562 LHS Cum 4 3.00 4 1 12.00 8
May'18 5-May-18 NKC Gabion Retaining Wall 3rd Gabion RW 3rd lift 251+640 251+840 LHS Cum 200.00 10.5 0.125
May'18 5-May-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 239+700 239+800 LHS Cum 14 112.00 2.00 9.00 1.00 241+000
May'18 5-May-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 237+600 237+700 LHS Cum 23 184.00
May'18 5-May-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 237+600 237+700 LHS Cum 5 88.15 248+700 B NKC Camp
May'18 5-May-18 NKC GSB (W&SER) GSB Top bed preperation completed 240+070 240+110 LHS Cum 1.00 1.00
May'18 5-May-18 NKC GSB (W&SER) GSB Top bed preperation 240+000 240+055 LHS Cum 10 283.86
May'18 5-May-18 NKC WMM Top (W&SER) WMM Bed Preperation 243+340 243+380 LHS Cum
May'18 5-May-18 NKC WMM Top (W&SER) WMM Bed Preperation 243+180 243+240 LHS Cum
May'18 5-May-18 NKC WMM Dumping WMM Unloading 241+240 241+360 MT Cum 10 297.28
May'18 5-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 246+120 246+200 LHS Cum 45 360.00 2.00 4.00 radha swami 42, 252+000=3 trips
May'18 5-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+120 246+200 LHS Cum 10 164.59 248+700 B NKC Camp
May'18 5-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+120 246+200 LHS Cum 1.00
May'18 5-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 246+700 246+800 LHS Cum 1.00 2.00
May'18 5-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+700 246+800 LHS Cum 9 148.13 2.00 248+700 B NKC Camp
May'18 5-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+700 246+800 LHS Cum
May'18 5-May-18 NKC Subgrade Layers (W&SER) Bed Preperation 2399+900 RHS Cum
May'18 5-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 238+900 LHS Cum 5 1.00 3.00
May'18 5-May-18 Bhupender Singh Excavation Ordinary Soil (W&SER) Excavation upto SG Top 259+890 259+960 RHS Cum 52 416.00 3.00 2.00 1.00 259+750
May'18 5-May-18 KG Excavation Ordinary Soil (W&SER) Excavation upto SG Top 256+950 257+050 RHS Cum 2.00 1.00
May'18 5-May-18 Jham Jham Excavation Ordinary Soil (W&SER) Excavation upto SG Top 256+640 256+740 RHS Cum 275.00 1.00 1.00 1.00
May'18 5-May-18 NKC Subgrade Layers (W&SER) Bed Preperation 260+900 261+000 RHS Cum 100.00 11 0.25 1.00 1.00
May'18 5-May-18 NKC Subgrade Layers (W&SER) Bed Preperation 260+800 260+830 RHS Cum 6 48.00 1.00 2.00
May'18 5-May-18 Bhupender Singh Excavation Hard Rock (W&SER) Excavation upto SG Top 259+850 259+900 RHS Cum 5 258+550 B Gabion
May'18 5-May-18 Bhupender Singh Excavation Hard Rock (W&SER) Excavation upto SG Top 259+850 259+900 RHS Cum 2 263+580 B Gabion
May'18 5-May-18 Bhupender Singh Excavation Hard Rock (W&SER) Excavation upto SG Top 259+850 259+900 RHS Cum 1 264+500 B Gabion
May'18 5-May-18 Bhupender Singh Excavation Hard Rock (W&SER) Excavation upto SG Top 259+850 259+900 RHS Cum 1 260+140 B Gabion
May'18 5-May-18 Bhupender Singh Excavation Hard Rock (W&SER) Excavation upto SG Top 259+850 259+900 RHS Cum 1 258+540 B Gabion
May'18 5-May-18 Jham Jham Excavation Hard Rock (W&SER) Excavation upto SG Top 256+700 256+750 RHS Cum 3 49.73 248+700 B NKC Camp
May'18 5-May-18 Jham Jham Excavation Hard Rock (W&SER) Excavation upto SG Top 256+700 256+750 RHS Cum 1 254+600 B Gabion
May'18 6-May-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 237+600 237+700 LHS Cum 13 104.00
May'18 6-May-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 239+700 239+800 LHS Cum 7 56.00 2.00 9.00 1.00 241+000
May'18 6-May-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 237+600 237+700 LHS Cum
May'18 6-May-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 237+600 237+700 LHS Cum 2 33.94 248+700 B NKC Camp
May'18 6-May-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 237+700 239+800 LHS Cum
May'18 6-May-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 239+700 239+800 LHS Cum 10 169.72 248+700 B NKC Camp
May'18 6-May-18 KG Excavation Hard Rock (W&SER) Excavation upto SG Top 257+000 257+050 RHS Cum 1 19.97 248+700 B NKC Camp
May'18 6-May-18 Jham Jham Excavation Hard Rock (W&SER) Excavation upto SG Top 256+700 256+750 RHS Cum 7 86.83 248+700 B NKC Camp
May'18 5-May-18 Kul Bahadur Gabion Retaining Wall 2nd Gabion RW 2nd lift 264+559 264+565 LHS Cum 4 6.00 2 1 12.00 5
May'18 5-May-18 Devi Singh Gabion Retaining Wall 2nd Gabion RW 2nd lift 264+565 264+568 LHS Cum 2 3.00 2 1 6.00 2
May'18 5-May-18 Surender mahant Gabion Retaining Wall 5th Gabion RW 5th lift 263+649 263+652 LHS Cum 2 3.00 2 1 6.00 5
May'18 5-May-18 Surender mahant Gabion Retaining Wall 6th Gabion RW 6th lift 263+646 263+649 LHS Cum 2 3.00 2 1 6.00
May'18 5-May-18 Chandan Premi Gabion Retaining Wall 3rd Gabion RW 3rd lift 261+113 261+119 LHS Cum 6 6.00 3 1 18.00 9
May'18 5-May-18 Ashok Kumar Contractor Gabion Retaining Wall 3rd Gabion RW 3rd lift 258+516 258+525 LHS Cum 12 9.00 4 1 36.00 12
May'18 5-May-18 Ashok Kumar Contractor Gabion Retaining Wall 3rd Gabion RW 3rd lift 258+540 258+549 LHS Cum 12 9.00 4 1 36.00
May'18 6-May-18 Ashok Kumar Contractor Gabion Retaining Wall 3rd Gabion RW 3rd lift 258+549 258+558 LHS Cum 12 9.00 4 1 36.00 9
May'18 6-May-18 Surender mahant Gabion Retaining Wall 7th Gabion RW 7th lift 263+600 263+609 LHS Cum 3 9.00 1 1 9.00 4
May'18 6-May-18 Chandan Premi Gabion Retaining Wall 3rd Gabion RW 3rd lift 261+079 261+085 LHS Cum 4 6.00 2 1 12.00 6
May'18 7-May-18 KG Excavation Hard Rock (W&SER) Excavation upto SG Top 257+000 RHS Cum 6 60.41 248+700 B NKC Camp
May'18 7-May-18 KG Excavation Hard Rock (W&SER) Excavation upto SG Top 257+000 RHS Cum 2 24.00 254+600 B Gabion
May'18 7-May-18 Jham Jham Excavation Hard Rock (W&SER) Excavation upto SG Top 256+700 RHS Cum 2 28.86 248+700 B NKC Camp
May'18 7-May-18 Bhupender Singh Excavation Hard Rock (W&SER) Excavation upto SG Top 258+850 RHS Cum 3 36.00 261+100 B Gabion
May'18 7-May-18 Surender mahant Gabion Retaining Wall 7th Gabion RW 7th lift 263+609 263+624 LHS Cum 5 15.00 1 1 15.00 4
May'18 7-May-18 Chandan Premi Gabion Retaining Wall 4th Gabion RW 4th lift 261+085 261+091 LHS Cum 4 6.00 2 1 12.00 5
May'18 7-May-18 Bhupender Singh Excavation Ordinary Soil (W&SER) Excavation upto SG Top 259+820 259+960 RHS Cum 55 440.00 3.00 2.00 1.00 259+750
May'18 7-May-18 KG Excavation Ordinary Soil (W&SER) Excavation upto SG Top 256+950 257+050 RHS Cum 2.00 1.00
May'18 7-May-18 Jham Jham Excavation Ordinary Soil (W&SER) Excavation upto SG Top 256+640 256+740 RHS Cum 2.00 1.00
May'18 7-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 260+800 260+830 RHS Cum 9 72.00 1.00 1.00 263+500
May'18 7-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+700 LHS Cum 9 248+700 B NKC Camp
May'18 7-May-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 237+400 LHS Cum 5 78.64 2.00 7.00 1.00 248+700 B NKC Camp
May'18 7-May-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 236+700 LHS Cum 5 78.64 248+700 B NKC Camp
May'18 7-May-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 239+650 LHS Cum 6 94.36 248+700 B NKC Camp
May'18 7-May-18 NKC WMM Top (W&SER) WMM Bed Preperation 252+000 252+100 RHS Cum 100.00 10.5 0.125 131.25
May'18 7-May-18 NKC WMM Top (W&SER) WMM Bed Preperation 251+670 251+840 RHS Cum 170.00 10.5 0.125 223.13 1.00 1.00 1.00
May'18 7-May-18 NKC WMM Dumping WMM Unloading Camp 248+000 BHS Cum 7 193.78
May'18 7-May-18 Madan Singh Chauhan Gabion Retaining Wall 3rd Gabion RW 3rd lift 254+532 254+571 LHS Cum 3 9.00 1 1 9.00 8
May'18 7-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 243+180 243+280 RHS Cum 17 136.00 1.00 2.00 17 trips radha swami
May'18 7-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 243+180 243+280 RHS Cum
May'18 7-May-18 NKC GSB (W&SER) GSB Unloading 243+180 243+280 RHS Cum 2 55.00
May'18 7-May-18 NKC WMM Top (W&SER) WMM Bed Preperation 241+240 241+360 LHS Cum 1.00 1.00
May'18 7-May-18 NKC WMM Top (W&SER) WMM Bed Preperation 240+000 240+110 LHS Cum
May'18 7-May-18 NKC WMM Dumping WMM Unloading 240+000 240+110 LHS Cum 10 290.10
May'18 7-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 246+700 246+800 LHS Cum 1.00 3.00
May'18 7-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+700 246+800 LHS Cum 9 157.15
May'18 7-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+700 246+800 LHS Cum 2.00
May'18 7-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 246+120 246+200 LHS Cum 32 256.00 Radha swami
May'18 7-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+120 246+200 LHS Cum 1.00
May'18 8-May-18 NKC WMM Dumping WMM Unloading 240+000 243+250 RHS Cum 3 83.61
May'18 8-May-18 NKC GSB Dumping GSB Unloading 243+180 243+280 RHS Cum 2 50.88
May'18 8-May-18 NKC WMM Dumping WMM Unloading 243+180 243+240 LHS Cum 4 81.25
May'18 8-May-18 NKC WMM Dumping WMM Unloading 243+180 243+280 RHS Cum 3 109.18
May'18 8-May-18 NKC GSB (W&SER) GSB Top layer Bed Preperation 243+180 243+280 RHS Cum
May'18 8-May-18 NKC WMM Top (W&SER) Excavation upto SG Top 243+180 243+280 RHS Cum 1.00 1.00
May'18 8-May-18 NKC WMM Top (W&SER) WMM Bed Preperation 243+180 243+280 LHS Cum
May'18 8-May-18 NKC WMM Top (W&SER) WMM Bed Preperation 240+000 240+050 LHS Cum
May'18 8-May-18 NKC WMM Top (W&SER) WMM Bed Preperation 240+065 240+110 LHS Cum
May'18 8-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 246+120 246+200 LHS Cum 58 464.00 1.00 6.00 radha swami dumping yard 58 trips
May'18 8-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+120 246+200 LHS Cum 5 1.00 1.00
May'18 8-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+120 246+200 LHS Cum 1.00
May'18 8-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 246+700 246+200 LHS Cum
May'18 8-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+700 246+800 LHS Cum 6 2.00
May'18 8-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+700 246+800 LHS Cum
May'18 8-May-18 NKC WMM Dumping WMM Unloading Camp 248+450 BHS Cum 267.00 3.00
May'18 8-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+700 LHS Cum 6 98.03 248+700 B NKC Camp
May'18 8-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+120 LHS Cum 5 81.69 248+700 B NKC Camp
May'18 8-May-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 237+400 LHS Cum 11 193.96 2.00 6.00 1.00 248+700 B NKC Camp
May'18 9-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 246+120 246+200 LHS Cum 36 288.00 1.00 3.00 radha swami 32 trips
May'18 9-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+120 246+200 LHS Cum 1.00
May'18 9-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+700 246+740 LHS Cum 20 402.14 1.00 3.00 248+700 B NKC Camp
May'18 9-May-18 NKC WMM Top (W&SER) WMM Bed Preperation 241+240 241+340 LHS Cum 1.00 1.00
May'18 9-May-18 NKC WMM Top (W&SER) WMM Bed Preperation 241+360 241+420 LHS Cum 3 81.91
May'18 9-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 243+600 243+680 LHS Cum 5 1.00 3.00
May'18 9-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+700 246+800 LHS Cum 40.00 1.00 1.00 radha swami
May'18 9-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 243+600 243+630 LHS Cum 4
May'18 9-May-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 237+600 237+700 LHS Cum 10 80.00 5.00
May'18 9-May-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 239+700 239+500 LHS Cum 9 72.00 2.00 7.00 1.00 241+000
May'18 9-May-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 237+600 237+700 LHS Cum
May'18 9-May-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 239+700 239+500 LHS Cum 16 283.04 248+700 B NKC Camp
May'18 9-May-18 NKC WMM Top (W&SER) WMM Bed Preperation 252+100 252+200 RHS Cum 100.00 10.5 0.125 131.00
May'18 9-May-18 NKC WMM Top (W&SER) WMM Bed Preperation 251+840 251+900 LHS Cum 60.00 10.5 0.125 76.00 1.00 1.00 1.00
May'18 9-May-18 Madan Singh Chauhan Gabion Retaining Wall 3rd Gabion RW 3rd lift 254+562 254+574 LHS Cum 4 12.00 1 1 12.00 8
May'18 9-May-18 Jham Jham Excavation Hard Rock (W&SER) Excavation upto SG Top 6 71.38 248+700 B NKC Camp
May'18 9-May-18 KG Excavation Hard Rock (W&SER) Excavation upto SG Top 257+000 2 20.00 261+130 B Gabion
May'18 9-May-18 Jham Jham Excavation Hard Rock (W&SER) Excavation upto SG Top 256+700 1 10.00 254+600 B Gabion
May'18 9-May-18 Bhupender Singh Excavation Hard Rock (W&SER) Excavation upto SG Top 258+850 2 20.00 258+560 B Gabion
May'18 9-May-18 Surender mahant Gabion Retaining Wall 7th Gabion RW 7th lift 263+624 263+633 LHS Cum 3 9.00 1 1 9.00 4
May'18 9-May-18 Chandan Premi Gabion Retaining Wall 4th Gabion RW 4th lift 261+091 261+097 LHS Cum 4 6.00 2 1 12.00 5
May'18 9-May-18 Ashok Kumar Contractor Gabion Retaining Wall 3rd Gabion RW 3rd lift 258+558 258+561 LHS Cum 4 3.00 4 1 12.00 9
May'18 9-May-18 Ashok Kumar Contractor Gabion Retaining Wall 3rd Gabion RW 3rd lift 258+513 258+516 LHS Cum 4 3.00 4 1 12.00
May'18 10-May-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 236+900 236+700 LHS Cum 10 80.00 2.00 7.00 1.00
May'18 10-May-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 239+500 239+700 LHS Cum 96.00 5.00
May'18 10-May-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 239+500 239+700 LHS Cum 12 211.54 248+700 B NKC Camp
May'18 10-May-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 236+900 237+700 LHS Cum
May'18 10-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+120 246+200 LHS Cum 1.00
May'18 10-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+120 246+200 LHS Cum 8 182.34 1.00 3.00 248+700 B NKC Camp
May'18 10-May-18 NKC WMM Top (W&SER) WMM Bed Preperation 240+000 240+060 LHS Cum 8 217.18 1.00 1.00
May'18 10-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+700 246+740 LHS Cum 3.00 3.00
May'18 10-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+700 246+740 LHS Cum 4 1.00
May'18 10-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 243+060 243+700 LHS Cum 7 56.00 1.00 2.00
May'18 10-May-18 Bhupender Singh Excavation Ordinary Soil (W&SER) Excavation upto SG Top 259+820 259+960 RHS Cum 28 224.00 3.00 2.00 1.00 259+750
May'18 10-May-18 KG Excavation Ordinary Soil (W&SER) Excavation upto SG Top 256+950 257+100 RHS Cum 2.00 1.00
May'18 10-May-18 Jham Jham Excavation Ordinary Soil (W&SER) Excavation upto SG Top 256+640 256+750 RHS Cum 1.00 1.00 1.00
May'18 10-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 261+800 260+830 RHS Cum 6 48.00 1.00 2.00 263+500
May'18 10-May-18 NKC GSB Dumping GSB Unloading 260+900 260+990 RHS Cum 11 280.58
May'18 10-May-18 Jham Jham Excavation Hard Rock (W&SER) Excavation upto SG Top 256+700 RHS Cum 4 50.24 248+700 B NKC Camp
May'18 10-May-18 Jham Jham Excavation Hard Rock (W&SER) Excavation upto SG Top 256+700 RHS Cum 1 10.00 254+600 B Gabion
May'18 10-May-18 Bhupender Singh Excavation Hard Rock (W&SER) Excavation upto SG Top 258+850 RHS Cum 1 10.00 258+560 B Gabion
May'18 10-May-18 Bhupender Singh Excavation Hard Rock (W&SER) Excavation upto SG Top 258+850 RHS Cum 1 10.00 261+120 B Gabion
May'18 10-May-18 Bhupender Singh Excavation Hard Rock (W&SER) Excavation upto SG Top 258+850 RHS Cum 2 20.00 263+580 B Gabion
May'18 10-May-18 Bhupender Singh Excavation Hard Rock (W&SER) Excavation upto SG Top 258+850 RHS Cum 2 20.00 264+550 B Gabion
May'18 10-May-18 Devi Singh Gabion Retaining Wall 1st Gabion RW 1st lift 261+580 261+581 LHS Cum 1 1.00 3 1 3.00 2
May'18 10-May-18 Surender mahant Gabion Retaining Wall 7th Gabion RW 7th lift 263+633 263+642 LHS Cum 3 9.00 1 1 9.00 4
May'18 10-May-18 Chandan Premi Gabion Retaining Wall 4th Gabion RW 4th lift 261+097 261+109 LHS Cum 8 12.00 2 1 24.00 10
May'18 10-May-18 Ashok Kumar Contractor Gabion Retaining Wall 3rd Gabion RW 3rd lift 258+510 258+513 LHS Cum 4 3.00 4 1 12.00 9
May'18 10-May-18 Ashok Kumar Contractor Gabion Retaining Wall 3rd Gabion RW 3rd lift 258+561 258+564 LHS Cum 4 3.00 4 1 12.00
May'18 10-May-18 Bhagat Singh Gabion Retaining Wall 4th Gabion RW 4th lift 264+600 264+606 LHS Cum 2 6.00 1 1 6.00 5
May'18 11-May-18 NKC WMM Top (W&SER) WMM Bed Preperation 252+180 252+100 LHS Cum 80.00 10.5 0.125 105.00 1.00 1.00
May'18 11-May-18 NKC WMM Top (W&SER) WMM Bed Preperation 248+050 248+140 LHS Cum 90.00 10.5 0.125 118.00
May'18 11-May-18 Madan Singh Chauhan Gabion Retaining Wall 1st Gabion RW 1st lift 254+562 254+566 LHS Cum 4 4.00 3 1 12.00 8
May'18 11-May-18 NKC WMM Top (W&SER) WMM Bed Preperation 240+000 240+057 LHS MT 3 86.95 1.00
May'18 11-May-18 NKC WMM Top (W&SER) WMM Bed Preperation 240+060 240+110 LHS Cum 1.00 1.00
May'18 11-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 244+150 244+230 RHS Cum 1 8.00
May'18 11-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 244+150 246+800 RHS Cum 1.00 3.00
May'18 11-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+700 246+800 LHS Cum 8 2.00
May'18 11-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+700 246+800 LHS Cum 1.00
May'18 11-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+700 246+200 LHS Cum 1.00 5.00 1.00
May'18 11-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 246+126 246+200 LHS Cum 26 208.00 Radha swami 26 trips
May'18 11-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+120 246+200 LHS Cum 12
May'18 11-May-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 239+500 239+700 LHS Cum 13 104.00 2.00 7.00 1.00 241+000
May'18 11-May-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 236+900 237+700 LHS Cum 10 80.00 5.00
May'18 11-May-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 236+900 237+700 LHS Cum
May'18 11-May-18 Bhupender Singh Excavation Ordinary Soil (W&SER) Excavation upto SG Top 259+820 259+960 RHS Cum 58 464.00 3.00 2.00 1.00 259+750
May'18 11-May-18 KG Excavation Ordinary Soil (W&SER) Excavation upto SG Top 256+950 257+100 RHS Cum
May'18 11-May-18 Jham Jham Excavation Ordinary Soil (W&SER) Excavation upto SG Top 256+640 256+800 RHS Cum 2.00 1.00
May'18 11-May-18 NKC GSB Dumping GSB Unloading 260+900 260+990 RHS MT 7 191.45
S.No Date Contractor Progress work Layer Misc works From To Side Unit Nos Length Breadth Depth Quantity Excavators Dumpers JCB Grader Roller Water Tanker Exca with
Loader Breaker Boulder screning Labour Dumping Lead (One Dumping at Remarks
dumper Chainage Side) KM

