Sunteți pe pagina 1din 3

Inspection & Test Plan for

ITP Doc. No :
Rev. :
Discipline Code : 01
Masonry Works Date :
Project Name: THE LANA LEGEND:
Main Contractor: China State Construction Overseas Development Shanghai (CSCODS) S (Surveillance), W (Witness), R (Review),
Project Manager: Brewin Mesa (BMS) I (Inspection), H (Hold Point), T (Testing)
ACCEPTANCE TESTING CERTIFICATES/
REFERENCE DOCUMENTS/ CRITERIA QUALITY RECORDS/
NO. ACTIVITY FREQUENCY CSCODS BMS
CONTROLLING DOCUMENTS QUALITY VERIFYING DOCUMENTS
DOCUMENTS
1 Approval of documents related * Approved shop drawings All related ONCE H Material technical data, R
to Block Work installation * Project specifications documents must be Suppliers/Subcons Pre-
* Approved Project Quality Plan reviewed and qualification approval
* Approved Method Statement approved
2 Material approval * Material submittal approval Material must be ONCE H Material technical data R
* Project specifications reviewed and
approved
3 Delivery of materials Delivery receipts Material delivered For every H Material Delivered on Site I
on site must comply material Inspection Report
with approved delivery on
Material Submittals site
4 Mock-up Wall Construction As per approved drawings Approved drawings ONCE H Request for Inspection/Testing I
5 Subtrate preparation and As per approved drawings Approved drawings For every H Request for Inspection/Testing I
marking layout Grid
6 (1st Lift) - After laying the 1st Method Statement, Project Approved drawings For every H Request for Inspection/Testing I
Course, Corners and Ends Specifications and Method Grid
Masonry Block (up to 4th Statement
Courses)
7 (2nd Lift) - to the soffit/lintel Method Statement, Project Approved drawings For every H Request for Inspection/Testing I

Page 1 of 3
Inspection & Test Plan for
ITP Doc. No :
Rev. :
Discipline Code : 01
Masonry Works Date :
level Specifications and Method Grid
Statement
8 Accessories Installation Method Statement, Project Approved drawings Each H Inspection Checklist S
Specifications and Method succeeding
Statement layers
9 MEP accessories, openings, and Method Statement, Project Approved drawings Prior to H Inspection Checklist S
penetrations Specifications and Method grouting of
Statement joints
10 Concrete stiffeners Method Statement, Project Approved drawings Prior to H Inspection Checklist I
Specifications and Method casting
Statement concrete
11 Expansion joints and other Method Statement, Project Approved drawings Prior to H Inspection Checklist I
wall joints Specifications and Method application
Statement of sealant
12 Curing Method Statement, Project Approved drawings Daily for H Inspection Checklist S
Specifications and Method completed
Statement layers for a
period of
72 hours
13 Material Testing: Method Statement, Project Third party test H Test Reports from Third Party R
Specifications results Laboratory/Testing Agency

CMU tests For each type of For every


CMU indicated, units 10.000 units
will be tested of fraction
according to ASTM thereof:

Page 2 of 3
Inspection & Test Plan for
ITP Doc. No :
Rev. :
Discipline Code : 01
Masonry Works Date :
C140 1.dimensions,
2.compressive
strength,
3.absorption/
density

Mortar tests To be tested Random as


according to ASTM requested by
C109 Engineer
Change in mix

Mortar aggregates tests Grading For every


1.000 m3

Grout aggregates test Grading For every


1.000 m3
14 Final approval for the entire Method Statement, Project Approved drawings Upon H Request for Inspection/Testing I
wall up to soffit Specifications and Method Completion
Statement

Page 3 of 3