12-1/4" Hole Drilling Performance - S-927, Jan 2013

ROP (m/hr) WOB (kdaN) Surface RPM Torque (kNm)


0 150 0 15 0 150 0 30
700

850
Well Data
Operator BSP Location SERIA (F-32)
Well Name S-927 Run Date 20/01/2013
1000 Contractor KCA Deutag Rig Name T-201

Bit Data
1150 Size/Type 12-1/4" QD505X Serial No 7903616
Run No. : NEW/RR New IADC PDC Bit
Nozzle 3X14, 2X15 TFA (sq-in) 0.796
1300
Mud Hydraulics
Type WBM SP Pressure (Ave.) 14795kPag
Density (MW) 11.0-11.2 Flow Rate (Ave.) 3361LPM
1450
Bit Performance
MD IN MD OUT Drilled Bit Hour Av. ROP WOB Surf. RPM kRev
1600 716 2265 1549 21.62 71.65 14.5kdaN 57-133 -

Inner Outer Row Major Location Bearing Gauge Other Dull Reason
1750 Row Dull Pulled
0 1 CT G X I ER TD

BHA Components Length Total Length (m)


1900
Heavy Weight Drill Pipe 18.55 18.55
Accelerator 10.01 28.56
Heavy Weight Drill Pipe 18.65 47.21
2050
Drilling Jar 9.81 57.02
Heavy Weight Drill Pipe 27.79 84.81
Drill Pipe 201.43 286.24
2200 Heavy Weight Drill Pipe 27.79 314.03
Crossover 1.15 315.18
Non-Mag Drill Collar 2.68 317.86
2350 3 Point Roller Reamer 1.83 319.69
Non-Mag Drill Collar 8.44 328.13
Float Sub 1.03 329.16
3 Point Roller Reamer 1.83 330.99
2500
Pulser Sub 3.55 334.54
MWD Tool 9.41 343.95
MWD Tool 2.19 346.14
Steering Tool 2.78 348.92
Rotary Steerable System 6.63 355.55
12-1/4" QD505X PDC Bit 0.41 355.96

Directional Data
TVD IN TVD OUT Inc. IN Inc. OUT Azi. IN Azi. OUT DLS (max) % Slide
645.5 943.8 46.66 136.2 23.5 13.6 1.494 100

Comments:
The 12-1/4" QD505X was drilled on Well S-927 for the 12-1/4" section using Halliburton's
EDL GeoPilot system. Drilling process began by drilling out the float collar, cement
shoetrack and float shoe from 698 meters to 712.7 meters followed by the the rathole
from 712.7 meters to 716.5 meters as well as the new formation until 719 meters with the
following parameters; Flow Rate 2650 - 3050 LPM, SPP 6850 - 9400 kPa, RPM 40 - 60
and WOB of 0.9 - 4.4 kdaN.

Drilling then commenced from 719 meters to 1248 meters where at 1248 meters the flow
rate was dropped from 3150 LPM to 3050 LPM due to overflow at the shakers. Drilling
then continued from 1248 meters until 2155 meters.

At 2155 meters, it was observed that the standpipe pressure dropped and mud spraying
from the top drive system. The TDS was then lowered and it was observed that there was
a crack in the gooseneck which has lead to the leak.

Once the new gooseneck had been installed, drilling commenced from 2155 meters to
section TD at 2265.5 meters as per recommendation from BSP geologist. The total
number of hours drilling was 21.62 hours to a total distance of 1549 meters with an
average ROP of 71.65 m/hr.

The final dull grading of the bit is given at 0-1-CT-G-X-I-ER-TD.

122 QD505X SN7903616 S-927.xlsx