May'18 11-May-18 NKC WMM Dumping WMM Unloading 261+660 261+780 RHS MT 3 82.10 1.00 1.00
May'18 11-May-18 NKC WMM Top (W&SER) WMM Bed Preperation 260+900 260+990 RHS Cum
May'18 11-May-18 NKC WMM Top (W&SER) WMM Bed Preperation 260+370 260+430 RHS Cum
May'18 11-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 260+800 260+830 RHS Cum 15 120.00 1.00 2.00 263+530
May'18 11-May-18 Jham Jham Excavation Hard Rock (W&SER) Excavation upto SG Top 256+700 RHS Cum 6 71.77 248+700 B NKC Camp
May'18 11-May-18 Bhupender Singh Excavation Hard Rock (W&SER) Excavation upto SG Top 258+850 RHS Cum 1 258+560 B Gabion
May'18 11-May-18 Bhupender Singh Excavation Hard Rock (W&SER) Excavation upto SG Top 258+850 RHS Cum 2 261+120 B Gabion
May'18 11-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+120 LHS Cum 12 182.97 248+700 B NKC Camp
May'18 11-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+700 LHS Cum 8 121.98 248+700 B NKC Camp
May'18 11-May-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 237+400 LHS Cum 23 382.22 248+700 B NKC Camp
May'18 11-May-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 236+700 LHS Cum 248+700 B NKC Camp
May'18 11-May-18 Devi Singh Gabion Retaining Wall 1st Gabion RW 1st lift 264+581 264+582 LHS Cum 1 1.00 3 1 3.00 2
May'18 11-May-18 Bhagat Singh Gabion Retaining Wall 4th Gabion RW 4th lift 264+606 264+612 LHS Cum 2 6.00 1 1 6.00 4
May'18 11-May-18 Surender mahant Gabion Retaining Wall 7th Gabion RW 7th lift 263+642 263+648 LHS Cum 2 6.00 1 1 6.00 4
May'18 11-May-18 Chandan Premi Gabion Retaining Wall 4th Gabion RW 4th lift 261+109 261+115 LHS Cum 4 6.00 2 1 12.00 8
May'18 11-May-18 Ashok Kumar Contractor Gabion Retaining Wall 3rd Gabion RW 3rd lift 258+507 258+510 LHS Cum 4 3.00 4 1 12.00 9
May'18 11-May-18 Ashok Kumar Contractor Gabion Retaining Wall 4th Gabion RW 4th lift 258+520 258+523 LHS Cum 4 3.00 4 1 12.00
May'18 12-May-18 Bhupender Singh Excavation Ordinary Soil (W&SER) Excavation upto SG Top 259+820 259+960 RHS Cum 42 336.00 3.00 2.00 1.00 260+750
May'18 12-May-18 KG Excavation Ordinary Soil (W&SER) Excavation upto SG Top 256+950 257+100 RHS Cum
May'18 12-May-18 Jham Jham Excavation Ordinary Soil (W&SER) Excavation upto SG Top 256+840 256+800 RHS Cum 2.00 1.00
May'18 12-May-18 NKC GSB Dumping GSB Unloading 260+900 261+990 RHS Cum 3 79.99
May'18 12-May-18 NKC GSB (W&SER) GSB Top layer Bed Preperation 260+900 260+990 RHS Cum 1.00 1.00
May'18 12-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 263+500 263+580 LHS Cum 8 1.00 2.00 263+650
May'18 12-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 261+130 261+150 LHS Cum 1 8.00
May'18 12-May-18 NKC WMM Top (W&SER) WMM Bed Preperation 252+000 256+100 LHS Cum 100.00 10.5 0.125 132.00 1.00 1.00
May'18 12-May-18 Madan Singh Chauhan Gabion Retaining Wall 2nd Gabion RW 2nd lift 254+562 254+566 LHS Cum 4 4.00 3 1 12.00 8
May'18 12-May-18 NKC WMM Top (W&SER) WMM BED Completed 241+190 241+520 LHS Cum
May'18 12-May-18 NKC GSB (W&SER) GSB Top layer Bed Preperation 244+150 244+300 LHS Cum 1.00 1.00
May'18 12-May-18 NKC WMM Dumping WMM Unloading 241+400 241+520 LHS Cum 5 151.69
May'18 12-May-18 NKC GSB Dumping GSB Unloading 240+700 240+780 LHS Cum 2 56.20
May'18 12-May-18 NKC GSB Dumping GSB Unloading 244+150 244+300 LHS Cum 5 147.57
May'18 12-May-18 NKC GSB Dumping GSB Unloading 243+660 243+700 LHS Cum 2 59.03
May'18 12-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 246+120 246+200 LHS Cum 34 272.00 2.00 4.00 radha swami trips 32 trips & 244+220=2trips
May'18 12-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+120 246+200 LHS Cum 8
May'18 12-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+120 246+200 LHS Cum 1.00
May'18 12-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 246+700 246+800 LHS Cum 1.00
May'18 12-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+700 246+800 LHS Cum 13 1.00 2.00
May'18 12-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+700 246+800 LHS Cum
May'18 12-May-18 Jham Jham Excavation Hard Rock (W&SER) Excavation upto SG Top 256+700 LHS Cum 5 54.07 248+700 B NKC Camp
May'18 12-May-18 Bhupender Singh Excavation Hard Rock (W&SER) Excavation upto SG Top 259+850 LHS Cum 4 258+560 B Gabion
May'18 12-May-18 Bhupender Singh Excavation Hard Rock (W&SER) Excavation upto SG Top 259+850 LHS Cum 2 261+120 B Gabion
May'18 12-May-18 Bhupender Singh Excavation Hard Rock (W&SER) Excavation upto SG Top 259+850 LHS Cum 1 263+520 B Gabion
May'18 12-May-18 Bhupender Singh Excavation Hard Rock (W&SER) Excavation upto SG Top 259+850 LHS Cum 1 264+550 B Gabion
May'18 12-May-18 Bhagat Singh Gabion Retaining Wall 4th Gabion RW 4th lift 264+612 264+621 LHS Cum 3 9.00 1 1 9.00 5
May'18 12-May-18 Devi Singh Gabion Retaining Wall 1st Gabion RW 1st lift 264+582 264+583 LHS Cum 1 1.00 3 1 3.00 2
May'18 12-May-18 Surender mahant Gabion Retaining Wall 8th Gabion RW 8th lift 263+609 263+624 LHS Cum 5 15.00 1 1 15.00 7
May'18 12-May-18 Chandan Premi Gabion Retaining Wall 4th Gabion RW 4th lift 261+115 261+118 LHS Cum 2 3.00 2 1 6.00 9
May'18 12-May-18 Ashok Kumar Contractor Gabion Retaining Wall 3rd Gabion RW 3rd lift 258+504 258+507 LHS Cum 4 3.00 4 1 12.00 9
May'18 12-May-18 Ashok Kumar Contractor Gabion Retaining Wall 4th Gabion RW 4th lift 258+523 258+526 LHS Cum 4 3.00 4 1 12.00
May'18 12-May-18 Madan Singh Chauhan Gabion Retaining Wall 2nd Gabion RW 2nd lift 254+568 254+572 LHS Cum 4 4.00 3 1 12.00 6
May'18 12-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+120 LHS Cum 8 323.56 248+700 B NKC Camp
May'18 12-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+700 LHS Cum 13 248+700 B NKC Camp
May'18 12-May-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 237+600 LHS Cum 3 280.01 248+700 B NKC Camp
May'18 12-May-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 239+800 LHS Cum 14 248+700 B NKC Camp
May'18 12-May-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 239+500 239+700 LHS Cum 10 80.00 7.00 7.00 1.00 241+040
May'18 12-May-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 236+900 236+700 LHS Cum
May'18 13-May-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 239+500 239+700 LHS Cum
May'18 13-May-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 236+900 237+700 LHS Cum 10 80.00 7.00 7.00 1.00 241+040
May'18 13-May-18 Bhupender Singh Excavation Ordinary Soil (W&SER) Excavation upto SG Top 259+820 259+960 RHS Cum 45 360.00 2.00 2.00 1.00 259+750
May'18 13-May-18 KG Excavation Ordinary Soil (W&SER) Excavation upto SG Top 256+950 257+100 RHS Cum 1.00 1.00
May'18 13-May-18 Jham Jham Excavation Hard Rock (W&SER) Excavation upto SG Top 256+640 256+800 RHS Cum 2 22.41 2.00 2.00 248+700 B NKC Camp
May'18 13-May-18 Devi Singh Gabion Retaining Wall 1st Gabion RW 1st lift 264+583 264+584 LHS Cum 1 1.00 3 1 3.00 2
May'18 13-May-18 Surender mahant Gabion Retaining Wall 8th Gabion RW 8th lift 263+576 263+585 LHS Cum 3 9.00 1 1 9.00 4
May'18 13-May-18 Ashok Kumar Contractor Gabion Retaining Wall 3rd Gabion RW 3rd lift 258+501 258+504 LHS Cum 4 3.00 4 1 12.00 12
May'18 13-May-18 Ashok Kumar Contractor Gabion Retaining Wall 4th Gabion RW 4th lift 258+526 254+532 LHS Cum 8 6.00 4 1 24.00
May'18 14-May-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 237+400 237+450 LHS Cum 6 48.00 2.00 5.00 241+000
May'18 14-May-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 237+400 237+450 LHS Cum
May'18 14-May-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 237+400 237+450 LHS Cum 4 60.66 248+700 B NKC Camp
May'18 14-May-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 236+700 237+800 LHS Cum 2.00
May'18 14-May-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 236+700 237+800 LHS Cum 1.00
May'18 14-May-18 NKC WMM Top (W&SER) WMM BED Completed
May'18 14-May-18 Madan Singh Chauhan Gabion Retaining Wall 2nd Gabion RW 2nd lift 254+566 264+584 LHS Cum 4 4.00 3 1 12.00 8
May'18 14-May-18 Madan Singh Chauhan Gabion Retaining Wall 3rd Gabion RW 3rd lift 254+566 263+585 LHS Cum 4 4.00 3 1 12.00
May'18 14-May-18 NKC WMM Dumping WMM Unloading Camp 251+000 RHS MT 349.00 3.00 251+670
May'18 14-May-18 NKC GSB (W&SER) GSB Top layer Bed Preperation 240+800 240+860 LHS Cum 1 29.81 1.00 1.00
May'18 14-May-18 NKC WMM Top (W&SER) WMM Bed Preperation 240+800 246+800 LHS Cum 4 119.02
May'18 14-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 246+700 246+800 LHS Cum 22 176.00 3.00 4.00 Radha swami
May'18 14-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+700 246+800 LHS Cum
May'18 14-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+120 246+200 LHS Cum 12 196.53 248+700 B NKC Camp
May'18 14-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 246+120 246+200 LHS Cum 56 448.00 2.00 5.00
May'18 14-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+120 246+200 LHS Cum 1.00
May'18 14-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+030 246+090 LHS Cum 6 98.26 248+700 B NKC Camp
May'18 14-May-18 NKC WMM Top (W&SER) WMM BED Completed 243+600 243+700 LHS Cum
May'18 14-May-18 NKC GSB (W&SER) GSB Top layer Bed Preperation 244+150 244+300 LHS Cum 1.00
May'18 14-May-18 Bhupender Singh Excavation Ordinary Soil (W&SER) Excavation upto SG Top 259+820 259+940 RHS Cum 38 304.00 3.00 2.00 1.00 259+750
May'18 14-May-18 KG Excavation Ordinary Soil (W&SER) Excavation upto SG Top 256+950 256+100 RHS Cum 1.00 1.00
May'18 14-May-18 Jham Jham Excavation Ordinary Soil (W&SER) Excavation upto SG Top 256+640 256+800 RHS Cum 2.00 2.00
May'18 14-May-18 NKC WMM Dumping WMM Unloading 261+670 261+780 RHS Cum 8 233.62
May'18 14-May-18 NKC WMM Top (W&SER) WMM BED Completed 261+670 261+780 RHS Cum 1.00 1.00
May'18 14-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 260+800 260+830 RHS Cum 10 80.00 1.00 2.00 sevbag 3, 263+500=7
May'18 14-May-18 Jham Jham Excavation Hard Rock (W&SER) Excavation upto SG Top 6 64.56 248+700 B NKC Camp
May'18 14-May-18 Surender mahant Gabion Retaining Wall 8th Gabion RW 8th lift 263+570 263+576 LHS Cum 2 6.00 1 1 6.00 4
May'18 14-May-18 Chandan Premi Gabion Retaining Wall 1st Gabion RW 1st lift 261+123 261+129 LHS Cum 10 6.00 5 1 30.00 12
May'18 14-May-18 Ashok Kumar Contractor Gabion Retaining Wall 3rd Gabion RW 3rd lift 258+532 258+538 LHS Cum 8 6.00 4 1 24.00 10
May'18 14-May-18 Devi Singh Gabion Retaining Wall 1st Gabion RW 1st lift 264+584 264+585 LHS Cum 1 1.00 3 1 3.00 2
May'18 14-May-18 Bhupender Singh Excavation Hard Rock (W&SER) Excavation upto SG Top 259+850 RHS Cum 1 9.00 258+560 B Gabion By nKC Hyva
May'18 14-May-18 Bhupender Singh Excavation Hard Rock (W&SER) Excavation upto SG Top 259+850 RHS Cum 1 9.00 263+520 B Gabion By nKC Hyva
May'18 14-May-18 Bhupender Singh Excavation Hard Rock (W&SER) Excavation upto SG Top 259+850 RHS Cum 1 9.00 261+150 B Gabion By nKC Hyva
May'18 15-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 246+120 246+200 LHS Cum 16 128.00 1.00 3.00 radha swami=16 trips
May'18 15-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+120 246+200 LHS Cum 6 210.66 248+700 B NKC Camp
May'18 15-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+120 246+200 LHS Cum 2.00
May'18 15-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 246+700 246+800 LHS Cum 17 136.00 1.00 3.00 radha swami=9 trips, 252+800= 8 trips
May'18 15-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+700 246+800 LHS Cum 6 1.00 248+700 B NKC Camp
May'18 15-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+700 246+800 LHS Cum 1.00 1.00
May'18 15-May-18 NKC WMM Top (W&SER) WMM BED Completed 240+800 240+860 MT Cum 3 1.00
May'18 15-May-18 NKC WMM Top (W&SER) WMM BED Completed 236+700 236+400 LHS Cum
May'18 15-May-18 NKC WMM Top (W&SER) WMM BED Completed
May'18 15-May-18 NKC WMM Dumping WMM Unloading
May'18 15-May-18 NKC Gabion Retaining Wall 3rd Gabion RW 3rd lift 254+570 254+574 LHS Cum 4 4.00 3 1 12.00 8
May'18 15-May-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 237+400 237+500 LHS Cum 14 112.00 2.00 5.00 241+000
May'18 15-May-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 237+400 237+500 LHS Cum 3 49.14 248+700 B NKC Camp
May'18 15-May-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 236+400 236+500 LHS Cum
May'18 15-May-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 236+400 236+500 LHS Cum 2.00 1.00
May'18 15-May-18 Bhupender Singh Excavation Ordinary Soil (W&SER) Excavation upto SG Top 259+820 259+960 RHS Cum 32 256.00 3.00 2.00 1.00
May'18 15-May-18 KG Excavation Ordinary Soil (W&SER) Excavation upto SG Top 256+950 256+800 RHS Cum 2.00 1.00
May'18 15-May-18 Jham Jham Excavation Ordinary Soil (W&SER) Excavation upto SG Top 256+640 260+830 RHS Cum 9 72.00 2.00 2.00
May'18 15-May-18 NKC GSB (W&SER) GSB for road maintance 260+800 259+610 RHS Cum 1 27.00 1.00 1.00 sevbag =3, 258+500=6
May'18 15-May-18 NKC WMM Dumping WMM Unloading 260+990 260+990 RHS Cum 10 273.43
May'18 15-May-18 NKC WMM Top (W&SER) WMM BED Completed 261+780 261+780 RHS Cum 1.00 1.00
May'18 15-May-18 NKC WMM Top (W&SER) WMM Bed Preperation 260+990 260+990 RHS Cum
May'18 15-May-18 Jham Jham Excavation Hard Rock (W&SER) Excavation upto SG Top 256+700 RHS Cum 5 55.60 248+700 B NKC Camp
May'18 15-May-18 Bhupender Singh Excavation Hard Rock (W&SER) Excavation upto SG Top 259+850 RHS Cum 3 24.00 258+560 B Gabion
May'18 15-May-18 Bhupender Singh Excavation Hard Rock (W&SER) Excavation upto SG Top 259+850 RHS Cum 1 8.00 264+520 B Gabion
May'18 15-May-18 Bhupender Singh Excavation Hard Rock (W&SER) Excavation upto SG Top 259+850 RHS Cum 1 8.00 261+150 B Gabion
May'18 15-May-18 Devi Singh Gabion Retaining Wall 1st Gabion RW 1st lift 264+585 263+576 LHS Cum 1 1.00 3 1 3.00 2
May'18 15-May-18 Chandan Premi Gabion Retaining Wall 1st Gabion RW 1st lift 261+129 261+129 LHS Cum 5 3.00 5 1 15.00 8
May'18 15-May-18 Ashok Kumar Contractor Gabion Retaining Wall 4th Gabion RW 4th lift 258+538 258+538 LHS Cum 8 6.00 4 1 24.00 9
May'18 15-May-18 Madan Singh Chauhan Gabion Retaining Wall 3rd Gabion RW 3rd lift 254+551 264+585 LHS Cum 8 8.00 3 1 24.00 10
May'18 16-May-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 239+500 239+700 LHS Cum 20 160.00 1.00 2.00 241+000
May'18 16-May-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 237+400 237+500 LHS Cum 2.00
May'18 16-May-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 237+400 237+500 LHS Cum 12 207.26 5.00 248+700 B NKC Camp
May'18 16-May-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 236+400 236+500 LHS Cum 1.00 1.00
May'18 16-May-18 NKC WMM Dumping WMM Unloading Camp 251+000 LHS Cum 19 543.00 3.00 251+670
May'18 16-May-18 NKC WMM Top (W&SER) WMM BED Completed 251+670 251+770 LHS Cum 100.00 9.1 0.125 114.00 1.00 1.00 1.00
May'18 16-May-18 Madan Singh Chauhan Gabion Retaining Wall 4th Gabion RW 4th lift 254+540 254+543 LHS Cum 3 9.00 1 1 9.00 8
May'18 16-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 246+120 246+200 LHS Cum 30 240.00 1.00 4.00 252= 7 trips, radha swami=23 trips
May'18 16-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+120 246+200 LHS Cum 7 248+700 B NKC Camp
May'18 16-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+120 246+200 LHS Cum 1.00
May'18 16-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 246+700 246+800 LHS Cum 1.00 3.00
May'18 16-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+700 246+800 LHS Cum 11 302.18 2.00 248+700 B NKC Camp
May'18 16-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+700 246+800 LHS Cum
May'18 16-May-18 NKC Embankment top (W&SER) bed pperation emb 240+920 240+960 LHS Cum 1.00 1.00
May'18 16-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 240+920 240+940 LHS Cum 1.00 246+700
May'18 16-May-18 Devi Singh Gabion Retaining Wall 2nd Gabion RW 2nd lift 264+565 261+129 LHS Cum 4 6.00 2 1 12.00 6
May'18 16-May-18 Chandan Premi Gabion Retaining Wall 1st Gabion RW 1st lift 261+132 258+538 LHS Cum 5 3.00 5 1 15.00 9
May'18 16-May-18 Ashok Kumar Contractor Gabion Retaining Wall 4th Gabion RW 4th lift 258+544 258+538 LHS Cum 8 6.00 4 1 24.00 12
May'18 16-May-18 Ashok Kumar Contractor Gabion Retaining Wall 4th Gabion RW 4th lift 258+517 258+538 LHS Cum 4 3.00 4 1 12.00
May'18 16-May-18 Madan Singh Chauhan Gabion Retaining Wall 4th Gabion RW 4th lift 264+564 258+538 LHS Cum 6 9.00 2 1 18.00 8
May'18 16-May-18 Jham Jham Excavation Hard Rock (W&SER) Excavation upto SG Top 256+700 RHS Cum 1 11.59 248+700 B NKC Camp
May'18 16-May-18 Bhupender Singh Excavation Hard Rock (W&SER) Excavation upto SG Top 259+850 RHS Cum 1 258+560 B Gabion
May'18 16-May-18 Bhupender Singh Excavation Ordinary Soil (W&SER) Excavation upto SG Top 259+820 259+960 RHS Cum 45 360.00 2.00 2.00 1.00 259+750
May'18 16-May-18 KG Excavation Ordinary Soil (W&SER) Excavation upto SG Top 256+950 257+100 RHS Cum 1.00 1.00
May'18 16-May-18 Jham Jham Excavation Ordinary Soil (W&SER) Excavation upto SG Top 256+640 258+800 RHS Cum 2.00 1.00
May'18 16-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 260+800 260+830 RHS Cum 14 112.00 1.00 2.00 sevbag=6, 258+500=8
May'18 16-May-18 NKC WMM Dumping WMM Unloading 260+900 260+990 RHS Cum 82.35
May'18 16-May-18 NKC WMM Dumping WMM Unloading 260+370 260+430 RHS Cum 112.06
May'18 16-May-18 NKC WMM Top (W&SER) WMM Bed Preperation 260+900 260+990 RHS Cum 1.00 1.00
May'18 16-May-18 NKC WMM Top (W&SER) WMM BED Completed 260+370 260+480 RHS Cum
May'18 17-May-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 239+450 239+490 RHS Cum 9 72.00 1.00 3.00 241+000
May'18 17-May-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 239+800 239+700 RHS Cum 14 112.00
May'18 17-May-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 237+400 237+500 LHS Cum 2.00
May'18 17-May-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 237+400 237+500 LHS Cum 17 129.77 5.00 248+700 B NKC Camp
May'18 17-May-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 237+600 237+600 LHS Cum 16 208.00 1.00 4.00 1.00
May'18 17-May-18 NKC WMM Top (W&SER) WMM BED Completed 251+770 251+900 LHS Cum 130.00 9.1 0.125 148.00 1.00 1.00 247+830
May'18 17-May-18 NKC WMM Dumping WMM Unloading Camp 248+000 RHS Cum 22 641.00 3.00
May'18 17-May-18 Madan Singh Chauhan Gabion Retaining Wall 4th Gabion RW 4th lift 254+549 254+554 LHS Cum 2 6.00 1 1 6.00 8
May'18 17-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 246+120 246+200 LHS Cum 12 96.00 1.00 7.00 252+020
May'18 17-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+120 246+200 LHS Cum 15 225.16 248+700 B NKC Camp
May'18 17-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+120 246+200 LHS Cum 1.00
May'18 17-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 246+700 246+800 LHS Cum 17 136.00 1.00 2.00 252+020
May'18 17-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+700 246+800 LHS Cum 1
May'18 17-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+700 246+800 LHS Cum 1.00
May'18 17-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 239+000 259+960 LHS Cum 4 1.00 4.00
May'18 17-May-18 Bhupender Singh Excavation Ordinary Soil (W&SER) Excavation upto SG Top 259+820 257+100 RHS Cum 38 304.00 3.00 2.00 1.00 259+750
May'18 17-May-18 KG Excavation Ordinary Soil (W&SER) Excavation upto SG Top 256+950 256+800 RHS Cum 1.00 1.00
May'18 17-May-18 Jham Jham Excavation Hard Rock (W&SER) Excavation upto SG Top 256+840 260+830 RHS Cum 2 27.90 2.00 1.00 248+700 B NKC Camp
May'18 17-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 260+800 260+830 RHS Cum 13 104.00 1.00 2.00 sevbag 2, 264+500=10
May'18 17-May-18 NKC WMM Top (W&SER) WMM BED Completed 260+900 260+999 RHS Cum 1 26.50 1.00 1.00 1.00 1.00
May'18 17-May-18 NKC WMM Dumping WMM Unloading 260+990 260+990 RHS Cum 2 54.28
May'18 17-May-18 Devi Singh Gabion Retaining Wall 2nd Gabion RW 2nd lift 264+571 261+129 LHS Cum 6 9.00 2 1 18.00 7
May'18 17-May-18 Surender mahant Gabion Retaining Wall 8th Gabion RW 8th lift 264+570 258+538 LHS Cum 2 6.00 1 1 6.00 4
May'18 17-May-18 Chandan Premi Gabion Retaining Wall 1st Gabion RW 1st lift 261+135 258+538 LHS Cum 5 3.00 5 1 15.00 12
May'18 17-May-18 Ashok Kumar Contractor Gabion Retaining Wall 1st Gabion RW 1st lift 259+700 258+538 LHS Cum 14 21.00 2 1 42.00 15
May'18 17-May-18 Madan Singh Chauhan Gabion Retaining Wall 4th Gabion RW 4th lift 254+561 258+538 LHS Cum 2 3.00 2 1 6.00 5
May'18 18-May-18 NKC WMM Top (W&SER) WMM BED preperation 251+840 251+900 RHS Cum 60.00 9.1 0.125 68.25 1.00 1.00
May'18 18-May-18 NKC WMM Dumping WMM Unloading Camp 248+000 LHS Cum 14 415.00 4.00
May'18 18-May-18 NKC WMM Top (W&SER) WMM BED preperation 252+180 254+560 LHS Cum 100.00 9.1 0.125
May'18 18-May-18 Madan Singh Chauhan Gabion Retaining Wall 4th Gabion RW 4th lift 254+554 252+280 LHS Cum 2 6.00 1 1 6.00 8
May'18 18-May-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 239+490 239+580 RHS Cum 20 160.00 1.00 4.00
May'18 18-May-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 239+700 239+800 RHS Cum 1.00
May'18 18-May-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 237+600 237+700 LHS Cum 25 200.00 1.00 4.00
May'18 18-May-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 237+600 237+700 LHS Cum 1.00
May'18 18-May-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 237+600 237+700 LHS Cum 3 59.72 1.00 2.00 248+700 B NKC Camp
May'18 18-May-18 NKC Subgrade Layers (W&SER) Bed Completed 239+450 239+580 RHS Cum 1.00 1.00
May'18 18-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 246+800 246+800 LHS Cum 16 128.00 1.00 4.00
May'18 18-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+800 246+800 LHS Cum 1
May'18 18-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+800 246+800 LHS Cum 1.00
May'18 18-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top RHS Cum 7 1.00
May'18 18-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top Cum
May'18 18-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+120 246+200 LHS Cum 16 345.50 1.00 5.00 248+700 B NKC Camp
May'18 18-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+120 246+200 LHS Cum 10 1.00
May'18 18-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 238+120 LHS Cum 2 1.00
May'18 18-May-18 Bhupender Singh Excavation Ordinary Soil (W&SER) Excavation upto SG Top 259+820 259+960 RHS Cum 38 304.00 3.00 2.00 1.00 259+850
May'18 18-May-18 KG Excavation Ordinary Soil (W&SER) Excavation upto SG Top 256+850 257+100 RHS Cum 1.00
May'18 18-May-18 Jham Jham Excavation Ordinary Soil (W&SER) Excavation upto SG Top 256+640 256+800 RHS Cum 2.00 1.00
May'18 18-May-18 NKC WMM Dumping WMM Unloading 260+900 260+990 RHS Cum 3 88.24
May'18 18-May-18 NKC WMM Top (W&SER) WMM BED preperation 260+370 260+430 RHS Cum 1.00 1.00
May'18 18-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 260+800 260+830 RHS Cum 10 80.00 1.00 2.00 sevbag=2, 264+580=8
May'18 18-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 258+250 258+260 RHS Cum 6 254+600
May'18 18-May-18 Bhagat Singh Gabion Retaining Wall 4th Gabion RW 4th lift 264+621 264+633 LHS Cum 4 12.00 1 1 12.00 8
May'18 18-May-18 Ashok Kumar Contractor Gabion Retaining Wall 1st Gabion RW 1st lift 259+800 258+538 LHS Cum 20 30.00 2 1 60.00 5
May'18 18-May-18 Madan Singh Chauhan Gabion Retaining Wall 4th Gabion RW 4th lift 254+558 254+561 LHS Cum 2 3.00 2 1 6.00 18
May'18 19-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 249+500 249+570 RHS Cum 10.00 7 2 140.00 1.00 4.00
May'18 19-May-18 NKC Subgrade Layers (W&SER) Bed Completed 252+360 252+500 LHS Cum 1.00 1.00 1.00
May'18 19-May-18 Madan Singh Chauhan Gabion Retaining Wall 4th Gabion RW 4th lift 254+560 254+566 LHS Cum 2 6.00 1 1 6.00 8
May'18 19-May-18 NKC WMM Dumping WMM Unloading Camp 252+000 LHS Cum 3 86.00 3.00
May'18 19-May-18 NKC GSB (W&SER) Bed Preperation 239+450 239+580 RHS Cum
May'18 19-May-18 NKC GSB Dumping GSB Unlading 239+450 239+580 RHS Cum 10 289.99 1.00 1.00
May'18 19-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 246+120 246+200 LHS Cum 29 232.00 2.00 8.00
May'18 19-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+120 246+200 LHS Cum 16 393.12 1.00 248+700 B NKC Camp
May'18 19-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+120 246+200 LHS Cum 1.00
May'18 19-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 246+700 246+800 LHS Cum 1.00
May'18 19-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+700 246+800 LHS Cum
May'18 19-May-18 Chandan Premi Gabion Retaining Wall 1st Gabion RW 1st lift 261+138 258+538 LHS Cum 5 3.00 5 1 15.00 10
May'18 19-May-18 Ashok Kumar Contractor Gabion Retaining Wall 1st Gabion RW 1st lift 259+810 258+538 LHS Cum 4 6.00 2 1 12.00 12
May'18 19-May-18 Ashok Kumar Contractor Gabion Retaining Wall 2nd Gabion RW 2nd lift 259+807 258+538 LHS Cum 6 9.00 2 1 18.00
May'18 19-May-18 Devi Singh Gabion Retaining Wall 2nd Gabion RW 2nd lift 264+580 258+538 LHS Cum 4 6.00 2 1 12.00 8
May'18 19-May-18 Bhupender Singh Excavation Ordinary Soil (W&SER) Excavation upto SG Top 259+820 259+960 RHS Cum 23 184.00 3.00 2.00 1.00
May'18 19-May-18 KG Excavation Ordinary Soil (W&SER) Excavation upto SG Top 256+850 257+800 RHS Cum
May'18 19-May-18 Jham Jham Excavation Ordinary Soil (W&SER) Excavation upto SG Top 256+640 256+800 RHS Cum
May'18 19-May-18 NKC WMM Dumping WMM Unloading 260+900 260+900 RHS Cum 2 54.18 1.00 1.00
May'18 19-May-18 NKC WMM Top (W&SER) WMM BED preperation 260+900 260+990 RHS Cum
May'18 19-May-18 NKC GSB (W&SER) Bed Preperation 261+350 261+400 RHS Cum
May'18 19-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 258+110 258+120 RHS Cum 10 80.00 1.00 2.00 258+200
May'18 19-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 254+900 254+920 RHS Cum 1 1.00 254+600
May'18 19-May-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top Cum 5 140.43 4.00 7.00 248+700 B NKC Camp
May'18 20-May-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 239+700 239+800 LHS Cum 21 168.00 2.00 4.00 241+000
May'18 20-May-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 237+600 237+700 LHS Cum 23 184.00 2.00 3.00
May'18 20-May-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 239+600 239+700 LHS Cum 1.00
May'18 20-May-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 236+400 236+500 LHS Cum 1.00
May'18 20-May-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 239+600 239+700 LHS Cum 2
May'18 20-May-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 236+400 236+500 LHS Cum 7 177.56 248+700 B NKC Camp
May'18 20-May-18 Bhupender Singh Excavation Ordinary Soil (W&SER) Excavation upto SG Top 259+820 259+960 RHS Cum 32 256.00 3.00 2.00 1.00 259+750
May'18 21-May-18 NKC WMM Top (W&SER) WMM BED preperation 247+830 247+880 RHS Cum 50.00 9.1 0.125 56.88 1.00 1.00 1.00
May'18 21-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 249+500 249+520 BHS Cum 20.00 6 2 240.00 1.00 4.00 252+000
May'18 21-May-18 NKC Subgrade Layers (W&SER) Bed Completed 252+360 252+500 BHS Cum 28 224.00
May'18 21-May-18 NKC WMM Dumping WMM Unloading Camp 248+000 BHS MT 18 504.00 248+060
May'18 21-May-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 236+700 236+800 LHS Cum 10 80.00 1.00 5.00 241+000
May'18 21-May-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 237+400 237+500 LHS Cum 5 40.00 2.00 2.00
May'18 21-May-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 237+400 237+500 LHS Cum 3 150.36 1.00 2.00 248+700 B NKC Camp
May'18 21-May-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 236+700 236+800 LHS Cum 3 1.00 2.00
May'18 21-May-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 239+800 239+900 LHS Cum 11 88.00 1.00 2.00
May'18 21-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+700 246+800 LHS Cum 1.00
May'18 21-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 246+120 246+200 LHS Cum 21 168.00 1.00 6.00
May'18 21-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+120 246+200 LHS Cum 1.00
May'18 21-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+120 246+200 LHS Cum 5 110.37 248+700 B NKC Camp
May'18 21-May-18 NKC Subgrade Layers (W&SER) Bed Completed 239+590 239+660 RHS Cum
May'18 21-May-18 NKC GSB (W&SER) Bed Preperation 239+450 239+660 RHS Cum 1.00 1.00
May'18 21-May-18 NKC GSB Dumping GSB Unloading 239+590 239+660 RHS Cum 2 53.17
May'18 21-May-18 NKC GSB Dumping GSB Unloading 238+600 Cum 1 27.49
May'18 21-May-18 Devi Singh Gabion Retaining Wall 3rd Gabion RW 3rd lift 264+565 258+538 LHS Cum 6 9.00 2 1 18.00 8
May'18 21-May-18 Chandan Premi Gabion Retaining Wall 1st Gabion RW 1st lift 261+141 258+538 LHS Cum 5 3.00 5 1 15.00 7
May'18 21-May-18 Madan Singh Chauhan Gabion Retaining Wall 4th Gabion RW 4th lift 254+552 258+538 LHS Cum 4 6.00 2 1 12.00 8
May'18 21-May-18 Ashok Kumar Contractor Gabion Retaining Wall 2nd Gabion RW 2nd lift 259+774 258+538 LHS Cum 2 6.00 1 1 6.00 4
May'18 21-May-18 Bhupender Singh Excavation Ordinary Soil (W&SER) Excavation upto SG Top 259+820 259+960 RHS Cum 21 168.00 3.00 2.00 1.00 259+800
May'18 21-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 257+900 257+920 RHS Cum 16 128.00 1.00 2.00 1.00 258+200
May'18 21-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 258+160 258+230 RHS Cum 1.00
S.No Date Contractor Progress work Layer Misc works From To Side Unit Nos Length Breadth Depth Quantity Excavators Dumpers JCB Grader Roller Water Tanker Exca with
Loader Breaker Boulder screning Labour Dumping Lead (One Dumping at Remarks
dumper Chainage Side) KM

