ITP Doc. No :
Rev. :
Discipline Code : 01
Masonry Works Date :
Project Name: THE LANA LEGEND:
Main Contractor: China State Construction Overseas Development Shanghai (CSCODS) S (Surveillance), W (Witness), R (Review),
Project Manager: Brewin Mesa (BMS) I (Inspection), H (Hold Point), T (Testing)
ACCEPTANCE TESTING CERTIFICATES/
REFERENCE DOCUMENTS/ CRITERIA QUALITY RECORDS/
NO. ACTIVITY FREQUENCY CSCODS BMS
CONTROLLING DOCUMENTS QUALITY VERIFYING DOCUMENTS
DOCUMENTS
1 Approval of documents related * Approved shop drawings All related ONCE H Material technical data, R
to Block Work installation * Project specifications documents must be Suppliers/Subcons Pre-
* Approved Project Quality Plan reviewed and qualification approval
* Approved Method Statement approved
2 Material approval * Material submittal approval Material must be ONCE H Material technical data R
* Project specifications reviewed and
approved
3 Delivery of materials Delivery receipts Material delivered For every H Material Delivered on Site I
on site must comply material Inspection Report
with approved delivery on
Material Submittals site
4 Mock-up Wall Construction As per approved drawings Approved drawings ONCE H Request for Inspection/Testing I
5 Subtrate preparation and As per approved drawings Approved drawings For every H Request for Inspection/Testing I
marking layout Grid
6 (1st Lift) - After laying the 1st Method Statement, Project Approved drawings For every H Request for Inspection/Testing I
Course, Corners and Ends Specifications and Method Grid
Masonry Block (up to 4th Statement
Courses)
7 (2nd Lift) - to the soffit/lintel Method Statement, Project Approved drawings For every H Request for Inspection/Testing I
Page 1 of 3
Inspection & Test Plan for
ITP Doc. No :
Rev. :
Discipline Code : 01
Masonry Works Date :
level Specifications and Method Grid
Statement
8 Accessories Installation Method Statement, Project Approved drawings Each H Inspection Checklist S
Specifications and Method succeeding
Statement layers
9 MEP accessories, openings, and Method Statement, Project Approved drawings Prior to H Inspection Checklist S
penetrations Specifications and Method grouting of
Statement joints
10 Concrete stiffeners Method Statement, Project Approved drawings Prior to H Inspection Checklist I
Specifications and Method casting
Statement concrete
11 Expansion joints and other Method Statement, Project Approved drawings Prior to H Inspection Checklist I
wall joints Specifications and Method application
Statement of sealant
12 Curing Method Statement, Project Approved drawings Daily for H Inspection Checklist S
Specifications and Method completed
Statement layers for a
period of
72 hours
13 Material Testing: Method Statement, Project Third party test H Test Reports from Third Party R
Specifications results Laboratory/Testing Agency
Page 2 of 3
Inspection & Test Plan for
ITP Doc. No :
Rev. :
Discipline Code : 01
Masonry Works Date :
C140 1.dimensions,
2.compressive
strength,
3.absorption/
density
Page 3 of 3