May'18 21-May-18 NKC GSB Dumping GSB for road maintance 263+320 RHS Cum 1 21.35
May'18 21-May-18 KG Excavation Hard Rock (W&SER) Excavation upto SG Top 3 70.95 248+700 B NKC Camp
May'18 22-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 246+150 246+200 LHS Cum 30 240.00 1.00 7.00
May'18 22-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 246+150 246+200 LHS Cum 3 24.00
May'18 22-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+150 246+200 LHS Cum 1.00 2.00
May'18 22-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+150 246+200 LHS Cum 2
May'18 22-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+500 246+800 LHS Cum 1.00
May'18 22-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+500 246+500 LHS Cum 6 205.75 1.00 2.00 248+700 B NKC Camp
May'18 22-May-18 NKC GSB (W&SER) Bed Preperation 239+450 239+540 RHS Cum 4 117.29 1.00 1.00
May'18 22-May-18 NKC GSB Dumping GSB Unlading 239+540 239+660 RHS Cum 2 60.71
May'18 22-May-18 NKC WMM Top (W&SER) WMM BED preperation 248+050 248+140 RHS Cum 140.00 9.1 0.125 159.25 1.00 1.00
May'18 22-May-18 NKC WMM Dumping WMM Unloading Camp 248+000 RHS Cum 12 336.00 3.00 247+860
May'18 22-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 249+500 249+520 RHS Cum 29 203.00 4.00 252+000
May'18 22-May-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 239+700 239+800 LHS Cum 6 48.00 1.00 2.00
May'18 22-May-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 237+400 237+500 LHS Cum 21 168.00 1.00 5.00
May'18 22-May-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 236+700 236+800 LHS Cum 3 24.00 241+000
May'18 22-May-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 237+400 237+500 LHS Cum 1.00
May'18 22-May-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 236+700 236+800 LHS Cum 1.00
May'18 22-May-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 237+400 237+500 LHS Cum 5 131.31 1.00 3.00 248+700 B NKC Camp
May'18 22-May-18 Bhupender Singh Excavation Ordinary Soil (W&SER) Excavation upto SG Top 259+820 259+960 RHS Cum 38 304.00 3.00 2.00 1.00 259+800
May'18 22-May-18 KG Excavation Ordinary Soil (W&SER) Excavation upto SG Top 256+950 257+100 RHS Cum
May'18 22-May-18 Jham Jham Excavation Ordinary Soil (W&SER) Excavation upto SG Top 256+640 256+800 RHS Cum 1.00 1.00
May'18 22-May-18 NKC WMM Top (W&SER) WMM BED preperation 260+900 260+990 RHS Cum
May'18 22-May-18 NKC Subgrade Layers (W&SER) Bed Completed 260+860 260+900 RHS Cum 1.00 1.00
May'18 22-May-18 NKC Subgrade Layers (W&SER) Bed Completed 258+160 258+230 RHS Cum
May'18 22-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 260+100 260+160 RHS Cum 7 56.00 1.00 2.00 jia bridge =6, 259+050=10, sevbag=1
May'18 22-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+600 246+700 LHS Cum 1.00
May'18 22-May-18 Devi Singh Gabion Retaining Wall 3rd Gabion RW 3rd lift 264+574 264+583 LHS Cum 6 9.00 2 1 18.00 8
May'18 22-May-18 Madan Singh Chauhan Gabion Retaining Wall 4th Gabion RW 4th lift 254+540 254+552 LHS Cum 8 12.00 2 1 24.00 8
May'18 22-May-18 Ajay Pathania RRM Masonary 246+090 246+110 LHS Cum 20.00 1 2.35 47.00 15
May'18 22-May-18 Ajay Pathania RRM Masonary 246+202 246+840 LHS Cum 20 1 2.50 50.00 14
May'18 22-May-18 Bhagwan Singh RRM Masonary 237+620 237+640 LHS Cum 20 1 2.50 50.00 15
May'18 23-May-18 NKC WMM Top (W&SER) WMM BED preperation 248+060 248+150 LHS Cum 90.00 9.1 0.125 102.38 1.00 1.00 1.00
May'18 23-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 249+500 249+520 BHS Cum 36 288.00 1.00 4.00 252+700
May'18 23-May-18 NKC Subgrade Layers (W&SER) 2nd layer Bed preperation 252+360 252+500 BHS Cum 140.00 22.6 0.15 474.60
May'18 23-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 246+150 246+200 LHS Cum 24 192.00 1.00 8.00 252+600
May'18 23-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+150 246+200 LHS Cum 1.00
May'18 23-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+150 246+200 LHS Cum 10
May'18 23-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+500 246+600 LHS Cum 1.00
May'18 23-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+500 246+600 LHS Cum 4 1.00 2.00
May'18 23-May-18 NKC GSB (W&SER) Top Bed Preperation 239+540 239+660 LHS Cum 1.00 1.00
May'18 23-May-18 NKC WMM Dumping WMM Unloading 239+450 243+800 LHS Cum 3 83.38
May'18 23-May-18 Bhupender Singh Excavation Ordinary Soil (W&SER) Excavation upto SG Top 259+820 259+960 RHS Cum 35 280.00 3.00 2.00 1.00
May'18 23-May-18 KG Excavation Ordinary Soil (W&SER) Excavation upto SG Top 256+950 257+100 RHS Cum 1.00
May'18 23-May-18 Jham Jham Excavation Ordinary Soil (W&SER) Excavation upto SG Top 256+640 259+800 RHS Cum 1.00 2.00
May'18 23-May-18 Jham Jham Excavation Hard Rock (W&SER) Excavation upto SG Top 256+640 259+800 RHS Cum 1 19.29 248+700 B NKC Camp
May'18 23-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 266+700 260+760 RHS Cum 12 96.00 1.00 2.00
May'18 23-May-18 NKC GSB Dumping GSB Unloading 260+870 260+900 RHS Cum 6 173.10
May'18 23-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 254+640 254+680 RHS Cum 8 64.00 1.00 1.00
May'18 23-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 254+700 264+720 LHS Cum 8 339.80 1.00 1.00 248+700 B NKC Camp
May'18 23-May-18 Chandan Premi Gabion Retaining Wall 1st Gabion RW 1st lift 261+144 261+147 LHS Cum 5 3.00 5 1 15.00 8
May'18 23-May-18 Madan Singh Chauhan Gabion Retaining Wall 4th Gabion RW 4th lift 254+537 254+540 LHS Cum 2 3.00 2 1 6.00 4
May'18 23-May-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 237+400 237+500 LHS Cum 20 160.00 1.00 4.00 241+000
May'18 23-May-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 237+402 237+500 LHS Cum 1 18.56 2.00 248+700 B NKC Camp
May'18 23-May-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 237+400 237+300 LHS Cum 1.00
May'18 23-May-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 236+700 236+800 LHS Cum 1 18.56 1.00 1.00 248+700 B NKC Camp
May'18 23-May-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 239+680 239+780 LHS Cum 40.00 1.00 2.00
May'18 24-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+500 246+800 LHS Cum 2.00
May'18 24-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 246+150 246+200 LHS Cum 10 80.00 1.00 238+300
May'18 24-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 246+150 246+200 LHS Cum 10.00
May'18 24-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 246+150 246+200 LHS Cum 6 48.00 1.00 248+400
May'18 24-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 246+150 246+200 LHS Cum 6 48.00 252+600
May'18 24-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+150 246+200 LHS Cum 2 40.36 248+700 B NKC Camp
May'18 24-May-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 237+400 237+500 LHS Cum 21 168.00 2.00 5.00 241+000
May'18 24-May-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 237+402 237+500 LHS Cum 27 216.00 1.00 3.00
May'18 24-May-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 237+400 237+300 LHS Cum 1.00
May'18 24-May-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 236+700 236+800 LHS Cum 6 168.11 3.00 1.00 248+700 B NKC Camp
May'18 24-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 249+500 249+520 BHS Cum 10.00 10 2 200.00 1.00 4.00 252+600
May'18 24-May-18 NKC Embankment Layers (W&SER) Top layer bed preperation 252+600 252+700 LHS Cum 26 208.00
May'18 24-May-18 Bhupender Singh Excavation Ordinary Soil (W&SER) Excavation upto SG Top 259+820 259+960 RHS Cum 42 336.00 1.00 2.00 1.00
May'18 24-May-18 KG Excavation Ordinary Soil (W&SER) Excavation upto SG Top 256+950 257+100 RHS Cum 1.00
May'18 24-May-18 Jham Jham Excavation Ordinary Soil (W&SER) Excavation upto SG Top 256+640 256+800 RHS Cum
May'18 24-May-18 NKC Subgrade Layers (W&SER) Top layer Bed preperation 260+870 260+900 RHS Cum 1.00 1.00
May'18 24-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 260+160 260+200 RHS Cum 8 64.00 1.00 2.00 259090=3, 264+9000=5
May'18 24-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 254+640 254+680 RHS Cum 15 120.00 1.00 1.00 254+540
May'18 24-May-18 Devi Singh Gabion Retaining Wall 3rd Gabion RW 3rd lift 264+585 264+588 LHS Cum 2 3.00 2 1 6.00 8
May'18 24-May-18 Devi Singh Gabion Retaining Wall 3rd Gabion RW 3rd lift 264+586 264+587 LHS Cum 1 1.00 3 1 3.00
May'18 24-May-18 Devi Singh Gabion Retaining Wall 4th Gabion RW 4th lift 264+575 264+587 LHS Cum 4 12.00 1 1 12.00
May'18 24-May-18 Madan Singh Chauhan Gabion Retaining Wall 4th Gabion RW 4th lift 254+528 254+537 LHS Cum 6 9.00 2 1 18.00 8
May'18 25-May-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 240+600 239+940 LHS Cum 6 48.00 1.00 3.00 241+000
May'18 25-May-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 240+600 239+940 LHS Cum 1.00
May'18 25-May-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 239+700 239+800 LHS Cum 5 140.84 248+700 Nkc camp
May'18 25-May-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 237+400 237+600 LHS Cum 6 48.00 1.00 4.00
May'18 25-May-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 237+400 237+600 LHS Cum 5 140.84 1.00 248+700 Nkc camp
May'18 25-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 249+500 249+520 LHS Cum 200.00 1.00 4.00 252+400
May'18 25-May-18 NKC WMM Dumping WMM Unloading camp 248+000 280.00 3.00
May'18 25-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+150 246+200 LHS Cum 9 249.02 2.00 7.00 248+700 Nkc camp
May'18 25-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+500 246+800 LHS Cum 1.00
May'18 25-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+500 246+800 LHS Cum 6 166.02 1.00 4.00 248+700 NKC Camp
May'18 25-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+500 246+800 LHS Cum 4 236+800
May'18 25-May-18 Ajay Pathania PCC For RMM Breast wall PCC 246+120 246+140 LHS Cum 4.80 3
May'18 25-May-18 NKC WMM Dumping WMM Unloading 239+540 239+660 LHS Cum 4 112.09 1.00
May'18 25-May-18 Bhupender Singh Excavation Ordinary Soil (W&SER) Excavation upto SG Top 259+820 259+960 RHS Cum 42 336.00 3.00 1.00 1.00 259+800
May'18 25-May-18 KG Excavation Ordinary Soil (W&SER) Excavation upto SG Top 256+950 257+100 RHS Cum 1.00
May'18 25-May-18 Jham Jham Excavation Ordinary Soil (W&SER) Excavation upto SG Top 256+840 256+800 RHS Cum 2.00 2.00
May'18 25-May-18 Jham Jham Excavation Hard Rock (W&SER) Excavation upto SG Top 256+840 256+800 RHS Cum 1 25.67 248+700 NKC Camp
May'18 25-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 260+160 260+200 RHS Cum 13 104.00 1.00 2.00 264+950
May'18 25-May-18 NKC WMM Dumping Dumping for Top Layer 260+870 260+900 RHS Cum 3 80.10 1.00 1.00
May'18 25-May-18 NKC WMM Dumping Dumping for 1st Layer 260+870 260+900 RHS Cum 2 51.60
May'18 25-May-18 NKC Subgrade Layers (W&SER) Top layer Bed preperation Completed 260+990 260+820 RHS
May'18 25-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 264+680 LHS Cum 1.00
May'18 25-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 258+520 LHS Cum
May'18 25-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 254+640 254+680 RHS Cum 14 112.00 1.00 1.00 254+540
May'18 25-May-18 Surender mahant Gabion Retaining Wall 8th Gabion RW 8th lift 263+600 263+606 LHS Cum 2 6.00 1 1 6.00 3
May'18 25-May-18 Chandan Premi Gabion Retaining Wall 1st Gabion RW 1st lift 261+147 261+150 LHS Cum 5 3.00 5 1 15.00 8
May'18 25-May-18 Ashok Kumar Contractor Gabion Retaining Wall 2nd Gabion RW 2nd lift 259+789 259+804 LHS Cum 5 15.00 1 1 15.00 12
May'18 25-May-18 Ashok Kumar Contractor Gabion Retaining Wall 2nd Gabion RW 2nd lift 259+810 259+816 LHS Cum 2 6.00 1 1 6.00
May'18 25-May-18 Ashok Kumar Contractor Gabion Retaining Wall 4th Gabion RW 4th lift 258+550 258+556 LHS Cum 8 6.00 4 1 24.00
May'18 25-May-18 Madan Singh Chauhan Gabion Retaining Wall 4th Gabion RW 3rd lift 254+522 254+525 LHS Cum 2 3.00 2 1 6.00 8
May'18 25-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 264+500 LHS Cum 4 36.00 236+800
May'18 26-May-18 NKC Kerb Laying Camp 1.50 2
May'18 26-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 249+500 249+520 BHS Cum 20.00 10 1.5 300.00 1.00 4.00
May'18 26-May-18 NKC WMM Top (W&SER) WMM BED preperation 247+860 248+010 RHS Cum 150.00 9.1 0.125 237.17 1.00 1.00 1.00
May'18 26-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 246+150 246+200 LHS Cum 5 40.00 1.00 3.00 238+805
May'18 26-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 246+150 246+200 LHS Cum 3 24.00 252+020
May'18 26-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+150 246+200 LHS Cum 1.00
May'18 26-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+150 246+200 LHS Cum 19 424.62 1.00 6.00 248+700 NKC Camp
May'18 26-May-18 Bhupender Singh Excavation Ordinary Soil (W&SER) Excavation upto SG Top 259+820 259+960 RHS Cum 22 176.00 3.00 1.00 1.00
May'18 26-May-18 NKC WMM Top (W&SER) WMM BED 1st layer preperation 256+380 256+420 RHS Cum 1.00 1.00
May'18 26-May-18 NKC GSB Dumping GSB Unloading 260+990 261+020 RHS Cum 6 172.50
May'18 26-May-18 NKC WMM Dumping WMM Unloading 260+870 260+900 RHS Cum 1 25.51
May'18 26-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 258+160 258+230 RHS Cum 12 96.00 1.00 2.00 259+090
May'18 26-May-18 Manjeet Singh Excavation Hard Rock (W&SER) Excavation upto SG Top 258+260 258+280 RHS Cum 3 261+100
May'18 26-May-18 Devi Singh Gabion Retaining Wall 4th Gabion RW 4th lift 264+572 264+575 LHS Cum 1 3.00 1 1 3.00 2
May'18 26-May-18 Ashok Kumar Contractor Gabion Retaining Wall 2nd Gabion RW 2nd lift 259+801 259+810 LHS Cum 3 9.00 1 1 9.00 10
May'18 26-May-18 Ashok Kumar Contractor Gabion Retaining Wall 4th Gabion RW 4th lift 258+541 258+547 LHS Cum 8 6.00 4 1 24.00
May'18 26-May-18 Madan Singh Chauhan Gabion Retaining Wall 5th Gabion RW 5th lift 254+567 254+573 LHS Cum 4 6.00 2 1 12.00 8
May'18 26-May-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 7 194.28 248+700 NKC Camp
May'18 26-May-18 KG Excavation Hard Rock (W&SER) Excavation upto SG Top 4 93.51 248+700 NKC Camp
May'18 27-May-18 Surender mahant Gabion Retaining Wall 8th Gabion RW 8th lift 263+606 LHS Cum 1 3.00 1 1 3.00 2
May'18 27-May-18 Ashok Kumar Contractor Gabion Retaining Wall 4th Gabion RW 4th lift 258+511 LHS Cum 4 3.00 4 1 12.00 12
May'18 27-May-18 Ashok Kumar Contractor Gabion Retaining Wall 5th Gabion RW 5th lift 258+515 LHS Cum 5 5.00 3 1 15.00
May'18 27-May-18 Chandan Premi Gabion Retaining Wall 2nd Gabion RW 2nd lift 261+122 LHS Cum 4 3.00 4 1 12.00 8
May'18 27-May-18 Madan Singh Chauhan Gabion Retaining Wall 5th Gabion RW 5th lift 254+561 LHS Cum 4 6.00 2 1 12.00 8
May'18 27-May-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 239+940 239+940 LHS Cum 12 96.00 1.00 3.00 241+000
May'18 27-May-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 239+940 239+940 LHS Cum 1.00
May'18 27-May-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 239+700 239+800 LHS Cum 6 249.90 248+700 NKC Camp
May'18 27-May-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 237+400 237+600 LHS Cum 15 20.00 1.00 4.00
May'18 27-May-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 237+400 237+600 LHS Cum 1.00
May'18 27-May-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 237+400 237+600 LHS Cum 5
May'18 27-May-18 Bhupender Singh Excavation Ordinary Soil (W&SER) Excavation upto SG Top 259+820 259+960 RHS Cum 29 232.00 3.00 2.00 259+800
May'18 27-May-18 KG Excavation Hard Rock (W&SER) Excavation upto SG Top 256+950 257+100 RHS Cum 5 120.28 1.00 2.00 248+700 NKC Camp
May'18 28-May-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 240+000 239+940 LHS Cum 18 144.00 1.00 3.00 241+000
May'18 28-May-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 240+000 239+940 LHS Cum 1.00
May'18 28-May-18 Ajay Pathania RRM Masonary DATA Given at end of month 237+617 237+647 LHS Cum 30.40 1 2.5 20.00
May'18 28-May-18 Ajay Pathania PCC For RMM DATA Given at end of month 237+617 237+647 LHS Cum 30.40 0.6 0.1 1.82
May'18 28-May-18 Ajay Pathania PCC For RMM DATA Given at end of month 237+617 237+647 LHS Cum 30.40 1.4 0.1 4.26
May'18 28-May-18 Ajay Pathania RRM Masonary DATA Given at end of month 246+073 246+136 LHS Cum 63.00 1 2.5 157.50
May'18 28-May-18 Ajay Pathania PCC For RMM DATA Given at end of month 246+073 246+136 LHS Cum 63.00 0.6 0.1 3.78
May'18 28-May-18 Ajay Pathania PCC For RMM DATA Given at end of month 246+073 246+136 LHS Cum 63.00 1.4 0.1 8.82
May'18 28-May-18 Ajay Pathania RRM Masonary DATA Given at end of month 243+600 243+614 LHS Cum 14.25 1.6 4 91.20
May'18 28-May-18 Ajay Pathania PCC For RMM DATA Given at end of month 243+600 243+614 LHS Cum 14.25 0.9 0.1 1.28
May'18 28-May-18 Ajay Pathania PCC For RMM DATA Given at end of month 243+600 243+614 LHS Cum 14.25 2.3 0.1 3.28
May'18 28-May-18 Bhagwan Singh RRM Masonary DATA Given at end of month 246+808 246+847 LHS Cum 39.00 1 2.5 47.50
May'18 28-May-18 Bhagwan Singh PCC For RMM DATA Given at end of month 246+808 246+847 LHS Cum 39.00 0.6 0.1 2.34
May'18 28-May-18 Bhagwan Singh PCC For RMM DATA Given at end of month 246+808 246+847 LHS Cum 39.00 1.4 0.1 5.46
May'18 28-May-18 Kamal Kant Gabion Retaining Wall DATA Given at end of month 165.00
May'18 28-May-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 239+700 239+800 LHS Cum 6 167.91 248+700 NKC Camp
May'18 28-May-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 237+400 237+600 LHS Cum
May'18 28-May-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 237+400 237+600 LHS Cum 19 152.00 1.00 4.00
May'18 28-May-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 237+400 237+600 LHS Cum 2 1.00
May'18 28-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 246+150 246+200 LHS Cum 23 184.00 2.00 7.00 22trips=252+000, 1 trip= 238+803
May'18 28-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+150 246+200 LHS Cum 7
May'18 28-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+150 246+200 LHS Cum 2.00
May'18 28-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 249+500 249+520 BHS Cum 20.00 5 1.25 125.00 1.00 4.00 252+000
May'18 28-May-18 NKC WMM Dumping WMM Unloading camp 248+200 BHS MT 959.68 5.00
May'18 28-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 249+500 252+360 BHS Cum 17 136.00 4.00 248+300
May'18 28-May-18 Surender mahant Gabion Retaining Wall 8th Gabion RW 8th lift 263+609 263+618 LHS Cum 3 9.00 1 1 9.00 9
May'18 28-May-18 Chandan Premi Gabion Retaining Wall 2nd Gabion RW 2nd lift 261+125 261+128 LHS Cum 4 3.00 4 1 12.00 12
May'18 28-May-18 Madan Singh Chauhan Gabion Retaining Wall 5th Gabion RW 5th lift 254+555 254+561 LHS Cum 4 6.00 2 1 12.00 12
May'18 28-May-18 Ashok Kumar Contractor Gabion Retaining Wall 4th Gabion RW 4th lift 258+508 258+511 LHS Cum 4 3.00 4 1 12.00 12
May'18 28-May-18 Ashok Kumar Contractor Gabion Retaining Wall 5th Gabion RW 5th lift 258+510 258+515 LHS Cum 5 5.00 3 1 15.00
May'18 28-May-18 Bhupender Singh Excavation Ordinary Soil (W&SER) Excavation upto SG Top 259+820 259+960 RHS Cum 11 88.00 2.00 1.00 259+800
May'18 28-May-18 KG Excavation Ordinary Soil (W&SER) Excavation upto SG Top 256+950 257+100 RHS Cum 4 1.00 3.00
May'18 28-May-18 Jham Jham Excavation Ordinary Soil (W&SER) Excavation upto SG Top 256+640 259+960 RHS Cum
May'18 28-May-18 NKC Subgrade Layers (W&SER) Top layer Bed preperation Completed 260+990 257+100 RHS Cum
May'18 28-May-18 NKC Subgrade Layers (W&SER) Top layer Bed preperation Completed 261+360 256+800 RHS Cum
May'18 28-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 260+120 261+020 RHS Cum
May'18 28-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 258+230 261+400 RHS Cum 10 80.00 258+330
May'18 28-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 258+150 260+130 RHS Cum 7 174.67 248+700 NKC Camp
May'18 28-May-18 KG Excavation Hard Rock (W&SER) Excavation upto SG Top 4 90.63 248+700 NKC Camp
May'18 29-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 246+150 246+200 LHS Cum 19 152.00 1.00 5.00 252+020
May'18 29-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+150 246+200 LHS Cum 1.00
May'18 29-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+150 246+200 LHS Cum 2 50.76 1.00 2.00 248+700 NKC Camp
May'18 29-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 246+080 246+130 LHS Cum
May'18 29-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 249+500 249+520 BHS Cum 23 200.00 1.00 5.00 252+000
May'18 29-May-18 NKC WMM Dumping WMM Unloading camp 248+500 LHS MT 10 330.00 2.00 248+450
May'18 29-May-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 240+000 239+940 LHS Cum 5 40.00 2.00 4.00 241+000
May'18 29-May-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 239+700 239+800 LHS Cum 22 176.00
May'18 29-May-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 237+600 237+700 LHS Cum 1.00
May'18 29-May-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 237+600 237+700 LHS Cum 5 120.20 1.00 3.00 248+700 NKC Camp
May'18 29-May-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 237+600 237+700 LHS Cum 19 152.00 2.00 1.00 238+800
May'18 29-May-18 Bhupender Singh Excavation Ordinary Soil (W&SER) Excavation upto SG Top 259+820 259+960 RHS Cum NO Work
May'18 29-May-18 KG Excavation Hard Rock (W&SER) Excavation upto SG Top 256+950 257+100 RHS Cum 5 112.77 1.00 2.00 248+700 NKC Camp
May'18 29-May-18 NKC Subgrade Layers (W&SER) Top layer Bed preperation 260+100 260+140 RHS Cum 40.00 11 0.25 110.00 1.00
May'18 29-May-18 NKC Subgrade Layers (W&SER) Top layer Bed preperation 258+160 258+230 RHS Cum 1.00 1.00
May'18 29-May-18 NKC WMM Dumping WMM Unloading 261+360 201+400 RHS Cum 5 132.61
May'18 29-May-18 NKC WMM Dumping WMM Unloading 260+990 261+020 RHS Cum 4 104.49
May'18 29-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 260+150 260+180 RHS Cum 7 56.00 1.00 2.00 264+580
May'18 29-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 260+160 260+180 RHS Cum 3 261+150
May'18 29-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 260+160 260+190 RHS Cum 1.00
May'18 29-May-18 Milap Chand RRM Masonary 1st Retaining Wall 264+448 264+458 RHS Cum 10.00 5
May'18 29-May-18 Milap Chand RRM Masonary 2nd Retaining Wall 264+470 264+080 RHS Cum 10.00
May'18 29-May-18 Chandan Premi Gabion Retaining Wall 2nd Gabion RW 2nd lift 261+128 261+134 LHS Cum 8 6.00 4 1 24.00 10
May'18 29-May-18 Chandan Premi Gabion Retaining Wall 1st Gabion RW 1st lift 261+150 261+153 LHS Cum 5 3.00 5 1 15.00
May'18 29-May-18 Ashok Kumar Contractor Gabion Retaining Wall 4th Gabion RW 4th lift 258+498 258+508 LHS Cum 13 10.00 4 1 40.00 12
May'18 29-May-18 Ashok Kumar Contractor Gabion Retaining Wall 5th Gabion RW 5th lift 258+520 258+530 LHS Cum 10 10.00 3 1 30.00
May'18 30-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 246+150 246+200 LHS Cum 22 176.00 2.00 6.00 4=252+000, 18=248+000
May'18 30-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+150 246+200 LHS Cum 1.00
May'18 30-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+150 246+200 LHS Cum 10 236.30 248+700 NKC Camp
May'18 30-May-18 Kamal Kant Gabion Retaining Wall Top Gabion RW Top lift 236+700 236+745 RHS Cum 15 45.00 1 1 45.00 15
May'18 30-May-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 240+000 239+940 LHS Cum 8 64.00 1.00 4.00
May'18 30-May-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 239+800 239+820 LHS Cum 5 40.00
May'18 30-May-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 239+800 239+820 LHS Cum 1
May'18 30-May-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 237+400 237+600 LHS Cum 14 112.00 2.00 4.00
May'18 30-May-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 237+400 237+600 LHS Cum 1.00
May'18 30-May-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 237+400 237+600 LHS Cum 7 226.60 1.00 248+700 NKC Camp
May'18 30-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 249+500 249+520 RHS Cum 25 200.00 1.00 4.00 252+400
May'18 30-May-18 NKC Subgrade Layers (W&SER) Top layer Bed preperation 252+360 252+460 RHS Cum 100.00 11 0.2 220.00 1.00 1.00
May'18 30-May-18 NKC WMM Dumping WMM Unloading camp 248+560 RHS MT 12 360.00 3.00
May'18 30-May-18 Bhupender Singh Excavation Ordinary Soil (W&SER) Excavation upto SG Top 259+820 259+960 RHS Cum 22 176.00 2.00 1.00 259+000
May'18 30-May-18 KG Excavation Ordinary Soil (W&SER) Excavation upto SG Top 256+950 256+100 RHS Cum 5 1.00 1.00
May'18 30-May-18 KG Excavation Hard Rock (W&SER) Excavation upto SG Top 256+950 256+100 RHS Cum 5 120.54 248+700 NKC Camp
May'18 30-May-18 NKC WMM Top (W&SER) WMM BED 1st layer preperation 261+360 261+400 RHS Cum 1.00 1.00
May'18 30-May-18 NKC Subgrade Layers (W&SER) Top layer Bed preperation 258+160 258+230 RHS Cum
May'18 30-May-18 NKC WMM Dumping WMM Unloading 261+360 261+400 RHS MT 3 76.01
May'18 30-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 26+060 260+190 RHS Cum 9 72.00 1.00 1.00 264+500
May'18 30-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 260+160 260+180 RHS Cum 5 1.00 1.00 261+120
May'18 30-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation for PCC Retaining Wall 264+360 261+400 RHS Cum 1.00
May'18 30-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 260+810 26+080 RHS Cum
May'18 30-May-18 Devi Singh Gabion Retaining Wall 2nd Gabion RW 2nd lift 261+014 261+134 LHS Cum 6 18.00 1 1 18.00 8.00
May'18 30-May-18 Devi Singh Gabion Retaining Wall 3rd Gabion RW 3rd lift 261+014 261+153 LHS Cum 2 6.00 1 1 6.00
May'18 30-May-18 Surender mahant Gabion Retaining Wall 8th Gabion RW 8th lift 263+618 258+508 LHS Cum 2 6.00 1 1 6.00 4.00
May'18 30-May-18 Kamlesh Thakur Gabion Retaining Wall 1st Gabion RW 1st lift 260+252 258+530 LHS Cum 6 18.00 1 1 18.00 12.00
May'18 30-May-18 Chandan Premi Gabion Retaining Wall 2nd Gabion RW 2nd lift 261+134 258+530 LHS Cum 4 3.00 4 1 12.00 6.00
May'18 31-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 246+150 246+200 LHS Cum 15 120.00 2.00 6.00 252+000
May'18 31-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+150 246+200 LHS Cum 11 436.15 248+700 NKC Camp
May'18 31-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+150 246+200 LHS Cum 2.00
May'18 31-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+700 246+800 LHS Cum 7 1.00 3.00
May'18 31-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 239+680 239+800 LHS Cum 1.00 1.00
May'18 31-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 246+080 246+130 LHS Cum
May'18 31-May-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 239+940 240+000 LHS Cum 12 96.00 1.00 4.00
May'18 31-May-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 237+400 237+600 LHS Cum 20 160.00 2.00 6.00 241+000
May'18 31-May-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 237+400 237+600 LHS Cum 1.00 237+940
May'18 31-May-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 237+400 237+600 LHS Cum 9 241.72 1.00 248+700 NKC Camp
May'18 31-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 249+500 252+360 LHS Cum 27 216.00 1.00 4.00 252+360
May'18 31-May-18 NKC Subgrade Layers (W&SER) Earthen Shoulder Preperation 251+670 251+900 LHS Cum 230.00 1.5 0.25 86.25 1.00 1.00
May'18 31-May-18 Bhupender Singh Excavation Ordinary Soil (W&SER) Excavation upto SG Top 269+820 259+960 RHS Cum 25 200.00 2.00 1.00 259+800
May'18 31-May-18 KG Excavation Ordinary Soil (W&SER) Excavation upto SG Top 256+950 257+100 RHS Cum 4 1.00 1.00
May'18 31-May-18 Jham Jham Excavation Ordinary Soil (W&SER) Excavation upto SG Top 256+840 256+800 RHS Cum
May'18 31-May-18 NKC WMM Top (W&SER) WMM BED 1st layer preperation 260+990 261+020 RHS Cum 1.00 1.00
May'18 31-May-18 NKC GSB (W&SER) GSB Bed Preperation 261+590 261+630 RHS Cum
May'18 31-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 260+810 260+830 RHS Cum 1.00
May'18 31-May-18 NKC WMM Dumping WMM Unloading 261+360 261+400 RHS Cum 3 73.74
May'18 31-May-18 NKC GSB Dumping GSB Unloading 260+100 260+150 RHS Cum 4 100.59
May'18 31-May-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 269+450 259+550 RHS Cum 5 40.00 1.00 1.00 261+030
May'18 31-May-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 259+500 RHS Cum 1
May'18 31-May-18 Kamlesh Thakur Retaining Wall PCC 264+428 264+437 RHS Cum 10.00 6
May'18 31-May-18 Kamlesh Thakur Gabion Retaining Wall 1st Gabion RW 1st lift 264+450 264+460 RHS Cum 20.00
May'18 31-May-18 Kamlesh Thakur Retaining Wall PCC 264+390 264+400 RHS Cum 10.00
May'18 31-May-18 Devi Singh Gabion Retaining Wall 3rd Gabion RW 3rd lift 261+020 261+029 LHS Cum 3 9.00 1 1 9.00 6
May'18 31-May-18 Kamlesh Thakur Gabion Retaining Wall 1st Gabion RW 1st lift 260+234 260+252 LHS Cum 6 18.00 1 1 18.00 12
May'18 31-May-18 Kamlesh Thakur Gabion Retaining Wall 1st Gabion RW 1st lift 260+390 260+402 LHS Cum 4 12.00 1 1 12.00
May'18 31-May-18 Madan Singh Chauhan Gabion Retaining Wall 5th Gabion RW 5th lift 254+534 254+540 LHS Cum 4 6.00 2 1 12.00 8
May'18 31-May-18 KG Excavation Hard Rock (W&SER) Excavation upto SG Top 256+950 257+100 RHS Cum 4 97.09 248+700 NKC Camp
Jun'18 1-Jun-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 239+940 240+700 LHS Cum 15 120.00 1.00 4.00 237+940
Jun'18 1-Jun-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 237+400 237+600 LHS Cum 20 160.00 2.00 4.00
S.No Date Contractor Progress work Layer Misc works From To Side Unit Nos Length Breadth Depth Quantity Excavators Dumpers JCB Grader Roller Water Tanker Exca with
Loader Breaker Boulder screning Labour Dumping Lead (One Dumping at Remarks
dumper Chainage Side) KM

Jun'18 1-Jun-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 237+400 237+600 LHS Cum 1.00
Jun'18 1-Jun-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 237+400 237+600 LHS Cum 4 111.20 1.00 248+700 NKC Camp
Jun'18 1-Jun-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 246+150 246+200 LHS Cum 25 200.00 1.00 4.00 252+000,11 trips, 248+000=14 trips
Jun'18 1-Jun-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+150 246+200 LHS Cum 1.00
Jun'18 1-Jun-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+150 246+200 LHS Cum 2 45.16 248+700 NKC Camp
Jun'18 1-Jun-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+600 246+700 LHS Cum 1.00
Jun'18 1-Jun-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 246+600 246+700 LHS Cum 1.00
Jun'18 1-Jun-18 NKC Subgrade Layers (W&SER) Bed Completed 246+080 246+130 LHS Cum 1.00
Jun'18 1-Jun-18 NKC Subgrade Layers (W&SER) Bed Completed 239+680 239+810 RHS Cum 1.00 1.00
Jun'18 1-Jun-18 NKC GSB Dumping GSB Unloading 238+790 LHS Cum 27.00
Jun'18 1-Jun-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 249+500 249+520 RHS Cum 30 240.00 1.00 3.00 252+000
Jun'18 1-Jun-18 NKC Subgrade Layers (W&SER) Bed Preperation 252+360 252+500 LHS Cum 1.00 1.00
Jun'18 1-Jun-18 Chandan Premi Gabion Retaining Wall 2nd Gabion RW 2nd lift 261+137 261+029 LHS Cum 1 3.00 1 1 3.00 8
Jun'18 1-Jun-18 Devi Singh Gabion Retaining Wall 2nd Gabion RW 2nd lift 261+032 260+252 LHS Cum 1 3.00 1 1 3.00 8
Jun'18 1-Jun-18 Devi Singh Gabion Retaining Wall 3rd Gabion RW 3rd lift 261+029 260+402 LHS Cum 2 6.00 1 1 6.00
Jun'18 1-Jun-18 Surender mahant Gabion Retaining Wall 8th Gabion RW 8th lift 263+624 254+540 LHS Cum 1 3.00 1 1 3.00 2
Jun'18 1-Jun-18 Kamlesh Thakur Gabion Retaining Wall 1st Gabion RW 1st lift 260+402 254+540 LHS Cum 3 9.00 1 1 9.00 13
Jun'18 1-Jun-18 Kamlesh Thakur Gabion Retaining Wall 1st Gabion RW 1st lift 260+225 254+540 LHS Cum 3 9.00 1 1 9.00
Jun'18 1-Jun-18 Jyoti Savroop Singh Gabion Retaining Wall 1st Gabion RW 1st lift Sevbag LHS Cum 2 6.00 1 1 6.00 6
Jun'18 1-Jun-18 Bhupender Singh Excavation Ordinary Soil (W&SER) Excavation upto SG Top 259+820 259+960 RHS Cum 40 320.00 2.00 1.00
Jun'18 1-Jun-18 KG Excavation Ordinary Soil (W&SER) Excavation upto SG Top 259+820 259+960 RHS Cum 4 1.00 11.00
Jun'18 1-Jun-18 Jham Jham Excavation Ordinary Soil (W&SER) Excavation upto SG Top 259+820 259+960 RHS Cum 1.00
Jun'18 1-Jun-18 NKC GSB (W&SER) GSB Top Bed Preperation 261+590 261+630 RHS Cum 1.00 1.00
Jun'18 1-Jun-18 NKC WMM Top (W&SER) WMM BED 1st layer preperation 260+990 261+020 RHS Cum
Jun'18 1-Jun-18 NKC GSB Dumping GSB Unloading 260+100 260+150 RHS Cum 6 162.90
Jun'18 1-Jun-18 NKC GSB Dumping GSB Unloading 258+160 258+230 RHS Cum 3 85.37
Jun'18 1-Jun-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 260+810 260+830 RHS Cum 1.00
Jun'18 1-Jun-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 259+450 259+550 RHS Cum 7 56.00 1.00 2.00
Jun'18 1-Jun-18 Suresh Kumar Retaining Wall PCC Plumb Concrete 264+548 264+558 RHS Cum 20.00 5
Jun'18 1-Jun-18 Suresh Kumar Retaining Wall PCC Plumb Concrete 264+558 264+570 RHS Cum 10.00
Jun'18 1-Jun-18 KG Excavation Hard Rock (W&SER) Excavation upto SG Top 4 89.43 248+700 NKC Camp
Jun'18 2-Jun-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 246+800 246+840 LHS Cum 27 216.00 1.00 4.00 248+200
Jun'18 2-Jun-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 246+800 246+840 LHS Cum
Jun'18 2-Jun-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+150 246+200 LHS Cum 1.00
Jun'18 2-Jun-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+700 246+750 LHS Cum 1.00
Jun'18 2-Jun-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+700 246+750 LHS Cum 22 562.13 1.00 5.00 248+700 NKC Camp
Jun'18 2-Jun-18 Bhupender Singh Excavation Ordinary Soil (W&SER) Excavation upto SG Top 259+820 259+960 RHS Cum 32 256.00 2.00 1.00 259+800
Jun'18 2-Jun-18 KG Excavation Ordinary Soil (W&SER) Excavation upto SG Top 256+950 257+100 RHS Cum 1.00 1.00
Jun'18 2-Jun-18 KG Excavation Hard Rock (W&SER) Excavation upto SG Top 256+950 4 67.05 248+700 NKC Camp
Jun'18 2-Jun-18 Jham Jham Excavation Ordinary Soil (W&SER) Excavation upto SG Top 256+640 256+800 RHS Cum 1.00 1.00
Jun'18 2-Jun-18 Jham Jham Excavation Hard Rock (W&SER) Excavation upto SG Top 256+640 256+800 RHS Cum 4 69.22 248+700 NKC Camp
Jun'18 2-Jun-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 260+800 260+820 RHS Cum 5 40.00 1.00 2.00
Jun'18 2-Jun-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 260+820 260+840 RHS Cum 4 254600=1, sevbag=2
Jun'18 2-Jun-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 259+500 259+550 RHS Cum 1.00
Jun'18 2-Jun-18 NKC GSB Dumping GSB Unloading 258+160 258+230 RHS Cum 11 292.62
Jun'18 2-Jun-18 NKC Excavation Ordinary Soil (W&SER) Excavation for retaining Wall 264+500 264+540 RHS Cum 1.00
Jun'18 2-Jun-18 Kamlesh Thakur Retaining Wall PCC 1st 264+428 264+239 RHS Cum 25.00 7
Jun'18 2-Jun-18 Veneet Kumar Retaining Wall PCC 264+820 264+537 RHS Cum 11.00 4
Jun'18 2-Jun-18 Chandan Premi Gabion Retaining Wall 3rd Gabion RW 3rd lift 261+119 260+252 LHS Cum 4 4.00 3 1 12.00 8
Jun'18 2-Jun-18 Chandan Premi Gabion Retaining Wall 2nd Gabion RW 2nd lift 261+140 260+402 LHS Cum 4 3.00 4 1 12.00
Jun'18 2-Jun-18 Ashok Kumar Contractor Gabion Retaining Wall 6th Gabion RW 6th lift 258+516 254+540 LHS Cum 4 4.00 3 1 12.00 10
Jun'18 2-Jun-18 Madan Singh Chauhan Gabion Retaining Wall 5th Gabion RW 5th lift 254+528 254+540 LHS Cum 4 6.00 2 1 12.00 6
Jun'18 2-Jun-18 Kamlesh Thakur Gabion Retaining Wall 1st Gabion RW 1st lift 260+213 254+540 LHS Cum 4 12.00 1 1 12.00 10
Jun'18 2-Jun-18 Jyoti Savroop Singh Gabion Retaining Wall 1st Gabion RW 1st lift Sevbag LHS Cum 3 9.00 1 1 9.00 6
Jun'18 3-Jun-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 239+940 24+000 LHS Cum 22 176.00 1.00 3.00
Jun'18 3-Jun-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 237+400 23+600 LHS Cum 19 152.00 1.00 4.00
Jun'18 2-Jun-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 237+400 4 106.94 248+700 NKC Camp
Jun'18 3-Jun-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 237+400 237+600 LHS Cum 1.00
Jun'18 3-Jun-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 237+400 237+600 LHS Cum 4 94.83 1.00 2.00 248+700 NKC Camp
Jun'18 3-Jun-18 Chandan Premi Gabion Retaining Wall 3rd Gabion RW 3rd lift 261+113 260+402 LHS Cum 3 3.00 3 1 9.00 6
Jun'18 3-Jun-18 Ashok Kumar Contractor Gabion Retaining Wall 6th Gabion RW 6th lift 258+512 254+540 LHS Cum 4 4.00 3 1 12.00 12
Jun'18 3-Jun-18 Ashok Kumar Contractor Gabion Retaining Wall 5th Gabion RW 5th lift 258+504 254+540 LHS Cum 4 4.00 3 1 12.00
Jun'18 3-Jun-18 Kamlesh Thakur Gabion Retaining Wall 1st Gabion RW 1st lift 260+204 254+540 LHS Cum 3 9.00 1 1 9.00 7
Jun'18 3-Jun-18 Jyoti Savroop Singh Gabion Retaining Wall 1st Gabion RW 1st lift Sevbag LHS Cum 3 9.00 1 1 9.00 6
Jun'18 3-Jun-18 Bhupender Singh Excavation Ordinary Soil (W&SER) Excavation upto SG Top 259+820 259+960 RHS Cum 22 176.00 2.00 1.00 259+800
Jun'18 3-Jun-18 KG Excavation Ordinary Soil (W&SER) Excavation upto SG Top 256+950 257+100 RHS Cum 1.00
Jun'18 3-Jun-18 KG Excavation Hard Rock (W&SER) Excavation upto SG Top 256+950 1 22.74 248+700 NKC Camp
Jun'18 3-Jun-18 Jham Jham Excavation Ordinary Soil (W&SER) Excavation upto SG Top 256+840 256+800 RHS Cum 1.00
Jun'18 3-Jun-18 Ram Dev patch work 21.71
Jun'18 4-Jun-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 246+800 246+840 RHS Cum 8 64.00 1.00 2.00
Jun'18 4-Jun-18 NKC GSB Dumping GSB Unloading 246+090 246+130 LHS Cum 6 161.73 1.00
Jun'18 4-Jun-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 246+150 246+200 LHS Cum 1.00 3.00
Jun'18 4-Jun-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+840 246+850 LHS Cum 5 1.00
Jun'18 4-Jun-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+700 246+750 LHS Cum
Jun'18 4-Jun-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+200 246+240 LHS Cum 1.00
Jun'18 4-Jun-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+840 246+850 LHS Cum 1
Jun'18 4-Jun-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+700 246+750 LHS Cum 13 357.55 248+700 NKC Camp
Jun'18 4-Jun-18 NKC GSB Dumping GSB Unloading 239+800 239+750 LHS Cum 3 80.92 1.00
Jun'18 4-Jun-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+250 246+300 LHS Cum 1.00
Jun'18 4-Jun-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 239+940 240+000 LHS Cum 6 48.00 1.00 2.00
Jun'18 4-Jun-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 237+400 237+500 LHS Cum 21 168.00 2.00 4.00
Jun'18 4-Jun-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 237+400 237+500 LHS Cum 1.00
Jun'18 4-Jun-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 237+400 237+500 LHS Cum 7 169.14 1.00 3.00 248+700 NKC Camp
Jun'18 4-Jun-18 NKC GSB Dumping GSB Unloading camp 252+360 RHS Cum 8 216.00 3.00
Jun'18 4-Jun-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 249+500 249+020 RHS Cum 6 48.00 1.00 4.00 252+360
Jun'18 4-Jun-18 Bhupender Singh Excavation Ordinary Soil (W&SER) Excavation upto SG Top 259+820 259+980 RHS Cum 18 144.00 1.00 1.00
Jun'18 4-Jun-18 KG Excavation Ordinary Soil (W&SER) Excavation upto SG Top 256+950 256+100 RHS Cum 1.00 1.00
Jun'18 4-Jun-18 Jham Jham Excavation Ordinary Soil (W&SER) Excavation upto SG Top 256+840 256+800 RHS Cum 1.00 1.00
Jun'18 4-Jun-18 NKC GSB (W&SER) GSB Top Bed Preperation 258+160 258+230 RHS Cum 1.00 1.00
Jun'18 4-Jun-18 NKC GSB Dumping GSB Unloading 258+160 258+230 RHS Cum 2 52.33
Jun'18 4-Jun-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 260+810 260+830 RHS Cum 6
Jun'18 4-Jun-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 258+730 258+750 RHS Cum 21 168.00 1.00 2.00
Jun'18 4-Jun-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 259+540 259+560 RHS Cum 1.00
Jun'18 4-Jun-18 NKC Excavation Ordinary Soil (W&SER) Excavation for retaining Wall 264+470 264+500 RHS Cum 1.00
Jun'18 4-Jun-18 Suresh Kumar Retaining Wall PCC 264+278 264+582 RHS Cum 4.00 2
Jun'18 4-Jun-18 Suresh Kumar Retaining Wall PCC 264+558 264+573 RHS Cum 12.50 4
Jun'18 4-Jun-18 Veneet Kumar Retaining Wall PCC 264+520 264+529 RHS Cum 13.50 5
Jun'18 4-Jun-18 Chandan Premi Gabion Retaining Wall 2nd Gabion RW 2nd lift 261+140 260+402 LHS Cum 4 3.00 4 1 12.00 8
Jun'18 4-Jun-18 Chandan Premi Gabion Retaining Wall 3rd Gabion RW 3rd lift 261+116 254+540 LHS Cum 2 2.00 3 1 6.00
Jun'18 4-Jun-18 Surender mahant Gabion Retaining Wall 8th Gabion RW 8th lift 263+627 254+540 LHS Cum 3 9.00 1 1 9.00 4
Jun'18 4-Jun-18 Kamlesh Thakur Gabion Retaining Wall 1st Gabion RW 1st lift 260+195 254+540 LHS Cum 3 9.00 1 1 9.00 7
Jun'18 4-Jun-18 Ashok Kumar Contractor Gabion Retaining Wall 5th Gabion RW 5th lift 258+498 254+540 LHS Cum 6 6.00 3 1 18.00 10
Jun'18 4-Jun-18 Ashok Kumar Contractor Gabion Retaining Wall 5th Gabion RW 5th lift 258+530 254+540 LHS Cum 2 2.00 3 1 6.00
Jun'18 4-Jun-18 Madan Singh Chauhan Gabion Retaining Wall 5th Gabion RW 5th lift 254+525 254+540 LHS Cum 2 3.00 2 1 6.00 8
Jun'18 4-Jun-18 Madan Singh Chauhan Gabion Retaining Wall 4th Gabion RW 4th lift 254+522 254+540 LHS Cum 2 3.00 2 1 6.00
Jun'18 4-Jun-18 Jyoti Savroop Singh Gabion Retaining Wall 1st Gabion RW 1st lift Sevbag LHS Cum 4 12.00 1 1 12.00 6
Jun'18 4-Jun-18 Jham Jham Excavation Hard Rock (W&SER) Excavation upto SG Top 7 108.41 248+700 NKC Camp
Jun'18 5-Jun-18 NKC Subgrade Layers (W&SER) Bed Preperation 252+370 252+420 LHS Cum 50.00 12.5 0.2 125.00 1.00 1.00
Jun'18 5-Jun-18 NKC GSB (W&SER) GSB Top Bed Preperation 252+370 252+420 RHS Cum 50.00 10.5 0.2 105.00
Jun'18 5-Jun-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 239+940 24+000 LHS Cum 29 232.00 1.00 3.00 241+000
Jun'18 5-Jun-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 237+600 237+700 LHS Cum 27 216.00 1.00 3.00 237+940
Jun'18 5-Jun-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 237+600 237+700 LHS Cum 1.00
Jun'18 5-Jun-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 237+600 237+700 LHS Cum 2 40.12 1.00 2.00 1.00 248+700 NKC Camp
Jun'18 5-Jun-18 Bhupender Singh Excavation Ordinary Soil (W&SER) Excavation upto SG Top 259+820 259+960 RHS Cum 15 120.00 2.00 1.00
Jun'18 5-Jun-18 KG Excavation Ordinary Soil (W&SER) Excavation upto SG Top 256+950 252+106 RHS Cum 1.00
Jun'18 5-Jun-18 Jham Jham Excavation Hard Rock (W&SER) Excavation upto SG Top 256+840 256+840 RHS Cum 14 236.34 1.00 1.00 248+700 NKC Camp
Jun'18 5-Jun-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 258+730 258+740 RHS Cum 18 144.00 1.00 1.00
Jun'18 5-Jun-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 263+520 263+600 RHS Cum 1.00
Jun'18 5-Jun-18 Surender mahant Retaining Wall PCC 264+558 264+573 RHS Cum 5
Jun'18 5-Jun-18 Veneet Kumar Retaining Wall PCC 264+529 264+538 RHS Cum 5
Jun'18 5-Jun-18 Kamlesh Thakur Retaining Wall PCC 264+400 264+406 RHS Cum 4
Jun'18 5-Jun-18 Chandan Premi Gabion Retaining Wall 2nd Gabion RW 2nd lift 261+143 260+402 LHS Cum 8 6.00 4 1 24.00 8
Jun'18 5-Jun-18 Madan Singh Chauhan Gabion Retaining Wall 4th Gabion RW 4th lift 254+519 254+540 LHS Cum 2 3.00 2 1 6.00 4
Jun'18 5-Jun-18 Kamlesh Thakur Gabion Retaining Wall 1st Gabion RW 1st lift 260+186 254+540 LHS Cum 3 9.00 1 1 9.00 7
Jun'18 5-Jun-18 Jyoti Savroop Singh Gabion Retaining Wall 1st Gabion RW 1st lift Sevbag LHS Cum 3 9.00 1 1 9.00 6
Jun'18 5-Jun-18 Ashok Kumar Contractor Gabion Retaining Wall 5th Gabion RW 5th lift 258+532 254+540 LHS Cum 6 6.00 3 1 18.00 14
Jun'18 5-Jun-18 Ashok Kumar Contractor Gabion Retaining Wall 1st Gabion RW 1st lift 259+741 254+540 LHS Cum 10 15.00 2 1 30.00
Jun'18 5-Jun-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 240+940 241+000 LHS Cum 5 40.00 1.00 1.00 240+920
Jun'18 5-Jun-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 246+200 246+250 LHS Cum 51 408.00 1.00 6.00 248+500
Jun'18 5-Jun-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+700 246+750 LHS Cum 1.00
Jun'18 5-Jun-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 240+910 240+920 LHS Cum 1.00
Jun'18 5-Jun-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+600 246+700 LHS Cum 7 171.76 1.00 2.00 248+700 NKC Camp
Jun'18 5-Jun-18 NKC GSB Dumping GSB Unloading 239+680 239+770 RHS Cum 5 144.22
Jun'18 5-Jun-18 NKC GSB Dumping GSB Unloading 246+120 246+140 LHS Cum 3 85.76
Jun'18 5-Jun-18 NKC GSB Dumping GSB Unloading 246+800 246+850 LHS Cum 7 195.43
Jun'18 6-Jun-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 254+780 254+800 RHS Cum 20.00 10 1 200.00 1.00 1.00 254+500
Jun'18 6-Jun-18 Madan Singh Chauhan Gabion Retaining Wall 254+500 254+512 LHS Cum 4 12.00 1 1 12.00 8
Jun'18 6-Jun-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top camp 254+500 LHS Cum 3 3.00 254+500
Jun'18 6-Jun-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 239+940 240+000 LHS Cum 17 136.00 1.00 3.00 241+000
Jun'18 6-Jun-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 237+600 237+700 LHS Cum 27 216.00 1.00 3.00 237+140
Jun'18 6-Jun-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 237+600 237+700 LHS Cum 1.00
Jun'18 6-Jun-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 237+600 237+700 LHS Cum 4 110.78 1.00 2.00 248+700 NKC Camp
Jun'18 6-Jun-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 241+280 24+130 LHS Cum 13 104.00 1.00 2.00
Jun'18 6-Jun-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 240+920 240+940 LHS Cum 3
Jun'18 6-Jun-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 240+926 240+930 LHS Cum 1.00
Jun'18 6-Jun-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 246+120 246+200 LHS Cum 26 208.00 1.00 4.00 240+920
Jun'18 6-Jun-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+120 246+200 LHS Cum 11 345.34 248+700 NKC Camp
Jun'18 6-Jun-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+120 246+200 LHS Cum 1.00
Jun'18 6-Jun-18 KG Excavation Hard Rock (W&SER) Excavation upto SG Top 257+000 LHS Cum 3 72.62 248+700 NKC Camp
Jun'18 6-Jun-18 NKC Subgrade Layers (W&SER) Bed Preperation 240+920 241+000 LHS Cum 1.00 1.00 248+200
Jun'18 6-Jun-18 NKC GSB (W&SER) GSB Top Bed Preperation 239+685 239+800 LHS Cum
Jun'18 6-Jun-18 Surender mahant Gabion Retaining Wall 8th 263+636 260+402 LHS Cum 3 9.00 1 1 9.00 4
Jun'18 6-Jun-18 Chandan Premi Gabion Retaining Wall 2nd 261+149 254+540 LHS Cum 4 3.00 4 1 12.00 7
Jun'18 6-Jun-18 Ashok Kumar Contractor Gabion Retaining Wall 5th 258+538 254+540 LHS Cum 4 4.00 3 1 12.00 14
Jun'18 6-Jun-18 Ashok Kumar Contractor Gabion Retaining Wall 1st 259+726 254+540 LHS Cum 10 15.00 2 1 30.00
Jun'18 6-Jun-18 Kamlesh Thakur Gabion Retaining Wall 5th 260+174 254+540 LHS Cum 4 12.00 1 1 12.00 7
Jun'18 6-Jun-18 Madan Singh Chauhan Gabion Retaining Wall 4th 254+513 254+540 LHS Cum 2 6.00 1 1 6.00 8
Jun'18 6-Jun-18 Bhupender Singh Excavation Ordinary Soil (W&SER) Excavation upto SG Top 259+820 259+960 RHS Cum 18 144.00 1.00 1.00
Jun'18 6-Jun-18 KG Excavation Ordinary Soil (W&SER) Excavation upto SG Top 256+950 257+100 RHS Cum 3 1.00 1.00
Jun'18 6-Jun-18 Jham Jham Excavation Ordinary Soil (W&SER) Excavation upto SG Top 256+640 256+800 RHS Cum 1.00 1.00
Jun'18 6-Jun-18 Jham Jham Excavation Hard Rock (W&SER) Excavation upto SG Top 256+640 256+800 RHS Cum 8 128.29 248+700 NKC Camp
Jun'18 6-Jun-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 258+730 258+770 RHS Cum 16 128.00 1.00 2.00
Jun'18 6-Jun-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 257+730 258+840 RHS Cum 1 1.00 1.00
Jun'18 6-Jun-18 NKC Subgrade Layers (W&SER) Bed Preperation 259+450 259+520 RHS Cum
Jun'18 6-Jun-18 NKC WMM Dumping WMM Unloading 258+760 258+230 RHS Cum 8 203.79
Jun'18 6-Jun-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 259+450 259+500 RHS Cum 1.00
Jun'18 6-Jun-18 Veneet Kumar Retaining Wall PCC 264+510 264+520 RHS Cum 15.00 5
Jun'18 6-Jun-18 Kamlesh Thakur Retaining Wall PCC 264+990 264+400 RHS Cum 10.00 4
Jun'18 6-Jun-18 NKC Excavation Ordinary Soil (W&SER) Excavation for retaining wall 264+470 264+500 RHS Cum 1.00
Jun'18 7-Jun-18 NKC GSB (W&SER) GSB Top Bed Preperation 252+370 252+420 LHS Cum 50.00 10.8 0.2 108.00 1.00 1.00
Jun'18 7-Jun-18 NKC WMM Top (W&SER) WMM BED 1st layer preperation 232+370 252+420 LHS Cum 50.00 9.2 0.125 57.00
Jun'18 7-Jun-18 NKC Gabion Retaining Wall 4th 254+512 254+521 LHS Cum 9.00 1 1 9.00 8
Jun'18 7-Jun-18 NKC GSB Dumping GSB Unloading camp 252+370 LHS Cum 9 270.00 3.00
Jun'18 7-Jun-18 NKC WMM Dumping WMM Unloading camp 252+370 LHS Cum 6 210.00
Jun'18 7-Jun-18 NKC WMM Top (W&SER) WMM BED 1st layer preperation 247+860 247+960 LHS Cum 100.00 9.2 0.125 115.00 1.00 1.00
Jun'18 7-Jun-18 NKC Excavation Ordinary Soil (W&SER) Excavation for retaining wall 254+800 254+820 LHS Cum 20 160.00 1.00 2.00 254+540
Jun'18 7-Jun-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 239+940 240+000 LHS 21 168.00 1.00 3.00 241+000
Jun'18 7-Jun-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 237+600 237+700 LHS 20 160.00 2.00 3.00 238+000
Jun'18 7-Jun-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 237+600 237+700 LHS 1.00
Jun'18 7-Jun-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 237+600 237+700 LHS 7 158.34 248+700 NKC Camp
Jun'18 7-Jun-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 246+150 246+200 LHS 7 56.00 1.00 3.00
Jun'18 7-Jun-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 240+900 240+920 LHS 1.00
Jun'18 7-Jun-18 NKC Subgrade Layers (W&SER) 2nd layer Bed Preperation 240+920 241+000 LHS 1.00 1.00
Jun'18 7-Jun-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 257+300 257+400 RHS Cum 7 56.00 1.00 3.00
Jun'18 7-Jun-18 NKC Subgrade Layers (W&SER) TOp Bed Preperation 259+450 259+520 RHS Cum
Jun'18 7-Jun-18 NKC WMM Top (W&SER) WMM BED 1st layer preperation 258+160 258+230 RHS Cum 1.00 1.00
Jun'18 7-Jun-18 NKC WMM Dumping WMM Unloading 261+590 261+630 RHS Cum 4 101.16
Jun'18 7-Jun-18 NKC WMM Dumping WMM Unloading 261+810 261+920 RHS Cum 2 41.85
Jun'18 7-Jun-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 264+240 RHS Cum 1.00
Jun'18 7-Jun-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 258+850 RHS Cum 1.00
Jun'18 7-Jun-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 258+730 258+770 RHS Cum 40.00 2.00 3.00
Jun'18 7-Jun-18 NKC Retaining Wall PCC 264+887 264+899 RHS Cum 7.00
Jun'18 7-Jun-18 KG Excavation Hard Rock (W&SER) Excavation upto SG Top 4 93.95 248+700 NKC Camp
Jun'18 8-Jun-18 Chandan Premi Gabion Retaining Wall 2 261+122 261+128 LHS Cum 6.00 3 1 18.00 8
Jun'18 8-Jun-18 Devi Singh Gabion Retaining Wall 1 264+510 264+514 LHS Cum 4.00 3 1 12.00 6
Jun'18 8-Jun-18 Madan Singh Chauhan Gabion Retaining Wall 5 254+561 254+573 LHS Cum 12.00 1 1 12.00 9
Jun'18 8-Jun-18 Madan Singh Chauhan Gabion Retaining Wall 6 254+546 254+561 LHS Cum 15.00 1 1 15.00
Jun'18 8-Jun-18 Kamlesh Thakur Gabion Retaining Wall 1 260+159 160+165 LHS Cum 6.00 1 1 6.00 5
Jun'18 8-Jun-18 Ashok Kumar Contractor Gabion Retaining Wall 5 258+544 258+546 LHS Cum 2.00 3 1 6.00 12
Jun'18 8-Jun-18 Ashok Kumar Contractor Gabion Retaining Wall 2 259+723 259+735 LHS Cum 12.00 1 1 12.00
Jun'18 8-Jun-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 239+940 240+000 LHS Cum 25 200.00 1.00 3.00 241+000
Jun'18 8-Jun-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 237+600 237+700 LHS Cum 18 2.00 2.00 238+000
Jun'18 8-Jun-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 237+600 237+700 LHS Cum 1.00 WIP
Jun'18 8-Jun-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 237+600 237+700 LHS Cum 3 66.56 1.00 2.00 248+700 NKC Camp
Jun'18 8-Jun-18 NKC WMM Dumping WMM Unloading 252+370 252+920 RHS Cum 9 72.00 3.00
Jun'18 8-Jun-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 254+700 254+800 RHS Cum 20 160.00 1.00 1.00 254+500
Jun'18 8-Jun-18 Madan Singh Chauhan Gabion Retaining Wall Top 254+521 254+530 RHS Cum 9.00 1 1 9.00 8
Jun'18 8-Jun-18 NKC Subgrade top (W&SER) Bed Preperation 240+950 241+000 LHS
Jun'18 8-Jun-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 240+900 240+910 LHS 1.00
Jun'18 8-Jun-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 257+300 257+400 RHS Cum 55 440.00 2.00 6.00 254+600
Jun'18 8-Jun-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 258+820 258+860 RHS Cum 15 120.00 1.00 2.00 259+400=12, 258+320=3
Jun'18 8-Jun-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 259+350 RHS Cum 1.00 WIP
Jun'18 8-Jun-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 264+280 RHS Cum 1.00 WIP
Jun'18 8-Jun-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 264+230 264+250 RHS Cum 3 24.00 1.00 1.00 264+130=2, 264+480=1
Jun'18 8-Jun-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 264+450 264+460 RHS Cum 6 48.00
Jun'18 8-Jun-18 NKC WMM 1st layer (W&SER) Bed Preperation 258+160 258+230 RHS Cum 1.00 1.00 Completed
Jun'18 8-Jun-18 NKC WMM 1st layer (W&SER) Bed Preperation 261+590 261+630 RHS Cum 1.00 1.00 WIP
Jun'18 8-Jun-18 Bhupender Singh Excavation Ordinary Soil (W&SER) Excavation upto SG Top 259+820 259+980 RHS Cum 15 120.00 1.00 1.00 259+750
Jun'18 8-Jun-18 KG Excavation Ordinary Soil (W&SER) Excavation upto SG Top 256+950 257+100 RHS Cum 1 8.00 1.00 1.00
Jun'18 8-Jun-18 KG Excavation Hard Rock (W&SER) Excavation upto SG Top 256+950 257+100 RHS Cum 1 23.16 248+700 NKC Camp
Jun'18 8-Jun-18 Jham Jham Excavation Ordinary Soil (W&SER) Excavation upto SG Top 256+640 257+820 RHS Cum 1.00 WIP
Jun'18 8-Jun-18 Kamlesh Thakur Retaining Wall PCC 264+380 264+330 RHS Cum 16.00 3
Jun'18 9-Jun-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 240+900 240+920 LHS Cum 7 56 1.00 3.00 Nkc Camp Completed
Jun'18 9-Jun-18 NKC GSB Dumping GSB Unloading 247+520 LHS Cum 2 16
Jun'18 9-Jun-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 237+500 237+600 LHS Cum 34 272.00 2.00 3.00 233+000
Jun'18 9-Jun-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 237+500 237+600 LHS Cum 1.00 WIP
Jun'18 9-Jun-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 239+940 240+000 LHS Cum 1.00 WIP
Jun'18 9-Jun-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 237+500 237+600 LHS Cum 7 160.83 1.00 3.00 248+700 NKC Camp
Jun'18 9-Jun-18 NKC WMM Top (W&SER) Bed Preperation 247+960 248+010 Cum 60.00 9.2 0.125 69.00 1.00 1.00
Jun'18 9-Jun-18 NKC WMM Dumping WMM Shifting camp 252+000 LHS Cum 4 32.00 3.00
Jun'18 9-Jun-18 NKC WMM Top (W&SER) Bed Preperation 252+370 252+420 RHS Cum 50.00 9.1 0.125 56.88 1.00 1.00
Jun'18 9-Jun-18 NKC Gabion Retaining Wall Top 254+521 254+530 LHS Cum 9.00 1 1 9.00 8
Jun'18 9-Jun-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 257+300 257+400 RHS Cum 49 392.00 1.00 5.00 254+600
Jun'18 9-Jun-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 258+820 258+860 RHS Cum 8 64.00 1.00 2.00 254+600
Jun'18 9-Jun-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 259+400 LHS Cum 1.00 WIP
Jun'18 9-Jun-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 264+280 RHS Cum 1.00 WIP
Jun'18 9-Jun-18 NKC WMM Top (W&SER) Bed Preperation 261+590 261+630 RHS Cum 1.00 1.00
Jun'18 9-Jun-18 NKC Subgrade top (W&SER) Bed Preperation 258+820 258+860 RHS Cum WIP
Jun'18 9-Jun-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 264+260 264+280 RHS Cum 10 184.73 1.00 1.00 248+700 NKC Camp 264+500=5, 263+650=1, 254+600=2
Jun'18 9-Jun-18 NKC WMM Dumping 261+810 261+920 RHS Cum 11 88.00
Jun'18 9-Jun-18 KG Excavation Hard Rock (W&SER) Excavation upto SG Top 5 116.23 248+700 NKC Camp
Jun'18 10-Jun-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 237+500 237+600 LHS Cum 45 360.00 2.00 4.00 238+000
Jun'18 10-Jun-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 237+500 237+600 Cum 1.00 WIP
Jun'18 10-Jun-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 239+940 240+000 LHS Cum 1.00 241+000 WIP
Jun'18 10-Jun-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 237+500 237+600 LHS Cum 10 214.64 1.00 3.00 248+700 NKC Camp
Jun'18 10-Jun-18 Devi Singh Gabion Retaining Wall 1 264+518 264+522 LHS Cum 4.00 3 1 12.00 8
Jun'18 10-Jun-18 Chandan Premi Gabion Retaining Wall 2 261+134 261+142 LHS Cum 8.00 3 1 24.00 10
Jun'18 10-Jun-18 Madan Singh Chauhan Gabion Retaining Wall 6 254+252 254+534 LHS Cum 9.00 1 1 9.00 9
Jun'18 10-Jun-18 Madan Singh Chauhan Gabion Retaining Wall 5 254+522 254+525 LHS Cum 3.00 1 1 3.00 9
Jun'18 10-Jun-18 KG Excavation Hard Rock (W&SER) Excavation upto SG Top 3 70.94 1.00 1.00 248+700 NKC Camp
Jun'18 11-Jun-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 237+400 237+500 LHS Cum 22 176.00 2.00 6.00 241+000 241+000
Jun'18 11-Jun-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 237+400 237+500 LHS Cum 7 191.38 1.00 248+700 NKC Camp
Jun'18 11-Jun-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 237+500 237+600 LHS Cum 12 96.00 1.00 1.00 238+000
Jun'18 11-Jun-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 237+500 237+600 LHS Cum 4 248+700 NKC Camp
Jun'18 11-Jun-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 239+940 240+000 LHS Cum 3 1.00 248+700 NKC Camp
Jun'18 11-Jun-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 239+940 240+000 LHS Cum 1.00
Jun'18 11-Jun-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 240+900 240+920 LHS Cum 8 64.00 1.00 2.00 241+000
Jun'18 11-Jun-18 NKC Subgrade top (W&SER) Bed Preperation 240+900 240+920 LHS Cum 1.00 1.00
Jun'18 11-Jun-18 NKC WMM Top (W&SER) Bed Preperation 252+370 252+420 LHS Cum 50.00 9.1 0.125 56.88 1.00 1.00 1.00
Jun'18 11-Jun-18 NKC WMM Top (W&SER) Bed Preperation 248+230 248+350 LHS Cum 120.00 9.1 0.125 136.50 1.00 1.00 1.00
Jun'18 11-Jun-18 NKC Gabion Retaining Wall 1 254+530 254+539 LHS Cum 9.00 1 1 9.00 7
Jun'18 11-Jun-18 Bhupender Singh Excavation Ordinary Soil (W&SER) Excavation upto SG Top 259+820 259+360 RHS Cum 31 1.00 1.00 259+750
Jun'18 11-Jun-18 KG Excavation Ordinary Soil (W&SER) Excavation upto SG Top 256+950 257+100 RHS Cum 1.00 1.00 WIP
Jun'18 11-Jun-18 KG Excavation Hard Rock (W&SER) Excavation upto SG Top 256+950 257+100 RHS Cum 3 68.70 248+700 NKC Camp
Jun'18 11-Jun-18 Jham Jham Excavation Hard Rock (W&SER) Excavation upto SG Top 286+640 286+600 RHS Cum 1 18.30 248+700 NKC Camp
Jun'18 11-Jun-18 Jham Jham Excavation Ordinary Soil (W&SER) Excavation upto SG Top 286+640 286+600 RHS Cum 2.00 2.00 WIP
Jun'18 11-Jun-18 Suresh Kumar Gabion Retaining Wall 2 264+547 264+557 RHS Cum 20.00 5
S.No Date Contractor Progress work Layer Misc works From To Side Unit Nos Length Breadth Depth Quantity Excavators Dumpers JCB Grader Roller Water Tanker Exca with
Loader Breaker Boulder screning Labour Dumping Lead (One Dumping at Remarks
dumper Chainage Side) KM

Jun'18 11-Jun-18 Suresh Kumar Gabion Retaining Wall 1 264+572 267+582 RHS Cum 12.50 5
Jun'18 11-Jun-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 257+300 257+400 RHS Cum 51 408.00 1.00 6.00 254+500
Jun'18 11-Jun-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 264+540 264+640 LHS Cum 21 168.00 1.00 3.00 264+300=18, Sevbag=3
Jun'18 11-Jun-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 264+500 LHS Cum 1.00 WIP
Jun'18 11-Jun-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 259+350 LHS Cum 1.00 WIP
Jun'18 11-Jun-18 NKC Subgrade top (W&SER) Bed Preperation 258+820 258+860 RHS Cum 1.00 1.00 Completed
Jun'18 11-Jun-18 NKC Subgrade top (W&SER) Bed Preperation 261+250 261+360 RHS Cum WIP
Jun'18 11-Jun-18 NKC WMM Dumping WMM Unloading 261+590 261+630 RHS MT 5 134.98
Jun'18 11-Jun-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 264+440 264+460 RHS Cum 10 80.00 1.00 2.00
Jun'18 11-Jun-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 258+860 258+880 RHS Cum 5 40.00 1.00 1.00 248+700 NKC Camp
Jun'18 11-Jun-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 259+350 LHS Cum 3 261+150
Jun'18 11-Jun-18 Devi Singh Gabion Retaining Wall 1 264+522 264+526 LHS Cum 4.00 3 1 12.00 8
Jun'18 11-Jun-18 Chandan Premi Gabion Retaining Wall 3 261+142 261+147 LHS Cum 5.00 3 1 15.00 10
Jun'18 11-Jun-18 Madan Singh Chauhan Gabion Retaining Wall 5 254+513 254+522 LHS Cum 9.00 1 1 9.00 8
Jun'18 11-Jun-18 Surender mahant Gabion Retaining Wall 8 263+549 263+555 LHS Cum 6.00 1 1 6.00 4
Jun'18 12-Jun-18 NKC GSB Dumping GSB Unloading 240+900 240+990 LHS Cum 11 282.92
Jun'18 12-Jun-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 246+126 246+200 LHS Cum 22 176.00 1.00 3.00 248+300
Jun'18 12-Jun-18 NKC GSB (W&SER) Bed Preperation 246+086 246+130 LHS Cum 1.00 WIP
Jun'18 12-Jun-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 237+500 237+600 LHS Cum 22 176.00 2.00 6.00 238+000
Jun'18 12-Jun-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 237+500 237+600 LHS Cum 1.00
Jun'18 12-Jun-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 239+940 240+000 LHS Cum 1.00 2.00
Jun'18 12-Jun-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 239+940 240+000 LHS MT 21 530.01 248+700 NKC Camp
Jun'18 12-Jun-18 NKC WMM Top (W&SER) Bed Preperation 248+230 248+390 RHS Cum 90.00 9.2 0.125 103.50 1.00 1.00 1.00
Jun'18 12-Jun-18 NKC WMM Top (W&SER) Bed Preperation 252+240 252+310 RHS Cum 70.00 9.2 0.125 80.50 1.00 1.00 1.00
Jun'18 12-Jun-18 NKC Gabion Retaining Wall 3 254+539 254+548 RHS Cum 9.00 1 1 9.00 8
Jun'18 12-Jun-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 257+300 257+450 RHS Cum 30 240.00 1.00 4.00 254+800
Jun'18 12-Jun-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 264+540 264+640 RHS Cum 22 176.00 1.00 4.00 259+300=18, 261+204=4
Jun'18 12-Jun-18 NKC Excavation Hard Rock (W&SER) Boulder Break 264+550 LHS Cum 1.00
Jun'18 12-Jun-18 NKC Excavation Hard Rock (W&SER) Boulder Break 259+380 LHS Cum 1.00
Jun'18 12-Jun-18 NKC Subgrade top (W&SER) Bed Preperation 261+250 261+360 RHS Cum 1.00
Jun'18 12-Jun-18 NKC WMM 1st layer (W&SER) Bed Preperation 261+810 261+920 RHS Cum
Jun'18 12-Jun-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 259+230 259+290 LHS Cum 60.00 3 0.5 90.00
Jun'18 12-Jun-18 NKC Excavation Hard Rock (W&SER) Boulder Break 259+370 259+390 LHS Cum 6 1.00 1.00 269+700=2, 259+200=3, 254+600=1
Jun'18 12-Jun-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 259+820 259+960 RHS Cum 32 256.00 2.00 1.00 259+750
Jun'18 12-Jun-18 KG Excavation Hard Rock (W&SER) Excavation upto SG Top 256+950 257+100 RHS MT 4 91.43 1.00 1.00 248+700 NKC Camp
Jun'18 12-Jun-18 Jham Jham Excavation Ordinary Soil (W&SER) RW 256+640 256+800 RHS Cum 7 4.00 2.00 248+700 NKC Camp
Jun'18 12-Jun-18 Veneet Kumar Retaining Wall PCC 264+450 264+460 RHS Cum 16.50 5
Jun'18 12-Jun-18 Suresh Kumar Gabion Retaining Wall Concrete 264+557 264+572 RHS Cum 11.00 4
Jun'18 12-Jun-18 Kamlesh Thakur Gabion Retaining Wall Concrete 264+428 264+439 RHS Cum 20.00 5
Jun'18 12-Jun-18 NKC Excavation Ordinary Soil (W&SER) RW 264+430 264+460 RHS Cum 1.00
Jun'18 12-Jun-18 Devi Singh Gabion Retaining Wall 1 264+526 264+531 LHS Cum 5.00 3 1 15.00 8
Jun'18 12-Jun-18 Joginder Pal Gabion Retaining Wall 1 264+495 264+505 LHS Cum 10.00 3 1 30.00 13
Jun'18 12-Jun-18 Chandan Premi Gabion Retaining Wall 3 261+147 161+152 LHS Cum 5.00 3 1 15.00 8
Jun'18 12-Jun-18 Surender mahant Gabion Retaining Wall 8 263+543 263+549 LHS Cum 6.00 1 1 6.00 3
Jun'18 12-Jun-18 Kamlesh Thakur Gabion Retaining Wall 1 259+225 259+227 LHS Cum 2.00 3 1 6.00 5
Jun'18 12-Jun-18 Bhawan Kumar Gabion Retaining Wall 1 259+255 259+257 LHS Cum 2.00 3 1 6.00 8
Jun'18 13-Jun-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 237+500 237+600 LHS Cum 25 200.00 2.00 6.00 238+100
Jun'18 13-Jun-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 237+500 237+600 LHS Cum 10 274.72 1.00 248+700 NKC Camp
Jun'18 13-Jun-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 239+940 240+000 LHS Cum 14 112.00 1.00 1.00 241+000
Jun'18 13-Jun-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 239+940 240+000 LHS Cum 1 248+700 NKC Camp
Jun'18 13-Jun-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 237+500 237+600 LHS Cum 9 248+700 NKC Camp
Jun'18 13-Jun-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 246+150 246+200 LHS Cum 1.00 1.00
Jun'18 13-Jun-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 246+150 246+200 LHS Cum 1 27.22 248+700 NKC Camp
Jun'18 13-Jun-18 NKC GSB (W&SER) Bed Preperation 240+900 240+990 LHS Cum 1
Jun'18 13-Jun-18 NKC WMM 1st layer (W&SER) Bed Preperation 246+080 246+130 LHS Cum 1
Jun'18 13-Jun-18 Devi Singh Gabion Retaining Wall 1 264+531 264+536 LHS Cum 5.00 3 1 15.00 8
Jun'18 13-Jun-18 Joginder Pal Gabion Retaining Wall 1 264+485 264+495 LHS Cum 10.00 3 1 30.00 13
Jun'18 13-Jun-18 Surender mahant Gabion Retaining Wall 8 263+537 263+543 LHS Cum 6.00 1 1 6.00 4
Jun'18 13-Jun-18 Chandan Premi Gabion Retaining Wall 4 261+118 261+127 LHS Cum 9.00 2 1 18.00 10
Jun'18 13-Jun-18 Kamlesh Thakur Gabion Retaining Wall 1 259+227 259+232 LHS Cum 5.00 3 1 15.00 7
Jun'18 13-Jun-18 Bhawan Kumar Gabion Retaining Wall 1 259+257 259+259 LHS Cum 2.00 3 1 6.00 5
Jun'18 13-Jun-18 Ashok Kumar Contractor Gabion Retaining Wall 5 258+546 258+550 LHS Cum 4.00 3 1 12.00 7
Jun'18 13-Jun-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 257+300 257+500 LHS Cum 26 208.00 1.00 3.00 254+700
Jun'18 13-Jun-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 264+620 264+650 LHS Cum 4 32.00 1.00 1.00 259+300
Jun'18 13-Jun-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 264+200 264+250 RHS Cum 1.00
Jun'18 13-Jun-18 NKC Subgrade top (W&SER) Bed Preperation 261+290 261+360 RHS Cum 1.00 1.00 Complete
Jun'18 13-Jun-18 NKC GSB Dumping Bed Preperation 258+830 258+860 RHS Cum 8 216.03 1.00
Jun'18 13-Jun-18 NKC GSB Dumping Bed Preperation 259+450 259+520 RHS Cum 12.00 311.07
Jun'18 13-Jun-18 NKC OGL Bed preparation 259+250 259+300 LHS Cum 1.00 1.00 complete
Jun'18 13-Jun-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 259+600 RHS Cum 1.00 D/N Work
Jun'18 13-Jun-18 NKC C&G Complete 259+250 259+300 LHS Cum 1.00 2.00 D/N Work
Jun'18 13-Jun-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 259+350 LHS Cum 4 261+150=2, 264+480=1, 254+600=1
Jun'18 13-Jun-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 264+280 RHS Cum 1.00
Jun'18 13-Jun-18 Bhupender Singh Excavation Ordinary Soil (W&SER) Excavation upto SG Top 259+820 259+960 RHS Cum 42 336.00 2.00 1.00 258+750
Jun'18 13-Jun-18 KG Excavation Ordinary Soil (W&SER) Excavation upto SG Top 256+950 257+100 RHS Cum 1.00 1.00
Jun'18 13-Jun-18 Jham Jham Excavation Ordinary Soil (W&SER) Excavation upto SG Top 256+640 256+800 RHS Cum 10 176.00 4.00 2.00 248+700 NKC Camp
Jun'18 14-Jun-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 239+960 240+000 LHS Cum 17 136.00 1.00 3.00 241+000
Jun'18 14-Jun-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 237+400 237+500 LHS Cum 29 232.00 2.00 4.00 238+000
Jun'18 14-Jun-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 237+400 237+500 LHS Cum 4 112.05 1.00 248+700 NKC Camp
Jun'18 14-Jun-18 Bhagwan Singh Gabion Breast Wall PCC 243+805 243+860 LHS Cum 5.00 3
Jun'18 14-Jun-18 NKC WMM Dumping WMM Unloading 246+080 246+130 LHS Cum 111.52 1.00
Jun'18 14-Jun-18 NKC WMM Top (W&SER) Bed Preperation 298+920 298+550 RHS Cum 130.00 9.2 0.125 149.50 1.00 1.00 1.00
Jun'18 14-Jun-18 NKC WMM Top (W&SER) Bed Preperation 252+230 252+300 RHS Cum 70.00 9.2 0.125 80.50 1.00 1.00 1.00
Jun'18 14-Jun-18 NKC Subgrade top (W&SER) Bed Preperation 252+410 252+450 RHS Cum 40.00 12.5 0.2 100.00
Jun'18 14-Jun-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 264+210 264+260 RHS Cum 1.00
Jun'18 14-Jun-18 NKC Embankment Layers (W&SER) 1 Bed Preperation 259+250 259+350 LHS Cum 1.00 1.00
Jun'18 14-Jun-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 259+250 259+350 LHS Cum 1.00 1.00
Jun'18 14-Jun-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 259+350 LHS Cum 2 264+500=1, 261+140=1
Jun'18 14-Jun-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 259+620 RHS Cum
Jun'18 14-Jun-18 NKC WMM Dumping WMM Unloading 258+160 258+230 RHS Cum 8 222.47
Jun'18 14-Jun-18 NKC GSB Dumping Bed Preperation 261+290 261+360 RHS Cum 1 26.31
Jun'18 14-Jun-18 NKC GSB (W&SER) Bed Preperation 258+830 258+860 RHS Cum 1.00 1.00
Jun'18 14-Jun-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 257+360 257+400 RHS Cum 1.00
Jun'18 14-Jun-18 Jham Jham Excavation Hard Rock (W&SER) Excavation upto SG Top 256+480 256+700 RHS Cum 10 180.20 3.00 2.00 1.00 248+700 NKC Camp
Jun'18 14-Jun-18 Milap Chand Retaining Wall PCC 2 Concrete 264+482 264+488 RHS Cum 10.00 4
Jun'18 14-Jun-18 Milap Chand Retaining Wall PCC 3 Concrete 264+500 264+512 RHS Cum 15.00
Jun'18 14-Jun-18 Veneet Kumar Retaining Wall PCC 264+460 264+512 RHS Cum 20.00 5
Jun'18 14-Jun-18 Raj Kumar Retaining Wall PCC 2 Concrete 264+400 264+410 RHS Cum 5.00 2
Jun'18 14-Jun-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 264+460 264+480 RHS Cum 5 40.00 1.00 2.00 259+350
Jun'18 14-Jun-18 Devi Singh Gabion Retaining Wall 1 264+530 264+540 LHS Cum 4.00 3 1 12.00 8
Jun'18 14-Jun-18 Chandan Premi Gabion Retaining Wall 4 261+127 261+136 LHS Cum 9.00 2 1 18.00 10
Jun'18 14-Jun-18 Ashok Kumar Contractor Gabion Retaining Wall 5 258+550 258+556 LHS Cum 6.00 3 1 18.00 8
Jun'18 14-Jun-18 Madan Singh Chauhan Gabion Retaining Wall 2 254+505 254+512 LHS Cum 7.00 3 1 21.00 9
Jun'18 14-Jun-18 Kamlesh Thakur Gabion Retaining Wall 1 259+232 259+236 LHS Cum 4.00 3 1 12.00 6
Jun'18 14-Jun-18 Bhawan Kumar 1 259+259 259+261 LHS Cum 2.00 3 1 6.00 5
Jun'18 15-Jun-18 NKC WMM Top (W&SER) Bed Preperation 248+430 248+560 RHS Cum 130.00 9.2 0.125 149.50 1.00 1.00 1.00
Jun'18 15-Jun-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top camp 298+800
Jun'18 15-Jun-18 Bhagwan Singh PCC For RMM Breastwall PCC 243+860 243+845 LHS Cum 4.50 3
Jun'18 15-Jun-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 240+950 240+960 RHS Cum 4 113.72 1.00 2.00 248+700 NKC Camp
Jun'18 15-Jun-18 NKC WMM Dumping WMM Unloading 246+080 246+130 LHS Cum 4 113.06
Jun'18 15-Jun-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 239+940 240+000 LHS Cum 21 168.00 1.00 3.00 241+000
Jun'18 15-Jun-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 237+000 237+500 LHS Cum 22 176.00 2.00 4.00 238+000
Jun'18 15-Jun-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 237+100 237+500 LHS Cum 1.00
Jun'18 15-Jun-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 237+100 237+500 LHS Cum 2 38.19 248+700 NKC Camp
Jun'18 15-Jun-18 Chandan Premi Gabion Retaining Wall 4 261+136 261+142 LHS Cum 6.00 2 1 12.00 8
Jun'18 15-Jun-18 Kamlesh Thakur Gabion Retaining Wall 1 259+236 259+240 LHS Cum 4.00 3 1 12.00 6
Jun'18 15-Jun-18 Bhawan Kumar Gabion Retaining Wall 1 259+261 259+267 LHS Cum 6.00 3 1 18.00 12
Jun'18 15-Jun-18 Madan Singh Chauhan Gabion Retaining Wall 2 254+502 254+505 LHS Cum 3.00 3 1 9.00 5
Jun'18 15-Jun-18 Ashok Kumar Contractor Gabion Retaining Wall 1 259+711 259+723 LHS Cum 12.00 2 1 24.00 9
Jun'18 15-Jun-18 Ashok Kumar Contractor Gabion Retaining Wall 2 259+714 259+723 LHS Cum 9.00 1 1 9.00
Jun'18 15-Jun-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 257+300 257+400 RHS Cum 32 256.00 1.00 3.00 259+350=14, 257+400=18
Jun'18 15-Jun-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 257+300 257+400 RHS Cum 5 259+400
Jun'18 15-Jun-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 264+210 264+250 RHS Cum 25 200.00 1.00 4.00 259+350
Jun'18 15-Jun-18 NKC GSB Dumping Block Filling 264+280 RHS Cum 2 56.52
Jun'18 15-Jun-18 NKC GSB Dumping Bed Preperation 261+290 261+360 RHS Cum 11 292.40
Jun'18 15-Jun-18 NKC WMM Dumping 1 WMM Unloading 258+830 258+860 RHS Cum 11 294.20 1.00 1.00
Jun'18 15-Jun-18 NKC C&G Bed preparation 259+350 259+440 LHS Cum 2.00 1.00
Jun'18 15-Jun-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 259+400 LHS Cum 1.00
Jun'18 15-Jun-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 263+550 263+630 LHS Cum 1.00
Jun'18 15-Jun-18 NKC Embankment Layers (W&SER) 2 Bed Preperation 259+250 259+350 LHS Cum 1.00 1.00
Jun'18 15-Jun-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 259+400 LHS Cum 2 1.00 1.00 261+150=1, 258+530==1
Jun'18 15-Jun-18 Jham Jham Excavation Ordinary Soil (W&SER) Excavation upto SG Top 256+500 256+700 RHS Cum 3.00 2.00 1.00
Jun'18 15-Jun-18 Raj Kumar Gabion Retaining Wall 1 Concrete 264+379 264+400 RHS Cum 15.00 5
Jun'18 15-Jun-18 Jham Jham Excavation Hard Rock (W&SER) Excavation upto SG Top 256+500 256+700 RHS Cum 8 131.72 248+700 NKC Camp
Jun'18 16-Jun-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 246+150 246+200 LHS Cum 21 1.00 3.00 248+300
Jun'18 16-Jun-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 236+700 4 2.00 248+700 NKC Camp
Jun'18 16-Jun-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 239+940 240+000 LHS Cum 13 104.00 1.00 1.00 241+000
Jun'18 16-Jun-18 Ajay Pathania Excavation Ordinary Soil (W&SER) Excavation upto SG Top 237+400 237+500 LHS Cum 30 240.00 2.00 3.00 238+000
Jun'18 16-Jun-18 Ajay Pathania Excavation Hard Rock (W&SER) Excavation upto SG Top 237+400 237+500 LHS Cum 5 127.35 1.00 248+700 NKC Camp
Jun'18 16-Jun-18 Kul Bahadur Gabion Retaining Wall 2 248+485 248+490 RHS Cum 3.00 2 1 6.00 3
Jun'18 16-Jun-18 NKC Subgrade top (W&SER) Bed Preperation 254+790 254+890 LHS Cum 50.00 12.5 0.2 1.00 1.00 2.00
Jun'18 16-Jun-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 254+700 254+500 LHS Cum 25 1.00 1.00
Jun'18 16-Jun-18 Jham Jham Excavation Hard Rock (W&SER) Excavation upto SG Top 256+500 256+640 RHS Cum 3 50.80 3.00 1.00 1.00
Jun'18 16-Jun-18 KG Excavation Hard Rock (W&SER) Excavation upto SG Top 256+950 257+100 RHS Cum 3 69.15 1.00 1.00
Jun'18 16-Jun-18 Raj Kumar Gabion Retaining Wall 1 Concrete 264+379 264+400 RHS Cum 5.00 4
Jun'18 16-Jun-18 Raj Kumar Retaining Wall PCC 264+360 264+370 RHS Cum 10.00
Jun'18 16-Jun-18 Veneet Kumar Gabion Retaining Wall 1 Concrete 264+460 264+471 RHS Cum 34.00 5
Jun'18 16-Jun-18 Veneet Kumar Gabion Retaining Wall 3 Concrete 264+520 264+538 RHS Cum 11.00
Jun'18 16-Jun-18 Suresh Kumar Gabion Retaining Wall 3 Concrete 264+547 264+557 RHS Cum 10.00 4
Jun'18 16-Jun-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 257+300 257+400 RHS Cum 16 128.00 1.00 3.00 259+350
Jun'18 16-Jun-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 257+300 257+400 RHS Cum 4 104.95 259+400
Jun'18 16-Jun-18 NKC Excavation Ordinary Soil (W&SER) Excavation upto SG Top 264+200 264+260 RHS Cum 74 592.00 2.00 5.00 259+400=20, 263+550=18, 264+700=36
Jun'18 16-Jun-18 NKC C&G Soil Grading 264+640 264+700 LHS Cum
Jun'18 16-Jun-18 NKC Subgrade top (W&SER) Bed Preperation 264+560 264+620 LHS Cum 1.00 1.00
Jun'18 16-Jun-18 NKC Subgrade Layers (W&SER) 1 Bed Preperation 264+620 264+700 LHS Cum
Jun'18 16-Jun-18 NKC GSB (W&SER) Bed Preperation 261+290 261+360 RHS Cum
Jun'18 16-Jun-18 NKC C&G 259+150 259+250 RHS Cum 1.00
Jun'18 16-Jun-18 NKC Embankment Layers (W&SER) 1 Bed Preperation 259+350 259+440 LHS Cum 1.00 1.00
Jun'18 16-Jun-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 259+380 259+420 LHS Cum 8 264+500=1,261+150=2,259+200=2,258+550=3
Jun'18 16-Jun-18 NKC Excavation Hard Rock (W&SER) Excavation upto SG Top 258+400 LHS Cum 1.00
Jun'18 16-Jun-18 NKC WMM Dumping WMM Unloading 258+830 258+860 RHS Cum 2 56.60
Jun'18 16-Jun-18 NKC WMM Dumping WMM Unloading 259+450 259+520 RHS Cum 5 140.50
Jun'18 16-Jun-18 Chandan Premi Gabion Retaining Wall 4 261+142 261+151 LHS Cum 9.00 2 1 18.00 10
Jun'18 16-Jun-18 Kamlesh Thakur Gabion Retaining Wall 1 259+240 259+246 LHS Cum 6.00 2 1 12.00 5
Jun'18 16-Jun-18 Bhawan Kumar Gabion Retaining Wall 1 259+267 259+272 LHS Cum 5.00 3 1 15.00 10
Jun'18 16-Jun-18 Ashok Kumar Contractor Gabion Retaining Wall 6 258+520 258+523 LHS Cum 3.00 3 1 9.00 15
Jun'18 16-Jun-18 Ashok Kumar Contractor Gabion Retaining Wall 6 258+523 258+535 LHS Cum 12.00 4 1 48.00
Jun'18 16-Jun-18
Jun'18 16-Jun-18
Jun'18 16-Jun-18
Jun'18 16-Jun-18
Jun'18 16-Jun-18
Jun'18 16-Jun-18
Jun'18 16-Jun-18
Jun'18 16-Jun-18
Jun'18 16-Jun-18
Jun'18 16-Jun-18
Jun'18 16-Jun-18
Structure Works Progress Report 16-Jun-2018
S No Location Subcontractor Description Concrete Work Sinking Work Today Status Man power Total Work Status EX Dumper Crane
Major Bridges
1 Bajora Bridge Mohd Forman LP2 LP-2 4th lift steining concreting completed 10.4 M Completed well sinking in progress done upto 10.2M+ 0.200= 10.4m SW-3,USW-2 5

2 Bajora Bridge Mohd Forman RP2 steining 4th lift concrete Completed 11.5 m Completed

3 Bajora Bridge Mohd Forman LP3 10.1 M Completed 9.8m+0.300= 10.1 Completed 5

4 Bajora Bridge Mohd Forman RP3 Stening in Progress 15.00m Completed SW-3,USW-2 5+8

5 Jia Bridge Mohd Forman P4 Well 2nd lift steining concreting completed well sinking 4m sinking completed and in progress Overall down=4m SW-1, USW-3 4 1

6 Jia Bridge Sohan Lal P5 4th lift shuttering in Progress 9.7 M sinkage overall down completed Overall down=9.7m SW=2, USW-4 6

7 Jia Bridge Sohan Lal P2 P2 open foundation pier reinforcement work in progress

8 Jia Bridge Mohd Farman P3 open foundation Excavation

Minor Bridges A1 Side A2 side Today Status


1 258+800 S.K Contractor Abutment Cap Completed I Girder 3rd Bed Reinforcement in progress

2 245+710 Vijay Kumar A1 Abutment Raft Completed YTS

3 241+041 Deck slab completed Deck slab completed


Culverts Type LHS RHS Today Status
1 236+753 BC
2 236+803 BC (Wid) LHS BC 2nd lift & Top slab concreting completed Not Required
3 237+995 Shubham Shharma BC (Wid) LHS BC wall 2nd lift shuttering completed RHS BC Bed PCC
4 238+286 Vijay Kumar BC (Re-Con.) Completed
5 238+429 BC (Re-Con.) YTS BC Top Slab Completed
6 238+516 BC (Re-Con.) YTS Wall 1st lift Completed
7 238+805 Vijay Kumar PC (Re-Con) Completed BC Top Slab Completed
8 238+937 BC (Re-Con.) LHS BC Excavation in progress YTS
9 239+956 BC (Re-Con.) YTS
10 240+080 BC (Wid) Completed Not Required
11 240+580 BC (Re-Con.) LHS BC Raft Reinforcement work in progress
12 240+973 PC (Re-Con) LHS Head wall final lift Concreting completed RHS PC PCC Complete RHS PC PCC Complete SW=1,USW=2 3 6.5 1 2
13 241+494 PC (Re-Con) YTS RHS PC head wall 2nd lift concreting work
14 243+349 BC (Re-Con.) LHS BC 2nd lift & Slab concrete completed YTS
15 243+617 BC (Wid) LHS Wall 2nd lift & slab concrete completed RHS 1st lift completed
16 243+867 BC (Re-Con.) LHS BC PCC completed YTS LHS BC PCC completed 3 3.5
17 244+309 PC (Re-Con) Excavation Work completed
18 247+300 PC (Re-Con) LHS Head wall final lift Concreting completed
19 247+690 PC (Re-Con) LHS Pipe culvert Top lift of encasing concreting work completed
20 248+024 PC (Re-Con.) Completed Completed
21 248+214 PC (Re-Con.) Completed Completed
22 248+580 PC (Re-Con.) Completed Completed
23 250+492 Sanjay Kumar BC (Re-Con.) RHS BC wall final Lift and Top Slab Deshuttering Completed RHS BC wall final Lift and Top Slab Deshuttering Completed SW=1,USW=2 5
24 251+032 PC (Re-Con.) Completed

25 251+955 Expedite BC (Re-Con.) RHS BC Wall 1st lift Concrete Completed


Infraconstructors
26 252+400 NKC BC (Re-Con.)
27 258+512 BC (Wid) YTS PCC work completed
28 258+962 Suresh Kumar BC (Wid) LHS BC Haunch shuttering work completed LHS BC Haunch shuttering work completed SW=1,USW=4 5
29 259+090 Suresh Kumar BC (Wid) Completed LHS Top Slab Dismantling of inner side Shuttering Completed LHS Top Slab Dismantling of inner side Shuttering Completed SW=1, USW=3

30 259+437 Suresh Kumar BC (Re-Con.) Completed


31 260+087 BC (Re-Con.) YTS Completed
32 260+272 BC (Wid) Not Required RHS BC PCC Completed SW-1, USW-3 4.5
33 260+346 BC (Wid) Not Required Completed
34 261+148 PC (Re-Con.) YTS YTS
35 261+207 BC (Wid) excavation completed RHS BC Wall 1st lift Shuttering work in progress
36 261+646 BC (Re-Con.) YTS Completed
37 262+618 Suresh Kumar PC (Re-Con) Pipe Encasing Concrete completed Pipe Encasing Concrete completed SW-1, USW-3 4 5.5
\ 262+775 BC (Wid) Not Required RHS Paraphet 1st Lift Shuttering Completed RHS Paraphet 1st Lift Shuttering Completed SW-1,USW=4 5
#VALUE! 264+275 BC (Wid) RHS Paraphet 1st Lift Shuttering Completed RHS Paraphet 1st Lift Shuttering Completed
#VALUE! 264+412 Milap Chand PC (Re-Con) LHS head wall 1st lift shuttering in progress Completed
#VALUE! 264+912 BC (Re-Con.) Completed YTS
#VALUE! 264+539 Milap Chand PC (Re-Con) Completed Completed
#VALUE! 264+680 Milap Chand PC (Wid) Completed Completed
Page 28

Protection Work

Misc Crash
Works barrier
Page 29
Page 30
Page 31

1.6cum , 1-5-18
Page 32
Page 33
Page 34
Page 35
Page 36
Page 37
Page 38

LHS

Super
Sub Struct
Structure

Top
Slab
Lift
Page 39
Page 40

4.4cum, 26-5-18
Page 41

7-4-18, 20cum
Page 42

8-3-18,10 cum
Page 43
Page 44
Page 45

50.4cum, 6-6-18, suresh kumar 9cum, 24-5-18

52 cum, 23-5-18
Page 46
Page 47
Page 48

LHS

b Structure Found

2nd 1st
Raft
Lift Lift
Page 49
Page 50

4.45cum, 24-5-18 5.34cum, 17-05-18 5-5-18, 37cum

30-4-18,9.5cum 13.24 cum,16-4-18


Page 51
Page 52
Page 53
Page 54
Page 55

15-06-18, 31CUM

16-5-18, 12 cum 11.6cum,11-5-18 42 cum,24-7-18

7-5-18, 8cum 30-4-18, 6.8cum


Page 56
Page 57
Page 58

Foundation

PCC Exca.
Page 59
Page 60

3.4cum, 23-3-18
Page 61
Page 62

16-06-18, 3.5cum
Page 63
Page 64
Page 65

6cum, 29-5-18

8cum, 2-4-18

11 cum, 21-3-18
Page 66
Page 67
Page 68

BOX

Design
Chainage
Page 69

236+568
236+660
236+753
236+803
237+000
237+084
237+172
Page 70

237+728
237+995
238+286
238+429
238+516
238+715
238+937
Page 71

239+695
239+956
240+080
240+218
240+440
240+580
242+295
Page 72

243+025
243+192
243+353
243+617
243+867
244+050
245+410
Page 73

246+516
250+082
250+492
250+882
251+175
251+955
252+348
Page 74

252+400
253+160
253+660
253+838
254+509
255+843
256+906
Page 75

257+539
258+084
258+512
258+962
259+090
259+437
260+087
Page 76

260+272
260+346
261+206
261+646
262+775
262+909
263+082
Page 77

263+464
263+660
263+900
264+274
264+907
Page 78

BOX Culvert

DG No.
Page 79

Box‐GA‐035
Rev ‐C
Box‐GA‐077
Rev‐ O
Box‐GA‐060
Rev ‐ E
Box‐GA‐060
Rev ‐ E
Box‐GA‐060
Rev ‐ E
Box‐GA‐036
Rev ‐ B
Box‐GA‐062
Rev‐C
Page 80

Box‐GA‐034
Rev ‐ B
Box‐GA‐071
Rev‐ O
Box‐GA‐040
Rev ‐ B
Box‐GA‐041
Rev ‐ B
Box‐GA‐042
Rev ‐ B
Box‐GA‐037
Rev ‐ B
Box‐GA‐035
Rev‐B
Page 81

Box‐GA‐035
Rev ‐C
Box‐GA‐035
Rev ‐C
Box‐GA‐066
Rev ‐A
Box‐GA‐038
Rev ‐ B
Box‐GA‐040
Rev ‐ B
Box‐GA‐041
Rev ‐ B
Box‐GA‐041
Rev‐B
Page 82

Box‐GA‐038
Rev ‐ B
Box‐GA‐071
Rev‐ O
Box‐GA‐038
Rev ‐ B
Box‐GA‐075
Rev ‐A
Box‐GA‐041
Rev ‐ B
Box‐GA‐039
Rev‐B
Page 83

Box‐GA‐078
Rev‐O
Box‐GA‐079
Rev‐ O
Box‐GA‐051
Rev ‐ E
Box‐GA‐081
Rev ‐0
Box‐GA‐047
Rev ‐ D
Box‐GA‐050
Rev‐E
Page 84

Box‐GA‐048
Rev ‐D
Box‐GA‐079
Rev ‐A
Box‐GA‐052
Rev ‐C
Box‐GA‐056
Rev ‐C
Box‐GA‐047
Rev‐D
Box‐GA‐058
Rev‐C
Page 85

Box‐GA‐058
Rev ‐C
Box‐GA‐058
Rev ‐C
Box‐GA‐065
Rev‐ O
Box‐GA‐064
Rev ‐C
Box‐GA‐063
Rev ‐C
Box‐GA‐032
Rev ‐ E
Box‐GA‐033
Rev‐D
Page 86

Box‐GA‐074
Rev‐O
Box‐GA‐074
Rev‐ O
Box‐GA‐055
Rev ‐D
Box‐GA‐033
Rev ‐D
Box‐GA‐058
Rev ‐C
Box‐GA‐061
Rev ‐C
Box‐GA‐061
Rev‐C
Page 87

Box‐GA‐031
Rev ‐D
Box‐GA‐031
Rev ‐D
Box‐GA‐058
Rev ‐C
Box‐GA‐058
Rev‐C
Page 88

ert

Size Type
Page 89

1X2.0 Slab
1X2.0 Slab
1x1.8 Slab
1x1.8 Slab
1x1.8 Slab
1X1.2 Slab
1x1.8 Slab
Page 90

1X2.0 Slab
1X6. Slab
1X2.0 Slab
1X2.0 Slab
1X2.0 Slab
1X2.0 Slab
1X2.0 Slab
Page 91

1X2.0 Slab
1X2.0 Slab
1x3.0 Slab
1X2.0 Slab
1X2.0 Slab
1X2.0 Slab
1X2.0 Slab
Page 92

1X2.0 Slab
1x4.6 Slab
1X2.0 Slab
1x1.8 Slab
1X2.0 Slab
1X2.0 Slab
1 x 6.0 Slab
Page 93

1X2.0 Slab
1 x 3.0 Slab
2x2 Box
1 x 6.0 Slab
1 x 6.0 Slab
3x3 Box
3x3 Box
Page 94

3x3 Box
3x3 Box
6x3 Box
3x3 Box
1 x 6.0 Slab
1x3.0 Slab
1x3.0 Slab
Page 95

1X6. Slab
1X6. Slab
1x3.0 Slab
1X6. Slab
1X6. Slab
1X2.0 Slab
1X3.0 Slab
Page 96

1X6. Slab
1X6. Slab
1x3.0 Slab
1X2.0 Slab
1x3.0 Slab
1x3.5 Slab
1X2. Slab
Page 97

1X2.0 Slab
1X2.0 Slab
1X6. Slab
1x3.0 Slab
1X2.0 Slab
Page 98

Foundation

Exca. PCC Raft


Page 99
Page 100

3 cum
Page 101

4 cum, 19-03-18
Page 102
Page 103
Page 104
Page 105
Page 106

4.5cum, 14-6-18, Suresh Kumar


Page 107
Page 108

Sub Structure

1st 2nd Top


Lift Lift Lift
Page 109
Page 110
Page 111
Page 112
Page 113

10cum, 14-5-18 1-6-18, 31cum


Page 114
Page 115
Page 116

26.2.18, (8.2cum) 3-3-18,10 -9.6564986


Page 117
Page 118

RHS

Super
Structure

Slab
Page 119
Page 120
Page 121
Page 122
Page 123

1-6-18, 31cum
Page 124
Page 125
Page 126

3/23/2018
Page 127

29cum, 19-03-18
Page 128

RHS

Protection Work

Crash Misc
barrier Works
Page 129
Page 130
Page 131
Page 132
Page 133
Page 134
Page 135
Page 136

3.6cum, 24-3-18
Page 137
Page 138

Remarks
Page 139

Recon
Recon
Wide
Wide
Wide
Recon
Wide
Page 140

Recon
Wide
Recon
Recon
Recon
Recon
Recon
Page 141

Recon
Recon
Wide
Recon
Recon
Recon
Recon
Page 142

Recon
Wide
Recon
Wide
Recon
Recon
New
Page 143

Recon
New
New
New
New
New
New
Page 144

New
New
New
New
New
Wide
Wide
Page 145

Wide
Wide
Wide
Wide
Wide
Recon
Recon
Page 146

Wide
Wide
Wide
Recon
Wide
Wide
Wide
Page 147

Recon
Recon
Wide
Wide
Recon
LHS RHS
Protection Super
Sub Structure Foundation
Pipe Culvert Strip Chart Foundation
Work Structure
S.No HW HW HW
Misc Encasin Pipe Design
Top 2nd 1st Bedding HW PCC Exca. Dr. No. Size Exca. HW PCC Bedding
Works g Laying Chainage
Lift Lift Lift
1 236+374 Cul‐335 Rev‐A 1X1.2
2 236+902 Cul‐337 Rev‐A 1X1.2
3 237+490 Cul‐337 Rev‐A 1X1.2
4 237+576 Cul‐336 Rev‐A 1X1.2
5 237+824 Cul‐335 Rev‐A 1X1.2
6 238+133 Cul‐336 Rev‐A 1X1.2
7 2.7cum, 28-5-18 25-5-18, 13cum
238+805 Cul‐337 Rev‐A 1X1.2
6cum, 15-05-18 5/16/2018 6cum, 15-05-18 1.3 cum, 11-5-18

8 239+103 Cul‐335 Rev‐A 1X1.2


9 239+240 Cul‐336 Rev‐A 1X1.2
10 239+396 Cul‐335 Rev‐A 1X1.2
11 240+708 Cul‐341 Rev‐A 1X1.2
12 240+790 Cul‐341 Rev‐A 1X1.2
13 6.5 cum, 24-03-18
240+973 Cul‐335 Rev‐A 1X1.2 6/15/2018 16-06-18, 6.5cum

14 241+494 Cul‐341 Rev‐A 1X1.2


15 242+140 Cul‐344 Rev‐A 1X1.2
16 242+365 Cul‐342 Rev‐A 1X1.2
17 242+512 Cul‐346 Rev‐O 1X1.2
18 242+747 Cul‐346 Rev‐O 1X1.2
19 243+713 Cul‐343 Rev‐A 1X1.2
20 244+309 Cul‐342 Rev‐A 1X1.2
21 244+770 Cul‐347 Rev‐A 2x1.2
22 245+045 Cul‐351 Rev‐A 1x1.2
23 5.83 cum, 03-04-18 8.46 cum, 20-03-18
247+305 Cul‐342 Rev‐A 1X1.2
24 247+690 Cul‐342 Rev‐A 1X1.2
5 PIPE LAYED

25 248+024 2x1.2
26 248+214 2x1.2
27 248+580 2x1.2
28 248+932 Cul‐156 Rev‐A 2x1.2
29 251+032 Cul‐340 Rev‐B 2x1.2
30 254+943 Cul‐350 Rev‐A 2x1.2
31 256+674 Cul‐325 Rev‐A 1X1.2
32 257+290 Cul‐328 Rev‐A 1X1.2
33 257+828 Cul‐322 Rev‐A 1X1.2
34 259+645 Cul‐326 Rev‐A 1X1.2
35 259+752 Cul‐321 Rev‐A 1X1.2
36 260+681 Cul‐322 Rev‐A 1X1.2
37 260+977 Cul‐321 Rev‐A 1X1.2
38 261+148 Cul‐327 Rev‐B 1X1.2
39 262+487 Cul‐325 Rev‐A 1X1.2
40 262+618 Cul‐338 Rev‐O 1x1.2 1.5cum, 29-5-18 6.5cum, 5-6-18

41 263+000 Cul‐329 Rev‐O 1X1.2


42 263+174 Cul‐321 Rev‐A 1X1.2
43 263+364 Cul‐321 Rev‐A 1X1.2
44 263+832 Cul‐321 Rev‐A 1X1.2
45 263+999 Cul‐322 Rev‐A 1X1.2
46 264+412 Cul‐321 Rev‐A 1X1.2 16-3-18, 1.5 cum

47 6.5cum,29-5-18 3rd lift, 10.5 cum, 09-05-18


264+539 Cul‐321 Rev‐A 1X1.2
9.5 cum, 15-5-18 PCC , 16-3-18, 8*1.6*.3=3.84cum

48 10 cum, 20-4-18 16-3-18, =10.2*1.125*1.25-2=12.34


264+680 Cul‐352 Rev‐O 1X1.2
RHS
Super Protection
Sub Structure
Structure Work
HW HW Remarks
HW Pipe Encasin
2nd Top Misc Works
1st Lift Laying g
Lift Lift
Recon.
Recon.
Recon.
Recon.
Recon.
Recon.
Recon.
Recon.
Recon.
Recon.
Recon.
Recon.
Recon.
3 pipes layed 9 cum, 28-3-18
Recon.
Recon.
Recon.
Recon.
Recon.
Recon.
Recon.
New
New
Recon.
Recon.
New
New
New
New
10cum, 8-5-18 24-5-18, 3 cum
New
New
Recon.
Recon.
Recon.
Recon.
Recon.
Recon.
Recon.
Recon.
Recon.
6.5cum,2-6-18 15-06-18, 7cum Wide
Wide
Recon.
Recon.
Recon.
Recon.
Recon.
Recon.
Wide
BAJORA BRIDGE 249+435 WELL FOUNDATION BAJORA BRIDGE 249+435 WELL FOUNDATION
STEINING & SINKING STRIPCHART STEINING & SINKING STRIPCHART

Depth Steining Sinking Depth Steining Sinking Depth Steining Sinking Depth Steining Sinking
15.70 15.70 15.70 15.70

Well Steining

Well Steining
Well Steining

Well Steining
15.50 15.50 15.50 15.50
(14.7 to

(14.7 to

(14.7 to

(14.7 to
15.7M)

15.7M)

15.7M)
15.7M)

15.30 15.30 15.30 15.30


15.10 15.10 15.10 15.10
14.90 14.90 14.90 14.90
14.70 14.70 14.70 14.70
14.60 14.60 14.60 14.60
Well Steining (12.2 to 14.7M)

Well Steining (12.2 to 14.7M)

Well Steining (12.2 to 14.7M)

Well Steining (12.2 to 14.7M)


14.40 14.40 14.40 14.40
14.20 14.20 14.20 14.20
14.00 14.00 14.00 14.00

80 cum,22-5-18
14.1, 14-06-18
13.80 13.80 13.80 13.80
13.60 13.60 13.60 13.60
13.40 13.40 13.40 13.40
13.20 13.20 13.20 13.20
13.00 13.00 13.00 13.00
12.80 12.80 12.80 12.80
12.60 12.60 12.60 12.60
12.40 12.40 12.40 12.40
12.20 12.20 12.20 12.20
12.10 12.10 12.10 12.10
Well Steining (9.7 to 12.2M)

Well Steining (9.7 to 12.2M)

Well Steining (9.7 to 12.2M)

Well Steining (9.7 to 12.2M)


11.90 11.90 11.90 11.90
11.70 11.70 11.70 11.70 11.8, 10-05-18
14-05-18, 77 Cum

20-04-18, 85 Cum
11.50 11.50 11.50 11.50

79 cum,9-4-18
11.5m , 29-5-18 11.6 ,15-05-18
11.30 11.30 11.30 11.30 11.4 ,15-05-18
11.10 11.10 11.10 11.10
10.90 10.90 10.90 10.90 10.9,7-5-18
10.70 10.70 10.70 10.70
10.50 10.50 10.50 10.50 10.5,3-5-18
10.30 10.30 10.4m , 26-5-18 10.30 10.30
10.10 10.10 10.10 10.10
9.90 9.9, 13-05-18 9.90 9.9m, 18-5-18 9.90 9.8m,5-618 9.90 9.9,27-4-18

RP2

RP3
LP2

LP3
9.70 9.7, 10-05-18 9.70 9.70 9.70 9.7, 06-4-18
9.60 9.60 9.60 9.60
9.6, 28-03-18
9.40 9.40 9.40 9.40
Well Steining (7.2 to 9.7M)

Well Steining (7.2 to 9.7M)

Well Steining (7.2 to 9.7M)

Well Steining (7.2 to 9.7M)


9.4,1-5-18
9.20 9.4m, 5-6-18 9.20 9.20 9.20
27-02-18, 78 Cum

04-05-18, 78 Cum
9.2, 24-3-18
9.00 9.00 8.9,15-5-18 9.00 9.00
77cum,7-4-18

8.80 8.9m, 31-5-18 8.80 8.7,27-4-18 8.80 8.80 8.9, 23-3-18


8.60 8.6m, 08-5-18 8.60 8.60 8.60
8.40 8.5m, 05-5-18 8.40 8.40 8.5m, 31-5-18 8.40 8.5m , 19-03-18
8.20 8.2m, 02-5-18 8.20 8.3, 10-4-18 8.20 8.20 8.3, 9-3-18
8.00 8.00 8.0, 9-4-18 8.00 7.8m, 29-5-18 8.00
7.80 7.80 7.8, 6-4-18 7.80 7.8m, 29-5-18 7.80 7.6-8.0, 08-02-18
7.60 7.60 7.60 7.60 7.5-7.6m, 5-3-18
7.40 7.40 7.4, 04-4-18 7.40 7.40
7.20 7.3m, 27-4-18 7.20 7.1, 29-3-18 7.20 7.3m, 28-5-18 7.20
7.10 7.10 7.0, 28-3-18 7.10 7.10
6.90 6.90 6.90 6.90
Well Steining (4.7 to 7.2M)

Well Steining (4.7 to 7.2M)

Well Steining (4.7 to 7.2M)

Well Steining (4.7 to 7.2M)


6.7, 26-3-18
6.70 6.70 6.70 6.8,22-5-18 6.70 7.0, 270218
6.50 6.50 6.50 6.5,27-4-18 6.50
6.30 6.4m , 24-03-18 6.30 6.30 6.30 6.4, 240218
6.10 6.2m , 23-03-18 6.10 6.1 to 6.5 ( 20-02-18) 6.10 6.2, 20-4-18 6.10 06.01.18 6.20
5.90 5.9m , 21-03-18 5.90 5.90 5.90
6.0m, 16-4-18
5.70 5.7m , 19-03-18 5.70 5.70 5.70
5.50 5.50 5.60 5.50 5.6, 9-4-18 5.50
5.30 5.2 to 5.5m, 17- 5.30 5.30 5.30
5.4m, 4-4-18
5.10 03-18 5.10 5.10 5.10
4.90 4.9m, 12-3-18 4.90 4.90 4.90
4.70 4.70 4.70 4.9m, 2-4-18 4.70 22.01.18
4.60 4.60 4.60 4.60
4.7m,9-3-18
4.40 4.40 4.40 4.40
Well Steining (2.2 to 4.7M)

Well Steining (2.2 to 4.7M)

Well Steining (2.2 to 4.7M)

Well Steining (2.2 to 4.7M)


09/Jan/18
4.20 4.20 4.20 4.20 4.20
4.00 3.95 4.00 4.00 4.00
3.80 3.80 3.80 11.01.18(3.9) 3.80
3.60 3.60 STR/247, 20.12.17 05/Jan/18 3.60 STR/253, 22.12.17 3.60 STR/232, 14.12.17
3.40 3.40 04/Jan/17 3.40 3.40
3.20 3.20 3.20 09.01.18 (3.3) 3.20
3.00 3.00 3.00 3.00
2.80 2.80 2.80 2.80
2.60 12.01.18 (2.7) 2.60 2.60 2.60
2.40 2.40 2.40 03.1.18 (2.5) 2.40
2.20 STR/233, 2.20 STR/155, 19.11.17 STR/186, 29.11.17 2.20 STR/185, 28.11.17 STR/204, 07.12.17 2.20 STR/127, 13.11.17 STR/164, 21.11.17
14.12.17
2.00 2.00 2.00 2.00
1.80 1.80 1.80 1.80
Well Curb (0 to 2.2M)

Well Curb (0 to 2.2M)

Well Curb (0 to 2.2M)

Well Curb (0 to 2.2M)


1.60 1.60 1.60 1.60
1.40 1.40 1.40 1.40
1.20 1.20 1.20 1.20
1.00 1.00 1.00 1.00
0.80 0.80 0.80 0.80
0.60 0.60 0.60 0.60
0.40 0.40 0.40 0.40
0.20 0.20 0.20 0.20
JIA BRIDGE 255+230 WELL FOUNDATION STEINING & SINKING
STRIPCHART
Depth Steining Sinking Depth Steining Sinking
13.20 13.20
(12.4 to

(12.4 to
13.2M)

13.2M)
13.00 13.00
12.80 12.80
12.60 12.60
12.40 12.40
Well Steining (9.9 to 12.4M)

Well Steining (9.9 to 12.4M)


12.20 12.20
12.10 12.10
11.90 11.90
11.70 11.70
11.50 11.50
11.30 11.30
11.10 11.10
10.90 10.90
10.70 10.70
10.50 10.50
10.30 10.30
10.10 10.10
9.90 9.90
Well Steining (7.4 to 9.9M)

Well Steining (7.4 to 9.9M)


9.70 9.70 9.7m, 29-5-18
9.60 9.60
9.40 9.40

19-04-2018, 114 Cum


9.5m, 26-5-18
9.20 9.20
9.00 9.00
8.80 8.80
8.60 8.60 8.6m, 20-5-18
8.40 8.40
P4

P5
8.20 8.20
8.00 8.00
7.80 7.80
7.60 7.60 7.5m,15-5-18
7.40 7.40
Well Steining (4.9 to 7.4M)

Well Steining (4.9 to 7.4M)

7.20 7.20 7.3m,2-5-18


7.10 7.10
6.90 6.90
30-05-2018, 120 Cum

03-03-2018, 116 Cum

7 m ,5-4-18
6.70 6.70
6.50 6.50
6.30 6.30
6.10 6.10
5.90 5.90
5.70 5.70
5.50 5.50
5.30 5.30
5.10 5.10
4.90 4.90 4.6m to 5.6m ,
Well Steining (2.4 to 4.9M)

Well Steining (2.4 to 4.9M)

4.70 4.70 23.03.18


4.60 4.60 4.6m
4.40 4.40
4.20 4.20
83 cum,30-3-18

4.00 4m, 6-05-18 4.00


3.80 3.80
3.60 3.60
3.40 3.40
3.20 3.20
3.00 3.00 19.01.2018
2.80 2.80
2.60 2.5m ,20-4-18 2.60
2.40 2.40 STR/136, STR/207,
2.20 2.20 15.11.17 07.12.17
Well Curb (0 to 2.4M)

Well Curb (0 to 2.4M)

2.00 2.00
1.80 2.0m 1.80
1.60 1.60
1.40 1.40
1.20 1.20
1.00 1.00
0.80 0.80
0.60 0.60
0.40 0.40
0.20 0.20
Highway
16-Feb-18 DMC
Excavation Ordinary Soil
243+750
(W&SER) 243+800 LHS Trips 40 Radha swami dumping yard Layers Satus Date
17-Feb-18 MMKExcavation Ordinary Soil
246+100
(W&SER) 246+200 LHS Trips 27 Radha Swami Dumping Yard 246080 246130 Subgrade Completed 1/6/2018
17-Feb-18 DMC
Excavation Ordinary Soil
243+750
(W&SER) 243+800 LHS Trips 53 Radha Swami Dumping Yard 239680 239810 Subgrade Completed 1/6/2018
18-Feb-18 MMKExcavation Ordinary Soil
246+100
(W&SER) 246+200 LHS Trips 29 Radha Swami Dumping Yard
18-Feb-18 DMC
Excavation Ordinary Soil
243+750
(W&SER) 243+800 LHS Trips 35 Radha Swami Dumping Yard
19-Feb-18 MMKExcavation Ordinary Soil
246+100
(W&SER) 246+200 LHS Trips 45 Radha Swami Dumping Yard
19-Feb-18 DMC
Excavation Ordinary Soil
243+800
(W&SER) 243+850 LHS Trips 45 Radha Swami Dumping Yard
20-Feb-18 MMKExcavation Ordinary Soil
246+100
(W&SER) 246+200 LHS Trips 36 Radha Swami Dumping Yard
20-Feb-18 DMC
Excavation Ordinary Soil
243+700
(W&SER) 243+760 LHS Trips 52 Radha Swami Dumping Yard
21-Feb-18 DMC
Excavation Ordinary Soil
243+700
(W&SER) 243+760 LHS Trips 42 Radha Swami Dumping Yard
22-Feb-18 NKC
Excavation Ordinary Soil
243+900
(W&SER) 243+950 LHS Trips 20 Radha Swami Dumping Yard
23-Mar-18 DMC 243+280 243+320 LHS Trips 48 Radha Swami Dumping Yard
24-Feb-18 DMC
Excavation Ordinary Soil
243+280
(W&SER) 243+320 LHS Trips 10 Radha Swami Dumping Yard
24-Feb-18 NKC
Excavation Ordinary Soil
247+580
(W&SER) 247+680 LHS Trips 9 Radha Swami Dumping Yard
25-Feb-18 DMC
Excavation Ordinary Soil
243+280
(W&SER) 243+310 LHS Trips 12 Radha Swami Dumping Yard
26-Feb-18 NKC
Excavation Ordinary Soil
247+580
(W&SER) 247+680 RHS Trips 5 Radha Swami Dumping Yard
26-Feb-18 NKC
Excavation Ordinary Soil
243+500
(W&SER) 243+540 RHS Trips 15 Radha Swami Dumping Yard
27-Feb-18 DMC
Excavation Ordinary Soil
243+280
(W&SER) 243+320 LHS Trips 48 Radha Swami Dumping Yard
27-Feb-18 NKC
Excavation Ordinary Soil
246+050
(W&SER) 246+080 LHS Trips 14 Radha Swami Dumping Yard
27-Feb-18 NKC
Excavation Ordinary Soil
243+500
(W&SER) 243+560 RHS Trips 20 Radha Swami Dumping Yard
28-Feb-18 DMC 243+280 243+320 LHS Trips 43 Radha Swami Dumping Yard
6-Mar-18 DMC
Excavation Ordinary Soil
243+280
(W&SER) 243+320 LHS Trips 6 radha Swami Dumping Yard
7-Mar-18 DMC
Excavation Ordinary Soil
243+280
(W&SER) 243+320 LHS Trips 30 radha Swami Dumping Yard
7-Mar-18 NKC
Excavation Ordinary Soil
246+080
(W&SER) 246+120 LHS Trips 10 radha Swami Dumping Yard
8-Mar-18 DMC
Excavation Ordinary Soil
243+280
(W&SER) 243+320 LHS Trips 10 radha Swami Dumping Yard
8-Mar-18 NKC
Excavation Ordinary Soil
246+100
(W&SER) 246+120 LHS Trips 7 radha Swami Dumping Yard
14-Mar-18 DMC
Excavation Ordinary Soil
243+700
(W&SER) 243+760 LHS Trips 40 radha Swami Dumping Yard
15-Mar-18 DMC
Excavation Ordinary Soil
243+700
(W&SER) 243+760 LHS Trips 30 radha Swami Dumping Yard
16-Mar-18 DMC
Excavation Ordinary Soil
243+700
(W&SER) 243+760 LHS Trips 25 radha Swami Dumping Yard
16-Mar-18 NKC
Excavation Ordinary Soil
241+380
(W&SER) 241+460 LHS Trips 35 radha Swami Dumping Yard
17-Mar-18 DMC
Excavation Ordinary Soil
243+700
(W&SER) 243+760 LHS Trips 26 radha Swami Dumping Yard
18-Mar-18 Esquire Construction
Excavation
pvtOrdinary
ltd Soil
236+850
(W&SER) 236+900 LHS Trips 8 radha Swami Dumping Yard
19-Mar-18 NKC
Excavation Ordinary Soil
241+300
(W&SER) 241+360 LHS Trips 17 radha Swami Dumping Yard
20-Mar-18 NKC
Excavation Ordinary Soil
241+300
(W&SER) 241+360 LHS Trips 15 radha Swami Dumping Yard
21-Mar-18 DMC
Excavation Ordinary Soil
243+700
(W&SER) 243+760 LHS Trips 13 radha Swami Dumping Yard
21-Mar-18 NKC
Excavation Ordinary Soil
241+300
(W&SER) 241+360 LHS Trips 5 radha Swami Dumping Yard
22-Mar-18 NKC
Excavation Ordinary Soil
241+300
(W&SER) 241+360 LHS Trips 11 radha Swami Dumping Yard
22-Mar-18 NKC
Excavation Ordinary Soil
246+120
(W&SER) 246+130 LHS Trips 5 radha Swami Dumping Yard
24-Mar-18 NKC
Excavation Ordinary Soil
241+240
(W&SER) 241+300 LHS Trips 7 radha Swami Dumping Yard
24-Mar-18 NKC
Excavation Ordinary Soil
246+100
(W&SER) 246+160 LHS Trips 17 radha Swami Dumping Yard
24-Mar-18 DMC
Excavation Ordinary Soil
243+760
(W&SER) 243+800 LHS Trips 50 radha Swami Dumping Yard
25-Mar-18 DMC 243+760 243+800 LHS Trips 27 radha Swami Dumping Yard
26-Mar-18 DMC
Excavation Ordinary Soil
243+000
(W&SER) LHS Trips 36 radha Swami Dumping Yard
29-Mar-18 DMC
Excavation Ordinary Soil
243+760
(W&SER) 243+800 LHS Trips 40 radha Swami Dumping Yard
29-Mar-18 NKC
Excavation Ordinary Soil
246+120
(W&SER) 246+200 LHS Trips 2 radha Swami Dumping Yard
29-Mar-18 NKC
Excavation Ordinary Soil
240+380
(W&SER) 240+430 LHS Trips 16 radha Swami Dumping Yard
9-Apr-18 NKC 243+340 243+380 LHS Trips 20 radha Swami Dumping Yard
9-Apr-18 NKC 246+120 246+200 LHS Trips 15 radha Swami Dumping Yard
10-Apr-18 NKC 243+320 243+390 LHS Trips 24 radha Swami Dumping Yard
10-Apr-18 NKC 246+120 246+200 LHS Trips 4 radha Swami Dumping Yard
11-Apr-18 DMC 243+760 243+800 LHS Trips 4 radha Swami Dumping Yard
12-Apr-18 NKC 243+580 243+700 LHS Trips 13 radha Swami Dumping Yard
13-Apr-18 NKC 241+580 241+620 LHS Trips 11 radha Swami Dumping Yard
4-Jun-18 252+360 Water sprinkling 4 trips
5-Jun-18 252+360 Water sprinkling 6 trips

15.06.18 NKC ### 263+620 263+850 5m3 Patch work

Shubash Electrical 248+400 1.9 1.7 0.8 Electric polr foundation

Trips
NKC 317
DMC 374
Esquire Construction pvt ltd 8
MMK 137
Total 836

STR
28-Mar-18 BC 239+993 NKC Trips 3 Radha swami dumping yard
27-Mar-18 BC 239+993 NKC Trips 8 Radha swami dumping yard
26-Mar-18 BC 239+993 NKC Trips 9 Radha swami dumping yard
24-Mar-18 BC 239+993 NKC Trips 3 Radha swami dumping yard
20-Feb-18 Minor Bridge 245+710 NKC Trips 25 Radha swami dumping yard
19-Feb-18 Minor Bridge 245+710 NKC Trips 4 Radha swami dumping yard

Total
Trips 52
STR
28-Mar-18 BC 239+993 NKC Trips 3 16 Radha swami dumping yard
27-Mar-18 BC 239+993 NKC Trips 8 64 Radha Swami Dumping Yard
26-Mar-18 BC 239+993 NKC Trips 9 72 Radha Swami Dumping Yard
24-Mar-18 BC 239+993 NKC Trips 3 16 Radha Swami Dumping Yard
20-Feb-18 Minor Bridge 245+710 NKC Trips 25 200 Radha Swami Dumping Yard
19-Feb-18 Minor Bridge 245+710 NKC Trips 4 30 Radha Swami Dumping Yard
3-Apr-18 BC 239+995 NKC Trips 7 237+810
4-Apr-18 BC 239+995 NKC Trips 7 237+800
4-Apr-18 BC 239+995 NKC Trips 2 Radha Swami Dumping Yard
9-Apr-18 BC 236+753 NKC Trips 2 Radha Swami Dumping Yard
9-Apr-18 BC 236+753 NKC Trips 6 237800
9-Apr-18 BC 236+753 NKC Trips 6 236803
10-Apr-18 BC 236+753 NKC Trips 2 247320
10-Apr-18 BC 236+753 NKC Trips 2 236803
10-Apr-18 BC 236+753 NKC Trips 1 236803
5-Jan-18 BC 243+867 NKC Trips 4 16
7-Jun-18 veenet kumar 4 for jia batching plant
TOTAL Trips 95 414
swami dumping yard
wami Dumping Yard
wami Dumping Yard
wami Dumping Yard
wami Dumping Yard
wami Dumping Yard
237+810
237+800
wami Dumping Yard
wami Dumping Yard
237800
236803
247320
236803
236803

S-ar putea să vă placă și